# EVSE CCS2 Communication Handshake Test — Corridor CN→KR

A corridor-bound Standard Operating Procedure that walks an EVSE field engineer from cable inspection through SLAC pairing to a wired OCPP 1.6J transaction, then assembles a bilingual hand-off pack so the unit is ready to operate on the China → Korea trade lane.

Vertical: EVSEType: Process / SOPStandard: IEC 61851-1, ISO 15118-2Corridor: CN→KROwner role: Field EngineerIssued: 2026-09-21  Download SOP Checklist (PDF) [Request Quote — replies in 48h](#rfq)

## 1. Scope, Audience and Trigger

**Scope.** Every CCS2 DC fast charger commissioned, recommissioned, or returned to service after a control-board repair on the China → Korea corridor.

**Audience.** TradVolt field engineers, the client's O&M duty supervisor, and OEM factory service representatives who require a shared acceptance baseline.

**Trigger.** New install, firmware update, SLAC retry count above threshold, or an annual maintenance slot in the CMMS. [ Claim | Src: IEC 61851-1:2017 — Annex C | URL: https://webstore.iec.ch/publication/33611 | accessed 2026-09-21 ]

Plain English summary only; the binding text is the cited standard.

## 2. Step Sequence

Table 2.1 — End-to-end SOP step sequence; every action has an explicit owner. | Step # | Action | Owner | Input doc | Output doc | Done-when |
| --- | --- | --- | --- | --- | --- |
| 1 | Confirm EVSE model, firmware build, installed location, and that grid, internet and earth connections are healthy. | Field Engineer | tradvolt-ccs2-site-survey-v2.3.xlsx | sop-ccs2-cn-kr-precond-record.pdf | Asset tag, FW build and earth-bond reading recorded with timestamp. |
| 2 | Don arc-rated PPE; apply Lockout–Tagout on the upstream AC; obtain a live-work permit. | Field Engineer + Safety Officer | IEC 62955 safety checklist | lot-energise-photo-evidence.zip | LOTO tag affixed; permit countersigned by Safety Officer. |
| 3 | Inspect CCS2 cable, contacts, latch and inlet for wear, contamination, overheating marks and IP54 sealing integrity. | Field Engineer | cable-visual-guideline-iso-2859-1.pdf | cable-condition-form.pdf | Inspection sheet signed; pass = no thermal marks. |
| 4 | Measure Proximity Pilot resistance and Control Pilot voltage on a confirmed de-energised inlet. | Field Engineer | OEM EVSE wiring diagram | pp-cp-measurement-log.csv | PP within ±1 % of coded value; CP @ ±12 V / ±9 V / ±6 V per state. |
| 5 | Connect a CCS2 EV emulator; confirm the SLC module pairing state and short-link test status on the HMI. | Field Engineer | EV emulator user manual | emulator-link-screenshot.png | “Link OK / paired” indicator visible on HMI. |
| 6 | Run a 5-cycle HomePlug Green PHY handshake; capture the QoC bytes for each cycle. | Field Engineer | Oscilloscope (≥ 100 MHz, isolated) | slac-5cycle-trace.pdf | 5 / 5 cycles complete within ≤ 4.5 s each. |
| 7 | Run the PICS test cases for DIN 70121 / ISO 15118-2, including matching process and target parameters. | Field Engineer + OEM Engineer | PICS test suite (OEM-issued) | pics-conformance-report.pdf | All mandatory cases return PASS. |
| 8 | From the CSMS, push a StartTransaction to the EVSE; confirm StatusNotification and MeterValues. | Backend Operator + Field Engineer | OCPP 1.6J schema (OCPP-1.6-J-Specification) | ocpp-transaction-log.json | MeterValues backflow ≤ 60 s; transactionId returned. |
| 9 | Perform 500 V / 1 min insulation resistance and PE continuity tests. | Field Engineer | IEC 61851-1 Annex C | insulation-test-record.pdf | IR ≥ 1 MΩ; PE ≤ 0.1 Ω at 25 A. |
| 10 | Inject a CP signal-out-of-range, then a PP mismatch; confirm the EVSE trips safely and surfaces a coded fault. | Field Engineer | Fault-injection spreadsheet (OEM) | fault-trip-report.pdf | Unit opens contactor; fault code logged to CSMS. |
| 11 | Compile test sheet, oscilloscope captures and firmware-vendor pass report into a bilingual handoff pack. | Field Engineer | Section 5 checklist | tradvolt-cn-kr-handoff-pack-v1.pdf | PDF < 25 MB; SHA-256 logged in CMMS. |
| 12 | Lock the asset in the CMMS, file manuals into the on-site binder, brief the duty supervisor. | Field Engineer + Operations Lead | CMMS work order | cmms-acceptance-ticket.pdf | Status “Ready for Service”; duty supervisor signs. |

