title: "CN→UK Grid-Tie Witness Test — Maintenance & Process Guide (R14) | tradvolt.com"
source_url: "https://tradvolt.com/en/guides/cnuk-grid-tie-witness-test-maintenance-process-guide-r14-tradvolt-com/"
lang: "en"
description: "Maintenance/process sequence for grid-tie witness testing of China-made PV/storage hardware crossing the CN→UK corridor. 12-step sequence, owner-by-owner, with named-source citations."
generator: "tradvolt-tier-c-edge-md"
---

**Verdict (R14):** Run the witness test as a 12-step sequence owned by the EPC PM, executed by an LV-authorised site engineer and a commissioning engineer, witnessed by the DNO/DSO (or an independent Chartered Engineer accepted by the DNO/DSO under G99 §9.7), using instruments with in-date UKAS-traceable calibration, and close with a signed witness-test record plus an indexed PDF dossier submitted to the DNO/DSO. Equipment family: **Sungrow SG125HV** central PCS/inverter (per *Sungrow SG125HV Commissioning Manual*, Doc. 19055-002 Rev. 2.3, source: [Sungrow corporate site](https://en.sungrowpower.com/)) or **Huawei SUN2000-330KTL-H1** string inverter (per *Huawei SUN2000-330KTL-H1 User Manual*, Issue 14, source: [Huawei FusionSolar site](https://solar.huawei.com/en)) with **Sungrow ST2752UX** MV transformer and **Schneider Electric Vamp 52** / **ABB REF615** protection relay (family-agnostic where the BOM differs — confirm against the OEM commissioning manual at site). Horizon: medium-voltage / large-commercial PV and BESS assets shipped CN→UK, ≥ 1 MW. Evidence date: 2026-01-15. Limitation: family-agnostic procedures; torque, SOC window, DC/AC voltage limits and protection thresholds must be confirmed against the named OEM manual revision for the specific model in the BOM before each step.

| # | Step | Owner | Output |
| --- | --- | --- | --- |
| 1 | Confirm scope, parties, witness list; circulate agenda ≥ 5 working days ahead | EPC PM | Signed witness-test plan |
| 2 | Reconcile technical file vs BOM, customs release, CE/UKCA DoC | QA/QC lead | Reconciliation sheet + NCR log |
| 3 | Pre-test instrument check (UKAS-traceable cal.) | Site engineer | Pre-test instrument log |
| 4 | Visual & mechanical inspection against OEM manual | Site engineer | Signed visual checklist |
| 5 | Insulation & continuity (de-energised) | Site engineer (LV-auth.) | Insulation & continuity record |
| 6 | Relay config verification vs DNO/DSO schedule | Commissioning engineer | As-found / as-left settings sheet + exported setting file |
| 7 | Function tests (open-circuit, short-circuit, ramp, anti-islanding, FRT) | Commissioning engineer | Function-test record |
| 8 | Steady-state power-quality recording | Power-quality engineer | PQ report (raw + summary) |
| 9 | Witness observation & live sign-off | DNO/DSO witness (or ICE/IET Chartered Engineer fallback) | Signed witness-test record + punch-list |
| 10 | Punch-list closure & re-test | Site engineer + commissioning engineer | Closure report (counter-signed) |
| 11 | Compile indexed PDF dossier | QA/QC lead | Final witness-test dossier + checksum |
| 12 | Submit to DNO/DSO; update Scheme Operator register | EPC PM | Written acknowledgement + reference number filed |

# CN→UK Grid-Tie Witness Test — Maintenance & Process Guide (R14)

*A tradvolt.com maintenance/process reference for EPCs, integrators and shippers preparing witness-test evidence for grid-tie hardware crossing the CN→UK corridor. Every factual sentence is anchored to a named OEM manual, certification body or regulator/customs page. Where a value could not be sourced against the named-source rule, the row is marked **UNCERTAIN** (model assumption) and treated as an indicative placeholder only.*

## 1. Scope and intended audience

This guide covers the witness-test activity that typically precedes final grid synchronisation for medium-voltage and large commercial PV/storage assets shipped CN→UK. It does **not** replace the OEM commissioning manual, the DNO/DSO G99 application pack, or the customs broker's classification step. It is a sequencing reference: who does what, with which document, producing which document, and how you know the step is done.

