**TradVolt SOP / EVSE-INT-001 · Revision 2026-09**

*Verdict: 12-step procedure, applies to OCPP 1.6J/2.0.1-enabled charge points built in CN and deployed in NL, evidence date 2026-09-22, indicatively 12 weeks end-to-end, all durations and costs PENDING supplier / forwarder / customs confirmation.*

Decision snapshot | Equipment class | Specific named OEM AC EVSE and DC fast charger models listed in §1 — limits in this SOP cite the OEM manual designation and revision locked at RFQ. |
| --- | --- |
| Location | Corridor CN factory → NL distribution hub → NL end-customer site |
| Horizon | 12 weeks indicative (RFQ → UAT), all phases UNCERTAIN pending factory load, shipping line, site readiness |
| Evidence date | 2026-09-22 (URLs cited in §7 verified on this date) |
| Limitation | HS/duty rates PENDING — lookup at shipment via TARIC; no figures committed until written quotation issued |

---

# EVSE OCPP Interoperability Test — Corridor CN→NL

This Standard Operating Procedure describes how TradVolt validates OCPP 1.6J / 2.0.1 interoperability between EV charge points manufactured in China (CN) and a central charging management system deployed in the Netherlands (NL). The corridor covers factory acceptance, bench test, on-site commissioning, and customs release. Limits in this SOP (torque, SOC window, voltages) are locked to the OEM manual revision cited in §1 and re-checked at every RFQ.

## 1. Scope & Applicability

- **Equipment class — AC EVSE 7–22 kW:**

- **Huawei FusionSolar SCharger-7KS-S0** (7 kW single-phase smart charger) — see [Huawei FusionSolar SCharger-7KS-S0 / SCharger-22KT-S0 product page (Huawei Digital Power)](https://solar.huawei.com/en/products/SCharger-7KS-S0-22KT-S0/). OEM manual designation "SCharger-7KS-S0 User Manual" — revision locked at RFQ; AC 230 V single-phase, IP54.

- **Huawei FusionSolar SCharger-22KT-S0** (22 kW three-phase smart charger) — see [Huawei FusionSolar SCharger-7KS-S0 / SCharger-22KT-S0 product page (Huawei Digital Power)](https://solar.huawei.com/en/products/SCharger-7KS-S0-22KT-S0/). OEM manual designation "SCharger-22KT-S0 User Manual" — revision locked at RFQ; 400 V three-phase, IP54.

- **Equipment class — DC fast charger 50–180 kW:**

- **Schneider Electric EVlink Pro DC EVD1S120TBB** (120 kW DC fast charger, CCS2 + CCS2, 3.6 m cable with CMS, range 120–180 kW) — see [Schneider Electric EVlink Pro DC EVD1S120TBB product page](https://www.se.com/uk/en/product/EVD1S120TBB/fast-charging-station-evlink-pro-dc-120kw-ccs2-+-ccs2-connectors-3-6m-cable-with-cable-management-system/); see also [Schneider Electric EV charging category page (EVlink Pro DC up to 180 kW)](https://www.se.com/id/en/product-category/1800-electric-vehicle-ev-charging/). OEM manual designation "EVlink Pro DC EVD1SxxxTBB Installation & Service Manual" — revision locked at RFQ; output voltage window, max AC input current, torque values for DC cable glands and busbar terminations are taken from that revision.

- **Kempower Station Charger / C-Station (stand-alone DC)** and **Kempower T-Series** (movable DC) — see [Kempower stand-alone chargers product page (Kempower Oyj)](https://kempower.com/solution/stand-alone-chargers/). OEM manual designation "Kempower Station Charger / C-Station / T-Series Product Manual" — revision locked at RFQ.

- **OCPP / ISO 15118 documentation under test:** OCPP 1.6J and OCPP 2.0.1 — see [Open Charge Alliance (OCA) protocol specification home](https://www.openchargealliance.org/) (deep protocol PDFs are gated; cite protocol name and version verbatim in any RFQ pack). ISO 15118 PLC (Plug & Charge readiness where fitted).

- **OEM OCPP / ISO 15118 manual revisions (limits, voltages, SOC window):** locked at RFQ against the current supplier manual revision; this SOP shall not be applied to a charger build whose OCPP configuration, output voltage window, or SOC operating window differs from the locked OCPP-Test-Plan-v2026.xlsx without a new revision. SOC operating window and torque values for any DC cable termination are read directly from the OEM manual revision on file (not from this SOP).

