tradvolt.com Maintenance / Process Guide · r14

B2BGreen-tech tradeEN

# SCADA I/O Check — CN→AU Corridor Maintenance Process

A process guide for verifying supervisory-control I/O mappings on renewable-energy assets shipped along the China → Australia corridor. This page is for tradvolt internal use and approved counterparties; it is **not indexed**.

**Verdict (r14):** The 7-step SCADA I/O check produces a signed evidence pack (scope note → baseline config → I/O reconcile → comms validation → alarms/scaling → patch log → QA sign-off) for three equipment families covered by this revision: **Sungrow SG125HV** (1,500 V DC, Modbus via SCU, governed by the SG125HV User Manual V1.6 2023-08), **Huawei SUN2000-330KTL-H1** (1,500 V DC, MBUS/RS485, governed by the SUN2000-(330KTL-H1,275KTL-H1) User Manual Issue 03, 2023-04-30), and **CATL LFP battery modules** (SOC 5–100 %, 0–1,500 V DC, Modbus register map per the LFP Battery Module Modbus Manual Rev. 2.1). Indicative timeline **15–21 days**, signed off by tradvolt QA at Step 7.

| Field | Value |
| --- | --- |
| Output | 7-step SCADA I/O evidence pack (io-mapping-reconcile.xlsx, comms-validation, alarms/scaling) |
| Equipment families covered | Sungrow SG125HV · Huawei SUN2000-330KTL-H1 · CATL LFP battery modules (model assumption: listed families only — not Sungrow ST-series or Huawei SUN2000-330KTL-H0) |
| Location / corridor | China → Australia (CN→AU) |
| Horizon | Per-asset maintenance cycle; r14 effective for check runs initiated after publication |
| Indicative timeline | 15–21 days from Step 1 to Step 7 sign-off |
| Final sign-off | tradvolt QA (Step 7) |
| Evidence-date basis | OEM datasheets/manuals dated 2023-04-30 to 2023-08; ABF Working Tariff look-up 2024-Q1; CITES / UN Manual not in scope |
| Limitation | Day-rate cost table is UNCERTAIN — model assumption pending sourcing from a paid rate sheet. |

**How to use this guide.** Follow the seven-step sequence below for every periodic SCADA I/O check. Each step lists an owner and the documents that flow in and out. Scope is the three equipment families named in the verdict table above; for other families, derive a separate I/O register map from the relevant OEM manual. The downloadable PDF checklist captures the same evidence trail in a single artifact.   [Request RFQ — SCADA I/O Check](/rfq/?topic=cn-au-scada-io-check&src=guide-r14) [Download PDF checklist](https://tradvolt.com/downloads/cn-au-scada-io-check-r14.pdf)

## Step sequence

| Step # | Action | Owner | Input doc | Output doc | Done-when |
| --- | --- | --- | --- | --- | --- |
| 1 | Scope the asset: confirm controller model, firmware, and installed I/O count. Apply the OEM-published voltage/SOC envelope for the named family (Sungrow SG125HV max 1,500 V DC; Huawei SUN2000-330KTL-H1 max 1,500 V DC; CATL LFP SOC window 5–100 %). | tradvolt site engineer | SG125HV datasheet V1.6 2023-08; SUN2000-330KTL-H1 User Manual Issue 03 2023-04-30; CATL LFP Modbus Manual Rev. 2.1 | `scope-note-r14.md` | Asset ID, firmware string, and I/O count match the OEM datasheet line item; torque and SOC setpoints captured against the manual revision named. |
| 2 | Pull and archive the live SCADA configuration export from the Sungrow SCU / Huawei SmartLogger / CATL BCU. | site SCADA tech | `scada-live-config.json` | `scada-baseline-r14.zip` | Configuration snapshot timestamped and stored in the evidence folder. |
| 3 | Reconcile physical wiring, PLC address, and SCADA tag against the OEM register map (Sungrow Modbus map §3.2; Huawei SmartLogger RS485 map §5; CATL LFP register map §4). | commissioning engineer | Sungrow Modbus map; Huawei SmartLogger register map; CATL LFP register map | `io-mapping-reconcile.xlsx` | Every wired point has a matching PLC and SCADA tag with no orphan rows. |
| 4 | Validate link latency (≤4,000 ms Modbus poll; ≤30 s DNP3), retry counts (≤3), and integrity on the CN→AU telemetry path. | network engineer | `telemetry-link-log.csv` | `comms-validation-r14.pdf` | Poll latency stays inside the OEM-published envelope across a 24-hour window. |
| 5 | Capture alarms (priority 1–4), deadbands, and scaling factors per the OEM register map for each verified point. | site SCADA tech | `io-mapping-reconcile.xlsx` | `alarms-scaling-r14.xlsx` | Alarm priority and engineering units match the OEM datasheet. |
| 6 | Patch deviations and re-test the affected points only. | commissioning engineer | `comms-validation-r14.pdf` | `deviation-patch-log.md` | Re-test confirms the patched point reads inside tolerance. |
| 7 | Sign off the evidence pack and route for tradvolt QA review. | tradvolt QA | `alarms-scaling-r14.xlsx` | `scada-io-evidence-pack-r14.zip` | QA counter-signature recorded and pack archived under the asset ID. |

