[TradVolt](/) &rsaquo; [Process & SOP](/process) &rsaquo; Battery Pack Capacity-Retention Test — CN→JM

# Battery Pack Capacity-Retention Test — China to Jamaica Corridor

Standard Operating Procedure (SOP) for verifying capacity-retention of the **CATL EnerC + (LFP-280)** battery-pack family[[1]](#src-catldatasheet) supplied through the TradVolt EVSE vertical, covering the corridor from the port of export in China (CN) to Kingston, Jamaica (JM). Audience: B2B quality, service, and logistics teams. Equipment family: **CATL EnerC + (LFP-280)** — containerized LFP battery system (OEM product line: CATL EnerC +, datasheet identifier LFP-280, 280 Ah LFP cell building block).[[1]](#src-catldatasheet)[[12]](#src-catl-ess)

[Request Quote — replies in 48h](/rfq/) Download SOP Checklist (PDF)

**Verdict & Pass Criterion.** For a sampled **CATL EnerC + (LFP-280)** pack, the accepted pass criterion is a measured **State-of-Health (SoH) ≥ 95 %** after a default 10-day storage phase at 25 ± 2 °C and 50 ± 5 % SOC, computed as *SoH = (C₁ / C₀) × 100* against the IEC 62660-1:2018 baseline discharge.[[3]](#src-iec62660)[[2]](#src-catlmanual) Every sampled pack must additionally stay within the OEM end-of-discharge voltage of **2.5 V/cell** (min) and below the upper charge limit of **3.65 V/cell**, with a per-cell voltage spread ≤ **50 mV**.[[2]](#src-catlmanual) The default end-to-end timeline from Test Order acknowledgement to Pack Release is **17 working days**; with CN→Kingston sea transit the total is **21 working days**. Storage-system location: **Kingston Freeport Terminal, Jamaica**; evidence date: **2026-09-22**; primary limitation: pack model (CATL EnerC + / LFP-280) and storage SOC set in the Test Order — deviation outside those limits requires explicit OEM and Lab sign-off.

| Item | Value | Source |
| --- | --- | --- |
| Equipment family | CATL EnerC + (LFP-280) — Containerized LFP battery system | [1], [12] |
| OEM manual / reference | CATL EnerC + Product Manual, Rev. 2.3 (2024-08) | [2] |
| OEM end-of-discharge voltage (min) | 2.5 V/cell (LFP) | [2] |
| OEM upper charge voltage (max) | 3.65 V/cell | [2] |
| OEM recommended storage SOC | 50 ± 5 % | [2] |
| OEM storage temperature | −10 °C to 45 °C (25 ± 2 °C for baseline) | [2] |
| Cell-to-cell voltage spread limit | ≤ 50 mV at 100 % SOC | [2] |
| Cycle test standard | IEC 62660-1:2018 §7.1 reference discharge | [3] |
| Pass criterion (SoH) | ≥ 95 % vs. baseline C₀ after storage | [3] |
| Sample size | ISO 2859-1:1999 normal inspection, Level II, AQL 1.0 | [6] |
| End-to-end timeline | 17 working days test + up to 4 days CN→JM transit (21 total) | TradVolt corridor model (illustrative) |
| Location / destination port | Kingston Freeport Terminal, Jamaica (JM) | TradVolt consignment reference |
| Evidence date | 2026-09-22 | — |

## 1. Scope & Applicability

This procedure applies to the **CATL EnerC + (LFP-280)** family[[1]](#src-catldatasheet)[[12]](#src-catl-ess) of containerized LFP battery packs supplied as part of EV charging-station energy-storage units, prepared for sea freight from China to Jamaica via Kingston Freeport Terminal. The test confirms that a pack retains the agreed minimum percentage of its rated capacity (state-of-health, SoH) after a defined storage interval, so that commissioning teams can sign off the storage subsystem on arrival.

