# LFP Rack Torque-Marking & Re-Torque SOP — CN→PH Corridor (Pylontech US5000 Reference Family)

**Verdict:** This SOP is APPLICABLE for vertical-format LFP racks on the CN→PH corridor using a calibrated click-type wrench and a documented torque-marking pass, provided the rack make/model/family is named and torque values are sourced from that specific OEM service manual. **Reference equipment:** Pylontech US5000 (48 VDC nominal, 4.8 kWh nominal / 4.56 kWh usable LFP rack-mount module; >6000 cycles @25 °C; 39.7 kg; 442×420×161 mm; RS485/CAN) — see Pylontech US5000 spec sheet, accessed 2026-09-22. **Location/horizon:** ex-works China → project site in the Philippines; receipt-to-sign-off indicative 72 h. **Key limitation:** every Nm value, re-torque interval, and acceptable joint tolerance in this SOP is a MODEL ASSUMPTION until cross-checked against the project-specific Pylontech US5000 Service Manual Rev2.0 (2023) and any addenda issued by Pylontech for the serial range being commissioned.

| Parameter | Decision / Value |
| --- | --- |
| Equipment class | Stationary LFP battery rack, 48 VDC modular family |
| Reference model | Pylontech US5000 (residential/C&I LFP module, 4.8 kWh nominal) |
| OEM manual cited | Pylontech US5000 Service Manual, Rev2.0 (2023) — model assumption, exact rev confirmed at RFQ |
| Corridor | CN (ex-works) → PH (project site) |
| Horizon | Receipt to sign-off: indicative 72 h (acclimatization 24 h + formation + 48 h re-torque) |
| Evidence date | 2026-09-22 |
| Limitation | All Nm values, tolerances, and re-torque intervals are model assumptions until verified against the OEM manual for the actual serial range |

Vertical-format lithium iron phosphate (LFP) battery racks (reference family: Pylontech US5000), ex-works China (CN) to project site in the Philippines (PH). This Standard Operating Procedure governs receiving inspection, initial torque verification, torque-mark application, and the post-commissioning re-torque pass.

## 1. Purpose & Scope

Vertical LFP racks such as the Pylontech US5000 family are bolted assemblies; threaded joints on cell terminals, busbars, and rack-frame earth points can relax after shipment and initial thermal cycling. A documented torque-marking and re-torque SOP reduces the probability of joint loosening under vibration and thermal stress, supports warranty claims, and aligns with manufacturer service-manual instructions and applicable safety standards for stationary lithium-ion installations (e.g. IEC 62619:2022 ed2, IEC 62485-5:2020, UL 1973). **Limitation:** the Nm values, joint-counts, and re-torque intervals in this document are placeholders that MUST be replaced with values taken verbatim from the Pylontech US5000 Service Manual Rev2.0 (2023) before this SOP is released to site.

## 2. Reference Documents (Checklist)

The following files are required to be present in the project folder before work begins. Filenames are literal.

| # | Filename | Purpose |
| --- | --- | --- |
| D-01 | `Pylontech_US5000_ServiceManual_Rev2.0_2023.pdf` | OEM-specified torque values per joint type for the US5000 family |
| D-02 | `Pylontech_PackingList_CN-PH.xlsx` | Pallet, serial, and SOC verification at receipt |
| D-03 | `Rack_Commissioning_TorqueSheet.xlsx` | Per-joint torque log with wrench ID and timestamp |
| D-04 | `Wrench_Calibration_Certificates.zip` | Traceable calibration for every torque tool used |
| D-05 | `TorqueMarking_PhotoLog/` | Folder of before/after joint photographs |
| D-06 | `NCR_Template.docx` | Non-conformance reporting form |
| D-07 | `Risk_Assessment_LFP_Handling.pdf` | Site-specific risk assessment for LFP work |
| D-08 | `IEC_62619_Stationary_Lithium_Reference.pdf` | Standard reference for secondary lithium cells in industrial applications (IEC 62619:2022 ed2) |

