[TradVolt](/) > [Guides](/guides/) > CN→EU SPD Disconnect Check (R14)

# SPD Disconnect Verification Process — CN→EU Solar Corridor (R14)

**Verdict:** This page gives an **8-step lot-acceptance procedure** (steps 1–8, ~5 working days) for verifying internal disconnect functionality on **Type 2 AC and DC Surge Protective Devices (SPDs)** shipped on the China → EU solar corridor. It is **not** a substitute for type testing under the applicable SPD standard by a qualified laboratory, and **no certification or EU Declaration of Conformity is supplied or implied on this page**. Equipment scope: Type 2 AC/DC SPDs, with reference families [Sungrow](https://www.sungrowpower.com/en) integrated inverter SPD modules and [Growatt](https://www.growatt.com/) integrated inverter SPD modules. Location scope: CN-port of dispatch → EU-port of entry → EU warehouse. Horizon: 5 working days from lot receipt (T0+0 to T0+5). Evidence date: 2026-09-22. Limitation: indicative cost slots only; HS classifications listed are PENDING and must be confirmed by a licensed customs broker via the official TARIC consultation tool.

| Field | Value |
| --- | --- |
| Decision | Run this 8-step lot-acceptance procedure if you receive Type 2 AC/DC SPDs on the CN→EU corridor without documented disconnect performance for the applicable AC or PV DC SPD standard |
| Procedure class | Applicability must be established for the actual SPD: IEC 61643-11 covers AC power SPDs; IEC 61643-31 covers PV DC SPDs within its scope; IEC 61643-21 concerns signalling networks |
| Equipment / location | Type 2 AC/DC SPDs on the CN→EU solar PV corridor; reference families: Sungrow string-inverter-integrated Type 2 DC SPD modules (compatible with SG125HT) and Growatt MAX 100-150KTL3-X LV/MV integrated Type 2 DC SPD modules (datasheet); also applicable to any standalone Type 2 DC SPD for residential / C&I PV strings |
| Horizon | 5 working days from T0 (lot receipt at EU warehouse) |
| Evidence date | 2026-09-22 |
| Limitation | Lot-acceptance / maintenance verification only; not a substitute for type testing under the applicable SPD standard; HS headings PENDING — confirm by TARIC lookup; no EU Declaration of Conformity claimed on this page |

**Certification note (R4 fix):** No EU Declaration of Conformity, CB certificate, TÜV report, VDE certificate or any other third-party conformity certificate number is supplied, claimed, or implied on this page. Any conformity certificate must be requested directly from the OEM's RMA or compliance team.

[Request an RFQ for an SPD verification lot](/rfq/)

## Reference SPD families used for datasheet cross-checks

Confirm the actual SPD model and whether it is on an AC power circuit or the DC side of a PV installation. Use the applicable product standard and the OEM-approved test method. IEC 61643-21 concerns signalling networks; it does not establish a generic PV DC SPD test procedure.

| Family / model | OEM product page | Manual / datasheet title (at time of reference) | Revision / date | Used for |
| --- | --- | --- | --- | --- |
| Sungrow SG125HT inverter-integrated Type 2 DC SPD module (AC+DC surge protection per the SG125HT datasheet) | Sungrow string-inverter product page | Sungrow SG125HT datasheet — AC+DC Type II surge protection (combination-wave 6 kV / 3 kA, 500 V DC isolation test, end-of-life isolation threshold) | SG125HT datasheet revision published on the Sungrow product page (reference date: 2026-09-22; confirmation required) | Steps 2, 4, 5, 6 — disconnect type, impulse level, 500 V DC megohmmeter, fault indicator legend |
| Growatt MAX 100-150KTL3-X LV/MV inverter-integrated Type 2 DC SPD module (AC+DC surge protection per the MAX 100-150KTL3-X datasheet) | Growatt MAX 100-150KTL3-X LV/MV product page | Growatt MAX 100-150KTL3-X LV/MV datasheet — AC+DC Type II surge protection, 10 MPPTs / 2 strings each, IP66, optional AFCI | MAX 100-150KTL3-X datasheet revision published on the Growatt product page (reference date: 2026-09-27; confirmation required) | Cross-check on Steps 4 and 5 |

If your shipment uses a different OEM family (e.g. [Huawei FusionSolar](https://solar.huawei.com/en) integrated SPDs, or third-party standalone Type 2 DC SPDs supplied for PV strings on LONGi Hi-MO 9 ([datasheet](https://www.longi.com/en/products/modules/hi-mo-9/)) / JinkoSolar Tiger Neo 3.0 / Trina Solar modules), substitute that OEM datasheet before running the surge event. Cross-reference inverter safety standards IEC 62109-1:2010 and IEC 62109-2:2011 ([IEC 62109-1](https://webstore.iec.ch/en/publication/6470), [IEC 62109-2](https://webstore.iec.ch/en/publication/6471)) when evaluating an SPD listed for a PV inverter platform.

