# Inverter Reactive-Power Grid-Support Test — CN→AU Corridor (Sungrow SG125HT)

Standard Operating Procedure · Equipment: Sungrow SG125HT three-phase string inverter · Document ID: TVT-SOP-CN-AU-INV-014 · Revision: A · Effective: 2026-09-21

Type: Process / SOP Corridor: CN → AU Site class: B2B / utility-adjacent Owner role: Commissioning Engineer

**Verdict:** ~6 hours on-site. This SOP executes the volt-var / volt-watt acceptance test of the **Sungrow SG125HT** three-phase string inverter per AS/NZS 4777.2:2020. **Proceed only after firmware, LOTO, and AC source readiness are confirmed.**

**Equipment:** Sungrow SG125HT (1500 V DC, C&I three-phase string inverter) [Src: Sungrow product range | URL: https://www.sungrowpower.com/en/products/string-inverter | accessed 2026-09-21]. **Location:** CN → AU export corridor, on-site at AU PCC. **Horizon:** Single visit, Day 1. **Evidence date:** 2026-09-21.

| Item | Value | Source |
| --- | --- | --- |
| Equipment model | Sungrow SG125HT (3-phase string inverter) | https://www.sungrowpower.com/en/products/string-inverter |
| Standard | AS/NZS 4777.2:2020 (clause on grid-support volt-var/volt-watt) | https://www.standards.org.au |
| Duration | ~6 hours on-site (model assumption pending site survey) | Internal estimate |
| HS code candidate | 8504.40 (static converters — to be confirmed by licensed broker) | https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff |
| Incoterm default | CIF Australian port per Incoterms 2020 | https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ |
| Limitation | Specific SG125HT service-manual revision confirmed at RFQ; SOP parameters derived from public datasheet envelope only | Model assumption |

## 1. Purpose and Scope

This SOP governs the on-site acceptance test of the reactive-power (volt-var / volt-watt / Q(V)) grid-support functions of the **Sungrow SG125HT** three-phase string inverter before hand-over on the China-to-Australia export corridor. It applies to SG125HT units shipped under Tradvolt job numbers prefixed `TVT-CAU-`. The SG125HT is a 1500 V DC, C&I-rated three-phase string inverter; exact firmware parameter set, clearing time, and tolerance values must be reconfirmed against the current Sungrow SG125HT service manual revision at the time of commissioning.

## 2. Reference Documents

- AS/NZS 4777.2:2020 — Grid connection of energy systems via inverters, Part 2: Inverter requirements (specifically the volt-var (Table 4) and volt-watt (Table 5) clauses for Australia A/B/C regions) [Src: Standards Australia | URL: https://www.standards.org.au | accessed 2026-09-21].

- IEC 62109-1:2010 — Safety of power converters for use in photovoltaic power systems [Src: IEC Webstore catalogue query IEC 62109-1 | URL: https://webstore.iec.ch/en/products/?q=62109-1 | accessed 2026-09-21].

- IEC 61683:1999 — Photovoltaic systems — Power conditioners — Procedure for measuring efficiency [Src: IEC Webstore catalogue query IEC 61683 | URL: https://webstore.iec.ch/en/products/?q=61683 | accessed 2026-09-21].

- Sungrow SG125HT service manual, current regional (AU) revision — title and revision confirmed at RFQ [Src: Sungrow service documentation for SG125HT | URL: https://www.sungrowpower.com/en/products/string-inverter | accessed 2026-09-21].

- Sungrow SG125HT datasheet, current regional (AU) revision — title and revision confirmed at RFQ [Src: Sungrow SG125HT datasheet | URL: https://www.sungrowpower.com/en/products/string-inverter | accessed 2026-09-21].

- ISO 2859-1:1999 — Sampling procedures for inspection by attributes, General Level II / AQL 1.0 framework [Src: ISO catalogue search "2859" | URL: https://www.iso.org/search.html?q=2859 | accessed 2026-09-21].

- Incoterms 2020 — ICC publication 723E, CIF rule A3 / A4 / B3 / B4 [Src: ICC Incoterms 2020 official rules page | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | accessed 2026-09-21].

- ABF Working Tariff — current tariff-classification page for HS heading 8504.40 [Src: Australian Border Force | URL: https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff | accessed 2026-09-21].

- China Customs — General Administration of Customs, export tariff consultation [Src: GACC | URL: http://english.customs.gov.cn | accessed 2026-09-21].

## 3. Preconditions

- Equipment has cleared CN export inspection and AU import biosecurity with no open holds.

- DC string and LFP battery DC bus voltage measurements are within Sungrow SG125HT datasheet limits (MPPT voltage envelope and max DC input voltage per the current AU datasheet revision — confirmed at RFQ).

- AC grid-forming source is available at the point of common coupling (PCC).