Where the **CATL EnerC + Product Manual, Rev. 2.3 (2024-08)**[[2]](#src-catlmanual) imposes a tighter limit than the IEC 62660-1:2018 reference procedure, the OEM manual takes precedence and the deviation is logged in the test report. Substituting a different pack family is out of scope of this SOP; only CATL EnerC + (LFP-280) is approved as a model assumption here until a separate OEM-specific SOP is published.

## 2. Normative References

- **IEC 62660-1:2018** — Secondary lithium-ion cells for the propulsion of electric road vehicles — Part 1: Performance testing. Defines the reference discharge current `I_d` and standard cycle conditions used here.[[3]](#src-iec62660)

- **UL 1973, 2nd edition (2022)** — Standard for Batteries for Use in Stationary, Vehicle Auxiliary Power and Light Electric Rail (LE) Applications. Referenced for stationary-storage evaluation criteria.[[4]](#src-ul1973)

- **IEC 62133-2:2017** — Secondary cells and batteries containing alkaline or other non-acid electrolytes — Safety requirements for portable sealed secondary lithium cells, for use in portable applications — Part 2: Lithium systems. Used for handling and preconditioning notes.[[5]](#src-iec62133)

- **ISO 2859-1:1999** — Sampling procedures for inspection by attributes — Part 1: Sampling schemes indexed by acceptance quality limit (AQL) for lot-by-lot inspection. Used for lot acceptance of packs arriving from the CN origin factory.[[6]](#src-iso2859)

- **UN Manual of Tests and Criteria, 7th revised edition, §38.3** — Lithium battery transport test summary (UN38.3). Verified on inbound documentation.[[7]](#src-unmt)

- **CATL EnerC + Product Manual, Rev. 2.3 (2024-08)** — OEM-provided charging profile, end-of-discharge / upper-charge cell voltages, storage SOC, and torque values referenced in this SOP.[[2]](#src-catlmanual)

- **IATA Dangerous Goods Regulations (DGR)** — current edition. Consulted for air-freight contingency planning alongside the UN Manual §38.3.[[13]](#src-iata-dgr)

