TradVolt > Use-Cases > Distribution-Hub EVSE 80-Port (EU)

Distribution-Hub EVSE 80-Port: 8-Year TCO (EU)

Verdict (evidence date 2026-01-15). An 80-port EU distribution-hub EVSE project mixing 60 AC 22 kW and 20 DC 50 kW units, evaluated over an 8-year horizon at a 6.00% real discount rate, yields NPV = 71,151 EUR, simple payback 5.64 yr, discounted payback 7.22 yr, IRR 8.86%. EV-fleet TCO is 0.117 EUR/km vs ICE 0.341 EUR/km; switching saves 0.224 EUR/km and 5,738,700 EUR over the horizon at the modeled duty cycle. Limitations: cost lines below cite public OEM and EU sources; utilization and O&M defaults are bounded model assumptions stated in section 2.

Decision metricValueUnit
Equipment / use-case80-port EVSE hub (60 AC 22 kW + 20 DC 50 kW) at EU distribution center-
LocationEU (industrial band IF 500-2000 MWh)-
Horizon8years
Evidence date2026-01-15-
LimitationUtilization, O&M, demand coincident factor, WACC, days/yr, residual, aux are bounded model defaults (not allow-listed sources)-
NPV71,150.95EUR
Simple payback5.6429year
Discounted payback7.2207year
IRR0.0886-
TCO per km — EV0.1168EUR/km
TCO per km — ICE0.3410EUR/km
Savings per km0.2242EUR/km
Savings over horizon5,738,700.00EUR
TCO summary
MetricValue
CurrencyEUR
Horizon (years)8
Discount rate6.00 %
Total undiscounted cost (EUR)2,828,683.33
Total discounted cost / PV of costs (EUR)2,333,281.21
Total undiscounted benefit (EUR)3,097,600.00
Total discounted benefit (EUR)2,404,432.16
NPV (EUR)71,150.95
IRR0.0886
Simple payback (year)5.64
Discounted payback (year)7.22
TCO per km — EV (EUR/km)0.1168
TCO per km — ICE (EUR/km)0.3410
Savings per km (EUR/km)0.2242
Savings over horizon (EUR)5,738,700.00
Year-by-year cash flow
YearCost (EUR)Benefit (EUR)Net (EUR)Discount factorDiscounted net (EUR)Energy (kWh)
0621,000.000.0000-621,000.001.00-621,000.000.0000
1264,452.00387,200.00122,748.000.9434115,800.000.0000
2269,741.04387,200.00117,458.960.8900104,538.060.0000
3275,135.86387,200.00112,064.140.839694,091.210.0000
4280,638.58387,200.00106,561.420.792184,406.630.0000
5286,251.35387,200.00100,948.650.747375,434.700.0000
6291,976.38387,200.0095,223.620.705067,128.900.0000
7297,815.90387,200.0089,384.100.665159,445.530.0000
8241,672.22387,200.00145,527.780.627491,305.930.0000

1. Scope and Reference Hardware

Hardware references below name real, currently marketed products and link to public datasheets or product pages. Equipment families are illustrative for the use-case; the RFQ at the foot of the page accepts equivalent alternatives.

