CE Technical-File Compilation SOP — China to Georgia Corridor

Process / SOP · Vertical-solar Balance-of-System (BoS) · Equipment: Sungrow SG5K-D / SG8K-D / SG10K-D string inverters, Trina Vertex N NEG9RC.27 modules, LONGi Hi-MO 7 LR7-54HBB modules, ABB S900-G DC combiner, ABB OVR PV 40 1000 P Type 1+2 DC SPD, K2 Systems MultiRail aluminium vertical mounting · Corridor CN→GE · Owner: TradVolt Documentation Desk · Reviewer: Compliance Lead · Evidence date stamp: 2026-09-22

Answer / verdict (first 100 words): This SOP is applicable to a defined, named vertical-solar BoS kit: Sungrow SG5K-D / SG8K-D / SG10K-D single-phase string inverters paired with Trina Vertex N NEG9RC.27 bifacial modules and/or LONGi Hi-MO 7 LR7-54HBB modules, plus an ABB S900-G T1/T2 DC combiner, ABB OVR PV 40 1000 P Type 1+2 DC surge protection and K2 Systems MultiRail aluminium vertical mounting. It is not a generic BoS SOP. Horizon: CN→GE lane, indicative 10 working days from a complete RFQ. Evidence date stamp: 2026-09-22. Limitations: HS codes and Georgian import-duty/VAT rates are placeholders (PENDING — lookup on the RS.GE official portal); CE Technical File is procedural evidence, not a market-surveillance guarantee; torque, SOC and isolation voltages must be re-checked against the OEM manual revision listed below on the date of inspection.

Scope elementDecision
Applicable equipmentSungrow SG5K-D / SG8K-D / SG10K-D inverters; Trina Vertex N NEG9RC.27 modules; LONGi Hi-MO 7 LR7-54HBB modules; ABB S900-G DC combiner; ABB OVR PV 40 1000 P Type 1+2 DC SPD; K2 Systems MultiRail aluminium vertical mounting structure
Corridor / locationChina → Georgia (CN→GE), via Poti/Batumi sea or Tbilisi air
Horizon / duration10 working days indicative from a complete RFQ; subject to OEM evidence turnaround and RS.GE portal availability
Evidence-date stampAll cited documents accessed 2026-09-22
Key limitationHS/duty block is a PENDING — lookup placeholder against RS.GE; no hardcoded rates
Applicable directivesLVD 2014/35/EU, EMC 2014/30/EU, RoHS 2011/65/EU (+ Machinery 2006/42/EC where mounting system is treated as machinery)

1. Purpose and Scope

The procedure covers the documentary package required to demonstrate CE conformity for a defined vertical-solar Balance-of-System kit before goods are loaded for the CN→GE lane:

Procedures with technical limits (AQL, torque on module/mid-clamps, maximum system voltage, MPPT voltage window, isolation/battery interfaces where present) MUST be re-read against the OEM manual revision named in §3 before any inspection, packing or commissioning activity. The revisions stated here are the minimum reference set; later OEM revisions supersede.

[Claim: CE Technical Documentation must be assembled before a product is placed on the EU market and made available to authorities on request. | Src: Regulation (EU) 2019/1020 (Market Surveillance and Compliance of Products) | URL: https://eur-lex.europa.eu/eli/reg/2019/1020/oj | accessed 2026-09-22]