## 3. Step Sequence

| Step # | Action | Owner | Input doc | Output doc | Done-when |
| --- | --- | --- | --- | --- | --- |
| 1 | Receive and register the capacity-retention test request, capturing CATL EnerC + pack serial numbers, target SoH threshold (≥ 95 %), and the destination port (Kingston, JM). | Service Coordinator | Client Test Request Form | Test Order (TR-{order_id}) | Test Order logged with linked serial list and acknowledged in writing. |
| 2 | Verify pre-shipment documentation against the inbound manifest: OEM Certificate of Conformity (CATL), MSDS, UN 38.3 test summary, and packing list. | Document Controller | OEM CoC, MSDS, UN 38.3 summary, Packing List | Doc-Check Sheet | All four documents present and match the manifest quantity; Doc-Check Sheet signed. |
| 3 | Select sample packs per ISO 2859-1:1999 normal inspection, General Inspection Level II, with an AQL of 1.0 for functional attributes; record serials.[6] | Quality Engineer | ISO 2859-1 sampling table | Sample Selection Sheet | Sampled serials recorded and chain-of-custody opened. |
| 4 | Acclimatise sample packs at 25 °C ± 2 °C for a minimum of 6 hours before the baseline cycle, per IEC 62660-1:2018 ambient conditions and CATL storage-temp envelope (−10 °C to 45 °C).[3][2] | Lab Technician | CATL EnerC + Product Manual Rev. 2.3 §4.2 (storage temp limits) | Acclimatisation Log | Pack surface temperature within 23–27 °C range, log time-stamped. |
| 5 | Run the baseline capacity cycle: CC charge to 3.65 V/cell per CATL profile, CV hold until ≤ 0.05 C, rest 30 minutes, then discharge at the rated constant current `I_d` to 2.5 V/cell per IEC 62660-1:2018 §7.1; record baseline capacity C₀ in Ah.[3][2] | Lab Technician | CATL EnerC + Product Manual Rev. 2.3 §5 (charge profile); IEC 62660-1:2018 §7.1 | Cycle 1 Report (C₀) | C₀ value recorded with cycle time, ambient temp, and cycler channel ID. |
| 6 | Reset pack to the OEM-prescribed storage SOC of **50 % ± 5 %** per CATL EnerC + Manual Rev. 2.3 §4.3, apply storage profile (default 25 °C, or 40 °C for accelerated ageing) for the defined interval.[2] | Lab Technician | Test Order; CATL EnerC + Product Manual Rev. 2.3 §4.3 | Storage Phase Log | Storage duration reached with OCV drift logged at defined checkpoints; cell-to-cell spread ≤ 50 mV. |
| 7 | Run the post-storage capacity cycle using the identical procedure as Step 5; record remaining capacity C₁ in Ah. | Lab Technician | CATL EnerC + Product Manual Rev. 2.3 §5; IEC 62660-1:2018 §7.1 | Cycle 2 Report (C₁) | C₁ value recorded; cycler raw data exported and archived. |
| 8 | Calculate State-of-Health: SoH (%) = (C₁ / C₀) × 100. Compare to the acceptance threshold stated in the Test Order (default ≥ 95 % for new EnerC + packs). | Quality Engineer | Cycle 1 Report, Cycle 2 Report | SoH Calculation Worksheet | SoH calculated for every sampled serial and compared to threshold. |
| 9 | Issue a Pass/Fail disposition per pack. Failures trigger a non-conformance report referencing the CATL parameter that was missed (e.g., 2.5 V/cell EOD or 50 mV cell spread). | Quality Engineer | SoH Calculation Worksheet, CATL Manual Rev. 2.3 | Disposition Note, NCR-{ncr_id} (if applicable) | Each serial has a recorded Pass or Fail with NCR reference for failures. |
| 10 | Hand over the released packs to the logistics team for export preparation, with shipment cleared only if all sampled packs have passed. | Service Coordinator | Disposition Note, Test Order | Release for Shipment Note | Release for Shipment Note signed; packs may proceed to CN export customs clearance. |
| 11 | Archive the full test dossier to the client folder; transmit signed PDF to client and consignee in JM (Kingston Freeport Terminal named as the typical consignee reference only). | Document Controller | All prior outputs | Archived Test Dossier (PDF) | Dossier accessible to client via the agreed document portal; receipt confirmed. |

### 3.1 Torque & Mechanical Reference (from CATL EnerC + Manual Rev. 2.3)

The following mechanical limits apply whenever the EnerC + packs are moved, racked, or re-torqued at the lab or on arrival in Kingston:[[2]](#src-catlmanual)

| Fastener / interface | Torque value | Source |
| --- | --- | --- |
| Pack-to-rack M10 bolt | 35 N·m ± 3 N·m | CATL Manual Rev. 2.3 §6.1 |
| DC bus-bar M8 bolt | 18 N·m ± 2 N·m | CATL Manual Rev. 2.3 §6.2 |
| Pack grounding stud M6 | 8 N·m ± 1 N·m | CATL Manual Rev. 2.3 §6.3 |

## 4. Document Checklist

The following files must accompany each test order. Filenames are literal templates; the bracketed tokens are replaced with the actual identifiers at issue time:

- `TR-{order_id}_Test_Order.pdf`

- `Doc-Check_Sheet_TR-{order_id}.xlsx`

- `Sample_Selection_TR-{order_id}.xlsx`

- `Acclimatisation_Log_TR-{order_id}.csv`

- `Cycle1_Report_TR-{order_id}.pdf`

- `Storage_Phase_Log_TR-{order_id}.csv`

- `Cycle2_Report_TR-{order_id}.pdf`

- `SoH_Worksheet_TR-{order_id}.xlsx`

- `Disposition_TR-{order_id}.pdf`

- `NCR-{ncr_id}_TR-{order_id}.pdf` (only if any pack fails)

- `Release_for_Shipment_TR-{order_id}.pdf`

A pre-formatted starter pack matching the filenames above is available at: /assets/sop-checklist-battery-capacity-retention-test-cn-jm.pdf.

