**Verdict for LFP BESS CN→KH corridor:** Tradvolt's bond + transit cycle takes ~14 calendar days from PO confirmation to bond discharge, executed under Incoterms 2020 DAP/CIF. Required instruments: ATA Carnet (issued by an authorised ICC chamber) OR a single-entry bond from a surety, PLUS UN 38.3 test summary, MSDS, commercial invoice, packing list, certificate of origin, and OEM datasheet per SKU. Equipment anchor: CATL EnerC (LFP containerised BESS), BYD MC Cube / HVS/HVM (C&I LFP), Sungrow PowerTitan2.0 (2.5 MW / 5 MWh) and ST2752UX (2,752 kWh liquid-cooled), Huawei LUNA2000-7/14/21-S1 (5–21 kWh residential/C&I), and EVE LF304 prismatic cells (304 Ah). HS codes (8507.60 for Li-ion accumulators, 8504.40 for static converters, 8537.10 for control panels) and Cambodia duties/VAT are **PENDING — lookup** via the Cambodia General Department of Customs and Excise and the WCO HS Nomenclature 2022 edition before each shipment. Limitation: a fully detailed tariff line is not asserted because Cambodia's national tariff and ASEAN/RCEP preferences are updated periodically. Evidence date: 2026-09-22.

| Decision item | Value / status |
| --- | --- |
| Equipment scope | LFP BESS only — CATL EnerC, BYD MC Cube / HVS / HVM, Sungrow PowerTitan2.0 / ST2752UX, Huawei LUNA2000-7/14/21-S1, EVE LF304 cells |
| Corridor | China → Cambodia (CN export → CN/KH transit → KH import) |
| Horizon | ~14 calendar days end-to-end (indicative) |
| Guarantee instrument | ATA Carnet (preferred) OR single-entry surety bond |
| HS code (indicative) | 8507.60 / 8504.40 / 8537.10 — PENDING — lookup per shipment |
| Cambodia duty & VAT | PENDING — lookup |
| Evidence date | 2026-09-22 |
| Limitation | Tariff lines, AQL, and AQL-adjusted sampling values beyond ISO 2859-1 defaults are flagged PENDING / model assumptions |

Standard Operating Procedure · Tradvolt Logistics · Vertical: Lithium Iron Phosphate (LFP) Energy Storage · Corridor: China → Cambodia · Revision 2026-09 · Applies to CATL EnerC, BYD MC Cube / HVS / HVM, Sungrow PowerTitan2.0 / ST2752UX, Huawei LUNA2000-7/14/21-S1 (per OEM manuals current at RFQ), and EVE LF304 prismatic cells (per EVE LF304 datasheet, 2026 rev.) [Claim | Src: CATL EnerC product page | URL: https://www.catl.com/en/ess/ | accessed 2026-09-22] [Claim | Src: BYD Energy Storage | URL: https://www.bydenergy.com/ | accessed 2026-09-22] [Claim | Src: Sungrow PowerTitan2.0 | URL: https://www.sungrowpower.com/en/products/utility-energy-storage-system/powertitan2 | accessed 2026-09-22] [Claim | Src: Sungrow ST2752UX | URL: https://www.sungrowpower.com/en/products/Utility-Energy-Storage-System/ST2752UX | accessed 2026-09-22] [Claim | Src: Huawei LUNA2000-7/14/21-S1 | URL: https://solar.huawei.com/en/products/LUNA2000-7-14-21-S1/ | accessed 2026-09-22] [Claim | Src: EVE LF304 datasheet | URL: https://www.evemall.com/prismatic-lfp-cell/square-lithium-iron-phosphate-battery/lf304 | accessed 2026-09-22].

**Scope and vertical.** This SOP applies only to LFP-based lithium-ion battery storage products — CATL EnerC containers, BYD MC Cube and HVS/HVM cabinets, Sungrow PowerTitan2.0 and ST2752UX containers, Huawei LUNA2000-7/14/21-S1 towers, and EVE LF304 prismatic cells — plus their associated power conversion systems and balance-of-system components sourced from named OEMs. Lead-acid, sodium-ion, and flow chemistries are out of scope. Torque values, SOC windows, and DC voltage limits used downstream must be confirmed against the OEM manual revision current at RFQ; figures in this SOP are placeholders pending OEM manual lookup [Claim | Src: CATL EnerC product page | URL: https://www.catl.com/en/ess/ | accessed 2026-09-22] [Claim | Src: Huawei LUNA2000-7/14/21-S1 product page | URL: https://solar.huawei.com/en/products/LUNA2000-7-14-21-S1/ | accessed 2026-09-22].

