1. Purpose and Scope

This Standard Operating Procedure defines the TradVolt process for executing Potential-Induced Degradation (PID) testing of photovoltaic (PV) modules manufactured in the People's Republic of China and destined for solar farms in the Arab Republic of Egypt. The objective is to confirm PID resistance prior to vessel loading, mitigate warranty exposure, and align with the importer's technical due-diligence package. PID is a well-documented reliability concern in fielded PV arrays where high system voltages, humidity, and temperature drive leakage currents through the module encapsulation, leading to power loss measured in percent [%] of nameplate output1. The corridor CN→EG typically uses deep-sea lines calling at Alexandria (EGALY), Damietta (EGDAM), or Ain Sukhna (EGSUK) ports under CIF or CFR Incoterms2.

2. Normative References and Acceptance Framework

ReferenceTitle / scopeUse in this SOP
IEC 62804-1:2015Photovoltaic (PV) modules — Test methods for the detection of potential-induced degradation — Part 1: Crystalline siliconDefines the stress conditions (temperature, humidity, voltage bias, duration) used in step 63.
ISO 2859-1:1999Sampling procedures for inspection by attributes — Single sampling plans by AQLSample draw in step 5, General Inspection Level II, AQL 1.0 for major defects4.
Incoterms® 2020 (ICC)International Commercial Terms — CIF, CFR, FOB, DAPDefines point of transfer, cost, and risk allocation in step 82.
UL 1703 / UL 61730North-American PV module safety standardsReferenced only if Egyptian importer also requires UL-listed supply chain records5.
CE Marking (EU 2014/35/EU)Low Voltage DirectiveCross-checked on OEM datasheet, where applicable6.

3. Process Step-Sequence Table

Step #ActionOwnerInput docOutput docDone-when
1Receive importer RFQ; confirm OEM brand, module model (e.g. monocrystalline PERC/TOPCon), lot size in units, and Incoterm® 2020 selection.TradVolt Sales EngineerImporter RFQ email + OEM datasheetRFQ acknowledgement (PDF)Acknowledgement sent ≤ 24 h; RFQ ticket logged.
2Open internal process ticket; assign China Export (CEx) coordinator and confirm TradVolt SLA window.TradVolt Process OfficeAcknowledged RFQInternal ticket ID (e.g. TV-CN-EG-2026-XXXX)Ticket created; CEx named; SLA documented.
3Verify OEM datasheet PID class (typically PID-resistant or PID-free) and warranty terms.Technical EngineerOEM datasheet (manufacturer service manual)Technical review notePID class and warranty ceiling logged in ticket.
4Coordinate with CN-based accredited lab; confirm IEC 62804-1 chamber parameters: +85 °C, 85 % RH, 96 h, voltage bias equal to system max (commonly −1000 V DC or +1000 V DC).3CEx CoordinatorLab capability list + OEM datasheetLab quotation & test planLab booked; test plan signed by both parties.
5Draw the inspection sample per ISO 2859-1 General Inspection Level II, AQL 1.0 for major defects.4Independent InspectorLot quantity [units]Sample pick list + chain-of-custody formSample size recorded against ISO 2859-1 table; samples sealed and shipped to lab.
6Perform PID test under chamber conditions; record Pmax degradation [%] before and after stress.Accredited CN LabSealed samplesRaw test data sheetTest completed within 96 h + measurement window.
7Issue bilingual (English/Arabic) test report; verify degradation < 5 % (typical OEM threshold) for PID-free or < OEM-stated limit.Technical Engineer + TranslatorRaw data + OEM datasheetFinal PID test report (EN/AR PDF)Report issued; reviewed against OEM limits; archived.
8Ship pre-export documents (commercial invoice, packing list, draft PID report, certificate of origin) to EG importer under chosen Incoterm 2020.2CEx CoordinatorFinal PID report + shipping documentsPre-shipment document packDocuments received by EG importer before vessel arrival.
9Coordinate EG customs clearance: HS classification, ACID number, Nafeza platform submission, duty assessment.EG Import Desk (TradVolt local agent)Document pack + ACIDCustoms release orderGoods released by Egyptian Customs Authority.7
10Confirm delivery to EG warehouse or project site; close ticket; archive records.TradVolt Process OfficeCustoms release order + delivery receiptClosed ticket + archived PDF packTicket closed within SLA; audit trail preserved.
11Schedule post-shipment PID re-check after 12 months in service.Technical EngineerClosed ticketCalendar reminderRe-check window queued in CMMS.

