TradVolt Guide R14 · Slug: /guides/cn-us-ups-static-bypass-r14/ · Evidence date: 2025-01-15 · Horizon: 5-day on-site window (D0–D5) · Limitation: indicative only
| Decision Field | Value |
|---|---|
| Equipment | Vertiv NXC 60 kVA static bypass switch (family: NXC 60–200 kVA) |
| OEM Manual / Revision | Vertiv SL-25620_REV5 (NXC 60–200 kVA I&O Manual) |
| Location / Corridor | China → United States (CBP port of entry) |
| Time Horizon | 5-day on-site window (D0–D5) |
| Evidence Date | 2025-01-15 |
| Primary HS Code (suggested) | HTSUS 8537.10.91 (control panels) — verify at hts.usitc.gov |
| Duty Rate (MFN) | PENDING — verify at HTSUS |
| Section 301 Surcharge (CN origin) | PENDING — verify at USTR / CBP |
| Limitation | Indicative cost slots and duty figures are unverified; do not commit procurement on these values. |
| Step # | Action | Owner | Input Document | Output Document | Done-When |
|---|---|---|---|---|---|
| 1 | Receive OEM datasheet (Vertiv SL-25620_REV5 PDF), single-line diagram, and site survey for the installed NXC 60 kVA static bypass switch. | Site electrical lead | OEM datasheet SL-25620_REV5 | Document receipt log entry | Datasheet revision matches nameplate; serial logged. |
| 2 | Verify UL 1778 listing via UL Product iQ and IEC 62040-1 listing via IEC Webstore using the certificate number on the nameplate. | Compliance officer | UL 1778 / IEC 62040-1 certificate number | Listing verification screenshot | Listing ID resolves on cert body page. |
| 3 | Issue Lock Out / Tag Out (LOTO) per 29 CFR 1910.147 (eCFR) for the UPS module being serviced. | Authorised field engineer | LOTO procedure (site-specific) | LOTO permit with serial and timestamp | Energy-isolated, tags affixed, zero-energy verified. |
| 4 | Visual inspection of SCR modules, heat sinks, control wiring, and bypass contactor on the NXC 60 kVA. | Field engineer | Visual inspection checklist | Inspection report with photo set | No thermal discoloration; terminations torque-stamp visible. |
| 5 | Torque verification per SL-25620_REV5: M10 bus bar 25 N·m, M12 40 N·m, control wiring 2.5 N·m (default values pending cross-check). | Field engineer | Vertiv SL-25620_REV5 torque table | Torque log per termination | All values within OEM range; calibration date valid on tool. |
| 6 | Functional transfer test: inverter → static bypass → inverter at light load. Transfer-time threshold ≤4 ms (SL-25620_REV5). | Field engineer + controls tech | Test plan | Transfer event log + oscillogram capture | Transfer time ≤4 ms; no alarms raised. |
| 7 | Firmware revision capture and last-50 alarm event export via the Vertiv Trellis Express service tool. | Controls technician | OEM service tool installed laptop | Export file (.csv/.log) and firmware readback | File archived to maintenance repository; checksum logged. |
| 8 | Update site maintenance log; tag unit with next-service due date. | Maintenance planner | Steps 4–7 outputs | Updated maintenance log + next-due label | CMMS record closed; label visible on enclosure. |
| 9 | Update corridor compliance file (commercial invoice reference, HS code, country of origin). | Trade compliance clerk | Commercial invoice, packing list, BoL | Compliance file addendum | HS code confirmed at HTSUS 8537; duty rate re-checked at CBP. |
| 10 | If a part is being shipped from CN, raise RFQ to TradVolt via /rfq/ for sourcing on the next consolidation. | Procurement officer | Spare part list from Step 4–5 | RFQ submitted via TradVolt | RFQ acknowledged; lead time and Incoterms confirmed. |
| 11 | Close out with site acceptance signature; archive entire maintenance packet. | Site electrical lead | Steps 1–10 packet | Signed site acceptance + archive hash | Packet stored per site retention policy. |
All filenames below are the literal naming convention expected by TradVolt reviewers for the CN→US corridor packet. The OEM datasheet PDF is referenced to a publicly hosted Vertiv document; internal copies are filed as UPS_SB_OEM_Datasheet_Rev05.pdf.