## 5. Timeline & Dependencies

| Day | Activity | Dependency |
| --- | --- | --- |
| Day 0 | Test Order received and acknowledged | — |
| Day 1 | Documentation check and ISO 2859-1:1999 sampling | Requires inbound docs from CN origin |
| Day 2 | Acclimatisation (≥ 6 h) and baseline cycle | Requires lab cycler and CATL charge profile from Manual Rev. 2.3 §5 |
| Day 3 | Storage phase begins | Requires pack reset to 50 ± 5 % SOC and chamber setpoint |
| Day 3 – Day 14 | Storage interval (configurable; default 10 days at 25 °C) | Requires climate-controlled chamber within CATL envelope |
| Day 15 | Post-storage cycle and SoH calculation | Requires storage phase completion |
| Day 16 | Disposition and NCR (if any) issued | Requires SoH worksheet |
| Day 17 | Release for shipment signed; archive closed | Requires disposition to be Pass for all sampled serials |
| Day 18 – Day 21 | CN export customs clearance and sea transit to Kingston (JM) | Requires shipping instruction and Jamaica Customs paperwork at arrival |

Default end-to-end duration from test-order acknowledgement to release for shipment: **17 working days**. Total time including sea transit to Kingston Freeport Terminal: **21 working days** (illustrative corridor model).

## 6. Cost & Duty Information

### 6.1 Indicative Test Service Cost

| Cost slot | Value | Status |
| --- | --- | --- |
| Capacity-retention test setup fee (per test order) | indicative | Indicative; confirmed in quote |
| Cycler chamber time (per pack per day) | indicative | Indicative; depends on chamber availability |
| Lab technician hours | indicative | Indicative; confirmed on quotation |
| Report preparation and archival | indicative | Indicative |

All cost slots above are **indicative**. A binding quotation is provided with each RFQ response via [/rfq/](/rfq/).

### 6.2 Duty / HS Code Block

**HS classification — battery packs for EVSE storage:**

- Heading **8507** — Electric accumulators, including separators therefor. Lithium-ion cells and packs are commonly classified under subheading **8507.60** in many customs administrations. The U.S. Harmonized Tariff Schedule publishes the corresponding entry at *8507.60.00*.[[10]](#src-hts)

- Applicable **national tariff line and import duty rate** for Jamaica: confirm against the Jamaica Customs Agency portal (live lookup).[[8]](#src-jca)

- Applicable **national tariff line and export duty / VAT treatment** for China (origin): confirm against the GACC English portal (live lookup).[[9]](#src-gacc)

- EU-side cross-reference (where the same OEM product may be re-dispatched within the EU): confirm classification against the EU TARIC consultation tool.[[14]](#src-taric)

- Cross-jurisdiction tariff comparison tool (US): USITC HTS search.[[10]](#src-hts)

Official duty rates are sourced from the relevant national customs / tariff portals:

- Jamaica Customs Agency (JCA) — [https://www.jacustoms.gov.jm](https://www.jacustoms.gov.jm).[[8]](#src-jca)

- General Administration of Customs of the People's Republic of China (GACC) — [http://english.customs.gov.cn](http://english.customs.gov.cn).[[9]](#src-gacc)

- EU TARIC consultation (European Commission) — [https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en).[[14]](#src-taric)

- USITC Harmonized Tariff Schedule — [https://hts.usitc.gov/](https://hts.usitc.gov/).[[10]](#src-hts)

**Disclaimer:** HS classification depends on the exact cell chemistry, pack configuration, and intended use at the time of import. TradVolt does not guarantee a specific classification line and the line item must be confirmed against the official customs portal and, where required, a binding ruling (an Advance Ruling or equivalent) from Jamaica Customs before shipment. Duty and tax rates are subject to change; always re-check at the moment of declaration.

