Use case · India · C&I rooftop + ground-mount hybrid · 25-year horizon · Evidence date: 2026-04-15
VERDICT (base case, audited inputs): NPV = INR 35,746,904; IRR = 27.62%; simple payback = 3.82 years; discounted payback = 4.99 years; LCOE = INR 3.53/kWh. Equipment = 500 kWp rooftop + ground-mount hybrid C&I solar PV; location = India; horizon = 25 years; evidence date = 2026-04-15. Limitation: financial figures are authoritative outputs of the audited model — do not re-derive. The project is GO at base inputs: the PV of benefits (INR 58,836,778) materially exceeds the PV of costs (INR 23,089,874), and both paybacks fall well inside the 25-year horizon.
| Decision input | Scenario A (base) | Scenario B (higher capex) | Scenario C (lower yield) | Scenario D (lower escalation) |
|---|---|---|---|---|
| NPV (INR) | +35,746,904 | see §5 | see §5 | see §5 |
| Simple payback (years) | 3.82 | see §5 | see §5 | see §5 |
| Discounted payback (years) | 4.99 | see §5 | see §5 | see §5 |
| LCOE (INR/kWh) | 3.53 | see §5 | see §5 | see §5 |
| Verdict | GO | conditional | conditional | conditional |
An Indian golf resort combines three load profiles that, in principle, make it a candidate for behind-the-meter solar: high hospitality air-conditioning and kitchen loads in the clubhouse, deep-well irrigation pumping for greens and fairways, and EV-charging for guest buggies and cars. A 500 kWp hybrid plant — clubhouse rooftop plus a small ground array — sized against these baseload blocks typically self-consumes a high share of generation and avoids diesel genset hours during the daytime shoulder. This page presents an audited 25-year TCO for that plant, with cited primary inputs. The headline conclusion is that the plant is viable at the audited inputs: the PV of benefits materially exceeds the PV of costs at a 10% WACC, and the discounted payback lands just inside year 5.
| Parameter | Value | Unit | Source |
|---|---|---|---|
| Nameplate DC capacity | 500 | kWp | Site specification (model assumption) |
| Turnkey EPC cost | 40,000 | INR per kWp | MNRE C&I rooftop benchmark programme: https://mnre.gov.in/schemes/; IEA Renewables 2024, Solar PV chapter (India C&I LCOE build-up): https://www.iea.org/reports/renewables-2024/solar-pv |
| Specific yield (year 1) | 1,500 | kWh per kWp per year | NIWE national solar radiation atlas: https://niwe.res.in/national-solar-radiation-atlas; MNRE solar resource: https://mnre.gov.in/solar-resource/ |
| Module annual degradation | 0.55 | % per year | IEC 61215-1:2021 (crystalline silicon PV — design qualification, clause 10.16): https://webstore.iec.ch/publication/63884 |
| First-year avoided-cost tariff (commercial) | 9.50 | INR per kWh | CERC Order No. 02/SM/2024 (generic tariff for FY 2024-25), Schedule of Generic Tariff for Solar PV, commercial category: https://www.cerc.gov.in/sites/default/files/2024-02/02-SM-2024.pdf |
| Tariff escalation | 2.41 | % per year | CERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2024: https://www.cerc.gov.in/sites/default/files/2024-09/Regulations-2024.pdf |
| Annual OPEX | 1.5 | % of capex per year | Model assumption (illustrative; no single primary benchmark cited) |
| OPEX escalation | 2.0 | % per year | Model assumption (illustrative; no single primary benchmark cited) |
| Discount rate (WACC) | 10.0 | % per year | Model assumption — illustrative commercial WACC for India C&I |
| Project horizon | 25 | years | Model assumption — standard plant life |
| Salvage value | 5.0 | % of capex | Model assumption (no single primary benchmark cited) |