## 3. Factual Claim Rows

[ Claim | The CCS2 connector family is standardised in IEC 62196-3, which defines Type 2 pin spacing and the DC current-carrying contacts used in this SOP. | Src: IEC 62196-3:2022 | URL: https://webstore.iec.ch/publication/62266 | accessed 2026-09-21 ] [ Claim | DC EV charging stations require testing per IEC 61851-23, the international standard governing the DC charging control function, including PWM signalling and digital communication. | Src: IEC 61851-23:2023 | URL: https://webstore.iec.ch/publication/62244 | accessed 2026-09-21 ] [ Claim | IEC 61851-1 Annex C defines post-test insulation resistance thresholds applied at step 9 of this SOP. | Src: IEC 61851-1:2017 — Annex C | URL: https://webstore.iec.ch/publication/33611 | accessed 2026-09-21 ] [ Claim | ISO 15118-2 specifies the conformance test (PICS) executed at step 7, with SLAC validation as the first 802.3-style carrier and session setup prior to UDP/TLS. | Src: ISO 15118-2:2014 | URL: https://www.iso.org/standard/59666.html | accessed 2026-09-21 ] [ Claim | DIN 70121 defines a reduced feature-set predecessor protocol that some Korean fleets still require; both protocols are dispatched from the same SLAC layer. | Src: DIN 70121:2012 | URL: https://www.din.de/en/getting-involved/standards-committees/nasg/standards/wdc-beuth:din21:193604873 | accessed 2026-09-21 ] [ Claim | The physical-layer (HLE / SLAC) handshake used during PLC-based EV/EVSE matching is defined in ISO 15118-3, with HomePlug Green PHY as the customary carrier. | Src: ISO 15118-3:2015 | URL: https://www.iso.org/standard/61884.html | accessed 2026-09-21 ] [ Claim | OCPP 1.6J is the back-office protocol invoked at step 8; the open specification is published by the Open Charge Alliance. | Src: Open Charge Alliance — OCPP 1.6, JSON Edition | URL: https://www.openchargealliance.org/protocols/ocpp-16/ | accessed 2026-09-21 ] [ Claim | IEC 62955 gives in-cable residual current protection and the live-work permit reference invoked in step 2. | Src: IEC 62955:2016 | URL: https://webstore.iec.ch/publication/25246 | accessed 2026-09-21 ] [ Claim | Connector wear and contamination detected in step 3 are sampled by attributes and lot using ISO 2859-1 general inspection Level II, AQL 1.0. | Src: ISO 2859-1:1999 | URL: https://www.iso.org/standard/1141.html | accessed 2026-09-21 ] [ Claim | UL 2202 / UL 2734 provide the North-American safety baseline accepted by global bidders who source within or via the United States. | Src: UL 2202 (UL Product iQ) | URL: https://www.shopulstandards.com/ProductDetail.aspx?UniqueKey=33533 | accessed 2026-09-21 ]

## 4. Document Checklist

Literal filenames as they appear on the engineer tablet and in the CMMS. Mismatched filenames block handover.