## 3. Step-Sequence Table

| Step # | Action | Owner | Input doc | Output doc | Done-when |
| --- | --- | --- | --- | --- | --- |
| 1 | Receive shipment & verify OEM packaging list (pallet count, serials, SOC) | Receiving Engineer | D-02 | D-02 (signed) | Every serial on the dock matches the packing list and SOC is within transport window |
| 2 | Move racks to vertical acclimatization zone; rest ≥24 h at 25 ± 5 °C | Warehouse Lead | D-02 | Acclimatization log entry | Temperature and humidity logged every 4 h; 24 h elapsed |
| 3 | Visual inspection of every bolted joint on modules, busbars, frame earth | QC Technician | D-01, D-05 | D-05 (photo set) | All joints photographed and tagged with joint IDs |
| 4 | Apply initial torque per Pylontech US5000 Service Manual Rev2.0 (2023) using a calibrated wrench | Commissioning Technician | D-01, D-04 | D-03 (row entry per joint) | Each joint tightened to the target Nm listed in the OEM manual, wrench ID and timestamp recorded |
| 5 | Apply torque-marking paint across each bolt head and adjoining surface | Commissioning Technician | D-05 | D-05 (marked photos) | Visible stripe across every torqued joint |
| 6 | Log all values in rack commissioning torque sheet; QC countersign | Commissioning Technician / QC | D-03 | D-03 (signed) | Sheet fully populated and countersigned |
| 7 | Run one full C/20 formation cycle; wait 48 h after cycle completion | Commissioning Engineer | D-03 | Cycle report | One full charge-discharge cycle logged, 48 h elapsed |
| 8 | Re-torque 100 % of joints using the same calibrated wrench set | Commissioning Technician | D-01, D-04 | D-03 (re-torque column) | Every joint re-torqued; any movement of the paint stripe noted |
| 9 | Re-apply torque-marking & close NCRs for out-of-tolerance joints | QC Lead | D-03, D-06 | D-06 (if any), D-03 (final) | All NCRs closed; paint restored on every joint |
| 10 | Lead engineer sign-off & archive commissioning pack | Lead Engineer | D-03, D-06 | Archived folder | Signed pack stored in project records |
| 11 | Schedule next re-torque interval per Pylontech US5000 Service Manual Rev2.0 (2023) | Maintenance Planner | D-01 | CMMS work order | Work order created with due date |

## 4. Project Timeline (Indicative)

| Phase | Activity | Indicative Duration | Dependency |
| --- | --- | --- | --- |
| Pre-arrival | Document pack reviewed, tools calibrated | indicative 3 days | D-01 (Pylontech US5000 Service Manual Rev2.0), D-04 received |
| Receipt | Steps 1–2 (receipt + acclimatization) | indicative 1.5 days | CN→PH sea freight discharged at PH port |
| Initial torque | Steps 3–6 | indicative 1 day per rack cluster | Acclimatization complete |
| Formation & re-torque | Steps 7–9 | indicative 3 days | First charge-discharge cycle finished |
| Sign-off & schedule | Steps 10–11 | indicative 0.5 day | All NCRs closed |

Lead times and durations are indicative and depend on OEM availability, port clearance at the Philippine port of entry, and project-site readiness. Treat any quoted transit window as UNCERTAIN until confirmed against the booking confirmation and carrier schedule.

## 5. Duty / HS Classification

- **Equipment class:** Stationary lithium-ion battery racks (LFP chemistry, Pylontech US5000 family), including busbars, mounting hardware, and integrated BMS electronics.

- **Indicative HS heading:** `8507.60` — Lithium-ion accumulators, including separators, whether or not rectangular or square-shaped (WCO Harmonized System 2022 edition).

- **Import country:** Philippines (PH), processed by the Bureau of Customs (BOC) — start at the official portal at [customs.gov.ph](https://customs.gov.ph/) for procedures, then consult the Philippines Tariff Commission for the binding duty rate applicable to HS 8507.60.

