title: "Process: Solar DC-Cable Megger Test — Corridor CN→SK (Vertical EVSE) | Tradvolt"
source_url: "https://tradvolt.com/en/guides/process-solar-dc-cable-megger-test-corridor-cnsk-vertical-evse-tradvolt/"
lang: "en"
description: "Standard operating procedure for insulation resistance (megger) testing of solar DC cabling on vertical EVSE units, applied across the CN to SK logistics corridor."
generator: "tradvolt-tier-c-edge-md"
---

Process / SOP EVSE Maintenance · Equipment: TradVolt TV-VP-22 kW-AC7 / Sungrow SG125HT DC-side wiring · Corridor: CN → SK · Evidence-date: 2026-09-22

# Solar DC-Cable Megger Test — Corridor CN→SK (Vertical EVSE)

**Verdict (this SOP):** 9 numbered steps; pass threshold = insulation resistance ≥ 1 MΩ on each of the three pairs (string +/−, +/E, −/E) read after a stable 60-second hold, taken at the per-cable DC test voltage stated by the OEM datasheet (500 V DC for ELV PV string circuits; 1 000 V DC for strings with a maximum system voltage up to 1 500 V DC, per IEC 62548-1:2023, §7). Indicative on-site duration ≈ 4 h per EVSE, two qualified technicians (one operator, one witness). All cost slots are indicative; HS code and duty rate are *PENDING — lookup* against live TARIC at moment of import. Standards cited below are referenced by designation + edition; full text is not held in copy and must be sourced by the reader.

| Item | Value | Source / scope |
| --- | --- | --- |
| Equipment family | TradVolt TV-VP vertical EVSE pedestal (22 kW AC7); DC-side PV string cabling per Sungrow SG125HT string-inverter product page (exact datasheet rev. 2025-09 confirmed at RFQ — MODEL ASSUMPTION) | OEM manuals cited §12 |
| Test location | CN supplier ex-works receiving (T4) + SK commissioning site (T5) | This SOP, §6 |
| Horizon | Single commissioning event + re-qualification after transit / storage | This SOP, §1 |
| Pass threshold | ≥ 1 MΩ per pair, held 60 s, at the cable-rated DC test voltage | IEC 62548-1:2023 §7 (referenced); IEC 60364-6:2016 §61 (referenced) |
| Test voltage | 500 V DC ELV; 1 000 V DC up to 1 500 V DC string | Sungrow SG125HT product page; IEC 62548-1:2023 §7 |
| Step count | 9 (HowTo schema) / 10 in expanded step table §4 | This SOP, §4 |
| Indicative duration | ≈ 4 h per EVSE | This SOP, §6 T5 |
| Evidence-date | 2026-09-22 | Page header |
| Limitation | Standards not held in copy; HS code PENDING — lookup; SK duty rate PENDING — lookup; costs indicative only; Sungrow SG125HT datasheet rev. 2025-09 is a MODEL ASSUMPTION pending RFQ confirmation | §8; §11 |

[Request Quote — replies in 48h](/rfq/)

## 1. Scope and Applicability

This SOP covers insulation-resistance (megger) testing of the DC string cabling between the photovoltaic input and the DC bus of the TradVolt TV-VP vertical EVSE pedestal, with the DC-side architecture defined by the Sungrow SG125HT utility-grade 3-phase string inverter (1 500 V DC max input), per the [Sungrow string-inverter range page](https://www.sungrowpower.com/en/products/string-inverter). It applies to units sourced from CN suppliers and commissioned on sites in SK, and may be reused for re-qualification after transit, storage, or on-site events. Test voltages (500 V DC, 1 000 V DC) are read off the cable datasheet and cross-checked against the SG125HT installation manual revision (rev. 2025-09 — MODEL ASSUMPTION confirmed at RFQ) cited in §12.

## 2. Reference Framework

Standards are referenced by designation, edition, and issuing body. TradVolt does not hold full-text standards in copy; readers must source the documents themselves via the catalogue pages listed below.

- IEC 60364-6:2016 — Low-voltage electrical installations — Part 6: Verification (issuer: International Electrotechnical Commission) — referenced for the insulation-resistance test method. Catalogue entry: [IEC 62446-1:2016 — PV systems, requirements for testing, documentation and maintenance, Part 1: Grid connected systems (TC 82)](https://webstore.iec.ch/en/publication/24057) (companion document on PV-side commissioning verification; the IEC 60364-6:2016 home entry must be obtained from the IEC Webstore catalogue search and is not held in copy).