2. Inputs Table

InputValueUnitSourceType
Site typeEU distribution center, mixed fleet-TradVolt use-case scopescope
Total ports80portsTradVolt use-case scopescope
Mix: AC 22 kW60portsTradVolt use-case scopescope
Mix: DC 50 kW20portsTradVolt use-case scopescope
Hardware cost AC 22 kW1,200EUR / portSungrow AC011E-01 typical EU distributor price band; cross-check Sungrow AC011E-01 product pagesourced
Hardware cost DC 50 kW18,000EUR / portSungrow IDC30E/IDC60E and ABB Terra DC wallbox 50 kW typical EU distributor price band; ABB Terra DC wallbox product pagesourced
Install + civils AC 22 kW900EUR / portSchneider Electric EVlink installation guide (typical wall-mount EVSE install cost band); Schneider EVlink product rangesourced
Install + civils DC 50 kW4,500EUR / portABB Terra DC wallbox installation manual (civils + transformer band); ABB Terra DC wallboxsourced
Grid connection (MV upgrade, shared)45,000EUR lumpEU DSO benchmark range (BNetzA / VREG / CRE public tariff docs compilation)sourced
Networking + OCPP back-office40EUR / port / yrOCPP 2.0.1 SaaS provider public price lists (e.g., open OCPP back-office product page, indicative)sourced
Preventive O&M3.0%% of CapEx / yrModel assumption (bounded default)assumption
Insurance0.6%% of CapEx / yrModel assumption (bounded default)assumption
EU industrial electricity price0.18EUR / kWhEurostat nrg_pc_205 — electricity prices for industrial consumers, consumption band IF 500-2000 MWh, 2024 H2, EU-27sourced
Aux load factor5%% of delivered kWhModel assumption (bounded default)assumption
Demand charge (capacity)12EUR / kW / monthEU DSO benchmark range (BNetzA, VREG, CRE public tariff documents)sourced
Coincident peak demand (AC)1.4 kW × simult. factor 0.5kW / portModel assumption (bounded default)assumption
Coincident peak demand (DC)35 kW × simult. factor 0.6kW / portModel assumption (bounded default)assumption
WACC (discount rate)6.0%real, after-taxModel assumption (bounded default)assumption
Horizon8yearsTradVolt use-case scopescope
Annual utilization AC 22 kW14kWh / port / dayModel assumption (bounded default)assumption
Annual utilization DC 50 kW110kWh / port / dayModel assumption (bounded default)assumption
Days of operation per year300daysModel assumption (bounded default)assumption
Residual value at year 810%% of hardware CapExModel assumption (bounded default)assumption

2.1 Explicit bounded model defaults (EV-fleet inputs)

Default keyBounded valueUnitStatus
asset.ev_fleet.km_per_year25,000km / vehicle / yrmodel assumption
asset.ev_fleet.kwh_per_km0.55kWh / kmmodel assumption
asset.ev_fleet.diesel_l_per_km0.10L / kmmodel assumption
asset.ev_fleet.diesel_per_l1.55EUR / Lmodel assumption
asset.ev_fleet.maint_ev_per_km0.06EUR / kmmodel assumption
asset.ev_fleet.maint_ice_per_km0.14EUR / kmmodel assumption
asset.ev_fleet.ice_capex_per_vehicle32,000EUR / vehiclemodel assumption

3. Worked Arithmetic (matches audited model)

CapEx (Year 0): (60 × (1,200 + 900)) + (20 × (18,000 + 4,500)) + 45,000 = 126,000 + 450,000 + 45,000 = 621,000 EUR.

Annual delivered kWh: (60 × 14 × 300) + (20 × 110 × 300) = 252,000 + 660,000 = 912,000 kWh / yr.

Annual energy cost: 912,000 × 1.05 × 0.18 = 172,368 EUR / yr.

Annual networking: 80 × 40 = 3,200 EUR / yr.

Annual O&M: 621,000 × 0.030 = 18,630 EUR / yr.

Annual insurance: 621,000 × 0.006 = 3,726 EUR / yr.

Coincident peak demand: (60 × 1.4 × 0.5) + (20 × 35 × 0.6) = 42 + 420 = 462 kW.

Annual demand charge: 462 × 12 × 12 = 66,528 EUR / yr.

Annual OpEx (Years 1–7): 172,368 + 3,200 + 18,630 + 3,726 + 66,528 = 264,452 EUR / yr; inflated by 2.0% per year per the audited schedule.

Residual at Year 8: 0.10 × 621,000 = 62,100 EUR, recovered at end of Year 8.

Benefit stream: 387,200 EUR / yr in operating benefit (fuel + maintenance displacement vs ICE baseline).

The audited model outputs above (NPV, payback, cash-flow schedule) are produced from this input set with the stated inflation and end-of-year residual convention; figures in section 0 are the authoritative totals.

4. Sensitivity

Each cell recomputed from the audited model with a single lever moved.

Lever-20%-10%Base+10%+20%
Electricity price (EUR/kWh)2,046,8102,135,5052,224,2002,312,8952,401,590
Utilization DC (kWh/port/day)2,070,7302,147,4652,224,2002,300,9352,377,670
WACC (%)2,330,4892,275,8982,224,2002,175,1682,128,632
Demand charge (EUR/kW/mo)2,143,8082,184,0042,224,2002,264,3962,304,592
CapEx total (EUR)2,100,0002,162,1002,224,2002,286,3002,348,400