- Two qualified Commissioning Engineers are present with calibrated instruments traceable to ISO/IEC 17025.

## 4. Step Sequence

| Step # | Action | Owner | Input doc | Output doc | Done-when |
| --- | --- | --- | --- | --- | --- |
| 1 | Confirm single-line diagram, PCC, and AS/NZS 4777.2:2020 region setting (A/B/C) | Commissioning Engineer | TVT-PRJ-CAU-001 SLD | Pre-test checklist | Region code recorded and signed |
| 2 | Lock-out / tag-out DC and AC isolators per Sungrow SG125HT service manual (current AU revision) | Site Safety Officer | LOTO register; Sungrow SG125HT service manual | LOTO permit | Zero-energy verified on calibrated meter |
| 3 | Verify SG125HT firmware version matches AU parameter set (region code, volt-var / volt-watt curves) | Commissioning Engineer | Firmware manifest; SG125HT service manual | Firmware sign-off sheet | Hash match logged in commissioning folder |
| 4 | Connect programmable AC source ≥110% of SG125HT nominal apparent power | Test Technician | AC source calibration cert | Source connection log | Three-phase voltages balanced ±2% |
| 5 | Run volt-var curve through V1–V4 per AS/NZS 4777.2:2020 Table 4 | Commissioning Engineer | Volt-var test sheet | Reactive-power CSV | Q output within ±5% of setpoint at each step |
| 6 | Run volt-watt curve through Vw1–Vw4 per AS/NZS 4777.2:2020 Table 5 | Commissioning Engineer | Volt-watt test sheet | Active-power CSV | P curtailment within ±5% of setpoint at each step |
| 7 | Repeat Q(V) three times; compute mean reactive error against SG125HT datasheet tolerance | Test Technician | CSV set; SG125HT datasheet | Repeatability report | Mean error ≤ SG125HT datasheet tolerance band |
| 8 | Spot-check anti-islanding: open AC contactor, record clearing time against SG125HT service-manual limit | Commissioning Engineer | Anti-island log; SG125HT service manual | Anti-island record | Trip ≤ SG125HT service-manual clearing time |
| 9 | Visual AQL inspection per ISO 2859-1:1999 General Level II, AQL 1.0 | QC Inspector | ISO 2859-1 General Level II / AQL 1.0 sampling table | AQL inspection form | Sample defects ≤ accept number |
| 10 | Compile evidence pack: PDF report, screenshots, raw CSVs | Documentation Lead | All prior outputs | Final commissioning dossier | Dossier uploaded to job folder, link issued |

## 5. Acceptance Criteria

- Reactive-power response within ±5% of programmed curve across the V1–V4 window per AS/NZS 4777.2:2020 Table 4 [Src: Standards Australia — AS/NZS 4777.2:2020 | URL: https://www.standards.org.au | accessed 2026-09-21].

- Active-power curtailment within ±5% across the Vw1–Vw4 window per AS/NZS 4777.2:2020 Table 5 [Src: Standards Australia — AS/NZS 4777.2:2020 | URL: https://www.standards.org.au | accessed 2026-09-21].

- Anti-islanding clearing time within the interval stated in the Sungrow SG125HT service manual (current AU revision — confirmed at RFQ) [Src: Sungrow SG125HT service manual | URL: https://www.sungrowpower.com/en/products/string-inverter | accessed 2026-09-21].

- Efficiency measured per IEC 61683:1999 within Sungrow SG125HT datasheet tolerance band [Src: IEC — IEC 61683:1999 (catalogue query) | URL: https://webstore.iec.ch/en/products/?q=61683 | accessed 2026-09-21].

## 6. Document Checklist (filenames)

- `TVT-CAU-PRE-CHECK-001.pdf` — pre-test safety checklist

- `TVT-CAU-LOTO-PERMIT-001.pdf` — lock-out / tag-out permit (cites Sungrow SG125HT service-manual revision)

- `TVT-CAU-FW-SIGNOFF-001.pdf` — SG125HT firmware hash and parameter-set sign-off

- `TVT-CAU-VOLTVAR-CSV.zip` — volt-var raw measurement archive

- `TVT-CAU-VOLTWATT-CSV.zip` — volt-watt raw measurement archive

- `TVT-CAU-REPEAT-REP-001.pdf` — repeatability report

- `TVT-CAU-ANTIISLAND-001.pdf` — anti-islanding record

- `TVT-CAU-AQL-FORM-001.pdf` — ISO 2859-1:1999 AQL inspection form (General Level II, AQL 1.0)

- `TVT-CAU-FINAL-DOSSIER-001.pdf` — final commissioning dossier

## 7. Timeline and Dependencies

| Phase | Activity | Dependency | Indicative duration |
| --- | --- | --- | --- |
| Pre-arrival | Documentation review and SG125HT firmware staging | Job number issued; Sungrow SG125HT service-manual revision on file | 2 working days — UNCERTAIN pending AU customs hold |
| On-site Day 1 AM | LOTO, AC source connection | PCC energised, safety permits | 2 h |
| On-site Day 1 PM | Volt-var + volt-watt curves | Steps 1–4 closed | 2 h |
| On-site Day 1 PM | Repeatability and anti-islanding | Curve tests signed off | 1 h |
| On-site Day 1 PM | AQL visual + dossier upload | All measurements captured | 1 h |

## 8. Cost Indicative Slots

All figures below are **indicative** and **UNCERTAIN**; final quotation is issued only after RFQ intake and current carrier/authority tariff lookup on 2026-09-21.

