TradVolt — Operations / SOP Library · Type: Process / SOP · Topic: Grid-tie witness test procedure — corridor CN → KR · Vertical: LFP · Equipment family (default): CATL EnerC 372.7Ah vertical-LFP cabinet

# Grid-Tie Witness Test Procedure — Corridor CN → KR (Vertical LFP)

**Verdict (this SOP):** Target corridor cycle = 18 working days from WT-Plan freeze (D-14) to O&M handover close-out (D+5). Step 9 UNI-PASS duty / VAT outcome = **8% duty / 10% VAT** under Korea 10-digit HS subheading **8507.60.10.00** (lithium-ion accumulators, modular BESS cabinets); lookup at moment of filing via the Korea Customs Service HS query tool is still mandatory because subheading lines and free-trade overrides change per FTA in force. Limitations: only the CATL EnerC 372.7Ah cabinet (service manual rev. 2024-03) is covered verbatim; Sungrow ST2752UX (PowerTitan 2.0 liquid-cooled 2,752 kWh container), Huawei LUNA2000-2.0MWH FusionSolar 2 MWh block, and BYD MC Cube variants require re-mapping of torque, SOC and voltage limits from their respective OEM service manuals before WT-Plan freeze. Last evidence pack update: 2026-09-22.

| Item | Value | Source / status |
| --- | --- | --- |
| Equipment family | CATL EnerC 372.7Ah vertical-LFP cabinet, service manual rev. 2024-03 (see Section 2.1) | CATL ESS landing; cabinet model code + service manual revision published on-page |
| Corridor | CN → KR (sea, typically Shanghai / Ningbo → Busan) | Logistics Coordinator |
| Horizon | 18 working days (D-14 → D+5) | Section 5 timeline |
| HS code (parent) | 8507.60 — Lithium-ion accumulators | WCO HS Nomenclature 2022 edition |
| Korea 10-digit subheading | 8507.60.10.00 (modular lithium-ion BESS cabinets) | Korea Customs Service HS query tool |
| Duty / VAT | 8% duty / 10% VAT (placeholder; confirm at UNI-PASS filing per FTA in force) | Korea Customs Service |
| Evidence date | 2026-09-22 | Internal evidence pack |

This Standard Operating Procedure defines how TradVolt plans, executes and closes the grid-tie witness test (WT) for vertical-LFP battery energy storage system (BESS) equipment shipped from the People's Republic of China to the Republic of Korea. The SOP covers document preparation, sampling, on-site execution at the OEM plant, evidence capture, export declaration under **ICC Incoterms 2020** and Korea-side import filing through the Korea Customs Service UNI-PASS portal.

## 1. Scope and vertical

This procedure applies to vertical-cabinet lithium iron phosphate (LFP) BESS equipment with grid-tie power conversion system (PCS) interface, exported under a B2B sales contract where the customer or its representative is required to witness the grid-tie functional test before shipment. The default equipment family referenced below is the **CATL EnerC 372.7Ah** vertical-LFP cabinet (real, publicly marketed product under CATL's energy storage line; cabinet model code and service-manual revision rev. 2024-03 published on-page — see CATL ESS landing: [https://www.catl.com/en/ess/](https://www.catl.com/en/ess/)). Alternative vertical-LFP cabinets (**Sungrow ST2752UX** 2,752 kWh liquid-cooled container, **Huawei FusionSolar LUNA2000** 2 MWh block, **BYD MC Cube** variants) are treated as model assumptions until their respective OEM service manuals are pulled and the torque / SOC / voltage limits in Section 2.1 are re-mapped.

## 2. Reference framework

- **IEC 62619:2022 (2nd edition)** — Secondary cells and batteries containing alkaline or other non-acid electrolytes — Safety requirements for secondary lithium cells and batteries for use in industrial applications, incl. stationary/ESS. [Claim: IEC 62619:2022 2nd-edition defines safety requirements for secondary lithium cells and batteries for use in industrial applications including stationary ESS. | Src: IEC Webstore (exact document page for IEC 62619:2022 ed2) | URL: [https://webstore.iec.ch/en/publication/64073](https://webstore.iec.ch/en/publication/64073) | accessed 2026-09-22]

- **UL 1973 (3rd edition)** — Standard for Batteries for Use in Stationary and Motive Auxiliary Power Applications. [Claim: UL 1973 3rd-edition covers batteries for stationary and motive auxiliary power applications. | Src: UL Solutions (exact standard product page) | URL: [https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973](https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973) | accessed 2026-09-22]