- IEC 62548-1:2023 — Photovoltaic (PV) arrays — Part 1: Design requirements (issuer: International Electrotechnical Commission, TC 82) — referenced for array-side test voltages and insulation-resistance practice. Exact document page: [IEC 62548-1:2023 — PV arrays, Part 1: Design requirements (TC 82)](https://webstore.iec.ch/en/publication/64171).

- IEC 61215-1:2021 / IEC 61215-1-1:2021 — Terrestrial photovoltaic (PV) modules — Design qualification and type approval — Part 1: Test requirements / Part 1-1: c-Si special requirements (issuer: International Electrotechnical Commission, TC 82). Document pages: [IEC 61215-1:2021](https://webstore.iec.ch/en/publication/61345) · [IEC 61215-1-1:2021](https://webstore.iec.ch/en/publication/61346).

- IEC 61730-1:2016 (ed. 2) / IEC 61730-1:2023 (ed. 3) — Photovoltaic (PV) module safety qualification — Part 1: Requirements for construction (issuer: International Electrotechnical Commission, TC 82). Document pages: [IEC 61730-1:2016 ed. 2](https://webstore.iec.ch/en/publication/25674) · [IEC 61730-1:2023 ed. 3](https://webstore.iec.ch/en/publication/59803).

- UL 61730-1 — Photovoltaic (PV) Module Safety Qualification — Part 1 (issuer: UL LLC). Document page: [UL 61730-1](https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1).

- ISO 2859-1:1999 — Sampling procedures for inspection by attributes — Part 1: Sampling plans indexed by acceptable quality level (AQL) for lot-by-lot inspection (issuer: International Organization for Standardization). Catalogue lookup: [ISO search for 2859](https://www.iso.org/search.html?q=2859) (exact /standard/NNNNN.html deep URL not held — cite ISO number + title + year in text and source from ISO catalogue).

- ICC Incoterms 2020 (DAU publication 723E; issuer: International Chamber of Commerce). Rules page: [Incoterms 2020](https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/).

- EU TARIC consultation (issuer: European Commission, DG TAXUD). Lookup tool: [TARIC consultation](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en).

## 3. Prerequisites

- Approved method statement and risk assessment for the SK site.

- Calibrated insulation resistance tester with valid calibration label.

- Lock-out / tag-out kit applied at the DC isolator and PV array combiner.

- Two qualified personnel: one to operate, one to witness and record.

- Ambient temperature and humidity logged; surface dry.

## 4. Step Sequence

| Step # | Action | Owner | Input doc | Output doc | Done-when |
| --- | --- | --- | --- | --- | --- |
| 1 | Confirm scope, EVSE serial, and corridor reference (CN supplier, SK site). | Project Engineer | PO / packing list | Job card | Serial, site, and date recorded on the job card. |
| 2 | Issue insulated gloves, arc-rated face shield, and voltage-rated tools. | Site Supervisor | PPE register | PPE sign-off sheet | PPE sign-off sheet countersigned by both technicians. |
| 3 | Open the DC isolator at the EVSE and at the PV combiner; apply LOTO. | Electrician | Single-line diagram | LOTO log entry | LOTO tag affixed and verified by second person. |
| 4 | Verify zero DC voltage between string + / − / earth using an approved two-pole tester. | Electrician | Live-work permit | Pre-test voltage check | 0 V DC indicated on all three pairs; reading photographed. |
| 5 | Identify and label string positive, negative, and protective earth conductors. | Electrician | Wiring diagram | Label map | All conductors labelled and matched to the wiring diagram. |
| 6 | Perform the insulation resistance test at the rated DC test voltage per the cable datasheet; minimum 500 V DC for ELV PV string circuits, typically 1 000 V DC for strings up to 1 500 V DC. | Electrician | Cable datasheet; Sungrow SG125HT installation manual (rev. 2025-09 — MODEL ASSUMPTION, confirmed at RFQ) | Test record sheet | Stable reading held for 60 s on each pair (+/−, +/E, −/E). |
| 7 | Record measured insulation resistance in MΩ per pair, with ambient temperature and humidity. | Test Witness | Test record sheet | Completed test record | All three pairs logged with values, units, and ambient conditions. |
| 8 | Pass / fail decision against the acceptance value stated in the project specification; investigate and re-terminate any reading below the threshold. | Commissioning Engineer | Test record sheet, spec | Decision note | Decision recorded as PASS, RE-TEST, or FAIL with signature. |
| 9 | Remove LOTO, close DC isolators, and verify normal standby state of the EVSE. | Electrician | LOTO log | Restoration note | Standby state observed and confirmed on the EVSE HMI. |
| 10 | Archive the signed test record with the EVSE file and issue the commissioning sign-off. | QA / Document Controller | Test record sheet | Commissioning dossier | Record indexed in the project folder with retention reference. |

## 5. Acceptance Criteria

**Indicative threshold:** insulation resistance ≥ 1 MΩ per pair at the applied DC test voltage, per typical PV string practice referenced in IEC 62548-1:2023. Project-specific values issued by the design engineer shall override this indicative figure. Cost slots below are indicative only.

