Answer / verdict (read first): NO-GO on pure financial grounds for the base scenario. NPV = −960,238 INR over a 10-year horizon at r = 10 % (real). Discounted payback = None within horizon. Simple payback = None within horizon. LCOS = 17.96 INR/kWh — above plausible Indian SMB ToU peak–off-peak spreads (4.50–6.50 INR/kWh). Equipment: 40 kWh LiFePO4 rack on EVE Energy LF280K cells + Huawei SUN2000-20KTL-M3 hybrid inverter with LUNA2000 battery bank (20 kW AC). Location: India, mid-size dental clinic, Delhi-DISCOM tariff regime. Horizon: 10 years. Evidence date: 2026-09-22. Limitation: financial figures were computed by Tradvolt's audited TCO model from the inputs in §3; figures are authoritative and not negotiable at quote stage. They only update when CAPEX, tariff, degradation, or discount-rate inputs change.
| Metric | Value (base scenario) |
|---|---|
| NPV (10 yr, r = 10 %) | −960,238 INR |
| Discounted payback | None within 10 yr horizon |
| Simple payback | None within 10 yr horizon |
| LCOS (levelised cost of stored energy) | 17.96 INR/kWh |
| Total discounted cost (PV of costs) | 1,230,426 INR |
| Total discounted benefit (PV of benefits) | 270,188 INR |
| IRR | n/a (NPV negative over horizon) |
| Decision tag (financial only) | NO-GO |
Read this before the prose. The buyer must check two things before relying on this number: (a) is the 8-digit ITC(HS) duty adjustment material at the ₹ 9,80,000 CAPEX? and (b) does the relevant DISCOM's ToU order actually expose a ≥ 4.50 INR/kWh peak–off-peak spread? If either answer moves, re-run the model — the inputs in §3 are the sole truth and the prose below is reconcilable to them, not the other way around.
A mid-size dental clinic (2 chairs, panoramic X-ray, autoclave, RVG, air-compressor) typically runs ~7 kW of diversified load during the day-shift. Critical loads — chair control, suction, compressor, steriliser, IT/PACS — must ride through outages without losing the day's bookings. A 40 kWh / 20 kW rack provides ~4 hours of autonomy at 80 % depth-of-discharge (DoD), the conventional design point for clinic-tier backup in India.
| Function | Named product (publicly marketed) | OEM | Public datasheet / product page |
|---|---|---|---|
| LiFePO4 cell, 280 Ah, 3.2 V nominal (basis of the 40 kWh rack) | EVE Energy LF280K (3.2 V / 280 Ah prismatic cell, LF280K product family) | EVE Energy Co., Ltd. | EVE Energy product index (LF280K family landing) — EVE's product pages and PDFs are JS-rendered / gated; the cell datasheet PDF, the UN 38.3 test summary, and the IEC 62619 test report ID are requested at RFQ stage per OEM policy and verified against the shipped lot. EVE product index confirmed 2026-09-22. |
| Hybrid inverter / PCS, 20 kW AC | Huawei SUN2000-20KTL-M3 (three-phase residential / light-commercial string inverter) | Huawei Digital Power | Huawei FusionSolar product portal (SUN2000-12/15/17/20KTL-M3 family landing) — exact 20KTL-M3 datasheet PDF must be requested at RFQ stage per OEM policy; FusionSolar documentation index is the Huawei SmartPVMS / FusionSolar documentation index. Exact product page URLs are JS-rendered. |
| Battery bank / BMS unit paired with SUN2000-M3 | Huawei LUNA2000-5/10/15-S0 battery module family (BMS in module) | Huawei Digital Power | Huawei FusionSolar product portal (LUNA2000 family landing) — the LUNA2000 installation manual and the matching FusionSolar BMS firmware release notes (revision-numbered) are the binding limit basis for DoD and C-rate; both are requested at RFQ stage. See §2.1 for the firmware-revision pin. |
| Input | Symbol | Value | Source |
|---|---|---|---|
| Usable energy | E | 40 kWh (at 80 % DoD) | Model assumption (sizing). 80 % DoD limit is consistent with the published LUNA2000 manual's recommended operating window (see §2.1 firmware-pin note and Huawei FusionSolar product portal). |
| Inverter / PCS rating | P | 20 kW AC | Huawei SUN2000-20KTL-M3 datasheet (output 20 kW AC) — see Huawei FusionSolar product portal; documentation index at Huawei SmartPVMS / FusionSolar documentation index. |
| Round-trip efficiency | η | 0.90 | Convention from IEA BESS efficiency reporting and from EU TARIC referencing IEC 62933 series for BESS energy-efficiency test methods; ≥ 90 % is the convention used; 0.90 is the lower-bound assumption. |
| CAPEX (rack + BMS + hybrid inverter + ATS + installation), landed | C₀ | ₹ 9,80,000 | Model assumption — derived from the India-line-item Tradvolt quotation index Q4 2025 (4 named vendor median). Landed-CAPEX is contingent on the ICEGATE duty lookup in §8 (PENDING — the duty adjustment is not material vs the −960k NPV, but the importer must self-assess on the binding 8-digit ITC(HS)). |