- tradvolt-ccs2-site-survey-v2.3.xlsx

- sop-ccs2-cn-kr-precond-record.pdf

- lot-energise-photo-evidence.zip

- cable-visual-guideline-iso-2859-1.pdf

- cable-condition-form.pdf

- pp-cp-measurement-log.csv

- emulator-link-screenshot.png

- slac-5cycle-trace.pdf

- pics-conformance-report.pdf

- ocpp-transaction-log.json

- insulation-test-record.pdf

- fault-trip-report.pdf

- tradvolt-cn-kr-handoff-pack-v1.pdf

- cmms-acceptance-ticket.pdf

## 5. Timeline and Dependencies

Table 5.1 — Indicative durations for an 8-hour shift; cost slots are **indicative** and not a quotation. | Phase | Indicative duration | Depends on | Cost slot |
| --- | --- | --- | --- |
| Mobilisation to site (CN border warehouse) | ~ 4 h | Customs clearance of tools and emulator | Logistics slot: **indicative** |
| Road transit to KR site (Incheon / Busan) | ~ 18 h | Ferry slot, customs broker | Indicative; UNCERTAIN subject to weather |
| Pre-condition survey (Steps 1–3) | ~ 1.5 h | LOTO permit, OEM drawings | Engineering day rate: **indicative** |
| PP / CP / SLC measurement (Steps 4–5) | ~ 0.5 h | Emulator firmware alignment | UNCERTAIN until OEM stable build |
| PLC SLAC handshake (Step 6) | ~ 0.75 h | Stable mains; PLC coupling network | Indicative |
| PICS / DIN 70121 (Step 7) | ~ 2 h | OEM engineer on call | UNCERTAIN until OEM engineer availability confirmed |
| OCPP loop (Step 8) | ~ 0.5 h | CSMS connection, CA-signed certs | Indicative |
| Insulation + fault injection (Steps 9–10) | ~ 1.25 h | Test fixtures | Indicative |
| Handoff and CMMS (Steps 11–12) | ~ 1 h | All artifacts present | Indicative |

Routing, RoRo terms, and customs broker fees are described using Incoterms 2020 terminology in §6.

## 6. Logistics and Customs — CN→KR Corridor

**6.1 Incoterms baseline.** Equipment lots are typically quoted **CIP Incheon** or **DAP Incheon DC warehouse**. The Receiving Party must provide an *“Autorisation administrative pour le transit”* equivalent — in practice the **Korea Customs Service** import declaration via UNI-PASS.

**6.2 FIATA cross-border doc set.** A multi-modal truck + short-sea shipment uses a FIATA FBL (negotiable multimodal transport waybill) for the CN-port → Busan/Incheon leg, supported by commercial invoice, packing list and the FIATA FIATA Bill of Lading where a single carrier accepts loading.

**6.3 Cross-border CN customs.** Trucks exit through the General Administration of Customs of the People's Republic of China (GACC) at Manzhouli or Hunchun; **export-return** and ATA Carnet procedures apply when re-export is in scope.

**6.4 Cross-border KR customs.** Inbound road cargo clears through the Korea Customs Service — UNI-PASS. Hard declarations begin at the bonded warehouse attached to the entry port.

[ Claim | Incoterms 2020 defines the CIP and DAP rules cited above, assigning risk transfer, transport and customs handling responsibilities to each party. | Src: ICC Incoterms 2020 (ICC Publication No. 723E) | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | accessed 2026-09-21 ] [ Claim | The FIATA multimodal transport contract reference documents (FBL, FCR) are issued under FIATA's framework rules for forwarders. | Src: FIATA Multimodal Transport Waybill (FBL) Rules | URL: https://fiata.com/what-we-do/fiata-bills.html | accessed 2026-09-21 ] [ Claim | Inbound customs clearance is lodged through UNI-PASS, the Korea Customs Service Single Window platform. | Src: Korea Customs Service — UNI-PASS | URL: https://www.customs.go.kr/eng/main.do | accessed 2026-09-21 ] [ Claim | Outbound CN customs clearance, returns and ATA procedures are governed by the General Administration of Customs of the People's Republic of China (GACC). | Src: GACC | URL: http://english.customs.gov.cn/ | accessed 2026-09-21 ]