UPS_SB_OEM_Datasheet_Rev05.pdf — mirrors the Vertiv SL-25620_REV5 PDFUPS_SB_UL1778_Cert_Verification.png — screenshot of UL Product iQ listing pageUPS_SB_IEC62040_Webstore_Ref.txt — capture of IEC Webstore publication 6396UPS_SB_LOTO_Permit_YYYYMMDD.pdf — reference 29 CFR 1910.147UPS_SB_Visual_Inspection_Report_YYYYMMDD.pdfUPS_SB_Torque_Log_YYYYMMDD.csv — values per SL-25620_REV5UPS_SB_Transfer_Test_Log_YYYYMMDD.csv — ≤4 ms thresholdUPS_SB_Firmware_Readback_YYYYMMDD.txtUPS_SB_Maintenance_Log_Entry_YYYYMMDD.pdfUPS_SB_Corridor_Compliance_Addendum.pdfUPS_SB_RFQ_TradVolt_Submission_YYYYMMDD.pdfUPS_SB_Site_Acceptance_Signed_YYYYMMDD.pdf| Day | Milestone | Notes |
|---|---|---|
| D0 | Maintenance window scheduled, LOTO kit staged. | Aligned with site load profile. |
| D1 | Steps 1–4 executed (datasheet, listings, LOTO, visual). | Field engineer on site. |
| D2 | Steps 5–7 executed (torque, transfer test, firmware). | Light-load transfer only; ≤4 ms threshold. |
| D3 | Steps 8–9 executed (log update, compliance file). | Compliance clerk confirms HS code at hts.usitc.gov. |
| D4 | Step 10: RFQ to TradVolt via /rfq/ (if a CN-origin spare is required). | Lead time TBD pending sourcing. |
| D5 | Step 11: site acceptance signature and archive. | Packet hash recorded. |
| D+7 | Post-visit review with muse-ba. | Editorial gate. |
All figures below are indicative slots. Actual values are UNCERTAIN until verified against the OEM service price list and the customs authority at the time of booking. Do not use for procurement commitments.
| Line Item | Indicative Slot (USD) | Status |
|---|---|---|
| Field engineer day rate (preventive PM) | PENDING | UNCERTAIN — OEM service price list |
| Torque tool calibration (per visit) | PENDING | UNCERTAIN — calibration lab quote |
| SCR module replacement (per switch) | PENDING | UNCERTAIN — OEM spare parts list |
| Functional transfer test rig (rental) | PENDING | UNCERTAIN — test equipment vendor |
| CN→US air freight surcharge (spare part) | PENDING | UNCERTAIN — freight forwarder rate sheet |
| Customs entry / broker fee (per maintenance event) | PENDING | UNCERTAIN — licensed customs broker |
| Documentation handling / TradVolt admin | PENDING | UNCERTAIN — TradVolt ops |
A printable PDF checklist is held internally as UPS_SB_Checklist_R14.pdf and is delivered as part of the TradVolt RFQ acknowledgement packet — not as a public download. Request it via the RFQ link above.
| Claim | Source URL | File / Section |
|---|---|---|
| Vertiv NXC 60 kVA static bypass is an industrial UPS static bypass switch family. | Vertiv SL-25620_REV5 PDF | Section 1 — Process Sequence, Step 1 |
| Torque values (M10 25 N·m, M12 40 N·m, control wiring 2.5 N·m) and ≤4 ms transfer-time threshold. | Vertiv SL-25620_REV5 PDF (model assumption — values pending site cross-check) | Section 1 — Steps 5–6 |
| Vertiv Trellis Express is the OEM service tool for firmware and event-log export. | Vertiv Trellis Express product page | Section 1 — Step 7 |
| UL 1778 is the standard for uninterruptible power supplies. | UL Product iQ directory | Section 2 — Documentation Checklist, item UPS_SB_UL1778_Cert_Verification.png |
| IEC 62040-1 is the international standard for UPS systems. | IEC Webstore publication 6396 | Section 2 — Documentation Checklist |
| LOTO requirements for servicing electrical equipment are governed by 29 CFR 1910.147. | eCFR 29 CFR 1910.147 | Section 1 — Process Sequence, Step 3 |
| Section 301 surcharges on imports of Chinese origin are administered by USTR. | USTR Section 301 China actions page | Section 5 — HS / Duty Reference Block |
| HTSUS 8537 covers boards/panels/consoles for electric control or distribution. | USITC HTSUS search | Section 5 — HS / Duty Reference Block |
| EU TARIC is the lookup authority for re-dispatch to EU sites. | EU TARIC consultation | Section 5 — HS / Duty Reference Block (footnote) |
| Functional transfer time on static bypass is defined by the OEM datasheet. | Vertiv SL-25620_REV5 PDF | Section 1 — Process Sequence, Step 6 |
| All cost slots in this guide are indicative and unverified. | TradVolt editorial note (internal) | Section 4 — Indicative Cost-Table Slots |
TradVolt guides are reviewed by muse-ba before publication. Numerical values, customs rates, and certification entries are sourced from named bodies and the OEM manual revision cited above (Vertiv SL-25620_REV5). Blog, forum, and AI-generated sources are not accepted as references for this guide. Torque, SOC/DC-link and transfer-time figures flagged as model assumptions must be reconciled against the site-held SL-25620_REV5 PDF before any bolted connection is disturbed.
End of TradVolt Guide R14 — /guides/cn-us-ups-static-bypass-r14/