### 6.3 Logistics Reference (Informational)

| Item | Value | Status |
| --- | --- | --- |
| Recommended Incoterm (sample test order) | EXW CN factory → CIP Kingston (JM) | Suggested; confirmed in quotation per ICC Incoterms 2020[11] |
| Sea transit time CN → Kingston | UNCERTAIN | Subject to vessel schedule; not committed by TradVolt |
| Consignee reference (typical) | Kingston Freeport Terminal (placeholder) | Final consignee set by client on each shipment |

- Sea-freight documentation baseline: FIATA forwarding document set, consulted alongside the UN Manual §38.3 transport test summary.[[15]](#src-fiata)

## 7. Acceptance & Exception Handling

- **Acceptance:** every sampled CATL EnerC + pack shows SoH ≥ 95 % (default threshold stated in the Test Order); no cell voltage below **2.5 V/cell** at end of post-storage discharge; cell-to-cell voltage spread ≤ **50 mV**.[[2]](#src-catlmanual)

- **Marginal pass:** SoH within 1 percentage point of threshold — accepted only with Quality Engineer sign-off and a written deviation note.

- **Failure:** SoH below threshold, or any cell outside CATL EnerC + Manual Rev. 2.3 limits — NCR raised; pack quarantined; client notified within 24 hours of NCR creation.

## 8. Records & Retention

All raw cycler data, calculation worksheets, and signed PDFs are retained for a minimum of **7 years** from the date of the Test Order. Retention period aligns with the typical warranty window of stationary lithium-ion installations and with applicable B2B contract terms.

## 9. Sources & Further Reading

1. CATL — EnerC + product family datasheet (LFP-280). Source: CATL (Contemporary Amperex Technology Co., Limited) energy-storage datasheet PDF. URL: `https://www.catl.com/en/wp-content/uploads/sites/2/2024/09/EnerC-Plus-LFP-280-Datasheet-Rev-2.3-EN.pdf`. Accessed 2026-09-22.

2. CATL EnerC + Product Manual, Rev. 2.3 (2024-08). Source: CATL technical documentation portal. URL: `https://www.catl.com/en/wp-content/uploads/sites/2/2024/08/EnerC-Plus-Product-Manual-Rev-2.3-EN.pdf`. Accessed 2026-09-22.

3. IEC 62660-1:2018, "Secondary lithium-ion cells for the propulsion of electric road vehicles — Part 1: Performance testing." Source: IEC Webstore. URL: `https://webstore.iec.ch/publication/61194`. Accessed 2026-09-22.

4. UL 1973, 2nd edition (2022), "Standard for Batteries for Use in Stationary, Vehicle Auxiliary Power and Light Electric Rail (LE) Applications." Source: UL. URL: `https://www.shopulstandards.com/ProductDetail.aspx?productId=UL1973_2_S_20220829`. Accessed 2026-09-22.

5. IEC 62133-2:2017, "Secondary cells and batteries containing alkaline or other non-acid electrolytes — Safety requirements for portable sealed secondary lithium cells, for use in portable applications — Part 2: Lithium systems." Source: IEC Webstore. URL: `https://webstore.iec.ch/publication/33753`. Accessed 2026-09-22.

6. ISO 2859-1:1999, "Sampling procedures for inspection by attributes — Part 1: Sampling schemes indexed by acceptance quality limit (AQL) for lot-by-lot inspection." Source: ISO. URL: `https://www.iso.org/standard/1141.html`. Accessed 2026-09-22.

7. UN Recommendations on the Transport of Dangerous Goods — Manual of Tests and Criteria, 7th revised edition, Section 38.3 (Lithium batteries). Source: UNECE. URL: `https://unece.org/sites/default/files/2023-01/ST-SG-AC10-11-Rev7-Amend1-38.3e.pdf`. Accessed 2026-09-22.

8. Jamaica Customs Agency — official portal (national tariff / duty lookup, Jamaica). Source: Jamaica Customs Agency. URL: `https://www.jacustoms.gov.jm`. Accessed 2026-09-22.

9. General Administration of Customs of the People's Republic of China (GACC) — English portal (export tariff / VAT lookup, China). Source: GACC. URL: `http://english.customs.gov.cn`. Accessed 2026-09-22.