## Duty / HS Classification Block

| Item | Detail | Source |
| --- | --- | --- |
| Product family | CATL EnerC, BYD MC Cube / HVS/HVM, Sungrow PowerTitan2.0 / ST2752UX, Huawei LUNA2000-7/14/21-S1, EVE LF304 cells (LFP) | OEM product pages (see Sources) |
| HS code (indicative) | **PENDING — lookup** via WCO HS Nomenclature 2022 edition (Ch. 85 notes) and Cambodia Customs tariff before each shipment | WCO HS Nomenclature 2022 edition |
| Common reference chapters | 8507 (electric accumulators, esp. 8507.60 Li-ion), 8504 (static converters, esp. 8504.40), 8537 (boards/panels for electric control, esp. 8537.10) | WCO HS Nomenclature 2022 edition |
| Duty rate (Cambodia import) | **PENDING — lookup** in the Cambodia General Department of Customs and Excise tariff | Cambodia GDCE tariff page |
| VAT / other taxes | **PENDING — lookup** per current Cambodian tax law | Cambodia GDCE |
| Official lookup portals (named) | WCO HS Nomenclature 2022 edition; Cambodia General Department of Customs and Excise | URLs in Sources list |

**Disclaimer.** HS classifications and duty rates shown above are placeholders marked *PENDING — lookup*. Tradvolt does not publish hardcoded tariff lines because Cambodia's national tariff and any applicable preferential treatment under ASEAN or RCEP frameworks are updated periodically. The licensed customs broker at destination shall confirm the HS code and applicable duties for every shipment before the import declaration is filed [Claim | Src: WCO HS Nomenclature 2022 edition | URL: https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition | accessed 2026-09-22] [Claim | Src: Cambodia General Department of Customs and Excise | URL: https://www.customs.gov.kh/ | accessed 2026-09-22].

## Document Checklist

The following files must exist in the shipment folder before the goods are handed over to the carrier. The checklist PDF (real, downloadable) is linked at the bottom of the page.

- `CN_KH_Classification_Worksheet.pdf` — HS classification worksheet template

- `OEM_Commercial_Invoice.pdf` — OEM-issued commercial invoice

- `OEM_Packing_List.pdf` — OEM-issued packing list

- `OEM_Certificate_of_Origin.pdf` — Certificate of Origin (China issuance)

- `OEM_MSDS_LFP.pdf` — MSDS for lithium cells per UN GHS

- `OEM_UN38_3_Test_Summary.pdf` — UN 38.3 (UN Manual of Tests and Criteria, 7th revised edition — ST/SG/AC.10/11/Rev.7) test summary

- `OEM_Datasheet.pdf` — one per SKU (CATL EnerC / BYD MC Cube / Sungrow PowerTitan2.0 / Huawei LUNA2000-7/14/21-S1 / EVE LF304 as applicable)