2. Applicable Standards and References (specific document URLs)

3. Equipment, OEM Manuals and Reference Documents

Line itemModel / family (real, marketed)OEM manual / datasheet referenceRevision / version stampURL
String inverter 5 kWSungrow SG5K-D (Sungrow residential D-series)Sungrow SG3K-D / SG5K-D / SG8K-D / SG10K-D User ManualUM-Ver.1.7 or later OEM revision in force on inspection dayhttps://www.sungrowpower.com/en
String inverter 8 kWSungrow SG8K-D (Sungrow residential D-series)Same family manual as aboveUM-Ver.1.7 or laterhttps://www.sungrowpower.com/en
String inverter 10 kWSungrow SG10K-D (Sungrow residential D-series)Same family manual as aboveUM-Ver.1.7 or laterhttps://www.sungrowpower.com/en
PV module (n-type bifacial, vertical-array)Trina Solar Vertex N NEG9RC.27 (425–445 W class)Trina NEG9RC.27 Vertex N product datasheet (TS4-NEG9RC.27 datasheet edition)2024 edition or later OEM revisionhttps://www.trinasolar.com/us-en
PV module (back-contact, vertical-array)LONGi Hi-MO 7 LR7-54HBB (430–455 W class)LONGi Hi-MO 7 LR7-54HBB product datasheet2024 edition or laterhttps://www.longi.com/en/
DC combinerABB S900-G T1/T2 PV combiner box with DC disconnectABB S900-G Combiner Box Installation & Operation Manual (GE Industrial Solutions / ABB document family)Rev. A (2023) or later OEM revisionhttps://www.abb.com
DC surge protectionABB OVR PV 40 1000 P Type 1+2 PV SPDABB OVR PV 40 1000 P datasheet / installation instructions (OVR PV family)2022 edition or laterhttps://www.abb.com
Mounting systemK2 Systems MultiRail aluminium vertical-orientation rail-and-post systemK2 Systems MultiRail assembly instructions (referenced to UL 2703:2021)MultiRail assembly instructions, current editionhttps://k2-systems.com

[Claim: The named inverter models (Sungrow SG5K-D / SG8K-D / SG10K-D) are publicly marketed residential/commercial single-phase string inverters in Sungrow's residential D-series. | Src: Sungrow corporate product index | URL: https://www.sungrowpower.com/en | accessed 2026-09-22]

[Claim: Trina Vertex N NEG9RC.27 is a publicly marketed n-type bifacial module within the Trina Vertex N family. | Src: Trina Solar corporate product index | URL: https://www.trinasolar.com/us-en | accessed 2026-09-22]

[Claim: LONGi Hi-MO 7 LR7-54HBB is a publicly marketed back-contact PV module within the LONGi Hi-MO 7 family. | Src: LONGi corporate product index | URL: https://www.longi.com/en/ | accessed 2026-09-22]

[Claim: ABB S900-G is a marketed PV combiner box with T1/T2 surge and DC disconnect. | Src: ABB Combiner / String Combiner product index | URL: https://www.abb.com | accessed 2026-09-22]

[Claim: ABB OVR PV 40 1000 P is a marketed Type 1+2 PV SPD for DC-side surge protection. | Src: ABB Surge Protective Devices product index (OVR PV family) | URL: https://www.abb.com | accessed 2026-09-22]

[Claim: K2 Systems MultiRail is a marketed aluminium rail-and-post vertical PV mounting system, referenced to UL 2703. | Src: K2 Systems Mounting Systems product index | URL: https://k2-systems.com | accessed 2026-09-22]

Model assumption: the manual revisions stated above (e.g., "UM-Ver.1.7", "Rev. A (2023)", "2024 datasheet edition") are the latest OEM revisions TradVolt has on file as of 2026-09-22; the Documentation Desk must reconfirm the current revision with the supplier at the moment of inspection and update the OEP accordingly. The named OEM portals (Sungrow, Trina, LONGi, ABB, K2 Systems) are the authoritative source for the current datasheet / manual PDF — deep PDF paths on those sites are JS-rendered and must be pulled at RFQ intake.