- Engineering labour (2 engineers × 1 day) — indicative

- AC source rental — indicative

- Calibration certificates pass-through — indicative

- AU customs entry fee — UNCERTAIN pending ABF schedule at HS 8504.40

- CN export inspection fee — UNCERTAIN pending GACC schedule

## 9. Duty / HS Code Block

**Equipment / parts:** Sungrow SG125HT three-phase string inverter (1500 V DC, C&I class) with grid-support functions.

**Recommended HS code candidate (must be confirmed by a licensed customs broker at booking):**

- `8504.40` — Static converters — typical heading for power inverters on the AU Working Tariff [Src: Australian Border Force — current tariff-classification page for HS 8504.40 | URL: https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff | accessed 2026-09-21].

- `8504.40.00` sub-line — to be confirmed against the AU Working Tariff and CN Customs Export Tariff at the time of shipment.

**Duty rate:** PENDING — lookup against the ABF Working Tariff current-tariff section and any applicable Free Trade Agreement (e.g., ChAFTA) preference at the time of entry.

**GST / VAT:** PENDING — lookup.

**Official portals consulted:** Australian Border Force current tariff-classification page (https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff) and GACC (http://english.customs.gov.cn).

**Disclaimer:** HS classification and duty rates are jurisdiction-specific and time-sensitive. Tradvolt does not issue binding tariff rulings; the buyer is responsible for engaging a licensed customs broker and confirming the classification, preferential origin, and applicable rate at the date of export and import.

## 10. Incoterms Reference

Default quotation basis for this corridor is **CIF Australian port** per Incoterms 2020 (rule CIF, ICC publication 723E); alternative terms (FOB, DAP, DDP) available on RFQ. Risk transfer and cost allocation follow the official ICC Incoterms 2020 rules page [Src: ICC — Incoterms 2020 | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | accessed 2026-09-21].

## 11. Reader-facing CTAs

[Request Quote — replies in 48h](/rfq/)

## 12. Claim Rows

1. **Claim:** Volt-var curve is specified by V1–V4 setpoints in AS/NZS 4777.2:2020 (Table 4 referenced under the volt-var clause). [Claim | Src: Standards Australia — AS/NZS 4777.2:2020 | URL: https://www.standards.org.au | accessed 2026-09-21]

2. **Claim:** Volt-watt curve is specified by Vw1–Vw4 setpoints in AS/NZS 4777.2:2020 (Table 5 referenced under the volt-watt clause). [Claim | Src: Standards Australia — AS/NZS 4777.2:2020 | URL: https://www.standards.org.au | accessed 2026-09-21]

3. **Claim:** Reactive-power tolerance applied on this SOP is ±5% of programmed curve. [Claim | Src: Standards Australia — AS/NZS 4777.2:2020 | URL: https://www.standards.org.au | accessed 2026-09-21]

4. **Claim:** AQL sampling is conducted at General Level II, AQL 1.0 per ISO 2859-1:1999. [Claim | Src: ISO — ISO 2859-1:1999 (catalogue search) | URL: https://www.iso.org/search.html?q=2859 | accessed 2026-09-21]

5. **Claim:** HS heading 8504.40 is the typical classification for static converters / power inverters on the AU Working Tariff. [Claim | Src: Australian Border Force — current tariff-classification page for HS 8504.40 | URL: https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff | accessed 2026-09-21]

6. **Claim:** Incoterms 2020 CIF rule definition follows ICC publication 723E (official Incoterms 2020 rules page). [Claim | Src: ICC — Incoterms 2020 | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | accessed 2026-09-21]

7. **Claim:** Total on-site procedure duration is approximately six hours including dossier sign-off. [Model assumption | Src: Tradvolt internal estimate, TVT-SOP-CN-AU-INV-014 Rev A | accessed 2026-09-21]

8. **Claim:** Sungrow SG125HT is the specific equipment model governed by this SOP; service-manual revision, clearing-time limit, and Q/P tolerance bands are confirmed against the current AU service manual at RFQ. [Model assumption | Src: Sungrow SG125HT product page | URL: https://www.sungrowpower.com/en/products/string-inverter | accessed 2026-09-21]