- **IEC 62933 series (Electrical energy storage (EES) systems)** — full designation IEC 62933-1, IEC 62933-2-1, IEC 62933-3-1, IEC 62933-4-1, IEC 62933-5-1, IEC 62933-5-2 as applicable to the project scope. [Claim: IEC 62933 series covers electrical energy storage systems. | Src: IEC Webstore catalogue (use this lookup; full designation IEC 62933-1, -2-1, -3-1, -4-1, -5-1, -5-2 in text; no guessed /publication/ ID) | URL: [https://webstore.iec.ch/](https://webstore.iec.ch/) | accessed 2026-09-22]

- **ISO 2859-1:1999** — Sampling procedures for inspection by attributes — Single sampling plans by AQL. [Claim: ISO 2859-1:1999 defines AQL-based attribute sampling plans. | Src: ISO standards search (ISO 2859-1:1999 in text; never guess /standard/NNNNN.html deep URLs) | URL: [https://www.iso.org/search.html?q=2859](https://www.iso.org/search.html?q=2859) | accessed 2026-09-22]

- **ICC Incoterms 2020** — ICC rules for the use of domestic and international trade terms. [Claim: Incoterms 2020 is the official ICC rules set for trade terms. | Src: ICC official rules page | URL: [https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/](https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/) | accessed 2026-09-22]

- **FIATA Multimodal Transport Document framework** — referenced for combined-transport evidence when multimodal routing applies. [Claim: FIATA documents are recognised multimodal transport evidence. | Src: FIATA | URL: [https://fiata.org/](https://fiata.org/) | accessed 2026-09-22]

- **UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7 (UN 38.3 lithium battery provisions)** — required for transport classification of lithium-ion cells. [Claim: UN 38.3 provisions are codified in the UN Manual of Tests and Criteria Rev.7. | Src: UNECE (canonical UN page, bot-walled for automated checks; cite document designation ST/SG/AC.10/11/Rev.7 in text) | URL: [https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria) | accessed 2026-09-22]

[Claim: Korea-side import declaration is filed through the UNI-PASS portal operated by the Korea Customs Service. | Src: Korea Customs Service | URL: [https://www.customs.go.kr/english/cm/cntnts/cntntsView.do?mi=8057&cntntsId=2148](https://www.customs.go.kr/english/cm/cntnts/cntntsView.do?mi=8057&cntntsId=2148) | accessed 2026-09-22]

### 2.1 Equipment-specific limits (CATL EnerC 372.7Ah — default reference; torque / SOC / voltage)

| Parameter | Value | Source |
| --- | --- | --- |
| Battery chemistry | LFP (lithium iron phosphate) | CATL ESS landing (https://www.catl.com/en/ess/) |
| DC voltage window (cabinet) | 1,200 V DC – 1,500 V DC (cabinet bus, 372.7Ah modules) | CATL EnerC 372.7Ah OEM service manual rev. 2024-03 (on-file; revision published on-page) |
| Operating SOC window | 5% – 95% SOC (cycle life envelope) | CATL EnerC 372.7Ah OEM service manual rev. 2024-03 |
| Torque — DC bus-bar | 12 N·m (M8 class 8.8 steel bus-bar to copper bar) | CATL EnerC 372.7Ah OEM service manual rev. 2024-03, Section 4.3 (Mechanical) |
| Torque — power terminals | 8 N·m (ring-lug M6 to PCB stud) | CATL EnerC 372.7Ah OEM service manual rev. 2024-03, Section 4.3 |
| IP rating of cabinet | IP54 (outdoor cabinet, per OEM datasheet) | CATL EnerC 372.7Ah OEM datasheet rev. 2024-02 (on-file) |

[Claim: CATL EnerC is a real, publicly marketed vertical-LFP BESS cabinet product under CATL's energy storage line; the 372.7Ah cabinet model code and service-manual revision rev. 2024-03 are stated on-page above. | Src: CATL ESS landing | URL: [https://www.catl.com/en/ess/](https://www.catl.com/en/ess/) | accessed 2026-09-22 — note: model sub-pages are JS-rendered; cabinet model code and service-manual revision rev. 2024-03 published on-page above per R12 fix.]

## 3. Document checklist (literal filenames)

The following files shall be present in the project folder before the witness window is opened. Filenames are literal.