4. Step Sequence

Step #ActionOwnerInput docOutput docDone-when
1Receive BoS item list, quantities and target-market confirmation (Georgia). Item list must call out the specific models above (Sungrow SG5K-D / SG8K-D / SG10K-D; Trina NEG9RC.27 / LONGi LR7-54HBB; ABB S900-G combiner; ABB OVR PV 40 1000 P SPD; K2 Systems MultiRail mounting).Sales EngineerCustomer RFQ / POProject Brief (PB-CNGE-###)PB signed by Sales Engineer and Compliance Lead; named models logged.
2Identify applicable CE directives per item: LVD 2014/35/EU (inverter, ABB S900-G combiner, ABB OVR PV 40 1000 P SPD, cabling), EMC 2014/30/EU (inverter), RoHS 2011/65/EU (all electrical items), Machinery 2006/42/EC (K2 Systems MultiRail mounting where treated as machinery).Compliance LeadProject Brief; OEM service manualsDirective Map (DM)Each line item has at least one directive assigned with citation to the EUR-Lex article.
3Collect OEM service manuals, datasheets and test certificates (latest revision) for Sungrow SG5K-D / SG8K-D / SG10K-D, Trina NEG9RC.27, LONGi LR7-54HBB, ABB S900-G combiner, ABB OVR PV 40 1000 P SPD, K2 Systems MultiRail mounting, DC cable/connectors.Documentation DeskOEM service manuals / datasheetsOEM Evidence Pack (OEP)OEP contains one PDF per line item with revision tag and OEM URL.
4List applicable IEC / UL standards per component (see §2).Compliance LeadOEPStandards Index (SI)SI cross-references each item to clause-level requirements of IEC 61215-1:2021 / IEC 61730-1:2016 / IEC 62548:2016 / IEC 61643-31:2018 / UL 2703:2021 as applicable.
5Draft component-level risk assessment covering foreseeable misuse during install/service (vertical-array wind/snow loading, DC isolation, ABB S900-G combiner arc-flash, ABB OVR PV 40 1000 P let-through, K2 Systems MultiRail mid-clamp torque).Compliance LeadSI; OEM service manualsRisk Assessment (RA)RA scored for severity × probability with mitigations referencing OEM manual clauses.
6Issue or collect Declaration of Conformity per directive for each model.Documentation DeskOEP; test reportsDeclarations of Conformity (DoC)Each DoC signed, dated, lists directives and harmonised standards.
7Bundle accredited test reports (e.g., IEC 61215-1:2021 / IEC 61730-1:2016 reports for the named modules; IEC 61643-31:2018 for ABB OVR PV 40 1000 P SPD; Sungrow SG-family test certificate) and produce a traceability matrix linking reports to items.Compliance LeadDoC; test reportsTraceability Matrix (TM)100% of line items mapped to at least one accredited test report (lab + report number + date).
8Define pre-shipment AQL plan per ISO 2859-1:1999 (lot size, AQL level, sample size code letter). Default AQLs: 1.0 for major, 2.5 for minor — confirm against OEM datasheet tolerances for the named items.QA InspectorFinal packing listAQL Inspection Plan (AIP)AIP states lot, AQL (1.0 major / 2.5 minor), sample code letter per ISO 2859-1 Table 2-A, and acceptance number.
9Fix ICC Incoterms 2020 term and FIATA-aligned transport docs for CN→GE (e.g., FCA Shanghai, CIP Poti, DAP Tbilisi).Logistics CoordinatorCustomer PO; freight quoteTrade & Transport Sheet (TTS)TTS records the Incoterm code (e.g., FCA, CIP, DAP), sea/air mode, and either a FIATA FBL ref. (multimodal) or a sea B/L ref.
10Resolve HS code and duty block on the official Georgian customs portal (RS.GE).Logistics CoordinatorTTS; component classificationHS & Duty Sheet (HDS)HS codes logged against the live Georgian HS schedule; rates recorded as PENDING — lookup on the official portal with lookup date.
11Two-eye review of the technical file against the checklist below.Compliance Lead + Sales EngineerAll artefacts aboveReview Report (RR)RR shows zero open items or all items closed with evidence.
12Issue the CE Technical File to the customer; archive a signed copy.Documentation DeskRR-signed packReleased Technical File (TF-CNGE-###)Customer receipt confirmed; archive entry created with SHA-256 hash.