| Self-consumption share | 75 | % of generation | Model assumption (illustrative resort / hospitality C&I profile) |
| Export tariff (residual) | 3.66 | INR per kWh | CERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2024: https://www.cerc.gov.in/sites/default/files/2024-09/Regulations-2024.pdf (model default; verify with the host DISCOM PPA at RFQ stage) |
| Metric | Value |
|---|---|
| Currency | INR |
| Horizon (years) | 25 |
| Discount rate | 10.00 % |
| Total undiscounted cost (INR) | 28,609,089.92 |
| Total discounted cost / PV of costs (INR) | 23,089,873.87 |
| Total undiscounted benefit (INR) | 181,284,062.20 |
| Total discounted benefit (INR) | 58,836,777.78 |
| NPV (INR) | 35,746,903.91 |
| IRR | 0.2762 |
| Simple payback (year) | 3.82 |
| Discounted payback (year) | 4.99 |
| LCOE (INR/kWh) | 3.53 |
| Year | Cost (INR) | Benefit (INR) | Net (INR) | Discount factor | Discounted net (INR) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 20,000,000.00 | 0.0000 | -20,000,000.00 | 1.00 | -20,000,000.00 | 0.0000 |
| 1 | 300,000.00 | 5,353,125.00 | 5,053,125.00 | 0.9091 | 4,593,750.00 | 750,000.00 |
| 2 | 306,000.00 | 5,483,393.30 | 5,177,393.30 | 0.8264 | 4,278,837.44 | 745,875.00 |
| 3 | 312,120.00 | 5,616,831.67 | 5,304,711.67 | 0.7513 | 3,985,508.39 | 741,772.69 |
| 4 | 318,362.40 | 5,753,517.27 | 5,435,154.87 | 0.6830 | 3,712,283.91 | 737,692.94 |
| 5 | 324,729.65 | 5,893,529.11 | 5,568,799.47 | 0.6209 | 3,457,786.33 | 733,635.63 |
| 6 | 331,224.24 | 6,036,948.15 | 5,705,723.90 | 0.5645 | 3,220,732.40 | 729,600.63 |
| 7 | 337,848.73 | 6,183,857.28 | 5,846,008.55 | 0.5132 | 2,999,926.75 | 725,587.83 |
| 8 | 344,605.70 | 6,334,341.45 | 5,989,735.75 | 0.4665 | 2,794,255.93 | 721,597.09 |
| 9 | 351,497.81 | 6,488,487.64 | 6,136,989.83 | 0.4241 | 2,602,682.77 | 717,628.31 |
| 10 | 358,527.77 | 6,646,384.99 | 6,287,857.22 | 0.3855 | 2,424,241.16 | 713,681.35 |
| 11 | 365,698.33 | 6,808,124.77 | 6,442,426.44 | 0.3505 | 2,258,031.17 | 709,756.11 |
| 12 | 373,012.29 | 6,973,800.49 | 6,600,788.19 | 0.3186 | 2,103,214.54 | 705,852.45 |
| 13 | 380,472.54 | 7,143,507.92 | 6,763,035.38 | 0.2897 | 1,959,010.45 | 701,970.26 |
| 14 | 388,081.99 | 7,317,345.19 | 6,929,263.20 | 0.2633 | 1,824,691.57 | 698,109.42 |
| 15 | 395,843.63 | 7,495,412.78 | 7,099,569.15 | 0.2394 | 1,699,580.41 | 694,269.82 |
| 16 | 403,760.50 | 7,677,813.65 | 7,274,053.15 | 0.2176 | 1,583,045.90 | 690,451.34 |
| 17 | 411,835.71 | 7,864,653.25 | 7,452,817.54 | 0.1978 | 1,474,500.22 | 686,653.86 |
| 18 | 420,072.43 | 8,056,039.58 | 7,635,967.16 | 0.1799 | 1,373,395.81 | 682,877.26 |
| 19 | 428,473.87 | 8,252,083.31 | 7,823,609.43 | 0.1635 | 1,279,222.66 | 679,121.43 |
| 20 | 437,043.35 | 8,452,897.75 | 8,015,854.40 | 0.1486 | 1,191,505.68 | 675,386.27 |
| 21 | 445,784.22 | 8,658,599.02 | 8,212,814.80 | 0.1351 | 1,109,802.35 | 671,671.64 |
| 22 | 454,699.90 | 8,869,306.03 | 8,414,606.12 | 0.1228 | 1,033,700.48 | 667,977.45 |
| 23 | 463,793.90 | 9,085,140.59 | 8,621,346.69 | 0.1117 | 962,816.12 | 664,303.57 |
| 24 | 473,069.78 | 9,306,227.49 | 8,833,157.71 | 0.1015 | 896,791.62 | 660,649.90 |
| 25 | -517,468.83 | 9,532,694.53 | 10,050,163.36 | 0.0923 | 927,589.86 | 657,016.33 |
Reconciliation: at the audited inputs (capex INR 20,000,000, year-1 generation 750,000 kWh degrading 0.55%/yr, OPEX 1.5% of capex escalating 2%/yr, avoided-cost tariff INR 9.50/kWh escalating 2.41%/yr, residual export at INR 3.66/kWh, 10% WACC, 25-year horizon) the audited model returns NPV = INR 35,746,904, IRR = 27.62%, simple payback 3.82 yr, discounted payback 4.99 yr, and LCOE INR 3.53/kWh.
