# ESS Site Acceptance Test (SAT) — China → Türkiye Corridor

**Document type:** Process / SOP | **Vertical:** Solar Balance-of-System | **Trade lane:** CN &rarr; TR | **Scope:** Energy Storage System (BESS) site acceptance testing

**Verdict (see §6, §9):** SAT requires ~7 active on-site days after CN→TR sea transit; HS code and import duty/VAT are PENDING customs broker confirmation against the Republic of Türkiye Ministry of Trade tariff portal. Reference equipment family: CATL EnerC series containerised LFP BESS paired with a Sungrow SG3125HV-MV PCS (model-level torque, SOC window and DC-bus limits below are model assumptions to be re-confirmed against the OEM service manual revision at RFQ).

| Field | Value |
| --- | --- |
| Equipment / location | Lithium-ion BESS (EnerC container family) + Sungrow SG3125HV-MV PCS, TR project site |
| Horizon | ~7 active SAT days post-transit, plus 25–35 days CN→TR sea transit |
| Evidence date | Source reference date: 2026-09-22 |
| Duty / HS | PENDING — broker confirmation via Türkiye Ministry of Trade tariff portal |
| Limitation | Specific torque, SOC and voltage limits are model assumptions; OEM manual revision must be confirmed at RFQ |

## 1. Purpose

This Standard Operating Procedure (SOP) defines how Tradvolt executes a Site Acceptance Test (SAT) for an Energy Storage System (ESS) delivered on the China &rarr; Türkiye trade lane. It standardises the responsibilities, inputs, outputs, and gating criteria so that the SAT is reproducible across vertical solar BoS projects. [Claim | Src: Tradvolt internal SOP template (cross-referenced with public Tradvolt process documentation) | URL: https://tradvolt.com/guides/ | reference date: 2026-09-22]

The procedure aligns with the OEM service-manual requirement that final acceptance, including charge/discharge functionality, be witnessed on-site at the BESS location rather than at the factory. For the reference configuration, the CATL EnerC container service manual and the Sungrow SG3125HV-MV PCS installation and commissioning manual govern the on-site checks. [Claim | Src: CATL ESS product family page | URL: https://www.catl.com/en/ess/ | reference date: 2026-09-22] [Claim | Src: Sungrow product and service portal | URL: https://www.sungrowpower.com/en | reference date: 2026-09-22]

## 2. Scope

**In scope:** Containerised or skid-mounted lithium BESS (reference: CATL EnerC series), PCS (reference: Sungrow SG3125HV-MV), BMS, MV/LV interface cabinets, SCADA gateway, and associated cabling accessories delivered as Solar Balance-of-System equipment. The cell-level safety expectations align with IEC 62619 (Secondary cells and batteries containing alkaline or other non-acid electrolytes — Safety requirements for secondary lithium cells and batteries, for use in industrial applications), and the overall ESS vocabulary/terminology aligns with IEC 62933-1 (Electrical energy storage systems — Part 1: Vocabulary). [Claim | Src: IEC 62933-1 vocabulary for EES terminology | URL: https://webstore.iec.ch/ | reference date: 2026-09-22] [Claim | Src: IEC 62619 industrial lithium cell/battery safety | URL: https://webstore.iec.ch/ | reference date: 2026-09-22]

**Out of scope:** PV module flash tests, inverter DC-side commissioning handled under a separate SOP, and civil engineering acceptance.

## 3. Roles

- **Project Manager (PM):** Single point of contact; owns the SAT schedule and punch-list closure.

- **Site Engineer (SE):** Executes the on-site inspection and functional tests; signs daily site log.

- **Commissioning Lead (CL):** Owns functional testing and SCADA integration; signs functional test sheets.

- **QA / QC Officer (QA):** Owns document control, AQL sampling, and issuance of the SAT report.

- **Logistics Coordinator (LC):** Owns transport milestones, customs dossier, and seal/ETA tracking.

- **Customer Representative (CR):** Witnesses SAT, co-signs the acceptance certificate.

## 4. Reference documents

- *CATL EnerC container service manual — SAT section* (manual revision to be confirmed at RFQ; treat as model assumption). [Src: CATL ESS product family page | URL: https://www.catl.com/en/ess/ | reference date: 2026-09-22]

- *Sungrow SG3125HV-MV installation and commissioning manual* (revision to be confirmed at RFQ; treat as model assumption). [Src: Sungrow product and service portal | URL: https://www.sungrowpower.com/en | reference date: 2026-09-22]

- IEC 62933 (series) — Electrical energy storage systems; Part 1: Vocabulary. [Src: IEC Webstore catalogue | URL: https://webstore.iec.ch/ | reference date: 2026-09-22]

- IEC 62619 — Secondary cells and batteries containing alkaline or other non-acid electrolytes — Safety requirements for secondary lithium cells and batteries, for use in industrial applications. [Src: IEC Webstore catalogue | URL: https://webstore.iec.ch/ | reference date: 2026-09-22]

- UL 1973 — Batteries for Use in Stationary and Motive Auxiliary Power Applications. [Src: UL Standards | URL: https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973 | reference date: 2026-09-22]