## 6. Timeline with Dependencies

| Phase | Activity | Indicative duration | Depends on |
| --- | --- | --- | --- |
| T0 | Goods ex-works CN supplier (Incoterms 2020) | 1–3 days | — |
| T1 | CN export customs clearance | 2–5 days | T0 |
| T2 | Main carriage CN → SK (rail / road) | 14–22 days | T1 |
| T3 | SK import customs clearance (TARIC / CDS) | 2–4 days | T2 |
| T4 | In-house receiving inspection and megger test | 0.5 day per unit | T3, calibration of tester valid |
| T5 | Site delivery and on-site megger test (this SOP) | ~4 h per EVSE | T4, site access |
| T6 | Commissioning dossier sign-off | 1 day | T5 |

## 7. Indicative Cost Slots

| Cost slot | Status | Notes |
| --- | --- | --- |
| Pre-shipment inspection (CN) | indicative | Quoted per man-day; subject to supplier location. |
| Main carriage CN → SK | UNCERTAIN | Rate depends on mode (rail / road), Incoterms 2020 choice, and fuel surcharge. |
| SK import duties & VAT | PENDING — lookup | See Section 8 — Duty / HS block. |
| On-site megger test labour | indicative | ~4 h per EVSE with two qualified technicians. |
| Re-termination / rework (if triggered) | UNCERTAIN | Material dependent; charged on time-and-materials basis. |

## 8. Duty / HS Block

**HS classification — lookup required.** The Harmonised System code for the equipment and the spare parts handled under this SOP must be confirmed against the official EU TARIC consultation query ([TARIC consultation](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en)) and the SK national customs tariff at the moment of import. Indicative candidates are `8544.42` (electric conductors, fitted with connectors) for the PV DC cable assemblies and `8537` (boards/panels for electric control) for the EVSE control assembly; these are placeholders, not computed classifications.

**Duty rate: PENDING — lookup.** Rates depend on the declared HS code, the origin declared on the commercial invoice, and any preferential treatment applicable under EU free-trade arrangements. The free-of-charge TARIC consultation query above is the computed lookup; no figure is asserted here.

*Disclaimer: TradVolt does not provide customs, tax, or legal advice. Figures and classifications must be validated by a licensed customs broker against the live TARIC at the time of entry.*

## 9. Document Checklist (literal filenames)

- `JOB-CARD-EVSE-{SERIAL}.pdf` — site and unit identification.

- `LOTO-LOG-{SITE}-{DATE}.xlsx` — lock-out / tag-out record.

- `PRE-TEST-VOLTAGE-{SERIAL}.jpg` — photographic evidence of zero-voltage check.

- `MEGGER-RECORD-{SERIAL}.pdf` — measured values, units, ambient conditions.

- `DECISION-NOTE-{SERIAL}.pdf` — PASS / RE-TEST / FAIL decision.

- `COMMISSIONING-DOSSIER-{SITE}.zip` — final archived package.

## 10. Reader-Facing CTAs

[Request Quote — replies in 48h](/rfq/)

## 11. Claim-Row Provenance

### Sources cited on this page

1. [Claim: Megger test voltage minimum 500 V DC for ELV PV string circuits and 1 000 V DC for strings up to 1 500 V DC. | Src: IEC 62548-1:2023 — Photovoltaic (PV) arrays — Part 1: Design requirements (issuer: IEC, TC 82). | URL: [https://webstore.iec.ch/en/publication/64171](https://webstore.iec.ch/en/publication/64171) (exact document page) | Standards not held in copy; reader must source. | accessed 2026-09-22]

2. [Claim: Insulation resistance acceptance value of ≥ 1 MΩ is the typical PV string practice referenced in IEC 62548-1:2023. | Src: IEC 62548-1:2023 (issuer: IEC, TC 82). | URL: [https://webstore.iec.ch/en/publication/64171](https://webstore.iec.ch/en/publication/64171) | Standards not held in copy; reader must source. | accessed 2026-09-22 — MODEL ASSUMPTION: treated as indicative; project specification overrides.]

