ESS Site Acceptance Test (SAT) — China → Türkiye Corridor

Document type: Process / SOP  |  Vertical: Solar Balance-of-System  |  Trade lane: CN → TR  |  Scope: Energy Storage System (BESS) site acceptance testing

Verdict (see §6, §9): SAT requires ~7 active on-site days after CN→TR sea transit; HS code and import duty/VAT are PENDING customs broker confirmation against the Republic of Türkiye Ministry of Trade tariff portal. Reference equipment family: CATL EnerC series containerised LFP BESS paired with a Sungrow SG3125HV-MV PCS (model-level torque, SOC window and DC-bus limits below are model assumptions to be re-confirmed against the OEM service manual revision at RFQ).

FieldValue
Equipment / locationLithium-ion BESS (EnerC container family) + Sungrow SG3125HV-MV PCS, TR project site
Horizon~7 active SAT days post-transit, plus 25–35 days CN→TR sea transit
Evidence dateSource reference date: 2026-09-22
Duty / HSPENDING — broker confirmation via Türkiye Ministry of Trade tariff portal
LimitationSpecific torque, SOC and voltage limits are model assumptions; OEM manual revision must be confirmed at RFQ

1. Purpose

This Standard Operating Procedure (SOP) defines how Tradvolt executes a Site Acceptance Test (SAT) for an Energy Storage System (ESS) delivered on the China → Türkiye trade lane. It standardises the responsibilities, inputs, outputs, and gating criteria so that the SAT is reproducible across vertical solar BoS projects. [Claim | Src: Tradvolt internal SOP template (cross-referenced with public Tradvolt process documentation) | URL: https://tradvolt.com/guides/ | reference date: 2026-09-22]

The procedure aligns with the OEM service-manual requirement that final acceptance, including charge/discharge functionality, be witnessed on-site at the BESS location rather than at the factory. For the reference configuration, the CATL EnerC container service manual and the Sungrow SG3125HV-MV PCS installation and commissioning manual govern the on-site checks. [Claim | Src: CATL ESS product family page | URL: https://www.catl.com/en/ess/ | reference date: 2026-09-22] [Claim | Src: Sungrow product and service portal | URL: https://www.sungrowpower.com/en | reference date: 2026-09-22]

2. Scope

In scope: Containerised or skid-mounted lithium BESS (reference: CATL EnerC series), PCS (reference: Sungrow SG3125HV-MV), BMS, MV/LV interface cabinets, SCADA gateway, and associated cabling accessories delivered as Solar Balance-of-System equipment. The cell-level safety expectations align with IEC 62619 (Secondary cells and batteries containing alkaline or other non-acid electrolytes — Safety requirements for secondary lithium cells and batteries, for use in industrial applications), and the overall ESS vocabulary/terminology aligns with IEC 62933-1 (Electrical energy storage systems — Part 1: Vocabulary). [Claim | Src: IEC 62933-1 vocabulary for EES terminology | URL: https://webstore.iec.ch/ | reference date: 2026-09-22] [Claim | Src: IEC 62619 industrial lithium cell/battery safety | URL: https://webstore.iec.ch/ | reference date: 2026-09-22]

Out of scope: PV module flash tests, inverter DC-side commissioning handled under a separate SOP, and civil engineering acceptance.

3. Roles

4. Reference documents

5. Process sequence

Step #ActionOwnerInput docOutput docDone-when
1Confirm SAT scope, equipment list (incl. CATL EnerC container SN, Sungrow SG3125HV-MV firmware), contractual SAT window, and issue the SAT plan.PMContract / SAT clauseTVT-SAT-PLAN-v1.0.pdfSigned SAT plan received from CR and OEM.
2Witness or verify pre-shipment inspection (PSI) at the OEM facility in China prior to container sealing.QAPSI checklistTVT-PSI-REPORT.pdfPSI report countersigned; seal number recorded.
3Verify Chinese export customs pre-clearance declaration against the Bill of Lading and packing list.LCCommercial invoice, packing listTVT-CN-EXPORT-DECL.pdfDeclaration reference archived; goods permitted to gate out.
4Confirm booking, container seal number, and enable milestone tracking across the CN→TR sea lane.LCBooking confirmationTVT-TRACK-LOG.xlsxVessel ETA confirmed and tracking link active.
5Prepare the TR import pre-arrival dossier with the customs broker; flag the ESS equipment for HS classification (see §10).LCCI, PL, BL, OEM certificateTVT-TR-IMPORT-DOSSIER.pdfBroker confirms dossier completeness; reference number logged.
6Verify civil, electrical, fire-suppression, ventilation, and SCADA-network readiness at the BESS site.SESite readiness checklistTVT-PREREADY-CHECK.pdfAll site prerequisites checked on the pre-readiness form.
7Execute visual and mechanical inspection against the CATL EnerC service manual checklist (torque marks, labelling, IP integrity).SEOEM SAT checklist, ISO 2859-1 AQL tableTVT-VMI-REPORT.pdfAll visual items ticked; deviations logged as punch items.
8Run the OEM-mandated charge and discharge cycles with the CL per the Sungrow SG3125HV-MV commissioning manual; capture SCADA telemetry traces and cell-level logs.CLOEM PCS parameter fileTVT-FUNC-TEST.xlsxCycles completed; logged parameters meet OEM acceptance band.
9Verify grid-support functions (frequency ride-through, anti-islanding, voltage/reactive control) per the relevant grid code.CLGrid-code compliance sheetTVT-GRID-COMPLIANCE.pdfAll grid-support tests pass; trace evidence attached.
10Apply AQL sampling per ISO 2859-1 to cable accessories, labels, documentation sets, and cosmetic surfaces.QAISO 2859-1 tableTVT-AQL-SAMPLE.pdfSampling decision recorded (Accept / Reject / Continue).
11Compile and close the punch-list of non-conformities; secure re-test evidence for any open items.PMPunch-list registerTVT-PUNCH-LIST.pdfPunch-list status = CLOSED or formally documented as deferred.
12Obtain signatures on the SAT report and archive the full deliverable dossier to the customer O&M team.QASAT report draftTVT-SAT-REPORT-FINAL.pdfSigned SAT certificate archived; O&M hand-over acknowledged in writing.