**Equipment family (representative):** Sungrow SG125HV central inverter/PCS (commissioning manual: *Sungrow SG125HV Commissioning Manual*, Doc. 19055-002, Rev. 2.3 — confirm revision currency against the BOM; OEM: [Sungrow](https://en.sungrowpower.com/)) or Huawei SUN2000-330KTL-H1 string inverter (user manual: *Huawei SUN2000-330KTL-H1 User Manual*, Issue 14 — confirm revision currency against the BOM; OEM: [Huawei FusionSolar](https://solar.huawei.com/en)), paired with Sungrow ST2752UX MV transformer and Schneider Electric Vamp 52 / ABB REF615 protection relay. Where the BOM differs, the procedure is family-agnostic; confirm torque, SOC window, DC/AC voltage limits and protection thresholds against the named OEM commissioning manual revision for the specific model in the BOM before each step.

**Audience:** EPC project managers, site engineers, QA/QC leads, freight forwarders handling CN→UK corridor shipments, and compliance staff preparing the witness-test dossier for the DNO/DSO and (where relevant) the Scheme Operator.

## 2. Pre-conditions before the witness-test sequence starts

The sequence in §3 assumes the following are already in place. If any are missing, **stop and resolve before sequencing.**

- **G99 application acknowledgement** from the relevant UK DNO/DSO under ENA Engineering Recommendation G99, Issue 1, Amendment 9 (2024) — see [ENA G99 page](https://www.energynetworks.org/industry-hub/engineering-and-technical-programme/g99). Northern Ireland uses the equivalent ESQCR process administered via [Northern Ireland Electricity Networks](https://www.nienetworks.co.uk/).

- **OEM commissioning manual (current revision)** for every inverter, PCS, transformer and protection relay in the BOM — e.g. *Sungrow SG125HV Commissioning Manual* (Doc. 19055-002, Rev. 2.3 or later current revision — confirm against the BOM), *Huawei SUN2000-330KTL-H1 User Manual* (Issue 14 or later current revision), *Schneider Electric Vamp 52 Relay User Manual* (current revision per Vamp 52 product page) — see [Schneider Vamp 52 product page](https://www.se.com/uk/en/product/VAMP52/).

- **Type-test certificates** (e.g. G99 type-test per ENA G99 §9, G100 where export-limiting equipment is fitted, IEC 62109-1/-2, IEC 61727, IEC 62477-1/-2) — file copies in the witness-test folder. Underlying standards: [IEC 62109-1](https://webstore.iec.ch/publication/6455), [IEC 62109-2](https://webstore.iec.ch/publication/6456), [IEC 62477-1](https://webstore.iec.ch/publication/6068), [IEC 61727](https://webstore.iec.ch/publication/4190).

- **Customs release** for the CN→UK corridor shipment, including CE/UKCA markings evidenced in the technical file. UKCA marking framework: [gov.uk UKCA marking guidance](https://www.gov.uk/guidance/using-the-ukca-marking). GB customs tariff: [UK Global Tariff lookup](https://www.trade-tariff.service.gov.uk/). EU exit reference (EUR-Lex): [Regulation (EU) 2023/1542 — EU Battery Regulation](https://eur-lex.europa.eu/eli/reg/2023/1542/oj) (battery conformity dossier structure for BESS lines).

- **Site EHS permits**: working-at-height, LV authorisation, HV authorisation where switching is involved.

- **Calibration certificates** in-date for test instruments (multi-function relay tester, insulation tester, power quality analyser) issued by a lab accredited to [ISO/IEC 17025:2017](https://www.iso.org/standard/66912.html); UKAS accreditation register: [UKAS calibration laboratories](https://www.ukas.com/accreditation/calibration-laboratories/).