- UL 9540 — Standard for Energy Storage Systems and Equipment (referenced as applicable). [Src: UL Standards catalogue | URL: https://www.shopulstandards.com/ | reference date: 2026-09-22]

- ISO 2859-1 — Sampling procedures for inspection by attributes, single sampling plans by AQL. [Src: ISO standards search | URL: https://www.iso.org/search.html?q=2859 | reference date: 2026-09-22]

- UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7 (UN 38.3 lithium battery provisions). [Src: UNECE | URL: https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria | reference date: 2026-09-22]

- ICC Incoterms 2020 — DAP and CIP clauses relevant to delivery under SAT liability. [Src: ICC | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | reference date: 2026-09-22]

- FIATA multimodal transport documentation guidance (where MTD applies). [Src: FIATA | URL: https://fiata.org/ | reference date: 2026-09-22]

- Republic of Türkiye Ministry of Trade — customs and tariff reference. [Src: Republic of Türkiye Ministry of Trade | URL: https://www.trade.gov.tr/ | reference date: 2026-09-22]

## 5. Process sequence

| Step # | Action | Owner | Input doc | Output doc | Done-when |
| --- | --- | --- | --- | --- | --- |
| 1 | Confirm SAT scope, equipment list (incl. CATL EnerC container SN, Sungrow SG3125HV-MV firmware), contractual SAT window, and issue the SAT plan. | PM | Contract / SAT clause | TVT-SAT-PLAN-v1.0.pdf | Signed SAT plan received from CR and OEM. |
| 2 | Witness or verify pre-shipment inspection (PSI) at the OEM facility in China prior to container sealing. | QA | PSI checklist | TVT-PSI-REPORT.pdf | PSI report countersigned; seal number recorded. |
| 3 | Verify Chinese export customs pre-clearance declaration against the Bill of Lading and packing list. | LC | Commercial invoice, packing list | TVT-CN-EXPORT-DECL.pdf | Declaration reference archived; goods permitted to gate out. |
| 4 | Confirm booking, container seal number, and enable milestone tracking across the CN→TR sea lane. | LC | Booking confirmation | TVT-TRACK-LOG.xlsx | Vessel ETA confirmed and tracking link active. |
| 5 | Prepare the TR import pre-arrival dossier with the customs broker; flag the ESS equipment for HS classification (see §10). | LC | CI, PL, BL, OEM certificate | TVT-TR-IMPORT-DOSSIER.pdf | Broker confirms dossier completeness; reference number logged. |
| 6 | Verify civil, electrical, fire-suppression, ventilation, and SCADA-network readiness at the BESS site. | SE | Site readiness checklist | TVT-PREREADY-CHECK.pdf | All site prerequisites checked on the pre-readiness form. |
| 7 | Execute visual and mechanical inspection against the CATL EnerC service manual checklist (torque marks, labelling, IP integrity). | SE | OEM SAT checklist, ISO 2859-1 AQL table | TVT-VMI-REPORT.pdf | All visual items ticked; deviations logged as punch items. |
| 8 | Run the OEM-mandated charge and discharge cycles with the CL per the Sungrow SG3125HV-MV commissioning manual; capture SCADA telemetry traces and cell-level logs. | CL | OEM PCS parameter file | TVT-FUNC-TEST.xlsx | Cycles completed; logged parameters meet OEM acceptance band. |
| 9 | Verify grid-support functions (frequency ride-through, anti-islanding, voltage/reactive control) per the relevant grid code. | CL | Grid-code compliance sheet | TVT-GRID-COMPLIANCE.pdf | All grid-support tests pass; trace evidence attached. |
| 10 | Apply AQL sampling per ISO 2859-1 to cable accessories, labels, documentation sets, and cosmetic surfaces. | QA | ISO 2859-1 table | TVT-AQL-SAMPLE.pdf | Sampling decision recorded (Accept / Reject / Continue). |
| 11 | Compile and close the punch-list of non-conformities; secure re-test evidence for any open items. | PM | Punch-list register | TVT-PUNCH-LIST.pdf | Punch-list status = CLOSED or formally documented as deferred. |
| 12 | Obtain signatures on the SAT report and archive the full deliverable dossier to the customer O&M team. | QA | SAT report draft | TVT-SAT-REPORT-FINAL.pdf | Signed SAT certificate archived; O&M hand-over acknowledged in writing. |

## 6. Timeline & dependencies

| Phase | Activity | Indicative duration | Predecessor |
| --- | --- | --- | --- |
| A | SAT plan & scope (Steps 1) | 1 day | Contract handover complete |
| B | Pre-shipment (Step 2) | 2 days at OEM site | A closed |
| C | CN export + transit (Steps 3–4) | 25–35 days (sea CN→TR) | B signed |
| D | TR import dossier (Step 5) | 3 days pre-arrival | BL issued in C |
| E | On-site pre-readiness (Step 6) | 1 day | Civil works handover complete |
| F | On-site SAT execution (Steps 7–10) | 3 days | D delivered, E cleared |
| G | Punch-list + sign-off (Steps 11–12) | 2 days | F complete |
| **Total indicative** | **~7 days active + sea transit** | — |

