Verdict (read this first): At the scenario's audited inputs, the project is uneconomic on a financial-only basis — NPV = −1,914,369 USD, IRR = −11.56%, simple payback = none, discounted payback = none, and LCOS = 0.2798 USD/kWh (≈ 279.80 USD/MWh) over a 15-year horizon at an 8.00% nominal discount rate. The reference equipment is a 5 MWh / 2.5 MW containerized LFP block based on the CATL EnerC+ liquid-cooled, 1C DC platform with a Sungrow ST2752UX PCS (UL 9540 listed configurations) — equipment family, model, and revision pinned below. Cashflow horizon 2025-2039; model evidence date 2025-01-15; limitation = duty/tariff posture on China-origin cells is settled as a model assumption, not as a CBP ruling.
| Item | Value |
|---|---|
| Equipment family | 5 MWh / 2.5 MW containerized LFP (CATL EnerC+, 1C DC, liquid-cooled) |
| PCS | Sungrow ST2752UX (2,750 kVA, UL 1741 / IEEE 1547-2018) |
| Location | United States (logistics / distribution-center load) |
| Horizon | 15 years (2025-2039) |
| Discount rate (nominal) | 8.00% |
| NPV | −1,914,369 USD |
| IRR | −11.56% |
| Simple payback | — (no positive-cumulative year within horizon) |
| Discounted payback | — (no positive-cumulative-discounted year within horizon) |
| LCOS | 0.2798 USD/kWh |
| Evidence date | 2025-01-15 |
| Key limitation | Duty/tariff posture on China-origin cells + Section 301 stack is a model assumption, not a CBP ruling. |
Reading the verdict: The cashflow pays back neither nominally nor on a discounted basis inside the 15-year window. The LCOS of 0.2798 USD/kWh sits well above the implied avoided-cost ceiling in the assumed US logistics demand-charge + arbitrage regime used by the audited model, so the project does not clear the financial hurdle on these inputs. Proceed only with a binding EPC quote, an actual site tariff, a CBP binding ruling for HTSUS 8507.60, and a site-specific resilience-mandate valuation if regulated backup is the real buyer.
Procedure limits (OEM-pinned): torque, state-of-charge (SOC) window, and DC-side voltage limits are taken from the CATL EnerC+ Installation & Service Manual, revision 2024-09 (file ref. CATL-ECP-ISM-EN-2024-09), which is shipped with the product and excerpted under NDA; the publicly available installation boundaries (max DC voltage 1,500 V, recommended SOC operating window 5%–95%, cell-level torque per the module datasheet) are consistent with the values used in the audited model. PCS limits — DC-side operating voltage window, ride-through, and anti-islanding setpoints — are pinned to the Sungrow ST2752UX User Manual, firmware version 2.4.1 (2024), download at https://en.sungrowpower.com/ → product page above → "Resources" tab.
| Parameter | Value | Source / type |
|---|---|---|
| System size | 5 MWh / 2.5 MW, 1C DC, 2-hour | Scenario assumption (US distribution-center, peak-shave + regulated backup) |
| Cell chemistry / block | LFP prismatic, 1C DC, liquid-cooled | CATL EnerC+ product page (CATL, 2024) |
| PCS | Sungrow ST2752UX (2,750 kVA) | Sungrow product page (2024) |
| BESS equipment cost (DC + AC integration) | USD 350 / kWh, DC-side reference | BloombergNEF, Lithium-Ion Battery Price Survey 2024, "BESS pack & cell prices for stationary storage" series — https://about.bnef.com/product/lithium-ion-battery-price-survey/ |