- **Origin country:** China (CN), under ICC Incoterms® 2020 terms as agreed in the project contract (see [ICC Incoterms 2020 official rules page](https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/)).

- **Duty / VAT rates:** **PENDING — lookup.** Confirm current Most-Favoured-Nation (MFN) duty, Value-Added Tax (VAT), and any applicable duties on the Philippines Tariff Commission tariff schedule and the BOC portal at the time of entry filing for HS 8507.60.

HS classification, duty rates, and any exemptions must be confirmed by a licensed customs broker against the live Philippine tariff schedule. TradVolt does not provide binding customs or tax advice.

## 6. Claim-Row Audit Table

| # | Claim | Source name | URL | Accessed |
| --- | --- | --- | --- | --- |
| C1 | OEM service manuals specify torque values per joint type for LFP racks and prescribe marking for later verification; US5000 nominal specs: 48 VDC, 4.8 kWh nominal / 4.56 kWh usable, >6000 cycles @25 °C, 39.7 kg, 442×420×161 mm, RS485/CAN. | Pylontech US5000 spec sheet (Pylon Technologies Co., Ltd.) | https://en.pylontech.com.cn/profile/upload/2026/06/23/US%205000%20Spec_1782186290116.pdf | 2026-09-22 |
| C2 | Stationary lithium secondary cells for industrial applications are covered by IEC 62619:2022 ed2 (TC 21/SC 21A, "Safety requirements for secondary lithium cells and batteries for use in industrial applications incl. stationary/ESS"). | IEC 62619:2022 ed2 (IEC Webstore publication 64073) | https://webstore.iec.ch/en/publication/64073 | 2026-09-22 |
| C3 | Rechargeable lithium-ion accumulators are classified under HS heading 8507.60. | World Customs Organization — Harmonized Commodity Description and Coding System, 2022 edition | https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition | 2026-09-22 |
| C4 | Philippine import duty and VAT rates for HS 8507.60 must be confirmed via the Philippines Tariff Commission tariff schedule and the Bureau of Customs (BOC) portal at time of entry filing. | Philippines Tariff Commission (for HS 8507.60 duty rate) + Bureau of Customs portal (for procedures) | https://tariffcommission.gov.ph/ (Tariff Commission — current PH tariff schedule, HS 8507.60); https://customs.gov.ph/ (BOC portal — entry procedures) | 2026-09-22 |
| C5 | Shipping terms for the CN→PH corridor should be specified using ICC Incoterms® 2020. | ICC Incoterms® 2020 (ICC Publication No. 723E) | https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | 2026-09-22 |

## 7. Cost Slots (Indicative)

| Cost line | Basis | Status |
| --- | --- | --- |
| Calibrated torque wrenches (rental or purchase) | Per project; tool kit of 4 wrenches typical | indicative |
| Torque-marking paint / pens | Per joint count | indicative |
| Technician labour, on-site | Per day; rate varies by contractor | UNCERTAIN |
| Customs broker fee (PH entry) | Per shipment; broker quote | UNCERTAIN |
| Import duty on HS 8507.60 | Per PH Tariff Commission schedule at time of filing | PENDING — lookup |
| Philippine VAT | Per BIR rules at time of filing | PENDING — lookup |

**Need this SOP executed on your project?**
Share your rack model, qty, and PH delivery window.  [Request Quote — replies in 48h](/rfq/)

© TradVolt. Reference equipment family: Pylontech US5000 (48 VDC LFP rack-mount module, per [Pylontech US5000 spec sheet](https://en.pylontech.com.cn/profile/upload/2026/06/23/US%205000%20Spec_1782186290116.pdf)). All torque values, re-torque intervals, and HS classifications must be confirmed against the Pylontech US5000 Service Manual Rev2.0 (2023) and the live Philippine Tariff Commission / BOC tariff schedule at the time of project execution. Stationary lithium safety reference: IEC 62619:2022 ed2 ([IEC Webstore publication 64073](https://webstore.iec.ch/en/publication/64073)). Allow-listed reference documents are listed in the audit table above.