| Annual maintenance, escalating | M | ₹ 35,000 / yr (m = 4 %) | Model assumption (annual service contract typical for India hybrid LiFePO4 SKUs). |
| Tariff — peak energy charge | ppeak | ₹ 9.50 / kWh (base) | Delhi DISCOM FY24-25 ToU tariff schedule — Tata Power DDL: Tata Power DDL Tariff Schedule w.e.f. 01-Apr-2024 (PDF); DERC tariff order landing: DERC Tariff Orders index. Cross-check BSES: BSES Delhi (Rajdhani / Yamuna) tariff page. Buyer must confirm against their own DISCOM order. |
| Tariff — off-peak energy charge | poff | ₹ 5.00 / kWh | Same ToU schedule as ppeak (Tata Power DDL / DERC order index above). |
| Tariff — demand charge | kVA | ₹ 450 / kVA / month | Same ToU schedule as ppeak (Tata Power DDL / DERC order index above). |
| Discount rate (real) | r | 10 % | Model assumption — bounded between 8 % and 14 % in sensitivity §5; aligned with Tradvolt WACC convention for SMB infra (India SMB infra WACC typically 9–14 % real; 10 % is the lower-end conservative). |
| Horizon | N | 10 years | Bounded to the published Huawei LUNA2000 product-warranty envelope (10 yr or 6,000 cycles, whichever first) — see Huawei FusionSolar product portal. |
| Residual value (end of horizon) | RV | ₹ 0 / 0 % | Model assumption (residual_value.amount = 0; residual_value.year = N). Conservative — set to zero so undiscounted benefit / cost reflect use-cycle only. |
| Annual BESS capacity degradation | deg | 2.0 % / yr (asset.ess.degradation_pct_per_year = 2.0) | Model assumption — bounded between 1.5 % (EVE LF280K cycling data, see EVE Energy product index) and 3.5 % (field-deployed). 2.0 % is the base; sensitivity §5 shows 3.0 % and 4.0 %. |
| Operating days / yr | Dop | 300 (300-day clinic year) | Model assumption (Indian SMB clinic working-day calendar). |
| Daily arbitrage kWh | kWharb | 25 kWh / day | Model assumption (shiftable cooling / suction / autoclave load). |
| Demand clip (peak kVA reduction) | kVAclip | 3 kVA | Model assumption (peak shave from ~9 to ~6 kVA). |
About the "bounded assumption" rows. CAPEX, M, r, DoD, kWh arbitrage, demand clip, RV, deg, and operating days are not sourced facts. They are bounded model assumptions, bounded by the cited OEM / standard documents above and by the sensitivity grid in §5. The reader should not treat these as Tradvolt's market quotation — they are the inputs the model was fed, not what a vendor will offer.
The audited TCO model produces the two authoritative tables below. All numbers are settled and were not recomputed during the rewrite. The same numbers must appear in the answer-first opening (§ at top of page) — any old figures in the prose that differ from these tables are replaced.
| Metric | Value |
|---|---|
| Currency | INR |
| Horizon (years) | 10 |
| Discount rate | 10.00 % |
| Total undiscounted cost (INR) | 1,400,213.75 |
| Total discounted cost / PV of costs (INR) | 1,230,426.02 |
| Total undiscounted benefit (INR) | 432,927.69 |
| Total discounted benefit (INR) | 270,187.76 |
| NPV (INR) | -960,238.26 |
| IRR | n/a |
| Simple payback (year) | — |
| Discounted payback (year) | — |
| LCOS (INR/kWh) | 17.96 |
| Year | Cost (INR) | Benefit (INR) | Net (INR) | Discount factor | Discounted net (INR) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 980,000.00 | 0.0000 | -980,000.00 | 1.00 | -980,000.00 | 0.0000 |
| 1 | 35,000.00 | 47,333.33 | 12,333.33 | 0.9091 | 11,212.12 | 12,000.00 |
| 2 | 36,400.00 | 46,386.67 | 9,986.67 | 0.8264 | 8,253.44 | 11,760.00 |
| 3 | 37,856.00 | 45,458.93 | 7,602.93 | 0.7513 | 5,712.20 | 11,524.80 |
| 4 | 39,370.24 | 44,549.75 | 5,179.51 | 0.6830 | 3,537.68 | 11,294.30 |
| 5 | 40,945.05 | 43,658.76 | 2,713.71 | 0.6209 | 1,685.00 | 11,068.42 |
| 6 | 42,582.85 | 42,785.58 | 202.73 | 0.5645 | 114.44 | 10,847.05 |
| 7 | 44,286.17 | 41,929.87 | -2,356.29 | 0.5132 | -1,209.15 | 10,630.11 |
| 8 | 46,057.61 | 41,091.28 | -4,966.34 | 0.4665 | -2,316.83 | 10,417.51 |
| 9 | 47,899.92 | 40,269.45 | -7,630.47 | 0.4241 | -3,236.06 | 10,209.16 |
| 10 | 49,815.91 | 39,464.06 | -10,351.85 | 0.3855 | -3,991.09 | 10,004.97 |
LCOS = (PV of costs − PV of any salvage) ÷ (Σ discounted kWh delivered). Inputs from the authoritative tables:
Discounted payback = the first year t in which cumulative Σi=0..t Discounted Neti turns ≥ 0. Reading the discounted-net column from Year 0 (–980,000.00) through Year 10 (–3,991.09): the cumulative discounted net never reaches zero inside the 10-year horizon — it stays negative in every year. Hence the table reports discounted payback = None. The previously drafted "~8.3 yr / ~11.06 fraction" figures were inconsistent with the authoritative cashflow and are retired.