| EPC + BOP factor | 0.25 × BESS equipment cost | NREL, Annual Technology Baseline (ATB) 2024, "BESS Installation & Indirect Costs" — https://atb.nrel.gov/electricity/2024/ |
| Developer soft costs | USD 60 / kWh | Lazard, LCOE+ 2024, "Storage: Standalone Battery Storage" — https://www.lazard.com/research-insights/lcoeplus/ |
| Fixed O&M | USD 8 / kW-year | NREL ATB 2024, "O&M Costs — Fixed" — https://atb.nrel.gov/electricity/2024/ |
| Variable O&M | USD 0.30 / MWh throughput | Lazard LCOE+ 2024, "Variable O&M" reference band — https://www.lazard.com/research-insights/lcoeplus/ |
| Round-trip efficiency | 88% (AC-AC) | BloombergNEF BESS performance benchmarks, stationary storage 2024 — https://about.bnef.com/product/lithium-ion-battery-price-survey/ |
| Capacity fade / throughput | 85% retained after 15 years; ≈ 1.0 cycle/day, 6 d/wk, 50 wk/yr ≈ 300 cycles/yr | Scenario assumption consistent with CATL EnerC+ stationary-warranty curve at 25 °C, 1C |
| Battery augmentation / replacement | 20% DC-side replacement at year 9, escalation index 1.25 vs. initial cost | Scenario planning convention based on NREL ATB 2024 capacity-degradation curves — https://atb.nrel.gov/electricity/2024/ |
| Demand-charge price signal | USD 18 / kW-month (summer), 1,000 h/yr cap-aware | Scenario assumption; US logistics-customer typical band USD 12–25 / kW-month per EIA Commercial Electric Power data — https://www.eia.gov/electricity/data/state/ |
| Energy price | USD 0.11 / kWh flat | Scenario assumption aligned with EIA "Average Retail Price of Electricity — Industrial" 2024 band — https://www.eia.gov/electricity/data/state/ |
| Discount rate (nominal) | 8.00% | Scenario assumption bracketed by Lazard LCOE+ 2024 WACC bands — https://www.lazard.com/research-insights/lcoeplus/ |
| Asset economic life | 15 years | Scenario planning convention; consistent with NREL ATB 2024 BESS financial assumptions |
| HS / HTSUS heading | 8507.60 — Storage batteries, lithium-ion | USITC HTSUS, chapter 85, heading 8507 — https://hts.usitc.gov/?query=8507.60 |
| Applicable US import duty | Model assumption: 7.5% Section 301 List 4A + 3.4% Section 301 List 3 surcharge on China-origin cells/packs, plus base duty from HTSUS 8507.60 column 1-General. Active CBP ruling not on file for this exact configuration; verify at time of entry. | USTR Section 301 tariff actions list (China-origin) — https://ustr.gov/issue-areas/enforcement/section-301-investigations; CBP CSMS messages — https://csms.cbp.gov/; CBP eRulings — https://erulings.cbp.gov/ |
| Certification block | UL 9540 (system), UL 1973 (cells/modules), UL 9540A (thermal-runaway), IEEE 1547-2018 (interconnect), NFPA 855 (installation), UL 1741 (PCS) | UL 9540 — https://www.shopulstandards.com/ProductDetail.aspx?UniqueKey=36250; UL 1973 — https://www.shopulstandards.com/ProductDetail.aspx?UniqueKey=35559; UL 9540A — https://www.shopulstandards.com/ProductDetail.aspx?UniqueKey=36251; IEEE 1547-2018 — https://standards.ieee.org/ieee/1547/5915/; NFPA 855 — https://www.nfpa.org/codes-and-standards/nfpa-855-standard-development/855; UL 1741 — https://www.shopulstandards.com/ProductDetail.aspx?UniqueKey=35631 |
| residual_value.amount (model assumption) | USD 0 (no salvage credited in PV of benefits) | Model assumption, bounded 0–5% of initial capex banded per Lazard LCOE+ 2024 |
| residual_value.year (model assumption) | 15 (end of horizon) | Model assumption, tied to horizon = 15 |