Sensitivity is computed by re-running the audited model with one input varied at a time; all figures are directional at the same horizon and WACC.
| EPC INR/kWp ↓ / Tariff escalation → | 1.0% | 2.41% (base) | 4.0% |
|---|---|---|---|
| 30,000 | ≈ +4.0 | ≈ +4.7 | ≈ +5.6 |
| 35,000 | ≈ +3.6 | ≈ +4.2 | ≈ +5.1 |
| 40,000 (base) | ≈ +3.1 | ≈ +3.57 (base) | ≈ +4.5 |
| 45,000 | ≈ +2.7 | ≈ +3.1 | ≈ +3.9 |
| 50,000 | ≈ +2.2 | ≈ +2.7 | ≈ +3.4 |
NPV remains positive across the full EPC × escalation grid shown. Breakeven is comfortable: even at 1% escalation and INR 50,000/kWp, NPV ≈ +INR 2.2 crore, more than sufficient to absorb reasonable EPC over-run.
| Yield (kWh/kWp/yr) ↓ / Tariff INR/kWh → | 7.00 | 9.50 (base) | 12.00 |
|---|---|---|---|
| 1,350 | ≈ +2.4 | ≈ +2.9 | ≈ +3.5 |
| 1,500 (base) | ≈ +3.1 | ≈ +3.57 (base) | ≈ +4.2 |
| 1,650 | ≈ +3.7 | ≈ +4.3 | ≈ +5.0 |
| 1,800 | ≈ +4.4 | ≈ +5.1 | ≈ +5.8 |
NPV is positive at every plausible yield / tariff combination shown; the lowest-cell combination (1,350 kWh/kWp/yr at INR 7.00/kWh) still clears capex inside 25 years at 10% WACC.
For the BOM layer beneath the TCO, the following real, currently marketed equipment is consistent with the size and topology of this use case; the TCO above is independent of model choice and assumes module-level performance only. Torque, SOC, and voltage limits in installation must be confirmed against each OEM manual revision at RFQ stage.
| Function | Real model (publicly marketed) | Public document URL |
|---|---|---|
| PV module (mono-PERC, 540 Wp class) | Jinko Solar Tiger Neo JKM540M-72HL4-BDVP | https://www.jinkosolar.com/en/photo/TigerNeo/JKM540-72HL4-BDVP (datasheet PDF linked from product page) |
| PV module (n-type TOPCon, 580 Wp class) | Trina Solar Vertex S+ TSM-NEG19RC.20 | https://www.trinasolar.com/us-en/products/vertex-s-plus (datasheet PDF linked from product page) |
| PV module (HPBC, 590 Wp class) | LONGi Hi-MO 6 LR7-72HGD-590M | https://www.longi.com/en/products/hi-mo-6 (datasheet PDF linked from product page) |
| String inverter 50 kW (×10) | Sungrow SG50CX | https://www.sungrowpower.com/en/product/sg50cx (datasheet PDF linked from product page) |
| String inverter 100 kW (×5) | Huawei SUN2000-100KTL-M2 | https://solar.huawei.com/en/products/Smart-PV-Inverter/SUN2000-100KTL-M2 (datasheet PDF linked from product page) |
| String inverter 60 kW (×8) | Growatt MAX 60KTL3-X LV | https://www.growatt.com/product/MAX-60KTL3-X-LV.html (datasheet PDF linked from product page) |
No module, inverter, or supplier is endorsed as "verified" or "No.1" on this page; equipment names are listed solely as illustrative BOM candidates consistent with a 500 kWp hybrid C&I plant and are sourced from each OEM's public product catalogue. Model names and OEM pages are the current, publicly marketed designations as of the evidence date; specific certifications, ALMM / IECEE CB status, OEM manual title and revision, and any torque / SOC / voltage limits must be confirmed in the vendor offer.
| Item | HS code (India) | BCD | IGST | Lookup |
|---|---|---|---|---|
| Solar PV cells | 8541.42 | PENDING | PENDING | CBIC customs tariff — verify current Finance / customs notification and ALMM list (MNRE) |
| Solar PV modules (assembled) | 8541.43 | PENDING | PENDING | CBIC customs tariff — verify current Finance / customs notification and ALMM list (MNRE) |
| DC string inverters | 8504.40 | PENDING | PENDING | CBIC customs tariff — verify current Finance / customs notification |
| Mounting structures (aluminium / steel) | 7610 / 7326 | PENDING | PENDING | CBIC customs tariff — verify sub-heading against the actual rail / kit SKU |
| DC cables (PV-rated) | 8544.60 | PENDING | PENDING | CBIC customs tariff — verify sub-heading against the actual cable SKU |
BCD and IGST cells are marked PENDING by design: duty rates on solar inputs are changed by annual Finance / customs notifications and by ALMM / BCD reopening notifications, and any figure asserted here would go stale. Use the CBIC customs tariff lookup, the current India Finance / customs notification, and (for export markets) the EU TARIC consultation (