# Inverter Insulation-Resistance Test — CN→MY Shipment SOP

**Verdict.** Every Deye SUN-5/6/8/10/12K-SG04LP3-EU unit leaving the CN dispatch warehouse for Malaysia must pass an insulation-resistance (IR) test at 500 V DC (class I) or 1000 V DC (class II) with a ≥ 60 s hold and a resistance reading of ≥ 1 MΩ (basic insulation) or ≥ 100 MΩ (reinforced insulation) before the customs dossier can be lodged. Owners: QC Engineer (test execution), QC Supervisor (co-sign), Export Coordinator (customs dossier), Logistics Coordinator (FIATA multimodal carrier hand-over). Horizon: D − 2 dispatch pack → D − 1 test execution → D 0 export lodging → D + 4 to D + 10 arrival at the MY site. Evidence date: 2026-09-22. Limitation: figures are working references; MY duty/GST and CN export duty rows are flagged PENDING and must be re-verified on the JKDM / MyGov and GACC portals at the time of each shipment.

[Request Quote (RFQ form — live endpoint)](/rfq/) [IR Test Checklist — request via RFQ (PDF on reply)](/rfq/)

## 1. Scope and applicability

This SOP applies to **Ningbo Deye Inverter Technology Co., Ltd. — SUN-5/6/8/10/12K-SG04LP3-EU** hybrid inverters leaving the CN dispatch warehouse and entering Malaysia via the CN→MY trade corridor. The Deye product page is the canonical model reference: [https://www.deyeinverter.com/product/hybrid-inverter-1/sun5-6-8-10-12ksg04lp3.html](https://www.deyeinverter.com/product/hybrid-inverter-1/sun5-6-8-10-12ksg04lp3.html). The IR test is a safety verification, not a performance test, and is performed on every unit that has been powered-up or repaired before re-shipping.

Claim: This SOP covers the Deye SUN-5/6/8/10/12K-SG04LP3-EU family. | URL: https://www.deyeinverter.com/product/hybrid-inverter-1/sun5-6-8-10-12ksg04lp3.html | accessed 2026-09-22.

Claim: Tradvolt sources and ships China-made green-tech equipment on CN→MY corridors. | URL: https://tradvolt.com/ | accessed 2026-09-22.

## 2. Normative references

- **IEC 62477-2: — **Safety requirements for power electronic converter systems — Part 2: DC-to-DC converters (latest edition; cite full designation *IEC 62477-2:YYYY* with the year confirmed against the IEC catalogue query at [https://webstore.iec.ch/en/products/?q=62477-2](https://webstore.iec.ch/en/products/?q=62477-2), accessed 2026-09-22). The IEC 62477-2 step-3 verification procedure is the direct reference for the test sequence executed in §3.

- **IEC 62109-1** — Safety of power converters for use in photovoltaic power systems — Part 1: General requirements. Class I (basic insulation) and Class II (reinforced insulation) test voltages and minimum insulation-resistance thresholds are read from this standard. Source: IEC Webstore catalogue query at [https://webstore.iec.ch/en/products/?q=62109-1](https://webstore.iec.ch/en/products/?q=62109-1), accessed 2026-09-22.

- **Deye SUN-5/6/8/10/12K-SG04LP3-EU Service Manual** — OEM Service Manual for the SUN-5/6/8/10/12K-SG04LP3-EU family. The manual title, revision number and revision date are confirmed at RFQ; the test voltage (500 V DC / 1000 V DC), hold time (≥ 60 s) and pass thresholds (≥ 1 MΩ basic / ≥ 100 MΩ reinforced) are the limits stated in this manual. Source: Deye manufacturer site [https://www.deyeinverter.com/product/hybrid-inverter-1/sun5-6-8-10-12ksg04lp3.html](https://www.deyeinverter.com/product/hybrid-inverter-1/sun5-6-8-10-12ksg04lp3.html), accessed 2026-09-22. *(Manual revision: TBC at RFQ — model assumption until confirmed.)*

- **ISO 2859-1:1999** — Sampling procedures for inspection by attributes — Part 1: Sampling schemes indexed by acceptance quality limit (AQL) for lot-by-lot inspection. Source: ISO standards search at [https://www.iso.org/search.html?q=2859](https://www.iso.org/search.html?q=2859), accessed 2026-09-22.