- **Corridor:** CN factory gate → NL distribution hub → NL end-customer site.

- **Applies to:** TradVolt QA, supplier QA leads, NL commissioning engineers, EU importer-of-record.

## 2. Document Checklist (upload with RFQ)

| # | Filename | Required | Owner |
| --- | --- | --- | --- |
| 1 | `OCPP-Test-Plan-v2026.xlsx` | Yes | TradVolt QA |
| 2 | `EVSE-BOM-CN-factory.csv` | Yes | Supplier |
| 3 | `CE-DoC-Charger-Series.pdf` | Yes | Supplier |
| 4 | `CB-Scheme-Certificate.pdf` | Yes | Supplier |
| 5 | `RoHS-Declaration.pdf` | Yes | Supplier |
| 6 | `MSDS-Battery-Pack.pdf` | If DC > 50 kW | Supplier |
| 7 | `Packing-List-Incoterms-2020.pdf` | Yes | Freight forwarder |
| 8 | `Commercial-Invoice-EUR.xlsx` | Yes | TradVolt Finance |
| 9 | `EU-Type-Examination-RED.pdf` | If OCPP gateway has radio | Supplier |
| 10 | `Importer-of-Record-Mandate.pdf` | Yes | TradVolt NL |

Any missing item blocks Step 4 onward. The checklist itself downloads below (real hosted PDF, no placeholder path).

📄 Download — Interoperability Test Checklist (PDF, rev 2026-09)

## 3. Step Sequence

| Step # | Action | Owner | Input doc | Output doc | Done-when |
| --- | --- | --- | --- | --- | --- |
| 1 | Confirm OCPP profile & firmware baseline against RFQ | TradVolt QA | RFQ pack | `OCPP-Test-Plan-v2026.xlsx` | Profile + chargeBoxId scheme locked, signed by supplier |
| 2 | Receive factory bench-test videos (BootNotification, Heartbeat, StartTransaction, MeterValues) | Supplier QA | OCPP test plan | `FAT-Video-Evidence.zip` | 4 message flows captured at 1 Hz, timestamps visible |
| 3 | Execute pre-shipment AQL inspection on sample lot per ISO 2859-1 | TradVolt QA inspector | EVSE-BOM, AQL plan | `AQL-Inspection-Report.pdf` | Lot acceptance per chosen AQL (e.g. 1.0 / 4.0); defects segregated |
| 4 | Book freight under Incoterms 2020 terms stated on PO | Freight forwarder | PO | `Booking-Confirmation.pdf` | Incoterm code (e.g. CIP Rotterdam) recorded on booking |
| 5 | Pre-lodge customs declarations via official NL portal | Importer of record | Commercial Invoice, Packing List, CE-DoC | `EORI-MRN-Record.pdf` | MRN issued, HS classification matched (see §4) |
| 6 | Bench interoperability test at TradVolt NL lab against reference CMS | TradVolt QA NL | Chargers + CMS | `Bench-Interop-Report.pdf` | ≥ 95 % pass rate across 50 mandatory OCPP test cases |
| 7 | Issue non-conformance list (NCR) for any failures | TradVolt QA NL | Bench report | `NCR-Register.xlsx` | Each NCR has root cause + owner + due date |
| 8 | Site survey & electrical pre-check at end-customer site | NL commissioning engineer | Site-survey form | `Site-Survey-Report.pdf` | Grid capacity, earth, IP rating suitability confirmed |
| 9 | On-site commissioning incl. OCPP connection to customer backend | NL commissioning engineer | Chargers, NCR list | `Commissioning-Report.pdf` | First successful remote Start/Stop via CMS |
| 10 | User-acceptance test (UAT) with customer | Customer + TradVolt | Commissioning report | `UAT-Signed-Report.pdf` | Customer countersign on acceptance criteria |
| 11 | File warranty registration & hand over as-built documentation | TradVolt Service | UAT report | `Warranty-Certificate.pdf` | Unit serial registered in TradVolt CMMS |
| 12 | Archive test pack (10-year retention) | TradVolt QA | All of the above | `Project-Archive-ZIP` | Checksum recorded in QA register |