4. Timeline with Dependencies

PhaseStep(s)OwnerDuration (working days, indicative)Dependency
A. RFQ & intake1, 2Sales / Process Office1 dayImporter RFQ received
B. Tech review3Technical Engineer1 dayOEM datasheet supplied
C. Lab booking & sample draw4, 5CEx + Inspector2 daysLab capacity confirmed
D. PID test execution6CN Lab5 days (96 h stress + 1 d EL/flash)Samples received at lab
E. Reporting7Tech + Translator2 daysLab raw data delivered
F. Pre-export dispatch8CEx Coordinator2 daysFinal report signed off
G. Sea transit CN→EG (indicative)9Freight forwarder + EG desk18–22 days (UNCERTAIN, subject to line)Vessel departure
H. EG clearance & delivery9, 10EG Import Desk3–5 daysNafeza/ACID pre-lodgement
I. Closure & archive10, 11Process Office1 dayDelivery receipt
Total elapsed (door-to-door, indicative)~ 35 days—

Sea-transit durations are indicative and depend on carrier rotation, port congestion, and Suez Canal transit conditions. Lab turnaround assumes normal chamber availability and is not a guaranteed lead-time.

5. Document Checklist

6. Duty / HS Code Block

Equipment / parts in scope: Photovoltaic (PV) crystalline-silicon modules for electricity generation, with or without PID-resistance certification.

Suggested HS classification (to be confirmed by licensed customs broker): 8541.43 — Photovoltaic cells and modules. The Egyptian Customs Authority (MISA / Egyptian Customs) applies the HS code to the Harmonized Tariff Schedule of Egypt. The 6-digit HS subheading above is the internationally agreed subheading in the WCO Harmonized System nomenclature8; the 8- or 10-digit national tariff line, applicable duties, VAT treatment, and any Egyptian Customs Executive Regulations preferences (e.g. under COMESA, GAFTA, EU-Egypt Association Agreement, or the African Continental Free Trade Area — AfCFTA) must be verified at the time of import.

Duty / VAT rates: PENDING — lookup at the official Egyptian Customs Authority (MISA — مصلحة الجمارك المصرية) portal and the National Tax Authority (ETA — Egyptian Tax Authority) at the time of each shipment. TradVolt does not hardcode duty or VAT percentages in this SOP.

Pre-lodgement: The Egyptian ACID (Advance Cargo Information Declaration) number must be lodged on the Nafeza platform prior to vessel loading at origin7.

Disclaimer: HS classification, duty rates, VAT, exemptions, and preferential origin treatments vary by exact technical specification (e.g. cell technology, rated wattage, bifacial vs monofacial) and by current Egyptian Executive Regulations. Always confirm with a licensed Egyptian customs broker and the official portals cited above. This block is process-orientation only and does not constitute legal or tax advice.

7. Cost Slots (Indicative — UNCERTAIN)

Cost lineBasisStatus
CN accredited lab — PID test (IEC 62804-1)USD per sampleindicative — confirmed at quotation
ISO 2859-1 sample draw & inspector feeUSD per man-dayindicative
Bilingual EN/AR report translationUSD per pageindicative
Pre-export document pack handlingUSD per shipmentindicative
EG customs broker + duty / VAT assessmentPer shipmentUNCERTAIN — depends on HS line and Egyptian Executive Regulations at time of import
Sea freight CN→EGALY / EGDAM / EGSUKUSD per module or per containerindicative — BAF/CAF surcharges apply
ACID / Nafeza lodgementPer shipmentindicative

All cost figures are indicative and UNCERTAIN until a written TradVolt quotation is issued. Sea freight is subject to Bunker Adjustment Factor (BAF), Currency Adjustment Factor (CAF), and port congestion surcharges as published by the ocean carrier.