- **ICC Incoterms® 2020 (ICC Publication No. 723E)** — Rules for the trade-term assignment on the commercial invoice. Source: ICC Incoterms 2020 rules page at [https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/](https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/), accessed 2026-09-22.

- **FIATA — International Federation of Freight Forwarders Associations** — Multimodal transport documents for the CN→MY lane (FIATA Bill of Lading / FWB / FCR). Source: FIATA at [https://fiata.org/](https://fiata.org/), accessed 2026-09-22.

- **GACC (China)** — General Administration of Customs of China, export declaration portal: [http://english.customs.gov.cn](http://english.customs.gov.cn), accessed 2026-09-22.

- **JKDM / MyGov (Malaysia)** — Royal Malaysian Customs (JKDM) access via the MyGov portal: [https://www.mygov.gov.my](https://www.mygov.gov.my), accessed 2026-09-22.

## 3. Decision table — verdict in numbers

| Parameter | Class I (basic insulation) | Class II (reinforced insulation) | Source |
| --- | --- | --- | --- |
| Test voltage (DC) | 500 V DC | 1000 V DC | Deye SUN-5/6/8/10/12K-SG04LP3-EU Service Manual + IEC 62109-1 clause on dielectric/insulation testing. Manual: link; standard: IEC catalogue query. Accessed 2026-09-22. |
| Hold time | ≥ 60 s | ≥ 60 s | Deye Service Manual (revision TBC at RFQ) — model assumption until confirmed. |
| Pass threshold | ≥ 1 MΩ | ≥ 100 MΩ | Deye Service Manual pass criteria + IEC 62109-1 minimum insulation-resistance table. |
| HS heading | `8504.40` — Static converters (verify on the destination customs portal at the time of shipment) | WCO HS Nomenclature 2022, Chapter 85 Note 3 / heading 8504.40: WCO HS 2022. Accessed 2026-09-22. |
| CN export lodgement | GACC export declaration | http://english.customs.gov.cn. Accessed 2026-09-22. |
| MY import lodgement | JKDM via MyGov | https://www.mygov.gov.my. Accessed 2026-09-22. |
| Multimodal doc set | FWB / FCR per FIATA rules | https://fiata.org/. Accessed 2026-09-22. |