## Equipment families and OEM evidence

| Family | Model | Governing OEM manual | Revision / date | Key limits cited in this guide |
| --- | --- | --- | --- | --- |
| PV string inverter (utility-scale) | Sungrow SG125HV | SG125HV String Inverter Datasheet (and associated SG125HV User Manual) | V1.6 / 2023-08 | Max DC input 1,500 V; SCADA via Modbus TCP/RTU on Sungrow SCU; MPPT voltage window 860–1,450 V. |
| PV string inverter (utility-scale) | Huawei SUN2000-330KTL-H1 | SUN2000-(330KTL-H1, 275KTL-H1) User Manual | Issue 03 / 2023-04-30 | Max DC input 1,500 V; SmartLogger communication via MBUS / RS485; 12 digital + 6 analog I/O on SmartLogger. |
| BESS (LFP) | CATL LFP battery module (racked in 1U/2U form factor, used as model family) | CATL LFP Battery Module Modbus Register Map Manual | Rev. 2.1 / 2023 (publication) | SOC operating window 5–100 %; module DC voltage 0–1,500 V; BMS Modbus RTU over RS485. |

## Document checklist

- SG125HV datasheet / user manual (V1.6, 2023-08) — OEM reference of record for Sungrow scope

- SUN2000-330KTL-H1 user manual (Issue 03, 2023-04-30) — OEM reference of record for Huawei scope

- CATL LFP Modbus register map (Rev. 2.1) — OEM reference of record for BESS scope

- `scope-note-r14.md` — Asset scope note from Step 1

- `scada-live-config.json` — Live configuration pulled at Step 2

- `scada-baseline-r14.zip` — Archived baseline snapshot from Step 2

- OEM Modbus register map for the named family — reconciled mapping source for Step 3

- `io-mapping-reconcile.xlsx` — Reconciled mapping table from Step 3

- `telemetry-link-log.csv` — Raw link log from the SCADA historian

- `comms-validation-r14.pdf` — Communications validation report from Step 4

- `alarms-scaling-r14.xlsx` — Alarm and scaling register from Step 5

- `deviation-patch-log.md` — Patch log from Step 6

- `scada-io-evidence-pack-r14.zip` — Final signed evidence pack from Step 7

## Timeline (indicative)

| Phase | Window | Owner |
| --- | --- | --- |
| Steps 1–2: scope + baseline | Day 1 – Day 2 | tradvolt site engineer / SCADA tech |
| Steps 3–5: reconcile, validate, scale | Day 3 – Day 10 | commissioning + network engineers |
| Step 6: patch and re-test | Day 11 – Day 14 | commissioning engineer |
| Step 7: QA sign-off | Day 15 – Day 21 | tradvolt QA |

## Cost table (indicative)

**Indicative only.** Day-rate values below are a model assumption — no paid rate sheet has been sourced. Values marked **UNCERTAIN** have not been verified from an OEM, regulator, or customs source and must not be treated as a quote.

| Line item | Unit | Indicative rate (AUD) | Source status |
| --- | --- | --- | --- |
| Site engineering day rate | day | indicative · UNCERTAIN (model assumption) | PENDING — no paid rate sheet referenced |
| SCADA tech day rate | day | indicative · UNCERTAIN (model assumption) | PENDING — no paid rate sheet referenced |
| Network engineer day rate | day | indicative · UNCERTAIN (model assumption) | PENDING — no paid rate sheet referenced |
| QA review fee | pack | indicative · UNCERTAIN (model assumption) | PENDING — no paid rate sheet referenced |

## HS / duty reference (CN → AU)

**Disclaimer.** HS code descriptions below are taken from the ABF Working Tariff and duty rates from the WTO tariff database; traders must confirm the line item applies to the specific configuration on the day of entry.

| HS code | Description (source) | Source |
| --- | --- | --- |
| 8504.40 | Static converters (e.g., DC/AC inverters, incl. SG125HV and SUN2000-330KTL-H1 when classified separately) | ABF Working Tariff, Section XVI, Ch. 85, Heading 8504.40 — ABF §XVI Ch. 85 Heading 8504; WTO Tariff Database — WTO tariff data |
| 8537.10 | Boards, panels, consoles, desks, cabinets and other bases, equipped with two or more apparatus of heading 8535 or 8536, for electric control or distribution of electricity (SCADA cabinets) | ABF Working Tariff, Heading 8537.10 — ABF §XVI Ch. 85 Heading 8537 |
| 9032.89 | Automatic regulating or controlling instruments and apparatus, other (SCADA-adjacent controllers, BCUs) | ABF Working Tariff, Heading 9032.89 — ABF §XVIII Ch. 90 Heading 9032 |

Verify against the ABF Working Tariff Portal ([ABF Working Tariff landing page](https://www.abf.gov.au/importing-exporting-and-manufacturing/importing/how-much-duty-do-you-pay)) and the WTO Tariff Database on the day of entry. Duty outcome depends on configuration (inverter vs cabinet vs control instrument).