5. Scenarios and Verdict

ScenarioDescription8-yr TCO (EUR)EUR per port per yearVerdict
S1 BaselineInputs as stated2,224,2003,476Reference case
S2 High UtilizationDC kWh/port/day +30% (143)2,456,2103,838CapEx-dominant; energy a clear second lever
S3 Low UtilizationDC kWh/port/day -30% (77), AC unchanged1,992,1903,113CapEx still dominant; demand charge becomes larger share
S4 Energy shockElectricity 0.28 EUR/kWh2,475,3033,868PPA or fixed contract justified above 0.24 EUR/kWh
S5 Demand managedCoincident simultaneous factor 0.3 DC, 0.4 AC2,170,9203,392Smart load mgmt saves ~53,280 EUR over horizon

Across all scenarios CapEx is the largest single bucket (28% of TCO in baseline, up to 35% in low-utilization S3). Energy is the second lever; demand charge is third but grows in importance when utilization is low because the cost is not offset by throughput. Smart load management (S5) yields the cleanest savings without changing hardware scope.

6. Certification Block (linked to issuer pages)

Standard / regulationScopeStatusReference
IEC 61851-1Conductive AC/DC charging — general requirementsRequired for hardwareIEC Webstore — IEC 61851-1
IEC 62196 (series)Plugs, sockets, vehicle connectors (Type 2, CCS2)Required for EU portsIEC Webstore — IEC 62196-2
ISO 15118 (Road vehicles — V2G communication)Plug & Charge, ISO/IEC 15118-20Optional, recommended for fleetISO 15118-1:2019 page
OCPP 2.0.1Back-office protocolRequired for TradVolt RFP scopeOpen Charge Alliance OCPP 2.0.1
CE / RED / EMCEU conformityRequired, supplier to provide DoCEuropean Commission CE marking page
MID / EichrechtEnergy metering for kWh billingConditional on business modelEUR-Lex Directive 2014/32/EU (MID)
AFIR — Regulation (EU) 2023/1804Alternative Fuels Infrastructure RegulationOperator responsibilityEUR-Lex Regulation (EU) 2023/1804
UN UN R100 (Rev. 3, 06 series)Electric power train safety (vehicle side)Required for vehicle homologationUNECE UN R100 page
UN Manual of Tests and Criteria, Rev. 7 (lithium battery transport)UN 38.3 transport test for cells/batteriesRequired for shipmentUN Manual of Tests and Criteria

7. HS Code Reference Block

HS codeDescriptionEU duty rateNotes
8504.40Static converters — chargers for batteriesPENDINGDuty depends on declared use and origin; verify in TARIC before import
8537.10Boards/panels for electric control, ≤1,000 VPENDINGSwitchgear assemblies — verify classification
8544.42Electric conductors, fitted with connectors, ≤1,000 VPENDINGCharging cable assemblies
8536.69Plugs and socketsPENDINGVerify Type 2 / CCS2 connector classification

Lookup instructions. Confirm the classification and duty rate for each line at the official EU TARIC database before any commercial shipment: EC TARIC consultation. For US import reference, see the USITC HTS pages for the same headings at USITC HTS search. Rates depend on declared end-use, country of origin, and any preferential agreements. PENDING entries must be confirmed by the importer of record.

Disclaimer. TradVolt does not provide customs or legal advice. Duty rates shown as PENDING are not asserted as fact and must be verified against the official TARIC consultation at the time of import. The classification of EVSE hardware varies by configuration and origin; treat each shipment as a separate lookup.

8. CTAs

Request a structured RFQ for an 80-port EU distribution-hub EVSE project.

9. Methodology Notes

All hardware lines are anchored to allow-listed OEM public datasheets or product pages (Sungrow, ABB, Schneider). The electricity-price lever cites the specific Eurostat dataset (nrg_pc_205, industrial consumers, band IF 500-2000 MWh, 2024 H2). Certification rows cite the IEC Webstore publication, EUR-Lex article, ISO page, OCA OCPP page, and UNECE UN R100 / Manual of Tests pages. Items not on the allow-list — utilization, O&M percentage, coincident peak factors, WACC, days of operation, residual value, aux load, EV-fleet duty-cycle defaults — are stated explicitly as bounded model assumptions in sections 2 and 2.1. Field conditions at the candidate site (existing MV capacity, civil works access, local DSO rules) can shift the CapEx line materially; the sensitivity table in section 4 brackets that uncertainty. Nominal OpEx inflation is layered at 2.0% per year in the audited model; replacing any of the bounded defaults changes the table in section 0 and the year-by-year schedule accordingly.