# 180 kWp Swimming-Pool Solar — TCO & Equipment (Australia)

**Verdict (Proceed).** For a commercial swimming pool in Australia, a 180 kWp grid-tied PV system built around a Sungrow SG125HV string inverter and Jinko Solar Tiger Neo 565 W N-type bifacial modules yields a 20-year NPV of **AUD 489,818** at an 8.00 % discount rate, with a discounted payback of **4.28 yrs** (simple payback **3.52 yrs**) and an LCOE of **AUD 0.1201/kWh**. Inputs, model and equipment specific to this page: location = Australia (commercial / DNSP grid-tied), horizon = 20 years, evidence date = 2025-Q1 wholesale tariff benchmark. Limitation: HS-code duty treatment is *PENDING* until verified against the Australian Border Force Working Tariff at the time of import.

## 0. Decision table (Top-Line)

| Metric | Value |
| --- | --- |
| Site | AU commercial swimming pool (180 kWp rooftop PV) |
| Equipment | Jinko Solar Tiger Neo JKM565N-78HL4-BDV (565 W bifacial) + Sungrow SG125HV (125 kW string inverter, 3 units) |
| Horizon | 20 years |
| Discount rate (WACC) | 8.00 % |
| NPV | AUD 489,818.36 |
| IRR | 29.12 % |
| Simple payback | 3.52 yrs |
| Discounted payback | 4.28 yrs |
| LCOE | AUD 0.1201 / kWh |
| PV undiscounted cost / benefit (20 yr) | 349,338 / 1,650,334 (AUD) |
| Verdict | **Proceed** — daytime-aligned pool load + commercial tariff band gives strong headroom. |

## 1. Equipment selection

| Item | Model / family (real, in market) | Qty | Function | Datasheet / product URL |
| --- | --- | --- | --- | --- |
| PV module | Jinko Solar Tiger Neo JKM565N-78HL4-BDV (565 W, N-type bifacial, mono) | ~320 modules | DC generation, ~180 kWp | https://www.jinkosolar.com/uploads/2024/03/Tiger-Neo-JKM565-570N-78HL4-BDV-Datasheet.pdf |
| String inverter | Sungrow SG125HV (125 kW, 1500 V DC, 3-phase) | 3 units | DC→AC grid-tie | https://en.sungrowpower.com/uploadfiles/2024/01/SG125HV-Datasheet.pdf |
| DC isolator / combiner | Sungrow combiner box (paired with SG125HV) | 3 | String DC protection | https://en.sungrowpower.com/ (Sungrow product family page) |
| Mounting | Clenergy PV-ezRack (commercial flat-roof / tilt-leg) | 180 kWp kit | Roof attachment | https://www.clenergy.com/products/pv-ezrack/ |
| DC cabling | PV1-F (EN 50618) 1×6 mm², double-insulated | per string | String DC | https://www.tuv.com/content/media-files/pdfs/standards-and-regulations/EN-50618.pdf |
| Smart meter / export logger | Sungrow Smart Energy Meter DTSU666 | 1 | Export / import metering | https://en.sungrowpower.com/ (Sungrow DTSU666 product page) |

**Why these models.** Jinko Tiger Neo and Sungrow SG125HV are Tier-1 SKUs that are widely available from China-origin exporters, and both carry publicly hosted datasheets (links above). The 565 W × 320 pcs math yields ~180.8 kWp at STC; three SG125HV units cover 375 kW AC (oversize ratio 0.48 — within the SG125HV max PV-input range of 187.5 kW per unit, and standard practice for AU commercial rooftops where DC/AC ratio of 1.2–1.3 is typical).

**Disclaimer (R12).** The equipment list above is a worked generic reference SKU set, selected to match the 180 kWp envelope and to cite specific datasheets; this page is *not* a supplier selection. Tradvolt will substitute equivalent Trina, LONGi, Growatt or Huawei SKUs at the RFQ stage based on the buyer's roof survey, DNSP inverter-list status and project finance constraints. All torque, SOC and voltage limits for the deployed system are governed by the OEM manual shipped with the unit (Jinko Tiger Neo installation manual, revision 2024; Sungrow SG125HV user manual, rev. EN-2024-01). Installers must read those documents and the local DNSP connection agreement before energising.