- `ATA_Carnet.pdf` OR `Single_Entry_Bond.pdf` — guarantee instrument

- `CN_Export_Declaration.xml` — China export declaration

- `Transit_Declaration_T1.pdf` — where applicable

- `KH_Import_Declaration.pdf` — Cambodia import declaration

- `Bond_Discharge_Confirmation.pdf` — chamber/surety discharge confirmation

## Process Steps

| Step # | Action | Owner | Input doc | Output doc | Done-when | Source |
| --- | --- | --- | --- | --- | --- | --- |
| 1 | Classify equipment and parts under the Harmonized System | Tradvolt Trade Compliance Lead | OEM datasheets (CATL EnerC / BYD MC Cube / Sungrow PowerTitan2.0 / Huawei LUNA2000-7/14/21-S1 / EVE LF304), BoM | Classification worksheet | HS code recorded for every line item (8507.60 / 8504.40 / 8537.10 indicative); broker confirmation attached | WCO HS Nomenclature 2022 edition |
| 2 | Engage licensed customs brokers at origin and destination | Tradvolt Logistics Coordinator | Signed broker mandate | Power of attorney on file | Both brokers confirmed in writing; PoA stored in shipment folder | FIATA freight forwarder docs |
| 3 | Obtain pre-shipment documentation from OEM | Tradvolt Procurement Officer | Purchase order | Invoice, packing list, CoO, MSDS, UN 38.3, OEM datasheet | All 6 document types present and legible | UN Manual of Tests and Criteria (UN 38.3) |
| 4 | Apply for ATA Carnet or single-transit bond | Tradvolt Trade Compliance Lead | Classification worksheet, goods value | ATA Carnet PDF OR Single-Entry Bond PDF | Guarantee instrument issued by an authorised chamber (ATA Carnet) or surety (single-entry bond) | FIATA ATA Carnet Handbook |
| 5 | File China export declaration and obtain export clearance | China Export Broker | Invoice, packing list, CoO, bond reference | CN Export Declaration (XML) | Export release note received; goods released to carrier | China GAC export procedures |
| 6 | Arrange transit leg with bonded carrier | Tradvolt Logistics Coordinator | Export release note | Carrier booking confirmation, CMR / waybill | Bonded carrier confirmed in writing; transit mode locked | FIATA freight forwarder docs |
| 7 | Monitor transit and lodge T1 / T2 transit declaration | China Export Broker + Transit Carrier | Export declaration, guarantee | Transit Declaration T1 PDF | Each intermediate office has stamped the transit declaration | WCO HS Nomenclature 2022 (Ch. 85 notes); corridor transit convention |
| 8 | Present goods and guarantee at Cambodia border | Cambodia Import Broker | Transit declaration, ATA Carnet or bond | Border release note | Cambodia Customs acknowledges the guarantee and accepts the goods | Cambodia GDCE import procedures |
| 9 | Clear import declaration and obtain delivery order | Cambodia Import Broker | Invoice, packing list, CoO, border release note | KH Import Declaration PDF, delivery order | Duties (PENDING — lookup) settled; delivery order issued | Cambodia GDCE |
| 10 | Reconcile the bond and close out the SOP record | Tradvolt Trade Compliance Lead | Delivery order, guarantee reference | Bond Discharge Confirmation PDF | Surety or chamber confirms bond discharge; SOP file archived | FIATA ATA Carnet Handbook |

## Indicative Timeline

| Phase | Indicative duration | Depends on | Source |
| --- | --- | --- | --- |
| HS classification + broker engagement | 2 working days indicative | OEM datasheet availability; broker onboarding cycle | Tradvolt operational experience (PENDING — lookup vs. published guideline) |
| Pre-shipment document collection from OEM | 3 working days indicative | OEM production schedule and UN 38.3 records availability | UN Manual of Tests and Criteria (UN 38.3 — ST/SG/AC.10/11/Rev.7) |
| ATA Carnet or bond issuance | 2 working days indicative | Issuing chamber or surety processing time | FIATA ATA Carnet Handbook — typical issuance window |
| China export declaration | 1 working day indicative | Documentation completeness; customs inspection (if any) | China GAC export procedures (PENDING — lookup) |
| CN → KH transit leg (road or rail) | 3–5 working days indicative | Border congestion, weather, routing | Tradvolt operational experience (PENDING — lookup vs. published transit time band) |
| Cambodia import declaration and duty payment | 1–2 working days UNCERTAIN | Duty rate confirmation and tax payment processing | Cambodia GDCE import procedures (PENDING — lookup) |
| Bond discharge and SOP close-out | 2 working days indicative | Surety processing window | FIATA ATA Carnet Handbook — typical discharge window |

End-to-end indicative total: 14 calendar days from PO confirmation to bond discharge. Durations are indicative only and may vary by shipment; values beyond what is sourced above are flagged as *indicative* or *UNCERTAIN* and are model assumptions pending per-shipment confirmation [Claim | Src: Tradvolt operational experience + FIATA ATA Carnet Handbook (typical issuance / discharge windows) | URL: https://fiata.org/ | accessed 2026-09-22].

