# Solar String IV-Curve Trace Test — Standard Operating Procedure

Process / SOP • Vertical-solar Balance-of-System (BoS) • Corridor CN → SN

This Standard Operating Procedure (SOP) defines how TradVolt service engineers perform an I-V (current–voltage) curve trace test on individual PV strings within a China-to-Senegal vertical-solar BoS corridor. The procedure supports commissioning verification, warranty claims, and post-event diagnostics. Step sequence, document checklist, and trade-compliance notes are provided as field-ready references; rates and duties are deliberately marked as placeholders pending computed lookup.

## 1. Purpose & Scope

The purpose is to establish a repeatable method for tracing the I-V characteristic of each photovoltaic string in service, comparing measured values against manufacturer baseline, and producing traceable evidence for the asset record. The scope covers low-voltage DC-side string testing using a portable curve tracer, performed by trained field service personnel on operating plants or at incoming inspection.

## 2. Normative References

- [IEC 61215 series](https://webstore.iec.ch/) — Crystalline silicon PV module design qualification and type approval.

- [IEC 62446-3](https://webstore.iec.ch/) — Photovoltaic systems: outdoor infrared thermography, plus I-V curve tracing principles for strings.

- [ISO 2859-1](https://www.iso.org/standard/11436.html) — Sampling procedures for inspection by attributes (AQL framework).

- [ICC Incoterms® 2020](https://iccwbo.org/business-solutions/incoterms-2020/) — Trade-term definitions referenced in the corridor logistics note.

- [FIATA](https://www.fiata.com/) — Multimodal transport documents referenced for cross-border moves.

## 3. Step Sequence

| Step # | Action | Owner | Input doc | Output doc | Done-when |
| --- | --- | --- | --- | --- | --- |
| 1 | Receive work order and confirm site, inverter, string count, and access window. | Service Coordinator | WO (Work Order) | Acknowledged WO log | WO logged in CMMS with site code, expected string count, and visit date. |
| 2 | Review site safety plan, isolation scheme, and PPE requirements; brief the team. | Site Safety Officer | Site Safety Plan | Signed toolbox-talk sheet | All crew sign toolbox-talk; LOTO kit inspected. |
| 3 | Calibrate the I-V tracer against a reference cell or PV calibrator; record values. | Field Engineer (LE) | Tracer calibration log (last entry) | Updated calibration record | Calibration record shows date, reference values, and engineer signature. |
| 4 | Isolate the target string at combiner; verify zero energy with a DC voltage tester. | Field Engineer (LE) | Single-line diagram | Isolation tag placed | Voc reading ≤ 5 V at string terminals; lock and tag applied. |
| 5 | Connect tracer leads; capture irradiance and module temperature inputs. | Field Engineer (LE) | Module datasheet (STC) | Raw trace file (.csv/.trc) | Trace file saved with timestamp, irradiance W/m², and cell temperature °C. |
| 6 | Run the I-V sweep and validate shape (Voc, Isc, Vmpp, Impp, fill factor). | Field Engineer (LE) | Raw trace file | Validated trace sheet | Key points recorded; anomalies flagged if deviation > set tolerance. |
| 7 | Re-energize the string; confirm DC operating voltage on inverter string input. | Field Engineer (LE) | Validated trace sheet | Inverter readout note | Inverter recognises string; telemetry reflects expected Vdc range. |
| 8 | Repeat Steps 4–7 for each string in the inspection batch. | Field Engineer (LE) | String list | Batch of trace sheets | All strings in batch tested; missing strings justified in comments. |
| 9 | Sign off the test report; attach traces and photos to the asset record. | Field Engineer (LE) + Service Coordinator | Batch of trace sheets | Signed PDF test report | Report uploaded to CMMS; QA review completed. |
| 10 | Close ticket and notify the client with findings summary. | Service Coordinator | Signed PDF test report | Client email + CMMS ticket closed | Client acknowledges receipt; ticket status set to "Closed". |

## 4. Document Checklist (literal filenames)

- `WO_[SiteCode]_[YYYYMMDD].pdf` — Work order file.

- `SafetyPlan_[SiteCode]_v[XX].pdf` — Site safety and LOTO plan.

- `ToolboxTalk_[YYYYMMDD].pdf` — Signed toolbox-talk sheet.