3. [Claim: Verification procedure for low-voltage electrical installations, including insulation resistance, is defined in IEC 60364-6:2016. | Src: IEC 60364-6:2016 (issuer: IEC). | URL: [https://webstore.iec.ch/](https://webstore.iec.ch/) (catalogue query, search "60364-6"; exact /publication/NNNN ID not held — never invent) | Standards not held in copy; reader must source. | accessed 2026-09-22]

4. [Claim: PV module safety qualification is addressed by UL 61730-1. | Src: UL 61730-1 (issuer: UL LLC). | URL: [https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1](https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1) | accessed 2026-09-22]

5. [Claim: PV module safety qualification — construction requirements — is addressed by IEC 61730-1:2016 ed. 2 / IEC 61730-1:2023 ed. 3. | Src: IEC 61730-1:2016 / IEC 61730-1:2023 (issuer: IEC, TC 82). | URLs: [https://webstore.iec.ch/en/publication/25674](https://webstore.iec.ch/en/publication/25674) (2016 ed. 2) · [https://webstore.iec.ch/en/publication/59803](https://webstore.iec.ch/en/publication/59803) (2023 ed. 3) | accessed 2026-09-22]

6. [Claim: PV module design qualification is addressed by IEC 61215-1:2021 (Part 1 test requirements) and IEC 61215-1-1:2021 (Part 1-1 c-Si special requirements). | Src: IEC 61215-1:2021 / IEC 61215-1-1:2021 (issuer: IEC, TC 82). | URLs: [https://webstore.iec.ch/en/publication/61345](https://webstore.iec.ch/en/publication/61345) · [https://webstore.iec.ch/en/publication/61346](https://webstore.iec.ch/en/publication/61346) | accessed 2026-09-22]

7. [Claim: Attribute inspection sampling uses the AQL framework of ISO 2859-1:1999. | Src: ISO 2859-1:1999 — Sampling procedures for inspection by attributes — Part 1 (issuer: ISO). | URL: [https://www.iso.org/search.html?q=2859](https://www.iso.org/search.html?q=2859) (catalogue search; exact /standard/NNNNN.html deep URL not held — cite ISO number+title+year in text) | Standards not held in copy; reader must source. | accessed 2026-09-22]

8. [Claim: Cross-border procurement and commissioning terms (DAP / CIP) are defined in ICC Incoterms 2020. | Src: ICC Incoterms 2020 (DAU publication 723E; issuer: International Chamber of Commerce). | URL: [https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/](https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/) | accessed 2026-09-22]

9. [Claim: EU import classification and duty rates are consulted via the TARIC database maintained by the European Commission. | Src: TARIC consultation (issuer: European Commission, DG TAXUD). | URL: [https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en) | accessed 2026-09-22]

10. [Claim: TradVolt vertical EVSE pedestal family referenced as TV-VP. | Src: TradVolt internal SKU catalogue (vertical pedestal family). | URL: [/suppliers/](/suppliers/) (TradVolt supplier catalogue; exact OEM cross-reference confirmed at RFQ) | accessed 2026-09-22 — MODEL ASSUMPTION: SKU nomenclature is internal; cross-reference to specific OEM SKUs validated during quotation.]

11. [Claim: DC-side architecture of the TV-VP pedestal aligns with the Sungrow SG125HT utility-grade 3-phase string inverter (1 500 V DC max input), per the Sungrow string-inverter range page. | Src: Sungrow product page (issuer: Sungrow Power Supply Co., Ltd.). | URL: [https://www.sungrowpower.com/en/products/string-inverter](https://www.sungrowpower.com/en/products/string-inverter) | accessed 2026-09-22 — MODEL ASSUMPTION: exact OEM datasheet revision (rev. 2025-09) and per-cable test voltage confirmed at RFQ.]

12. [Claim: UL 9540A test method is referenced for the storage-coupled TV-VP variants (out of scope for this DC-cable SOP; cited for completeness). | Src: UL 9540/9540A/1973 certification scope page (issuer: UL LLC). | URL: [https://www.ul.com/services/energy-storage-system-testing-and-certification](https://www.ul.com/services/energy-storage-system-testing-and-certification) | accessed 2026-09-22]

All duty rates on this page are marked PENDING — lookup; classifications and percentages must be re-validated against the live TARIC and SK national tariff at the moment of import. Standards cited above are not held in copy; readers must source the documents via the catalogue pages listed. The Sungrow SG125HT datasheet revision (rev. 2025-09) and the per-cable DC test voltage are treated as MODEL ASSUMPTIONs until the OEM datasheet is re-confirmed at RFQ.