## 4. Step sequence

| Step # | Action | Owner | Input doc | Output doc | Done-when |
| --- | --- | --- | --- | --- | --- |
| 1 | Receive dispatch pack (PO line, packing list, Test Plan, prior IR record if any). | QC Engineer | `dispatch-pack.pdf` | `pack-receipt-ack.xlsx` | All line items reconciled against the PO; serial numbers logged. |
| 2 | Confirm model (Deye SUN-5/6/8/10/12K-SG04LP3-EU), rated DC voltage and rated AC voltage from the rating plate and OEM manual. | QC Engineer | Deye Service Manual (link) | `model-confirmation.md` | Model code and ratings transcribed; serial number matches the Test Plan. |
| 3 | Isolate the inverter: remove DC input, remove AC output, disconnect any communication cables and external PE bonding. | QC Engineer | Deye Service Manual isolation procedure | `isolation-log.md` | Voltage checks confirm zero residual on DC and AC terminals. |
| 4 | Verify ambient temperature (15–35 °C typical) and RH, prepare PPE (insulated gloves, face shield) per Risk Assessment and IEC 62477-2 environmental preconditions. | HSE Officer + QC Engineer | Risk Assessment `ra-ir-test.docx`; IEC 62477-2 (catalogue) | `env-and-ppe-check.xlsx` | Conditions recorded; PPE worn; pre-job safety briefing completed. |
| 5 | Calibrate-check the megohmmeter against a known reference; confirm calibration certificate is in date. | QC Engineer | Calibration certificate `megger-cal-*.pdf` | `megger-check-record.md` | Megger reads within tolerance of reference; certificate < 12 months old. |
| 6 | Connect leads per Deye Service Manual wiring diagram: shorted L/N/PE (or DC+/DC− and PE for DC-coupled paths) to the positive lead; chassis ground to the negative lead. | QC Engineer | Deye Service Manual wiring diagram (link) | `lead-connection-photo.jpg` | Lead layout matches the OEM wiring diagram; photo filed. |
| 7 | Apply test voltage — 500 V DC for Class I or 1000 V DC for Class II per IEC 62109-1 and Deye Service Manual — and hold for ≥ 60 s. | QC Engineer | Deye Service Manual test voltage table + IEC 62109-1 (catalogue) | `test-run.log` | Voltage and time held without breakdown; no trip of the instrument. |
| 8 | Read IR value at the end of hold time and compare against the pass threshold: ≥ 1 MΩ (basic) or ≥ 100 MΩ (reinforced) per Deye Service Manual + IEC 62109-1. | QC Engineer | Deye Service Manual pass criteria + IEC 62109-1 | `ir-test-sheet.pdf` | Value recorded in MΩ on the Test Sheet; pass/fail flagged. |
| 9 | Discharge the unit, restore grounds, and de-energise the megohmmeter; visual inspection for arc marks. | QC Engineer | — | `post-test-visual.md` | Terminals discharged to < 5 V; no arc marks; area restored. |
| 10 | Engineer signs Test Sheet; Supervisor co-signs; archive to project folder and attach to the shipment file. | QC Supervisor | `ir-test-sheet.pdf` | `signed-ir-pack.pdf` | Two signatures present; PDF archived under project ID. |
| 11 | Prepare commercial invoice, packing list, COO, Incoterms 2020 term (ICC rules page), and submit to broker for CN export (GACC) + MY import (JKDM / MyGov) declarations. | Export Coordinator | `signed-ir-pack.pdf`, Proforma Invoice | `customs-dossier.zip` | Broker lodges declarations on GACC and JKDM / MyGov portals; references recorded. |
| 12 | Carrier hand-over per FIATA multimodal rules (FIATA); share AWB or sea waybill with receiver; confirm arrival in MY and close the loop. | Logistics Coordinator | FIATA multimodal doc set | `as-shipped-record.pdf` | Receiver confirms arrival; POD filed; project tracker closed. |

## 5. Document checklist (literal filenames)

- `dispatch-pack.pdf` — PO, packing list, Test Plan.

- `ra-ir-test.docx` — Risk Assessment for the IR test.

- `megger-cal-YYYY-MM.pdf` — Megohmmeter calibration certificate (≤ 12 months).

- `ir-test-sheet.pdf` — Per-unit IR test record with MΩ reading and pass/fail.

- `signed-ir-pack.pdf` — Engineer + Supervisor signed IR file.

- `commercial-invoice.xlsx` — With Incoterms 2020 term ([ICC](https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/)) and HS code field.

- `packing-list.xlsx` — Per-unit serial numbers, weights, dimensions.

- `certificate-of-origin.pdf` — Issued per the destination's preference.

- `customs-dossier.zip` — Combined file for broker lodgement (GACC + JKDM).

- `awb-or-waybill.pdf` — Issued by the nominated carrier under FIATA rules ([FIATA](https://fiata.org/)).

- `as-shipped-record.pdf` — Final closed-loop file.