6. Timeline & dependencies

PhaseActivityIndicative durationPredecessor
ASAT plan & scope (Steps 1)1 dayContract handover complete
BPre-shipment (Step 2)2 days at OEM siteA closed
CCN export + transit (Steps 3–4)25–35 days (sea CN→TR)B signed
DTR import dossier (Step 5)3 days pre-arrivalBL issued in C
EOn-site pre-readiness (Step 6)1 dayCivil works handover complete
FOn-site SAT execution (Steps 7–10)3 daysD delivered, E cleared
GPunch-list + sign-off (Steps 11–12)2 daysF complete
Total indicative~7 days active + sea transit—

All transit durations above are indicative; vessel cut-offs and customs windows may shift the on-site SAT window. Sea-transit lead-time figures are not hard-coded because they depend on carrier schedule, port pair, and the Incoterms 2020 risk transfer point. [Claim | Src: ICC Incoterms 2020 | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | reference date: 2026-09-22]

7. Equipment limits (model assumption)

The numerical limits in this section are model assumptions for the reference configuration (CATL EnerC container + Sungrow SG3125HV-MV PCS) and must be re-validated against the OEM service-manual revision in force at the time of SAT. Tradvolt does not assert these as universal limits.

ParameterAssumed limitSource / status
DC bus voltage window (PCS)1,000–1,500 V DC (Sungrow SG3125HV-MV class)[Model assumption | Sungrow product family | URL: https://www.sungrowpower.com/en | reference date: 2026-09-22]
Battery SOC operating window5%–95% SOC during commissioning cycles[Model assumption | CATL EnerC operating envelope | URL: https://www.catl.com/en/ess/ | reference date: 2026-09-22]
Torque — DC power cable lugsPer OEM manual section (Nm value to be re-confirmed against revision)[Model assumption | CATL service manual | URL: https://www.catl.com/en/ess/ | reference date: 2026-09-22]
Torque — battery module busbarsPer OEM manual section (Nm value to be re-confirmed against revision)[Model assumption | CATL service manual | URL: https://www.catl.com/en/ess/ | reference date: 2026-09-22]
Cell safety referenceUN 38.3 (ST/SG/AC.10/11/Rev.7); IEC 62619[Claim | UNECE UN Manual of Tests and Criteria | URL: https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria | reference date: 2026-09-22] [Claim | IEC 62619 catalogue | URL: https://webstore.iec.ch/ | reference date: 2026-09-22]

8. Document checklist

Each item below corresponds to a literal filename in Tradvolt's document repository. Customers may request the package as a single ZIP via the RFQ flow for audit purposes.

9. Indicative cost slots

The slots below are indicative and not a quotation. Final figures depend on vessel schedule, Incoterms 2020 point of delivery, and TR customs duty assessment (see §10).

10. Duty / HS code block

FieldValue
EquipmentLithium-ion BESS (CATL EnerC container family) with Sungrow SG3125HV-MV PCS, BMS, MV/LV cabinet — solar BoS
HS code (equipment/parts)PENDING — lookup against the Turkish customs tariff (Gümrük Tarife İstatistik Pozisyonu) via the Republic of Türkiye Ministry of Trade portal; cross-reference with the WCO Harmonized System nomenclature for the exact configuration. [Claim | Src: Republic of Türkiye Ministry of Trade | URL: https://www.trade.gov.tr/ | reference date: 2026-09-22]
Applicable duty ratePENDING — lookup; rate depends on the exact HS heading/subheading determined for the shipment.
VAT / other leviesPENDING — lookup against the current VAT rate and any exempted/special-regime treatment published by the official customs portal.
Official portal consultedRepublic of Türkiye Ministry of Trade — trade.gov.tr
DisclaimerTradvolt does not hard-code duty rates. Final duty figures must be confirmed with the appointed customs broker against the actual HS classification of the equipment at the time of import. Trade remedies, anti-dumping, or safeguard measures may apply; these are not captured in this SOP.

Reference for trade documentation handling: ICC Incoterms 2020 risk-transfer clauses (DAP / CIP most common for SAT-liability deliveries). [Claim | Src: ICC Incoterms 2020 | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | reference date: 2026-09-22]

11. Request a quote

Send your project scope (equipment list including BESS container model and PCS SKU, Incoterms 2020 term, CN port, TR port/site) and Tradvolt will reply within 48 hours with a SAT execution plan and a fixed quote.