*All transit durations above are indicative; vessel cut-offs and customs windows may shift the on-site SAT window. Sea-transit lead-time figures are not hard-coded because they depend on carrier schedule, port pair, and the Incoterms 2020 risk transfer point. [Claim | Src: ICC Incoterms 2020 | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | reference date: 2026-09-22]*

## 7. Equipment limits (model assumption)

The numerical limits in this section are **model assumptions** for the reference configuration (CATL EnerC container + Sungrow SG3125HV-MV PCS) and must be re-validated against the OEM service-manual revision in force at the time of SAT. Tradvolt does not assert these as universal limits.

| Parameter | Assumed limit | Source / status |
| --- | --- | --- |
| DC bus voltage window (PCS) | 1,000–1,500 V DC (Sungrow SG3125HV-MV class) | [Model assumption \| Sungrow product family \| URL: https://www.sungrowpower.com/en \| reference date: 2026-09-22] |
| Battery SOC operating window | 5%–95% SOC during commissioning cycles | [Model assumption \| CATL EnerC operating envelope \| URL: https://www.catl.com/en/ess/ \| reference date: 2026-09-22] |
| Torque — DC power cable lugs | Per OEM manual section (Nm value to be re-confirmed against revision) | [Model assumption \| CATL service manual \| URL: https://www.catl.com/en/ess/ \| reference date: 2026-09-22] |
| Torque — battery module busbars | Per OEM manual section (Nm value to be re-confirmed against revision) | [Model assumption \| CATL service manual \| URL: https://www.catl.com/en/ess/ \| reference date: 2026-09-22] |
| Cell safety reference | UN 38.3 (ST/SG/AC.10/11/Rev.7); IEC 62619 | [Claim \| UNECE UN Manual of Tests and Criteria \| URL: https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria \| reference date: 2026-09-22] [Claim \| IEC 62619 catalogue \| URL: https://webstore.iec.ch/ \| reference date: 2026-09-22] |

## 8. Document checklist

Each item below corresponds to a literal filename in Tradvolt's document repository. Customers may request the package as a single ZIP via the RFQ flow for audit purposes.

- TVT-SAT-PLAN-v1.0.pdf

- TVT-PSI-REPORT.pdf

- TVT-CN-EXPORT-DECL.pdf

- TVT-TRACK-LOG.xlsx

- TVT-TR-IMPORT-DOSSIER.pdf

- TVT-PREREADY-CHECK.pdf

- TVT-VMI-REPORT.pdf

- TVT-FUNC-TEST.xlsx

- TVT-GRID-COMPLIANCE.pdf

- TVT-AQL-SAMPLE.pdf

- TVT-PUNCH-LIST.pdf

- TVT-SAT-REPORT-FINAL.pdf

## 9. Indicative cost slots

The slots below are **indicative** and not a quotation. Final figures depend on vessel schedule, Incoterms 2020 point of delivery, and TR customs duty assessment (see §10).

- **Indicative** — OEM pre-shipment inspection service fee

- **Indicative** — Ocean freight CN→TR (port pair: e.g., Shanghai → Ambarlı; subject to BAF/THC)

- **Indicative** — Türkiye customs broker fee (TR import pre-arrival dossier)

- **Indicative** — On-site SAT engineering days × applicable day-rate

- **UNCERTAIN** — TR import duty / VAT treatment pending HS-based assessment (see §10)

## 10. Duty / HS code block

| Field | Value |
| --- | --- |
| Equipment | Lithium-ion BESS (CATL EnerC container family) with Sungrow SG3125HV-MV PCS, BMS, MV/LV cabinet — solar BoS |
| HS code (equipment/parts) | PENDING — lookup against the Turkish customs tariff (Gümrük Tarife İstatistik Pozisyonu) via the Republic of Türkiye Ministry of Trade portal; cross-reference with the WCO Harmonized System nomenclature for the exact configuration. [Claim \| Src: Republic of Türkiye Ministry of Trade \| URL: https://www.trade.gov.tr/ \| reference date: 2026-09-22] |
| Applicable duty rate | PENDING — lookup; rate depends on the exact HS heading/subheading determined for the shipment. |
| VAT / other levies | PENDING — lookup against the current VAT rate and any exempted/special-regime treatment published by the official customs portal. |
| Official portal consulted | Republic of Türkiye Ministry of Trade — trade.gov.tr |
| Disclaimer | Tradvolt does not hard-code duty rates. Final duty figures must be confirmed with the appointed customs broker against the actual HS classification of the equipment at the time of import. Trade remedies, anti-dumping, or safeguard measures may apply; these are not captured in this SOP. |

*Reference for trade documentation handling:* ICC Incoterms 2020 risk-transfer clauses (DAP / CIP most common for SAT-liability deliveries). [Claim | Src: ICC Incoterms 2020 | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | reference date: 2026-09-22]