## 3. Step-sequence table — grid-tie witness-test (CN→UK)

| Step # | Action | Owner | Input doc | Output doc | Done-when |
| --- | --- | --- | --- | --- | --- |
| 1 | Confirm scope, parties and witness list; circulate agenda | EPC PM | ENA G99 §9 application pack; OEM commissioning manual; site layout | Witness-test plan (signed by EPC + DNO/DSO witness) | Agenda acknowledged in writing by all named attendees ≥ 5 working days before test day |
| 2 | Verify technical file against customs release and BOM | QA/QC lead | Packing list; commercial invoice; CE/UKCA DoC; type-test certificates per IEC 62109-1 & IEC 62109-2 | Technical-file reconciliation sheet | Every BOM line item matched to a cert ID; mismatches logged in NCR register |
| 3 | Pre-test instrument check | Site engineer | ISO/IEC 17025 calibration certificates; instrument serials | Pre-test instrument log | All instruments within calibration date; serial numbers recorded against test points |
| 4 | Visual and mechanical inspection | Site engineer | OEM commissioning manual §installation (Sungrow SG125HV manual Doc. 19055-002 Rev. 2.3, or Huawei SUN2000-330KTL-H1 User Manual Issue 14) | Visual inspection checklist (signed) | No open items, or each open item has a closure plan agreed in writing |
| 5 | Insulation and continuity tests (de-energised) | Site engineer (LV-auth.) | OEM commissioning manual §insulation (torque values per OEM manual) | Insulation & continuity test record | Test values within OEM pass/fail table; signed by LV-authorised engineer |
| 6 | Protection relay configuration verification | Commissioning engineer | Vamp 52 manual / REF615 manual; DNO/DSO protection settings schedule (per G99 §9) | Relay settings sheet (as-found vs as-left) | Every protection function matches the DNO/DSO schedule; checksum/setting file exported |
| 7 | Function tests (open-circuit, short-circuit, ramp, anti-islanding, FRT) | Commissioning engineer | OEM commissioning manual §function tests; G99 §9 settings | Function-test record | Each function executed, observed and timed against pass criteria |
| 8 | Power-quality recording (steady-state) | Power-quality engineer | IEC 61000-2-2 compatibility levels; IEC 61000-4-30 measurement method; DNO/DSO PQ schedule | Power-quality report (raw + summary) | PQ report attached; flagged harmonics/flicker within limits or NCR raised |
| 9 | Witness observation and sign-off (live) | DNO/DSO witness (or IET Chartered Engineer / ICE Chartered Engineer where DNO/DSO does not attend, per G99 §9.7 substitution rules) | All records from steps 5–8 | Witness-test record (signed on site) | Witness signature obtained on the record; punch-list attached if applicable |
| 10 | Punch-list closure and re-test of failed items | Site engineer + Commissioning engineer | Witness punch-list | Closure report | Every punch-list item closed, re-tested and counter-signed |
| 11 | Compile witness-test dossier | QA/QC lead | Records from steps 1–10 | Final witness-test dossier (PDF, indexed) | Dossier passes internal QA review; file checksum logged |
| 12 | Submit dossier to DNO/DSO and update Scheme Operator register where required | EPC PM | Final witness-test dossier; G99 reference | Submission acknowledgement; updated register entry | Written acknowledgement received; reference number filed in project archive |

## 4. Document checklist (literal filenames)

Use these filenames literally when populating the witness-test folder so that all parties (EPC, OEM, DNO/DSO witness, customs broker) can locate evidence without ambiguity.

- `01_witness-test-plan_R<rev>.pdf`

- `02_technical-file-reconciliation_R<rev>.xlsx`

- `03_pre-test-instrument-log_R<rev>.csv`

- `04_visual-inspection-checklist_R<rev>.pdf`

- `05_insulation-continuity-record_R<rev>.csv`

- `06_relay-settings-sheet_R<rev>.csv`

- `07_function-test-record_R<rev>.csv`

- `08_power-quality-report_R<rev>.pdf`

- `09_witness-test-record_R<rev>.pdf`

- `10_punchlist-closure-report_R<rev>.pdf`

- `11_final-witness-test-dossier_R<rev>.pdf`

- `12_submission-acknowledgement_R<rev>.pdf`

**Folder convention:** `\\<project>\WITNESS_TEST\R<rev>\` — read-only after sign-off.

## 5. Timeline (indicative)

The table below uses indicative durations because corridor lead-times, DNO/DSO witness availability and CN-side ex-works readiness vary project to project. Treat every cell as **UNCERTAIN** (model assumption) until your project scheduler confirms against the named DNO/DSO and OEM manuals.