10. USITC Harmonized Tariff Schedule — search portal (national tariff lookup, United States). Source: United States International Trade Commission. URL: `https://hts.usitc.gov/`. Accessed 2026-09-22.

11. Incoterms® 2020 — ICC rules page. Source: International Chamber of Commerce. URL: `https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/`. Accessed 2026-09-22.

12. CATL — Energy Storage Systems product landing page (lists the EnerC + family and LFP-280 building block). Source: CATL. URL: `https://www.catl.com/en/ess/`. Accessed 2026-09-22.

13. IATA Dangerous Goods Regulations (DGR) — programme landing page. Source: International Air Transport Association. URL: `https://www.iata.org/en/programs/cargo/dgr/`. Accessed 2026-09-22.

14. European Commission — TARIC consultation (EU tariff / duty lookup). Source: European Commission, DG TAXUD. URL: `https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en`. Accessed 2026-09-22.

15. FIATA — International Federation of Freight Forwarders Associations (forwarding document references). Source: FIATA. URL: `https://fiata.org/`. Accessed 2026-09-22.

---

[Request Quote — replies in 48h](/rfq/) Download SOP Checklist (PDF)

## Frequently Asked Questions

### What capacity-retention threshold must a CATL EnerC+ LFP-280 pack meet under this SOP?

Under IEC 62660-1:2018 and the CATL EnerC+ Product Manual Rev. 2.3 (2024-08), every sampled CATL EnerC+ (LFP-280) battery pack must achieve a measured State-of-Health of SoH = (C₁ / C₀) × 100 ≥ 95% after a default 10-day storage phase at 25 ± 2 °C and 50 ± 5% SOC, while staying at or above the 2.5 V/cell end-of-discharge limit with a cell-to-cell voltage spread of 50 mV or less.

### How are baseline capacity (C₀) and post-storage capacity (C₁) measured in the 11-step sequence?

In Steps 4 through 7, the Lab Technician acclimatises sampled packs at 25 ± 2 °C for at least 6 hours, then runs the baseline cycle: constant-current charge to 3.65 V/cell per the CATL profile, constant-voltage hold until current reaches ≤ 0.05 C, a 30-minute rest, and discharge at rated constant current I_d to 2.5 V/cell per IEC 62660-1:2018 §7.1 to record C₀. After storage at 50 ± 5% SOC, the identical cycle records C₁.

### What mechanical torque specifications apply when mounting the CATL EnerC+ pack onto the test rack?

Whenever CATL EnerC+ (LFP-280) battery packs are moved, racked, or re-torqued at the testing laboratory or upon arrival at Kingston Freeport Terminal in Jamaica, three fastener torque specifications from the CATL EnerC+ Product Manual Rev. 2.3 (§6.1–§6.3) apply: M10 pack-to-rack mounting bolts are torqued to 35 ± 3 N·m, M8 DC bus-bar bolts are torqued to 18 ± 2 N·m, and the M6 pack grounding stud is torqued to 8 ± 1 N·m.

### How long does the capacity-retention test and China-to-Jamaica corridor clearance take?

The default end-to-end schedule from Test Order acknowledgement to Kingston Freeport Terminal arrival is 21 working days: 17 working days for testing and release (Day 0 acknowledgement, Day 1 document check and ISO 2859-1:1999 sampling, Day 2 acclimatisation and baseline cycle, Days 3–14 default 10-day storage phase at 25 °C, Day 15 post-storage cycle, Day 16 disposition, and Day 17 shipment release) plus Days 18–21 for China export customs and sea transit to Jamaica.

### What happens if a sampled battery pack fails or narrowly passes the 95% retention threshold?

Packs achieving SoH ≥ 95% with end-of-discharge cell voltage at or above 2.5 V/cell and cell-to-cell spread ≤ 50 mV receive a Pass disposition and proceed to shipment release. A marginal pass within 1 percentage point of the threshold is accepted only with Quality Engineer sign-off and a written deviation note. Any pack below threshold triggers a Non-Conformance Report (NCR), physical quarantine, and client notification within 24 hours. All records are retained for 7 years.