[Claim: LVD 2014/35/EU applies to electrical equipment designed for use with a voltage rating of 50–1000 V AC or 75–1500 V DC. | Src: EUR-Lex Directive 2014/35/EU article 1 | URL: https://eur-lex.europa.eu/eli/dir/2014/35/oj | accessed 2026-09-22]

[Claim: EMC 2014/30/EU applies to equipment liable to create electromagnetic disturbance or be affected by it. | Src: EUR-Lex Directive 2014/30/EU article 1 | URL: https://eur-lex.europa.eu/eli/dir/2014/30/oj | accessed 2026-09-22]

[Claim: RoHS 2011/65/EU restricts hazardous substances in electrical and electronic equipment. | Src: EUR-Lex Directive 2011/65/EU article 4 | URL: https://eur-lex.europa.eu/eli/dir/2011/65/oj | accessed 2026-09-22]

5. Document Checklist (literal filenames)

Request Quote — replies in 48h Request Quote — replies in 48h

6. Indicative Timeline with Dependencies

DayActivityDepends on
D+1Steps 1–2: Project Brief, Directive MapCustomer RFQ/PO with named Sungrow / Trina / LONGi / ABB / K2 Systems models
D+3Steps 3–4: OEM pack, Standards IndexLatest-revision OEM manuals/datasheets from supplier (UM-Ver.1.7 or later for SG family; 2024 edition or later for Trina / LONGi)
D+5Steps 5–7: Risk Assessment, DoC, Traceability MatrixIEC 61215 / IEC 61730 / IEC 61643-31 test reports from accredited lab
D+7Step 8: AQL plan; Step 9: Trade & Transport SheetFinal packing list, freight quote
D+8Step 10: HS & Duty Sheet (rates PENDING — lookup)Official RS.GE portal access
D+9Step 11: Two-eye reviewAll artefacts above
D+10Step 12: Release Technical File to customerReview Report signed

Total indicative duration: 10 working days from a complete RFQ. Durations are indicative and depend on OEM evidence turnaround and customs portal availability.

7. Duty / HS Code Block (R5)

Equipment / parts covered: Sungrow SG5K-D / SG8K-D / SG10K-D string inverters; Trina Vertex N NEG9RC.27 modules; LONGi Hi-MO 7 LR7-54HBB modules; ABB S900-G PV combiner; ABB OVR PV 40 1000 P Type 1+2 DC SPD; K2 Systems MultiRail aluminium vertical mounting; PV1-F DC cable; MC4-compatible connectors.

HS codes: PENDING — lookup on the official portal of the Revenue Service of Georgia (RS.GE) for each line item. The exact sub-heading must be confirmed against the live Georgian HS schedule on the portal before quotation.

Duty rates: PENDING — lookup. TradVolt does not hardcode rates; the Customs Coordinator records the rate returned by the official portal, the lookup date and the officer reference (if any).

Official portal: RS.GE — Revenue Service of Georgia, https://www.rs.ge/ (accessed 2026-09-22).

EU-side cross-reference: TARIC consultation, https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en (accessed 2026-09-22) — for product-class cross-check only; Georgia applies its own HS schedule.

Disclaimer: This block is a procedural placeholder. Customs classification, preferential origin and applicable duties must be confirmed by a licensed customs broker against the actual commercial invoice, the HS schedule in force on the date of export, and any bilateral arrangements between China and Georgia. TradVolt accepts no liability for misclassification.

8. Cost Slots (indicative / UNCERTAIN)

Cost itemStatusSource / note
CE directive mapping & DoC reviewindicativeInternal labour estimate
ISO 2859-1:1999 AQL inspection (per lot)indicativePer Inspection Body quote
Pre-shipment test re-runs (if needed)UNCERTAINDependent on test report validity
Georgian import dutyPENDING — lookupRS.GE official portal
Georgian VATPENDING — lookupRS.GE official portal
CN→GE freight (sea or air)indicativeFreight quote per Incoterms 2020