- `IVTracer_CalLog_2026.xlsx` — Tracer calibration log.

- `SLD_[SiteCode].pdf` — Single-line diagram for isolation reference.

- `ModuleDatasheet_[Model].pdf` — OEM module datasheet (STC values).

- `Trace_String[NN]_[YYYYMMDD].csv` — Raw I-V trace data per string.

- `TestReport_[SiteCode]_[YYYYMMDD].pdf` — Final signed report.

## 5. Timeline & Dependencies

| Phase | Indicative duration | Dependencies |
| --- | --- | --- |
| Pre-mobilisation (Steps 1–3) | 1 working day (indicative) | Client WO, tracer availability, OEM datasheet. |
| On-site execution (Steps 4–8) | ~15–20 minutes per string (indicative) | Weather window ≥ 400 W/m² irradiance (indicative), safe access. |
| Reporting & close-out (Steps 9–10) | 1 working day (indicative) | QA review, client contact, CMMS availability. |
| Total field footprint | ~8 h on site for a 24-string batch (indicative) | Includes travel between combiner boxes; not measured. |

All durations are indicative and depend on site layout, string count, and weather. Actual times are recorded in the CMMS time-sheet per visit.

## 6. Cost & Logistics Slots

| Slot | Value | Status |
| --- | --- | --- |
| Mobilisation fee (per site visit) | indicative | UNCERTAIN — quote on RFQ |
| Per-string test labour | indicative | UNCERTAIN — quote on RFQ |
| Tracer rental / depreciation | indicative | UNCERTAIN — quote on RFQ |
| Report preparation | indicative | UNCERTAIN — quote on RFQ |
| Cross-border logistics (CN → SN) | indicative | UNCERTAIN — depends on Incoterms® 2020 selection and FIATA documents. |

## 7. Duty / HS Code Block

| Item | HS code | Duty rate | Source / portal |
| --- | --- | --- | --- |
| PV modules (crystalline silicon) | PENDING — lookup | PENDING — lookup | World Customs Organization HS nomenclature; national tariff portals. |
| Electrical measuring instruments (I-V tracer, multimeter) | PENDING — lookup | PENDING — lookup | World Customs Organization HS nomenclature; national tariff portals. |
| DC isolators / combiners (BoS parts) | PENDING — lookup | PENDING — lookup | World Customs Organization HS nomenclature; national tariff portals. |

**Disclaimer:** HS classifications and applicable duty/VAT rates for the corridor CN → SN must be verified against the official customs portal of each jurisdiction at the time of shipment. TradVolt does not hardcode duty rates; the placeholders above are intentional and must be resolved by a licensed customs broker or the importer of record before any commercial invoice is issued.

## 8. Reader-Facing CTAs

**Need this SOP executed on your site?** Submit your string count, site location, and target visit window. TradVolt service coordinators will respond.

[Request Quote — replies in 48h](/rfq?service=iv-curve-trace&amp;corridor=CN-SN) Download IV-Trace Checklist (PDF)

## 9. Source Claims

**Claim:** I-V curve tracing for PV strings is covered as a test method by IEC 62446-3. **Src:** IEC Webstore. **URL:** https://webstore.iec.ch/. **Accessed:** 2026-09-21. **Claim:** Crystalline-silicon PV module design qualification baseline is IEC 61215. **Src:** IEC Webstore. **URL:** https://webstore.iec.ch/. **Accessed:** 2026-09-21. **Claim:** Attribute inspection sampling is governed by ISO 2859-1 (AQL framework). **Src:** ISO. **URL:** https://www.iso.org/standard/11436.html. **Accessed:** 2026-09-21. **Claim:** Trade-term definitions follow ICC Incoterms® 2020. **Src:** International Chamber of Commerce. **URL:** https://iccwbo.org/business-solutions/incoterms-2020/. **Accessed:** 2026-09-21. **Claim:** Multimodal forwarding documents are issued per FIATA standards. **Src:** FIATA. **URL:** https://www.fiata.com/. **Accessed:** 2026-09-21. **Claim:** Harmonized System nomenclature is maintained by the World Customs Organization. **Src:** World Customs Organization. **URL:** https://www.wcoomd.org/. **Accessed:** 2026-09-21.