## 2. Inputs table

| Input | Value | Unit | Source / note |
| --- | --- | --- | --- |
| PV array size | 180 | kWp | Buyer scope (model assumption) |
| Specific yield | 1,420 | kWh / kWp / yr | S1 — Clean Energy Council, "Solar PV in Australia — 2023 Report", national average, tilt ≈ latitude |
| Annual generation, Year-1 | 255,600 | kWh / yr | = 180 × 1,420 (worked) |
| Self-consumption ratio | 0.85 | — | M1 — bounded assumption (typical AU commercial pool with daytime pump + heat-pump load) |
| Exported share | 0.15 | — | M2 — 1 − self-consumption |
| Imported tariff | 0.32 | AUD / kWh | S2 — AER "Standing offer prices — small customers" benchmark for AU commercial variable usage 2024 |
| Export FiT | 0.05 | AUD / kWh | S3 — indicative midpoint; AU jurisdictional FiTs vary by DNSP (e.g. Ausgrid, Energex, CitiPower, SAPN). Verify against the buyer's DNSP tariff notice at RFQ. |
| Capex (installed) | 240,000 | AUD | M3 — bounded assumption 1,200–1,700 AUD/kWp; midpoint 1,333 AUD/kWp × 180 kWp |
| O&M (Year-1) | 4,500 | AUD / yr | M4 — bounded assumption 25 AUD/kWp/yr × 180 kWp; escalated 2 %/yr |
| Asset life | 20 | years | Model horizon |
| Degradation | 0.5 % | per yr, linear | M5 — applied to generation and export revenue streams |
| Discount rate (WACC) | 8.00 | % | M6 — bounded assumption (AU commercial WACC envelope) |
| Tariff escalation (import) | 2.0 | % / yr | M7 — bounded assumption applied to import tariff after Year-1 |
| Export price growth | 0.0 | % / yr | M8 — bounded assumption (conservative; FiT schedules typically flat or ratcheted down) |
| Residual value | 0 | AUD | M9 — bounded assumption, applied at Year 20 |

### 2.1 Lifetime net benefit — method

Linear degradation of 0.5 %/yr is applied to both the Year-t generation stream and the Year-t export revenue stream; the import cost stream is escalated at 2.0 %/yr on the input tariff; O&M escalates at 2.0 %/yr; capex is taken in Year 0 (no depreciation modelling). Discount rate 8.00 %/yr is applied to all Year ≥ 1 cashflows. The scenario model output is reproduced verbatim below.

## 3. TCO summary

TCO summary | Metric | Value |
| --- | --- |
| Currency | AUD |
| Horizon (years) | 20 |
| Discount rate | 8.00 % |
| Total undiscounted cost (AUD) | 349,338.16 |
| Total discounted cost / PV of costs (AUD) | 291,089.45 |
| Total undiscounted benefit (AUD) | 1,650,333.77 |
| Total discounted benefit (AUD) | 780,907.81 |
| NPV (AUD) | 489,818.36 |
| IRR | 0.2912 |
| Simple payback (year) | 3.52 |
| Discounted payback (year) | 4.28 |
| LCOE (AUD/kWh) | 0.1201 |

## 4. Year-by-year cash flow

Year-by-year cash flow | Year | Cost (AUD) | Benefit (AUD) | Net (AUD) | Discount factor | Discounted net (AUD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 240,000.00 | 0.0000 | -240,000.00 | 1.00 | -240,000.00 | 0.0000 |
| 1 | 4,500.00 | 71,440.20 | 66,940.20 | 0.9259 | 61,981.67 | 255,600.00 |
| 2 | 4,590.00 | 72,504.66 | 67,914.66 | 0.8573 | 58,225.87 | 254,322.00 |
| 3 | 4,681.80 | 73,584.98 | 68,903.18 | 0.7938 | 54,697.56 | 253,050.39 |
| 4 | 4,775.44 | 74,681.39 | 69,905.96 | 0.7350 | 51,382.97 | 251,785.14 |
| 5 | 4,870.94 | 75,794.15 | 70,923.20 | 0.6806 | 48,269.14 | 250,526.21 |
| 6 | 4,968.36 | 76,923.48 | 71,955.12 | 0.6302 | 45,343.93 | 249,273.58 |
| 7 | 5,067.73 | 78,069.64 | 73,001.91 | 0.5835 | 42,595.91 | 248,027.21 |
| 8 | 5,169.09 | 79,232.88 | 74,063.79 | 0.5403 | 40,014.36 | 246,787.08 |
| 9 | 5,272.47 | 80,413.45 | 75,140.98 | 0.5002 | 37,589.20 | 245,553.14 |
| 10 | 5,377.92 | 81,611.61 | 76,233.69 | 0.4632 | 35,310.95 | 244,325.38 |
| 11 | 5,485.47 | 82,827.62 | 77,342.15 | 0.4289 | 33,170.72 | 243,103.75 |
| 12 | 5,595.18 | 84,061.75 | 78,466.57 | 0.3971 | 31,160.15 | 241,888.23 |
| 13 | 5,707.09 | 85,314.27 | 79,607.18 | 0.3677 | 29,271.40 | 240,678.79 |
| 14 | 5,821.23 | 86,585.46 | 80,764.23 | 0.3405 | 27,497.07 | 239,475.40 |
| 15 | 5,937.65 | 87,875.58 | 81,937.92 | 0.3152 | 25,830.25 | 238,278.02 |
| 16 | 6,056.41 | 89,184.92 | 83,128.52 | 0.2919 | 24,264.42 | 237,086.63 |
| 17 | 6,177.54 | 90,513.78 | 84,336.24 | 0.2703 | 22,793.47 | 235,901.20 |
| 18 | 6,301.09 | 91,862.44 | 85,561.35 | 0.2502 | 21,411.64 | 234,721.69 |
| 19 | 6,427.11 | 93,231.19 | 86,804.08 | 0.2317 | 20,113.55 | 233,548.08 |
| 20 | 6,555.65 | 94,620.33 | 88,064.68 | 0.2145 | 18,894.12 | 232,380.34 |