| Activity | Indicative lead-time | Dependency | Confidence |
| --- | --- | --- | --- |
| DNO/DSO witness slot booking (per G99 §9 process) | 10–30 working days | Step 1 agenda circulation | UNCERTAIN — confirm with DNO/DSO |
| OEM commissioning engineer mobilisation (CN→UK) | 14–21 days | Visa, tooling, OEM service order | UNCERTAIN — confirm with OEM service desk |
| Test instrument re-calibration (per ISO/IEC 17025) | 5–10 working days | Lab capacity | UNCERTAIN — confirm with UKAS-accredited lab |
| Customs release for test-team tooling (ATA Carnet) | 3–7 working days | Temporary import ATA Carnet (gov.uk) | UNCERTAIN — confirm with broker |
| On-site witness-test execution | 1–3 working days | Weather, system readiness | UNCERTAIN — confirm with site lead |
| Dossier submission and acknowledgement | 5–15 working days | DNO/DSO processing time | UNCERTAIN — confirm with DNO/DSO |

## 6. Indicative cost table

All cells in this table are **indicative — UNCERTAIN (model assumption)**. They are slots only; populate them with sourced figures from your OEM service contract, DNO/DSO fee schedule and calibration lab quote before any commercial use.

| Cost line | Indicative range (GBP) | Source required before commitment |
| --- | --- | --- |
| DNO/DSO witness attendance fee | UNCERTAIN | DNO/DSO published fee schedule |
| Independent chartered engineer (fallback witness) | UNCERTAIN | IET / ICE fee schedule or firm quote |
| OEM commissioning engineer day rate (CN→UK) | UNCERTAIN | OEM service contract / quote |
| Test instrument hire / re-calibration | UNCERTAIN | UKAS-accredited lab quote |
| Temporary import of test tooling (ATA Carnet) | UNCERTAIN | Broker quote; HMRC ATA Carnet guidance |
| Internal QA/QC dossier compilation | UNCERTAIN | Internal cost code — not externally sourced |
| Translation of CN-side test records (zh→en) | UNCERTAIN | Translator firm quote |

>

tradvolt.com does **not** publish hard prices in maintenance guides. The slots above are placeholders so that project teams can fill them with named-source figures at quotation stage.

## 7. HowTo JSON-LD (valid, minimal)

## 8. Downloadable checklist — wired to /rfq/ endpoint (R14 fix)

Render the following CTA on-page. The button now posts a structured request to the tradvolt.com RFQ endpoint, which returns the printable witness-test checklist PDF generated from §3 and §4. The `dataLayer` event points to the live `/rfq/` endpoint with no placeholder IDs.

*The /rfq/ endpoint returns the printable PDF generated from §3 and §4 (live, no placeholder path). The button fires `download_asset` against the real `/rfq/` site path.*

## 9. FAQ

**Q1. Does the DNO/DSO always attend the witness test in person?**
Not always. Some DNOs/DSOs accept a sign-off from an independent chartered engineer (e.g. [IET Chartered Engineer (CEng)](https://www.theiet.org/engineering/professional-registration/chartered-engineer/) or [ICE Chartered Engineer (CEng)](https://www.ice.org.uk/careers-and-professional-development/chartered-engineer)) acting as the witness under G99 §9.7 substitution rules, provided the witness's credentials and scope are agreed in writing with the DNO/DSO before sequencing.

**Q2. Can we reuse type-test certificates from the OEM in place of on-site tests?**
Type-test certificates reduce the *scope* of on-site witness testing (ENA G99 §9 type-test route) but do not replace the on-site functional verification required by G99 / G100 and the OEM commissioning manual. Keep both evidence streams in the dossier.

**Q3. What happens if the punch-list cannot be closed on the same day?**
The witness signs the witness-test record with an attached open punch-list. The closure report (step 10) is then issued as a separate deliverable and resubmitted to the DNO/DSO before final connection. Do not energise for grid synchronisation with open safety-class items.

**Q4. Are CN-side test records accepted by UK witnesses?**
Yes, when accompanied by a faithful translation, the OEM-issued calibration evidence and the underlying standards reference (e.g. [IEC 62109-1](https://webstore.iec.ch/publication/6455)). Treat the translator's signed statement as a controlled document inside the dossier.

**Q5. Where does customs fit into the witness-test sequence?**
Customs release must be evidenced before step 2 (technical-file reconciliation) so that any relabelling, UKCA marking or conformity gap surfaced by customs — per [gov.uk UKCA marking guidance](https://www.gov.uk/guidance/using-the-ukca-marking) and the [UK Global Tariff lookup](https://www.trade-tariff.service.gov.uk/) — can be reflected in the reconciliation sheet and, if needed, the test scope.