## FAQ

### What is the purpose of a SCADA I/O check?

It reconciles the physical wiring on an asset with the controller's logical address and the SCADA tag, so that telemetry and control commands map to the correct field equipment. The OEM datasheet or user manual is the reference of record.

### How often should the check run?

tradvolt runs a full check after commissioning and after any firmware or hardware change, with periodic spot checks aligned to the OEM service interval (typically annual for SG125HV / SUN2000-330KTL-H1 inverter cabinets; quarterly for CATL LFP BESS racks per OEM BMS recommendation). Site-specific cadence is set in the asset maintenance plan.

### What evidence is required?

At minimum: a baseline SCADA configuration export, a reconciled I/O mapping, a communications validation report, and an alarm-and-scaling register — bundled into a single evidence pack for tradvolt QA sign-off.

### Does this guide replace OEM service procedures?

No. The OEM manual is computed (SG125HV V1.6, SUN2000-330KTL-H1 Issue 03, CATL LFP Rev. 2.1). This guide only standardises how tradvolt captures and reviews the evidence before return-to-service.

### Who signs off the evidence pack?

tradvolt QA signs off after Step 7. Site engineering, commissioning, and network engineering each sign the rows they own in the step-sequence table.

[Request RFQ — SCADA I/O Check](/rfq/?topic=cn-au-scada-io-check&src=guide-r14-bottom) [Download PDF checklist](https://tradvolt.com/downloads/cn-au-scada-io-check-r14.pdf)

## Claim sources

| Claim | Source | Section / use |
| --- | --- | --- |
| Sungrow SG125HV max DC input 1,500 V; SCADA via Modbus TCP/RTU on SCU. | Sungrow SG125HV Datasheet / User Manual (revision V1.6, dated 2023-08) — file on the OEM portal: SG125HV-Datasheet-V1.6-202308.pdf | Step 1 input doc; Equipment table; voltage/SOC envelope |
| Huawei SUN2000-330KTL-H1 max DC input 1,500 V; SmartLogger MBUS / RS485 communication; 12 digital + 6 analog I/O. | Huawei SUN2000-(330KTL-H1, 275KTL-H1) User Manual, Issue 03 (2023-04-30) — Huawei support page (SUN2000 330KTL-H1 / 275KTL-H1 user manual) | Step 1 input doc; Equipment table; I/O count row in Step 1 |
| CATL LFP battery module SOC window 5–100 %; module DC voltage 0–1,500 V; Modbus RTU on RS485. | CATL LFP Battery Module Modbus Register Map Manual, Rev. 2.1 — CATL LFP Modbus Map Rev. 2.1 (PDF) | Step 1 input doc; Equipment table; SOC envelope |
| HS code 8504.40 — static converters (covers PV inverters classified separately). | ABF Working Tariff, Heading 8504.40 — ABF §XVI Ch. 85 Heading 8504; cross-check WTO tariff database — WTO tariff data | HS / duty reference |
| HS code 8537.10 — boards/panels/cabinets for electric control or distribution (SCADA cabinets). | ABF Working Tariff, Heading 8537.10 — ABF §XVI Ch. 85 Heading 8537 | HS / duty reference |
| HS code 9032.89 — automatic regulating or controlling instruments and apparatus, other (SCADA-adjacent). | ABF Working Tariff, Heading 9032.89 — ABF §XVIII Ch. 90 Heading 9032 | HS / duty reference |
| Indicative day rates for site, SCADA, and network engineers and QA fee. | No paid rate sheet referenced — model assumption pending sourcing. | Cost table (UNCERTAIN) |
| QA sign-off (Step 7) closes the evidence pack for return-to-service; OEM manual remains computed. | Internal process; OEM manuals named above. | Step 7; FAQ |

Sources restricted to OEM datasheets/manuals and regulator or customs pages. No blog, forum, or AI-generated sources cited. Any rate, code, or statistic not yet sourced is marked **UNCERTAIN** (model assumption) in-line. UN Manual of Tests and Criteria / UN 38.3 are not in scope for this maintenance page (no transport test of cells performed).