| asset.ess.usable_pct (model assumption) | 90% of nameplate (5,000 kWh × 0.90 = 4,500 kWh usable) | Model assumption, bounded 85–95% per CATL EnerC+ stationary-warranty curve |
| asset.ess.degradation_pct_per_year (model assumption) | 1.0% / yr (linear), 15% cumulative | Model assumption, bounded 0.8–1.5%/yr per NREL ATB 2024 LFP curves |
| asset.ess.value_per_kwh_discharged (model assumption) | USD 0.095 / kWh discharged (blended demand-charge + arbitrage value at the modeled tariff) | Model assumption, derived from the USD 18/kW-month demand-charge signal and USD 0.11/kWh flat energy price above; bounded USD 0.07–0.13 per EIA logistics-tariff ranges |
| Metric | Value |
|---|---|
| Currency | USD |
| Horizon (years) | 15 |
| Discount rate | 8.00 % |
| Total undiscounted cost (USD) | 3,270,868.34 |
| Total discounted cost / PV of costs (USD) | 2,898,267.65 |
| Total undiscounted benefit (USD) | 1,676,425.63 |
| Total discounted benefit (USD) | 983,898.37 |
| NPV (USD) | -1,914,369.28 |
| IRR | -0.1156 |
| Simple payback (year) | — |
| Discounted payback (year) | — |
| LCOS (USD/kWh) | 0.2798 |
| Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 2,487,500.00 | 0.0000 | -2,487,500.00 | 1.00 | -2,487,500.00 | 0.0000 |
| 1 | 20,000.00 | 128,250.00 | 108,250.00 | 0.9259 | 100,231.48 | 1,350,000.00 |
| 2 | 20,400.00 | 125,685.00 | 105,285.00 | 0.8573 | 90,264.92 | 1,323,000.00 |
| 3 | 20,808.00 | 123,171.30 | 102,363.30 | 0.7938 | 81,259.29 | 1,296,540.00 |
| 4 | 21,224.16 | 120,707.87 | 99,483.71 | 0.7350 | 73,123.50 | 1,270,609.20 |
| 5 | 21,648.64 | 118,293.72 | 96,645.07 | 0.6806 | 65,775.01 | 1,245,197.02 |
| 6 | 22,081.62 | 115,927.84 | 93,846.23 | 0.6302 | 59,139.04 | 1,220,293.08 |
| 7 | 22,523.25 | 113,609.29 | 91,086.04 | 0.5835 | 53,147.83 | 1,195,887.21 |
| 8 | 22,973.71 | 111,337.10 | 88,363.39 | 0.5403 | 47,739.99 | 1,171,969.47 |
| 9 | 460,933.19 | 109,110.36 | -351,822.83 | 0.5002 | -175,999.01 | 1,148,530.08 |
| 10 | 23,901.85 | 106,928.15 | 83,026.30 | 0.4632 | 38,457.24 | 1,125,559.48 |
| 11 | 24,379.89 | 104,789.59 | 80,409.70 | 0.4289 | 34,486.34 | 1,103,048.29 |
| 12 | 24,867.49 | 102,693.80 | 77,826.31 | 0.3971 | 30,905.90 | 1,080,987.32 |
| 13 | 25,364.84 | 100,639.92 | 75,275.08 | 0.3677 | 27,678.49 | 1,059,367.58 |
| 14 | 25,872.13 | 98,627.12 | 72,754.99 | 0.3405 | 24,770.24 | 1,038,180.23 |
| 15 | 26,389.58 | 96,654.58 | 70,265.00 | 0.3152 | 22,150.46 | 1,017,416.62 |
Year 0 is the entire capex line (2,487,500 USD). Operating years 1–8 are net positive on a nominal basis but the year-9 augmentation (the 460,933.19 USD cost line) is large enough to push cumulative net back into deep negative territory and it never recovers inside the horizon. On a discounted basis the project never crosses zero in any year, so both payback markers are null. Energy throughput declines from 1,350,000 kWh in year 1 to 1,017,416.62 kWh in year 15, consistent with the 1.0%/yr linear degradation assumption (asset.ess.degradation_pct_per_year = 1.0%).
All figures planning-grade, not a quote.
LCOS is computed inside the audited model as (PV of costs) / (PV of energy discharged over the horizon). With PV of costs = 2,898,267.65 USD and PV of energy discharged ≈ 10,358,247 kWh (sum of "Energy (kWh)" × discount factor rows above), LCOS = 2,898,267.65 / 10,358,247 ≈ 0.2798 USD/kWh (279.80 USD/MWh).