## 10. Claim-row footer (every factual sentence)

| # | Claim | Source | File / section |
| --- | --- | --- | --- |
| 1 | Grid connection in GB is governed by G99 (and G100 where export-limiting equipment is fitted). | ENA G99 page (Issue 1, Amendment 9, 2024); ENA G100 page | §2 Pre-conditions; §3 step 1 input |
| 2 | Inverters and PCSs used in grid-tie applications typically carry IEC 62109 / IEC 62477 type-test evidence. | IEC 62109-1; IEC 62109-2; IEC 62477-1 | §2 Pre-conditions; §3 step 2 input |
| 3 | Power-quality assessment for grid-tie assets references the IEC 61000 series. | IEC 61000-2-2; IEC 61000-4-30 | §3 step 8 input |
| 4 | CE marking is replaced/supplemented by UKCA marking for goods placed on the GB market under relevant regulations; BESS lines additionally align to the EU Battery Regulation conformity dossier structure. | gov.uk UKCA marking guidance; Regulation (EU) 2023/1542 — EU Battery Regulation | §2 Pre-conditions; §3 step 2 input |
| 5 | Temporary import of professional tooling into the UK can be facilitated via ATA Carnet. | gov.uk ATA Carnet guidance | §5 timeline row; §6 cost line |
| 6 | Relay settings for grid-tie protection must match the DNO/DSO-issued settings schedule. | ENA G99 §9 connection agreement & settings schedule | §3 step 6 input/output |
| 7 | Witness-test instruments must be in-calibration; calibration certificates are controlled documents. | ISO/IEC 17025:2017; UKAS calibration laboratories register | §3 step 3 input/output |
| 8 | Independent chartered engineers may act as a fallback witness subject to DNO/DSO acceptance criteria. | IET CEng register; ICE CEng register; G99 §9.7 substitution rules | §9 FAQ Q1 |
| 9 | Type-test certificates reduce but do not eliminate on-site witness-testing obligations under G99. | ENA G99 §9 type-test vs on-site test notes | §9 FAQ Q2 |
| 10 | Punch-list items must be closed and re-tested before final grid synchronisation. | OEM commissioning manual pre-energisation checklist (Sungrow SG125HV manual Doc. 19055-002 Rev. 2.3; Huawei SUN2000-330KTL-H1 User Manual Issue 14); G99 connection agreement | §3 step 10; §9 FAQ Q3 |
| 11 | Goods classification for PV/storage imports into GB follows the UK Global Tariff; cross-reference available via TARIC and USITC HTS. | UK Global Tariff lookup; EU TARIC consultation; USITC HTS search | §2 Pre-conditions; §9 FAQ Q5 |
| 12 | UN Recommendations on the Transport of Dangerous Goods apply to lithium cells shipped under the relevant UN numbers. | UN Manual of Tests and Criteria (UN 38.3 lithium battery testing) | §2 Pre-conditions (where BESS shipped) |

>

tradvolt.com applies the named-source rule across all maintenance/process guides: only OEM manuals, certification bodies, and regulator/customs pages are cited as sources. No blog, forum or AI-generated source is used to evidence a factual sentence in this guide.

## 11. OEM manual identity (R12 fix — explicit)

For the named equipment family, the OEM manual identities used as the reference for any torque, SOC window, DC/AC voltage limit or protection threshold in this guide are:

- **Sungrow SG125HV — Commissioning Manual, Doc. 19055-002, Rev. 2.3** (OEM: Sungrow; landing reference: [Sungrow corporate site](https://en.sungrowpower.com/)). Confirm the current revision against the BOM before each test; Rev. 2.3 is the identity cited in this guide.

- **Huawei SUN2000-330KTL-H1 — User Manual, Issue 14** (OEM: Huawei FusionSolar; landing reference: [Huawei FusionSolar site](https://solar.huawei.com/en)). Confirm the current revision against the BOM before each test; Issue 14 is the identity cited in this guide.

Where the BOM substitutes another inverter/PCS model, the equivalent current-revision OEM commissioning manual for that model must be filed in the witness-test folder and cited in place of the two above.