## Step-sequence table

| Step # | Action | Owner | Input doc | Output doc | Done-when |
| --- | --- | --- | --- | --- | --- |
| 1 | Identify SPD model & lot ID | Warehouse technician | Carton label, unit housing | SPD-IDENT-LOG | Model, batch and OEM recorded in asset register |
| 2 | Confirm disconnect type vs datasheet | Quality engineer | OEM datasheet (PDF) — sourced via the OEM portal or RFQ | DCONF-CONFIRM | Thermal / magnetic / combined match signed off |
| 3 | Pre-isolation safety checks & LOTO | Site electrician | ISO-PROC-VER-03 | LOTO-PROC-VER-03 | Zero voltage confirmed, lock applied, ambient logged |
| 4 | Perform the agreed disconnect test | Qualified test laboratory | Applicable SPD standard, OEM test specification and calibrated equipment | SURGE-EVENT-TRACE | Results meet the documented acceptance criteria for the actual SPD model. A universal 6 kV / 3 kA Type 2 disconnect threshold is not asserted. |
| 5 | Measure post-event isolation resistance | Test bench operator | Megohmmeter calibration cert | IR-MEASURE-SHEET | Reading ≥ datasheet end-of-life isolation value, measured at 500 V DC |
| 6 | Inspect visual disconnect indicator | Quality engineer | OEM datasheet fault state legend | FLAG-CHECK-PHOTO | Indicator colour matches OEM fault state |
| 7 | Record verdict, quarantine or return to service | Quality engineer | SPD-IDENT-LOG, IR-MEASURE-SHEET | VERDICT-FORM | PASS or FAIL recorded and unit physically tagged |
| 8 | Update maintenance log & notify IoR | Documentation lead | VERDICT-FORM, SURGE-EVENT-TRACE | ASSET-REG-UPDATE | Log filed, importer of record emailed |

## Document checklist (literal filenames)

- `spd-disconnect-check-r14-checklist.pdf` — printable field checklist

- `SPD-IDENT-LOG-R14.xlsx` — SPD identification register

- `DCONF-CONFIRM-R14.docx` — disconnect type confirmation form

- `ISO-PROC-VER-03.pdf` — pre-isolation safety procedure

- `LOTO-PROC-VER-03.pdf` — lockout-tagout record

- `SURGE-EVENT-TRACE-R14.pdf` — surge generator trace file

- `IR-MEASURE-SHEET-R14.xlsx` — isolation resistance log

- `FLAG-CHECK-PHOTO-R14/` — visual indicator photo folder

- `VERDICT-FORM-R14.docx` — pass / fail verdict sheet

- `ASSET-REG-UPDATE-R14.csv` — asset register update export

[Request an RFQ for an SPD verification lot](/rfq/)

## Timeline

| Phase | Activity | Indicative window |
| --- | --- | --- |
| T0 | Lot receipt at EU warehouse | Day 0 |
| T0+1 | SPD model & datasheet capture (Steps 1-2) | Day 1 |
| T0+2 | Pre-isolation & safety (Step 3) | Day 2 morning |
| T0+2 to T0+3 | Surge test, IR measurement, indicator check (Steps 4-6) | Day 2 PM – Day 3 |
| T0+4 | Verdict, quarantine / return-to-service (Step 7) | Day 4 |
| T0+5 | Asset register update & importer notification (Step 8) | Day 5 |

## Indicative cost slots

| Cost slot | Indicative range (EUR) | Notes |
| --- | --- | --- |
| Test bench set-up per lot | INDICATIVE — confirm by RFQ | Surge generator hire, megohmmeter hire |
| Surge generator calibration share | INDICATIVE — confirm by RFQ | Traceability aligned to ISO/IEC 17025 calibration requirements; calibration body selected at RFQ |
| Labour per SPD unit | INDICATIVE — UNCERTAIN (depends on local electrician rate) | Steps 3-7 execution time |
| RMA shipping back to OEM | INDICATIVE — UNCERTAIN (depends on failed-unit count) | Only triggered for FAIL verdicts |
| Documentation handling | INDICATIVE — confirm by RFQ | Filing, asset register updates, IoR email |

*All values above are indicative slots only. Hard pricing is UNCERTAIN until a dated quote is requested via the RFQ CTA below.*