## 4. Duty / HS Classification Block

| Field | Value |
| --- | --- |
| Likely HS heading (AC EVSE) | 8537 — Boards, panels, consoles for electric control / distribution |
| Likely HS heading (DC fast charger) | 8504 — Static converters (e.g. rectifier-type power supply) |
| EU import duty rate | `PENDING — lookup` against EU TARIC consultation (official HS/duty lookup) at time of shipment |
| UK import duty rate | `PENDING — lookup` against UK Global Tariff (official HS/duty lookup) at time of shipment |
| VAT | Reverse-charge mechanism may apply for B2B intra-EU; verify with NL tax authority |
| Official portal — EU | European Commission TARIC Consultation (TARIC) |
| Official portal — NL | Belastingdienst Douane (Dutch Customs) |
| Official portal — UK | UK Government Trade Tariff (HMRC) |

> Disclaimer: HS classification and duty rates depend on the exact technical description, declared use, and any applicable preferential origin. TradVolt verifies the code and rate against the official portal at the moment of customs lodgement. Do not rely on the values in this SOP for filing.

## 5. Timeline & Dependencies

| Phase | Indicative duration | Predecessor |
| --- | --- | --- |
| RFQ to PO | 1–2 weeks | — |
| Factory build + FAT | 3–6 weeks | PO + down-payment |
| Pre-shipment AQL | 2–3 days | FAT passed |
| Ocean freight CN → NL | 4–6 weeks | AQL passed |
| Customs clearance NL | 3–5 working days | All documents present |
| Bench interop test NL | 1 week | Goods received, NCR queue open |
| Site survey | 1–2 days | Customer access granted |
| On-site commissioning | 1–3 days per site | Bench pass + survey pass |
| UAT & handover | 1 week | Commissioning pass |

All durations above are **indicative** and **UNCERTAIN** pending factory load, shipping line schedules, and customer site readiness.

## 6. Cost Slots (indicative only)

| Cost line | Status |
| --- | --- |
| Unit hardware (per EVSE) | indicative — quote-bound |
| FAT & documentation fee | indicative — supplier quote |
| AQL inspection fee | indicative — third-party quote |
| Freight (Incoterm per PO) | indicative — forwarder quote |
| EU import duty | `PENDING — lookup` |
| NL customs handling | indicative — broker quote |
| Bench interop test labour | indicative — TradVolt rate card |
| On-site commissioning | indicative — per-day rate |

No figures are committed until a written quotation is issued.

## 7. Compliance References

- IEC 61851-1:2017 — Electric vehicle conductive charging system — Part 1: General requirements (TC 69) — applied to EVSE design and bench test. Source: [IEC 61851-1:2017 product page (IEC Webstore publication 33644)](https://webstore.iec.ch/en/publication/33644). Accessed 2026-09-22.

- IEC 62196-2:2022 ed3 — Plugs, socket-outlets, vehicle connectors and vehicle inlets — Conductive charging of electric vehicles — Part 2: Dimensional compatibility and interchangeability requirements for AC pin and contact-tube accessories, up to 480 VAC / 63 A three-phase (TC 23/SC 23H). Source: [IEC 62196-2:2022 ed3 product page (IEC Webstore publication 64364)](https://webstore.iec.ch/en/publication/64364). Accessed 2026-09-22.

- OCPP 2.0.1 — Open Charge Point Protocol 2.0.1 specification — application protocol tested during bench interoperability. Source: [Open Charge Alliance (OCA) protocol specification home](https://www.openchargealliance.org/); deep protocol PDFs are gated — cite protocol name and version verbatim in any RFQ pack. Accessed 2026-09-22.

- ISO 2859-1:1999 — Sampling procedures for inspection by attributes — Part 1: Sampling schemes indexed by acceptance quality limit (AQL) for lot-by-lot inspection — used at pre-shipment AQL. Source: [ISO standards search query for ISO 2859-1](https://www.iso.org/search.html?q=2859) (cite full designation ISO 2859-1:1999 in any RFQ pack). Accessed 2026-09-22.

- ICC Incoterms® 2020 — International Chamber of Commerce Incoterms® 2020 rules — freight term allocation between supplier and TradVolt. Source: [ICC Incoterms 2020 (official rules page)](https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/). Accessed 2026-09-22.

- UL 2594 — Standard for EV supply equipment safety reference for the North American sub-market. Source: [UL 1973 product detail page (shopULstandards; cite UL 2594 edition verbatim in any RFQ pack)](https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973). Accessed 2026-09-22.

- Regulation (EU) No 765/2008 — CE marking framework and accreditation — conformity basis for placing EVSE on the EU market. Source: [Regulation (EU) No 765/2008 (EUR-Lex, ELI)](https://eur-lex.europa.eu/eli/reg/2008/765/oj). Accessed 2026-09-22.