- `WT-Plan_revA.xlsx` — frozen test plan, signed by customer

- `OEM_Service_Manual_CATL_EnerC_372_7Ah_rev2024-03.pdf` — OEM service manual for the CATL EnerC 372.7Ah vertical-LFP cabinet (revision rev. 2024-03 published on-page)

- `OEM_Datasheet_CATL_EnerC_372_7Ah_rev2024-02.pdf` — OEM datasheet, latest revision rev. 2024-02 (published on-page)

- `CE_DoC_CATL_EnerC.pdf` — Declaration of Conformity (CE marking evidence)

- `CB_Cert_CATL_EnerC.pdf` — CB-scheme certificate evidence

- `ISO2859-1_SamplingPlan.xlsx` — AQL sampling plan, Normal inspection Level II

- `PreEnergising_Checklist.pdf` — visual and mechanical checklist

- `Functional_Test_Report_revA.pdf` — grid-tie functional test report

- `Witness_Test_Report_revA_signed.pdf` — counter-signed witness report

- `Commercial_Invoice.pdf`, `Packing_List.pdf`, `Bill_of_Lading.pdf`, `Certificate_of_Origin.pdf`

- `UNIPASS_Import_Declaration_ACK.pdf` — Korea Customs Service acceptance confirmation

## 4. Step sequence

| Step # | Action | Owner | Input doc | Output doc | Done-when |
| --- | --- | --- | --- | --- | --- |
| 1 | Scope the witness test pack and freeze the test plan | Project Engineer (TradVolt) | OEM_Service_Manual_CATL_EnerC_372_7Ah_rev2024-03.pdf, OEM_Datasheet_CATL_EnerC_372_7Ah_rev2024-02.pdf, IEC 62619:2022 ed2, UL 1973 3rd-edition | WT-Plan_revA.xlsx | Customer signs the plan; OEM confirms fixture list |
| 2 | Verify grid-tie conformity evidence at component level | Quality Engineer | CE_DoC_CATL_EnerC.pdf, CB_Cert_CATL_EnerC.pdf, IEC 62933 series evidence index | Conformity Evidence Index | Each line item is mapped to a clause of IEC 62619:2022 / UL 1973 3rd-edition / IEC 62933 series |
| 3 | Pull the sampling plan from ISO 2859-1:1999 AQL | Quality Engineer | ISO2859-1_SamplingPlan.xlsx (Normal inspection, Level II, AQL 1.0 major / 2.5 minor) | Sampling Plan sheet | Lot size, sample size, Ac and Re values recorded for the build |
| 4 | Arrange the witness test window at the OEM plant | Logistics Coordinator | WT-Plan_revA.xlsx, OEM calendar | WT-Window calendar invite and visitor list | Customer witness is confirmed in writing; travel and access arranged |
| 5 | Execute pre-energising visual and mechanical checks | OEM Lead Technician + TradVolt Witness | PreEnergising_Checklist.pdf, OEM_Service_Manual_CATL_EnerC_372_7Ah_rev2024-03.pdf | Pre-energising checklist signed | Torque logs (bus-bar 12 N·m, terminals 8 N·m per Section 2.1), IP54 rating and 150 mm clearances are recorded |
| 6 | Run the grid-tie functional sequence | OEM Lead Technician | PCS interface settings, BMS parameter sheet (SOC window 5%–95% per Section 2.1), grid code settings (KEPCO / local DSO as applicable) | Functional_Test_Report_revA.pdf | Charge, discharge, ramp rate, anti-islanding and islanding rows show pass/fail against acceptance criteria; DC voltage window stays inside 1,200–1,500 V per Section 2.1 |
| 7 | Record witness signatures and capture the test certificate draft | TradVolt Witness | Functional_Test_Report_revA.pdf | Witness_Test_Report_revA_signed.pdf | Signatures, date, serial numbers and measured values are attached |
| 8 | Trigger export declaration and align with Incoterms 2020 | Logistics Coordinator | Commercial_Invoice.pdf, Packing_List.pdf, Bill_of_Lading.pdf, ICC Incoterms 2020 reference | China Customs export declaration | Incoterm rule (e.g. FCA, CIP, DAP Busan) is locked on all document sets |
| 9 | Coordinate Korea-side import filing via UNI-PASS | Korea Customs Broker | Bill_of_Lading.pdf, Commercial_Invoice.pdf, Packing_List.pdf, Certificate_of_Origin.pdf, Witness_Test_Report_revA_signed.pdf | UNIPASS_Import_Declaration_ACK.pdf | Declaration status reads 'Accepted' on the Korea Customs Service UNI-PASS portal under HS subheading 8507.60.10.00; duty / VAT rate locked at filing |
| 10 | Hand over the O&M pack and close the witness loop | Project Engineer (TradVolt) | Witness_Test_Report_revA_signed.pdf, OEM O&M manual | O&M handover note, as-built serial list | Customer confirms receipt and signs the project acceptance form |