9. Roles and Responsibilities

10. Technical Limits — must be reconfirmed against the named OEM manual revisions on the day of inspection

ParameterReference value (from OEM datasheet as of 2026-09-22)Source / where to verify
Sungrow SG5K-D / SG8K-D / SG10K-D max DC input voltagePer OEM datasheet (600 V or 1100 V variant — confirm)Sungrow SG5K-D / SG8K-D / SG10K-D datasheet, "Electrical Data" section (UM-Ver.1.7 or later)
Sungrow SG5K-D / SG8K-D / SG10K-D MPPT voltage rangePer OEM datasheetSungrow SG5K-D / SG8K-D / SG10K-D datasheet
Trina Vertex N NEG9RC.27 max system voltage1500 V DC (per OEM datasheet)Trina NEG9RC.27 datasheet, "Electrical Characteristics" table
LONGi Hi-MO 7 LR7-54HBB max system voltage1500 V DC (per OEM datasheet)LONGi LR7-54HBB datasheet, "Electrical Characteristics" table
ABB S900-G DC combiner max string fuse ratingPer ABB S900-G datasheet (gPV class, sized per IEC 62548:2016 string-sizing calc)ABB S900-G Installation & Operation Manual, Rev. A (2023) or later
ABB OVR PV 40 1000 P SPD Uc / Iimp ratingsPer IEC 61643-31:2018 SPD datasheet (Uc ≥ 1.2 × Voc,string,corrected; Iimp / In per OVR PV 40 1000 P datasheet)ABB OVR PV 40 1000 P datasheet / installation instructions + IEC 61643-31:2018
K2 Systems MultiRail mid-/end-clamp torque on mounting systemPer K2 Systems MultiRail assembly instructions (typically 16–22 N·m for aluminium mid-clamps — confirm)K2 Systems MultiRail assembly instructions, current edition
SOC window for any Sungrow hybrid battery variantPer OEM manual (UN 38.3 transport + SOC limits for shipping)Sungrow hybrid user manual + UN Manual of Tests and Criteria §38.3

Model assumption: the reference values above are read from the OEM datasheets cited as of the evidence date 2026-09-22; the Compliance Lead must verify the values in force on the day of inspection and update the OEP if a newer datasheet revision has been published.

11. Records and Retention

The Released Technical File (TF-CNGE-###) and all upstream artefacts are retained for a minimum of 10 years from the date of release, in line with EU market-surveillance record-keeping expectations. [Src: Regulation (EU) 2019/1020 | URL: https://eur-lex.europa.eu/eli/reg/2019/1020/oj | accessed 2026-09-22]

12. Change Control

Any change to the named equipment (e.g., inverter variant, module family, combiner swap, SPD swap, mounting-system substitution), the directive/standards set, or the corridor (CN→GE) requires a new revision of this SOP, re-approval by the Compliance Lead, and a delta review against the active Technical File index.


[Claim: Pre-shipment AQL inspection plans in this SOP reference ISO 2859-1:1999 sampling procedures by attributes. | Src: ISO 2859-1:1999 | URL: https://www.iso.org/standard/114294.html | accessed 2026-09-22]

[Claim: The trade term for the CN→GE leg is set per ICC Incoterms 2020 (ICC Publication No. 723E). | Src: ICC Incoterms 2020 official rules page | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | accessed 2026-09-22]

[Claim: HS code and duty lookup is performed on the official portal of the Revenue Service of Georgia. | Src: RS.GE | URL: https://www.rs.ge/ | accessed 2026-09-22]

[Claim: The Trina NEG9RC.27 module family is qualified under IEC 61215-1:2021 / IEC 61215-2:2021 (crystalline-silicon PV modules). | Src: IEC 61215-1:2021 / IEC 61215-2:2021 | URL: https://webstore.iec.ch/publication/61347 | URL: https://webstore.iec.ch/publication/61348 | accessed 2026-09-22]

[Claim: The ABB OVR PV 40 1000 P SPD used in the ABB S900-G combiner is qualified under IEC 61643-31:2018. | Src: IEC 61643-31:2018 | URL: https://webstore.iec.ch/publication/61809 | accessed 2026-09-22]

[Claim: K2 Systems MultiRail clamping/grounding practices are referenced to UL 2703:2021. | Src: UL 2703:2021 | URL: https://ulstandards.ul.com/standard/ul-2703 | accessed 2026-09-22]