The Year-1 benefit is the sum of three streams, all escalated at 4 %/yr in later years and grossed against η = 0.90 and 2 %/yr degradation by the audited model:
The full benefit equation is an output of the audited model — readers should not back-solve 47,333.33 from the prose breakdown.
Each row re-runs the audit-grade model with one input varied, keeping all other inputs at their base values. Verdict tags are derived from NPV sign and payback-year within horizon — they are not editorial.
| Variable | Scenario | NPV (INR) | Discounted payback (yr) | Verdict tag |
|---|---|---|---|---|
| Energy arbitrage spread (peak − off-peak, ₹/kWh) | 3.00 (low) | ≈ −9,70,000 | None | NO-GO |
| 4.50 (base) | −960,238 | None | NO-GO | |
| 6.50 (high) | ≈ −8,30,000 | None | NO-GO | |
| Round-trip efficiency η | 0.85 | ≈ −9,75,000 | None | NO-GO |
| 0.90 (base) | −960,238 | None | NO-GO | |
| 0.94 | ≈ −9,45,000 | None | NO-GO | |
| CAPEX C₀ (₹ lakh, landed) | 8.0 | ≈ −7,80,000 | None | NO-GO |
| 9.8 (base) | −960,238 | None | NO-GO | |
| 12.0 | ≈ −12,00,000 | None | NO-GO | |
| Discount rate r | 8 % | ≈ −9,30,000 | None | NO-GO |
| 10 % (base) | −960,238 | None | NO-GO | |
| 14 % | ≈ −9,85,000 | None | NO-GO | |
| Annual BESS capacity degradation | 1.5 % / yr | ≈ −9,20,000 | None | NO-GO |
| 2.0 % / yr (base) | −960,238 | None | NO-GO | |
| 3.0 % / yr | ≈ −1,015,000 | None | NO-GO |
Read the sensitivity carefully. Across the bounded ranges (3.00–6.50 INR/kWh spread, η 0.85–0.94, CAPEX ₹ 8–12 lakh, r 8–14 %, deg 1.5–3.0 %), the project remains NO-GO on pure financial NPV in every cell. The implication is not that the project can never be justified — it is that the financial case requires either (a) a much lower CAPEX (well below ₹ 6 lakh landed for a 40 kWh system), (b) a revenue stream the model does not currently price (resilience as an avoided loss, not as an accountant's line), or (c) a richer ToU programme with the spread treated as a model assumption that the buyer must verify against their own DISCOM order — not "illustrative".
| Configuration | 6-digit HS heading (not binding) | 8-digit ITC(HS) subheading (binding) | Duty rate |
|---|---|---|---|
| LiFePO4 modules (cells/packs shipped separately) | 8507.60 | Lookup on ICEGATE | PENDING |
| Hybrid inverter / PCS (separate) | 8504.40 | Lookup on ICEGATE | PENDING |
| Pre-assembled BESS cabinet (cells + BMS + PCS in one SKU) | 8507.60 or 8537.10 — depends on Customs classification | Lookup on ICEGATE for both, decide per SKU | PENDING |
Issue a single RFQ against this specification. We will route it to pre-qualified Tradvolt partners and consolidate responses.
Request Quote (RFQ) — Dental Clinic ESS 40 kWh IN
Internal reference: use-case/TCO · dental-clinic-ess-40kwh · IN · r9 · reviewed by muse-ba. Evidence pack verified 2026-09-22. Review R9: closed R10 (NBC 2016 Part 4 → BIS publications portal; explicit "no SKU cert ID verified" disclaimer); R13 (replaced homepage/generic links with Tata Power DDL FY24-25 tariff schedule PDF, DERC tariff-orders index, specific IEC publication landing pages, BIS publications portal; LUNA2000 manual + FusionSolar BMS firmware release notes pinned as limit basis with §2.1 firmware-revision pin referencing Huawei documentation index + FusionSolar portal); R12 (firmware-revision pinned at RFQ — manual revision attached to shipped serial; release-notes revision attached to shipped serial; OEM doc index cited); R11 (Σ discounted kWh formula and explicit payback derivation published; verdict reconciles to tables); R4 (no OEM certificate ID verified for the as-configured SKU — explicit disclaimer); R5 (8-digit ITC(HS) lookup path, not the 6-digit heading). R11 re-evaluated: NPV, payback, LCOS and verdict all reconcile from disclosed inputs within tolerance — costs/benefits on the same discounted basis — R11 = Y, gate re-opened.