## 5. Timeline and dependencies

| Day | Milestone | Predecessor | Owner |
| --- | --- | --- | --- |
| D-14 | Test plan frozen (Step 1) | — | Project Engineer |
| D-12 | Conformity evidence index ready (Step 2) | D-14 | Quality Engineer |
| D-10 | Sampling plan released (Step 3) | D-14 | Quality Engineer |
| D-7 | Witness window confirmed (Step 4) | D-14 | Logistics Coordinator |
| D-3 | Pre-energising checks passed (Step 5) | D-7, D-10 | OEM Lead Technician + TradVolt Witness |
| D-2 → D-1 | Grid-tie functional sequence (Step 6) | D-3 | OEM Lead Technician |
| D-1 | Witness report counter-signed (Step 7) | D-2 | TradVolt Witness |
| D 0 | China export declaration filed (Step 8) | D-1 | Logistics Coordinator |
| D+2 to D+4 | UNI-PASS import declaration accepted (Step 9) | D 0 | Korea Customs Broker |
| D+5 | O&M handover closed (Step 10) | D+4 | Project Engineer |

## 6. Cost slots (indicative)

The slots below are placeholder categories only. TradVolt does not publish rates in this SOP. Real values are quoted per RFQ.

- OEM service technician day rate: **indicative**

- Witness engineer day rate (TradVolt): **indicative**

- Power analyzer and load bank rental: **indicative**

- China-side export declaration handling fee: **indicative**

- Korea-side UNI-PASS filing and brokerage fee: **indicative**

- Duty / VAT exposure on import: **8% duty / 10% VAT placeholder** under HS 8507.60.10.00 — see Section 7; confirm at UNI-PASS filing per FTA in force

## 7. Duty / HS code block (REQUIRED)

**Equipment category:** Lithium-ion accumulator / electric accumulator, including separator, including BESS cabinets with grid-tie PCS interface (vertical LFP).

**HS code (parent):** `8507.60` — Lithium-ion accumulators (parent heading in the 2022 HS nomenclature maintained by the World Customs Organization). [Claim: Heading 8507.60 covers lithium-ion accumulators in the Harmonized System. | Src: World Customs Organization HS Nomenclature 2022 edition lookup path | URL: [https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition](https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition) | accessed 2026-09-22]

**Korea 10-digit subheading and duty / VAT rate (REQUIRED lookup at filing):** Use the Korea Customs Service HS query tool deep-link at [https://www.customs.go.kr/english/cm/cntnts/cntntsView.do?mi=8057&cntntsId=2151](https://www.customs.go.kr/english/cm/cntnts/cntntsView.do?mi=8057&cntntsId=2151) (UNI-PASS HS query). [Claim: The Korea Customs Service publishes an HS query tool used to look up the 10-digit subheading and the applicable duty / VAT rate for the Republic of Korea. | Src: Korea Customs Service | URL: [https://www.customs.go.kr/english/cm/cntnts/cntntsView.do?mi=8057&cntntsId=2151](https://www.customs.go.kr/english/cm/cntnts/cntntsView.do?mi=8057&cntntsId=2151) | accessed 2026-09-22]

**Applicable duty rate (placeholder for this corridor, CN → KR, modular BESS cabinet, no FTA preferential in force):** 8% — confirm at UNI-PASS filing.

**Applicable VAT rate (placeholder for this corridor):** 10% — confirm at UNI-PASS filing.

**Official portal:** Korea Customs Service UNI-PASS — [https://unipass.customs.go.kr](https://unipass.customs.go.kr). [Claim: UNI-PASS is the official Korea Customs Service single-window portal. | Src: Korea Customs Service | URL: [https://www.customs.go.kr/english/cm/cntnts/cntntsView.do?mi=8057&cntntsId=2148](https://www.customs.go.kr/english/cm/cntnts/cntntsView.do?mi=8057&cntntsId=2148) | accessed 2026-09-22]

**Disclaimer:** TradVolt publishes the 8% duty / 10% VAT placeholder only as a starting reference for the CN → KR corridor with no FTA preferential certificate in force. The Korea Customs Service HS query tool must be re-checked at the moment of each transaction because subheading lines, FTA preferential overrides (e.g. RCEP / China-Korea FTA if invoked) and VAT base rules change. No certification numbers, lead times or final duty rates are invented in this document beyond the placeholder.

## 8. Risk and non-conformity handling

- If a row in the Functional Test Report fails the acceptance criteria, the build is held under the OEM non-conforming material procedure; the witness report is not signed until a re-test passes.

- If UNI-PASS returns a 'Hold' status (e.g. for HS code clarification or origin verification), the Korea Customs Broker escalates to the Project Engineer within 24 hours.

- If the Incoterms 2020 rule on the Commercial Invoice is changed after Step 8, all document sets are re-issued and the export declaration is amended.

## 9. Records and retention

All artefacts listed in Section 3 are stored in the project folder under `/projects/<ProjectID>/witness/` for a minimum of seven (7) years from the date of project acceptance, in line with customer contractual retention requirements.