## 7. Duties, HS Code and Cross-Border Duties

Table 7.1 — Harmful-tax reference only; rates are placeholders until the official portal is queried the same business day. | Item | HS code (WCO Rev. 2026 nomenclature; CN used by default) | Description | CN export duty rate | KR import duty rate |
| --- | --- | --- | --- | --- |
| DC fast EVSE ≤ 50 kW | 8504.40.40 | Static converters — power supplies for charging electric vehicles | PENDING — lookup | PENDING — lookup |
| DC fast EVSE > 50 kW | 8504.40.50 | Static converters — other, higher-power | PENDING — lookup | PENDING — lookup |
| CCS2 charge cable / connector (spare part) | 8536.69.00 | Plugs and sockets for apparatus of switching, protecting or connecting electrical circuits — other | PENDING — lookup | PENDING — lookup |
| Charge-controller PCB (spare) | 8542.31.00 | Electronic integrated circuits — mounted chips | PENDING — lookup | PENDING — lookup |

**Official portal — CN side:** GACC Customs Tariff Search — [http://english.customs.gov.cn/](http://english.customs.gov.cn/).

**Official portal — KR side:** Korea Customs Service Trade Portal — [https://www.customs.go.kr/eng/main.do](https://www.customs.go.kr/eng/main.do) and the HS Rulings section within UNI-PASS. Notice — All duty and VAT lines above are **placeholders** marked **PENDING — lookup**. We do not publish hard-coded rates because CN and KR tariff schedules change. Always confirm via the official portals above on the date of the customs declaration. TradVolt does not provide tax advice; consult a licensed customs broker.

## 8. Request Quote

Need a field engineer on the CN→KR corridor, an OEM-aligned firmware build, or a customs broker who understands CCS2 spare parts? TradVolt returns RFQs within 48 working hours in either Chinese or Korean.

[Request Quote — replies in 48h](/rfq?service=evse-commissioning&amp;corridor=cn-kr&amp;sop=ccs2-handshake)

Reply window is 48 working hours from receipt of a complete RFQ (items, quantities, pickup / delivery, payload list, target service date).

## 9. Roles and Responsibilities

- **Field Engineer** — Steps 1–12 physical execution; signatories of the bilingual hand-off pack.

- **Safety Officer** — countersigns LOTO permit (Step 2).

- **OEM Engineer** — remote support for PICS test and firmware versioning (Step 7).

- **Backend Operator** — operates the CSMS for the OCPP loop (Step 8).

- **Operations Lead** — receives the brief, locks CMMS status (Step 12).

- **Customs Broker** — CIP / DAP execution, FBL/FCR documentation (Section 6).

## 10. References

1. IEC 61851-1:2017, Annex C. URL: https://webstore.iec.ch/publication/33611

2. IEC 61851-23:2023. URL: https://webstore.iec.ch/publication/62244

3. IEC 62196-3:2022. URL: https://webstore.iec.ch/publication/62266

4. IEC 62955:2016. URL: https://webstore.iec.ch/publication/25246

5. ISO 15118-2:2014. URL: https://www.iso.org/standard/59666.html

6. ISO 15118-3:2015. URL: https://www.iso.org/standard/61884.html

7. ISO 2859-1:1999. URL: https://www.iso.org/standard/1141.html

8. DIN 70121:2012. URL: https://www.din.de/en/getting-involved/standards-committees/nasg/standards/wdc-beuth:din21:193604873

9. UL 2202. URL: https://www.shopulstandards.com/ProductDetail.aspx?UniqueKey=33533

10. Open Charge Alliance — OCPP 1.6, JSON Edition. URL: https://www.openchargealliance.org/protocols/ocpp-16/

11. ICC Incoterms 2020 (ICC Publication No. 723E). URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/

12. FIATA FBL Rules. URL: https://fiata.com/what-we-do/fiata-bills.html

13. Korea Customs Service — UNI-PASS. URL: https://www.customs.go.kr/eng/main.do

14. General Administration of Customs of China (GACC). URL: http://english.customs.gov.cn/

All sources accessed on 2026-09-21. TradVolt is not a customs authority; rates, HS codes and rulings must be validated through the official portals.