## 6. Timeline and dependencies

| Day (relative) | Milestone | Dependency |
| --- | --- | --- |
| D − 2 | Dispatch pack received and reconciled. | Project Coordinator issues PO and Test Plan. |
| D − 2 | Calibration certificate confirmed in date. | QC Engineer checks `megger-cal-YYYY-MM.pdf`. |
| D − 1 | IR test executed on all units; signed IR Pack archived. | Test Plan released; PPE available; area clear. |
| D 0 | Customs dossier handed to broker; export lodged on GACC (link). | Signed IR Pack + Commercial Invoice ready. |
| D + 1 to D + 4 | Carrier hand-over; AWB/waybill issued; consignment departs. | Broker confirmation; FIATA multimodal booking confirmed (FIATA). |
| D + 4 to D + 10 (indicative) | Import lodgement on JKDM / MyGov (link); duties/GST paid; delivery to MY site. | HS code, COO and Incoterms correct; duties cleared. |

## 7. Cost slots

The cost figures below are **indicative** placeholders for budgeting only. Real values are returned in the 48-hour RFQ response via the live RFQ form at [/rfq/](/rfq/).

- **IR test labour**: indicative — per-unit, based on volume.

- **Calibration**: UNCERTAIN — depends on local provider in CN.

- **CN export formalities**: indicative — per shipment.

- **MY import duties**: PENDING — lookup — see §8.

- **Carrier**: indicative — sea or air, per route and weight.

- **Broker fees**: indicative — per shipment.

## 8. HS code, duties and customs

| Item | Field | Value | Source |
| --- | --- | --- | --- |
| Deye SUN-5/6/8/10/12K-SG04LP3-EU (static converters) | HS code | `8504.40` — Static converters (commonly applied heading; verify against the destination customs portal at the time of shipment). | WCO HS Nomenclature 2022, Chapter 85, heading 8504.40: WCO HS 2022. Accessed 2026-09-22. |
| Deye SUN-5/6/8/10/12K-SG04LP3-EU — MY import duty rate | Rate | PENDING — lookup | Re-verify on JKDM / MyGov at shipment time: https://www.mygov.gov.my. Accessed 2026-09-22. |
| Sales tax / GST | Rate | PENDING — lookup | Re-verify on JKDM / MyGov at shipment time: https://www.mygov.gov.my. Accessed 2026-09-22. |
| CN export formalities | Status | Declared on the General Administration of Customs of China (GACC) portal. | http://english.customs.gov.cn. Accessed 2026-09-22. |
| MY import lodgement | Portal | Royal Malaysian Customs (JKDM) via the MyGov portal. | https://www.mygov.gov.my. Accessed 2026-09-22. |

**Disclaimer.** HS classifications and duty rates are jurisdiction-specific and change periodically. Tradvolt provides the HS heading above (8504.40, WCO HS Nomenclature 2022) as a working reference; the MY duty, GST and any excise lines are intentionally left as PENDING — lookup and must be confirmed against the JKDM / MyGov portal at the time of shipment. Tradvolt does not provide legal or fiscal advice.

## 9. Risk and non-conformance

- **IR failure (read below OEM threshold)**: Quarantine the unit, raise a Non-Conformance Report (`ncr-ir-failure.docx`), and route to the Repair Workflow before re-testing. Threshold reference: Deye SUN-5/6/8/10/12K-SG04LP3-EU Service Manual pass criteria ([link](https://www.deyeinverter.com/product/hybrid-inverter-1/sun5-6-8-10-12ksg04lp3.html)).

- **Calibration overdue**: Suspend testing until a current calibration certificate (`megger-cal-YYYY-MM.pdf`) is available.

- **Documentation gap on customs dossier**: Hold shipment; broker cannot lodge on GACC ([link](http://english.customs.gov.cn)) or JKDM / MyGov ([link](https://www.mygov.gov.my)) without a complete set.

## 10. RFQ

The RFQ form at [/rfq/](/rfq/) is the only live TradVolt endpoint for a priced offer on a CN→MY shipment that includes the IR test, documentation and customs clearance. Standard reply time: within 48 hours during business days. The IR Test Checklist PDF is also issued with the RFQ reply — there is no separate public download path; the form is the actual endpoint for both the quote and the checklist.