8. Acceptance Criteria & Re-test Rules

The PID test is considered PASS if the post-stress relative power degradation of the inspected samples does not exceed the threshold declared on the OEM datasheet — typically ≤ 5 % for PID-free modules and ≤ 8 % for standard PID-resistant modules3. A FAIL triggers a re-sample per ISO 2859-1 tightened inspection rules4; two consecutive FAILs escalate to a lot-level quarantine pending OEM root-cause review.

9. Roles and Responsibilities (RACI summary)

RoleResponsibility
TradVolt Sales EngineerAccountable — RFQ intake and SLA
TradVolt Process OfficeResponsible — ticket lifecycle
Technical EngineerResponsible — datasheet review, report sign-off
China Export (CEx) CoordinatorResponsible — lab booking, pre-export docs
Independent InspectorResponsible — ISO 2859-1 sample draw
Accredited CN LabResponsible — IEC 62804-1 test execution
EG Import Desk (TradVolt local agent)Responsible — Nafeza / ACID, customs release
Importer (EG)Consulted — accepts final report, signs off delivery

10. Records and Archiving

All step outputs (RFQ, test report, customs release, ticket archive) shall be retained for a minimum of 7 (seven) years from the date of delivery, in line with standard B2B documentation practice. Electronic copies shall be stored in the TradVolt document management system under the ticket ID; paper originals shall be filed by the Process Office.

11. Change Control

Changes to chamber parameters, AQL levels, or HS classification logic require a new version of this SOP and sign-off by the Process Office. Minor editorial changes (typo, contact details) may be made without version increment but shall be logged in the document footer.

12. Sources Cited (Allow-List)

  1. [Claim: PID is a high-voltage/ humidity-driven degradation phenomenon measured in % power loss.] | Src: IEC 62804-1:2015, Photovoltaic modules — Test methods for the detection of potential-induced degradation — Part 1: Crystalline silicon | URL: https://webstore.iec.ch/publication/6095 | accessed 2026-09-21
  2. [Claim: Incoterms® 2020 defines CIF, CFR, FOB, DAP cost and risk allocation.] | Src: ICC Incoterms® 2020 (International Chamber of Commerce) | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | accessed 2026-09-21
  3. [Claim: IEC 62804-1 PID chamber parameters +85 °C, 85 % RH, 96 h, ±1000 V DC bias.] | Src: IEC 62804-1:2015 | URL: https://webstore.iec.ch/publication/6095 | accessed 2026-09-21
  4. [Claim: ISO 2859-1 General Inspection Level II, AQL 1.0 for major defects is the default sampling plan.] | Src: ISO 2859-1:1999, Sampling procedures for inspection by attributes | URL: https://www.iso.org/standard/11437.html | accessed 2026-09-21
  5. [Claim: UL 1703 / UL 61730 cover North-American PV module safety.] | Src: UL Standards — UL 61730-1 / UL 61730-2 | URL: https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1 | accessed 2026-09-21
  6. [Claim: CE marking under EU 2014/35/EU Low Voltage Directive applies to electrical equipment placed on the EU market.] | Src: EUR-Lex Directive 2014/35/EU | URL: https://eur-lex.europa.eu/eli/dir/2014/35/oj | accessed 2026-09-21
  7. [Claim: Egyptian ACID must be lodged on the Nafeza platform prior to shipment origin.] | Src: Egyptian Customs Authority — Nafeza / ACID programme (MISA) | URL: https://www.customs.gov.eg | accessed 2026-09-21
  8. [Claim: HS subheading 8541.43 covers photovoltaic cells and modules.] | Src: World Customs Organization — Harmonized Commodity Coding and Description System, subheading 8541.43 | URL: https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition.aspx | accessed 2026-09-21
Operational note: PID stress is destructive for the inspected units. Sample modules are typically scrapped after the test. The importer should factor sample loss into procurement quantities.