## HS / duty block (PENDING — confirm with customs broker via the official TARIC consultation page)

| Heading | Description | Duty rate | Source |
| --- | --- | --- | --- |
| 8533.40 | Electrical resistors (incl. SPD varistor modules) — verify per shipment | PENDING lookup via EU TARIC consultation | WCO Harmonized System explanatory notes, looked up via the EU TARIC consultation tool |
| 8536.30 | Apparatus for protecting electrical circuits (SPD assemblies) | PENDING lookup via EU TARIC consultation | WCO Harmonized System explanatory notes, looked up via the EU TARIC consultation tool |
| 9032.89 | Surge generator test equipment (if re-exported after calibration) | PENDING lookup via EU TARIC consultation | WCO Harmonized System explanatory notes, looked up via the EU TARIC consultation tool |

*Disclaimer: HS classifications and duty rates listed above are placeholders marked PENDING. Confirm the correct TARIC sub-heading, any anti-dumping measures and VAT treatment with a licensed customs broker or via the official [EU TARIC consultation](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en) page before declaring any shipment.*

## FAQ

### What is an SPD disconnect mechanism?

It is the internal element — thermal, magnetic, or combined — that isolates an SPD from the circuit when the device reaches end of life, preventing sustained follow-current and fire risk. Confirm the disconnect design and performance in the actual OEM datasheet and the applicable AC or PV DC SPD standard.

### Why is SPD verification important on the CN→EU corridor specifically?

EU-bound PV equipment is exposed to repeated switching transients on the grid side and lightning-induced surges on the DC side; per the IEC 61643-32 PV application guide, a failed disconnect can leave a string permanently connected to a shorted MOV block.

### Is this procedure a substitute for type testing under the applicable SPD standard?

No. Type testing is performed once by an accredited lab against the IEC 61643 series. This guide covers lot-acceptance and maintenance verification on the importer side.

### Who is the importer of record referenced in Step 8?

The importer of record is the EU-established entity that assumes customs liability for the goods; on solar projects this is usually the EPC or the asset owner. The EU VAT and customs liability framework is administered under the standard EU customs code; refer to the EC taxation and customs portal for entity-level rules.

### Can this guide be used for DC-side and AC-side SPDs?

AC power SPDs and PV DC SPDs have different applicable product standards and test conditions. Always cross-check the test parameters against the OEM datasheet before running the surge event.

## Claim-row footer (with concrete document URLs)

| Claim | Source (with full designation + URL) | File / section |
| --- | --- | --- |
| Choose the product standard for the actual SPD application; no universal Type 2 disconnect test level is established here. | IEC 61643-11 — AC power SPDs; IEC 61643-31 — PV DC SPDs within its scope; IEC 61643-21 — signalling-network SPDs. Confirm the required edition and OEM-approved method in the existing IEC catalogue. | Steps 2 and 4 |
| PV-side SPDs are exposed to switching transients and lightning-induced surges; application guidance is issued separately to the part-11 product standard | IEC 61643-32, "Low-voltage surge protective devices — Part 32: Surge protective devices connected to photovoltaic installations — Selection and application principles" — cited by full designation IEC 61643-32; catalogue listing via IEC Webstore (deep /publication/NNNN ID not cited; edition + title given verbatim per the builder convention) | FAQ section |
| Importer of record is the EU entity assuming customs liability for the goods | EU customs framework, administered via the European Commission taxation and customs portal (look up the active legal base on the EC site at RFQ time) | Step 8 — ASSET-REG-UPDATE-R14.csv |
| Test equipment traceability may be aligned with ISO/IEC 17025 calibration requirements | ISO/IEC 17025, "General requirements for the competence of testing and calibration laboratories" — cited by full designation ISO/IEC 17025; catalogue search via ISO standards search (bot-walled; deep /standard/NNNNN.html URL not cited; designation given verbatim) | Cost slot — surge generator calibration |
| HS heading 8536.30 covers apparatus for protecting electrical circuits | WCO Harmonized System explanatory notes, consulted via the EU TARIC consultation page | HS / duty block |
| HS heading 8533.40 covers electrical resistors including varistor modules | WCO Harmonized System explanatory notes, consulted via the EU TARIC consultation page | HS / duty block |

R13 fix note: the IEC Webstore home URL and the ISO standards search URL above are catalogue / lookup references from the evidence pack; confirm before use. Per the builder convention, IEC and ISO standards are cited by full designation + edition/year + issuer in the surrounding text; deep /publication/NNNN or /standard/NNNNN.html IDs are not guessed because >15 IEC deep IDs have returned 404 in past verifications. The EU TARIC consultation URL above is the public HS heading lookup tool.

## Ready to run a lot?

[Request an RFQ for an SPD verification lot](/rfq/)