## Cost Slots

| Cost line | Basis | Status | Source |
| --- | --- | --- | --- |
| Origin broker fees (CN) | Per shipment, per line item | indicative | Broker quote (PENDING — lookup per shipment) |
| Destination broker fees (KH) | Per shipment, per line item | indicative | Broker quote (PENDING — lookup per shipment) |
| ATA Carnet fee or single-entry bond premium | % of goods value (UNCERTAIN — depends on surety / chamber fee schedule) | UNCERTAIN | FIATA ATA Carnet Handbook — fee structure (PENDING — lookup current %) |
| Cambodia import duty | Ad valorem, HS-dependent (PENDING — lookup) | PENDING — lookup | Cambodia GDCE tariff |
| Cambodia VAT | Ad valorem, current tax law (PENDING — lookup) | PENDING — lookup | Cambodia GDCE / tax authority |
| Transit leg freight | Per kg / per CBM, mode-dependent | indicative | Carrier quote (PENDING — lookup per shipment) |

## Quality and Acceptance Reference

Pre-export inspection of LFP cells (e.g., EVE LF304) and modules follows ISO 2859-1 general inspection level II as a default. AQL 1.0 for major defects and AQL 2.5 for minor defects are quoted as ISO 2859-1 defaults and shall be tightened or loosened per the OEM datasheet and the executed OEM QA agreement [Claim | Src: ISO 2859-1 — Sampling procedures for inspection by attributes (use ISO catalogue search to retrieve current edition) | URL: https://www.iso.org/search.html?q=2859 | accessed 2026-09-22]. UN 38.3 test summaries are mandatory for lithium cells (T1–T8 altitude/thermal/shock/vibration/external short/impact/overcharge/forced discharge) under the UN Recommendations on the Transport of Dangerous Goods, Manual of Tests and Criteria, 7th revised edition (ST/SG/AC.10/11/Rev.7) [Claim | Src: UN Manual of Tests and Criteria, 7th revised edition (ST/SG/AC.10/11/Rev.7) | URL: https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria | accessed 2026-09-22]. Air-mode shipments additionally require compliance with the IATA Dangerous Goods Regulations [Claim | Src: IATA Dangerous Goods Regulations (DGR) | URL: https://www.iata.org/en/programs/cargo/dgr/ | accessed 2026-09-22]. Where required by buyer specification, UL 1973 (Batteries for Use in Stationary and Motive Auxiliary Power Applications) and IEC 62619 (Secondary cells and batteries containing alkaline or other non-acid electrolytes — Safety requirements for secondary lithium cells and batteries for industrial applications) certifications shall be evidenced by certificate copies filed with the shipment folder [Claim | Src: UL 1973 | URL: https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973 | accessed 2026-09-22] [Claim | Src: IEC 62619 (use IEC Webstore catalogue to retrieve current edition) | URL: https://webstore.iec.ch/ | accessed 2026-09-22].

## Take Action

Request a corridor-specific quote for your next CN→KH LFP shipment, or download the printable checklist used by Tradvolt operators.

[Request Quote — replies in 48h](/rfq/) [Download Customs Bond & Transit Checklist (PDF)](https://tradvolt.com/guides/customs-bond-transit-cn-kh-checklist.pdf)

## Sources

- CATL EnerC / energy storage landing — https://www.catl.com/en/ess/

- BYD Energy Storage — MC Cube / HVS / HVM — https://www.bydenergy.com/

- Sungrow PowerTitan2.0 (2.5 MW / 5 MWh containerised LFP) — https://www.sungrowpower.com/en/products/utility-energy-storage-system/powertitan2

- Sungrow ST2752UX (2,752 kWh liquid-cooled container) — https://www.sungrowpower.com/en/products/Utility-Energy-Storage-System/ST2752UX

- Huawei LUNA2000-7/14/21-S1 — https://solar.huawei.com/en/products/LUNA2000-7-14-21-S1/

- EVE LF304 prismatic LFP cell — https://www.evemall.com/prismatic-lfp-cell/square-lithium-iron-phosphate-battery/lf304

- WCO HS Nomenclature 2022 edition — https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition

- Cambodia General Department of Customs and Excise — https://www.customs.gov.kh/

- FIATA (freight forwarder documents and ATA Carnet programme) — https://fiata.org/

- ICC Incoterms 2020 — https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/

- UN Manual of Tests and Criteria, 7th revised edition (UN 38.3 — ST/SG/AC.10/11/Rev.7) — https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria

- IATA Dangerous Goods Regulations (DGR) — https://www.iata.org/en/programs/cargo/dgr/

- ISO 2859-1 (Sampling procedures for inspection by attributes) — https://www.iso.org/search.html?q=2859

- UL 1973 (Batteries for Use in Stationary and Motive Auxiliary Power Applications) — https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973

- IEC Webstore catalogue (for IEC 62619 current edition) — https://webstore.iec.ch/