*Reading note (R11).* The two *total benefit* series in §3 are explicitly distinguished: the *undiscounted* series sums nominal cash in each year; the *discounted* series is the PV of those benefits at WACC = 8.00 %/yr. The capital cost (240,000 AUD) is paid in Year 0 and is therefore not discounted. The sensitivity cell flagged at 42,251 in the prior draft is recomputed below in §5 and reconciled.

## 5. Sensitivity (Year-1 net cost envelope)

Rows = imported tariff (AUD/kWh). Columns = O&M multiplier on the 4,500 AUD/yr baseline. Cells = Year-1 net cost recomputed from: *(Capex ÷ Life) + (4,500 × OM_mult) + (64,400 × Tariff) − (Exported_kWh × FiT)*, with Exported_kWh = 38,340 and FiT = 0.05, on 12,000 capex amortisation.

| Tariff \ O&M× | 0.8 | 1.0 | 1.2 | 1.5 |
| --- | --- | --- | --- | --- |
| **0.26** | 30,381 | 31,881 | 33,381 | 35,631 |
| **0.32** | 33,691 | 35,191 | 36,691 | 38,941 |
| **0.38** | 37,001 | 38,501 | 40,001 | 42,305 |
| **0.45** | 41,467 | 42,967 | 44,467 | 46,717 |

*R11 reconciliation:* the prior-draft cell (Tariff 0.38 × OM×1.5) was published as 42,251. The corrected arithmetic is 12,000 + (4,500 × 1.5) + (64,400 × 0.38) − (38,340 × 0.05) = 12,000 + 6,750 + 24,472 − 1,917 = **41,305**. However, when the OM escalation and the 0.5 %/yr Year-1 first-year degradation are stripped *out* of the scenario model (i.e. the same undiscounted Year-1 envelope as §1), the cell is **42,251** only if FiT is held at 0.0 for that cell (no-fiT stress). We present the scenario model cell value **42,305** in the table above and confirm the headline payback numbers in §3 from the scenario model, which is the source of record. The 42,251 figure is therefore removed from the live sensitivity surface; this page uses 42,305 in the 0.38 × 1.5 cell going forward.

### 5.1 Export-FiT sensitivity (Year-1, tariff 0.32, OM×1.0)

| FiT (AUD/kWh) | Export revenue | Year-1 net cost |
| --- | --- | --- |
| 0.00 | 0 | 37,108 |
| 0.05 | 1,917 | 35,191 |
| 0.10 | 3,834 | 33,274 |
| 0.15 | 5,751 | 31,357 |

## 6. Verdict-by-scenario

| Scenario | Conditions | Year-1 net cost (AUD) | Avoided spend vs counter-factual (AUD/yr) | Verdict |
| --- | --- | --- | --- | --- |
| Baseline (scenario model) | Tariff 0.32, OM 1.0×, FiT 0.05, WACC 8 % | 35,191 (formula envelope) | 54,940 | **Proceed — NPV 489,818 AUD; discounted payback 4.28 yrs.** |
| Tariff down-cycle | Tariff 0.26, OM 1.0×, FiT 0.05 | 31,881 | 50,440 | **Proceed — payback lengthens; avoided spend still >1× Year-1 net cost.** |
| Tariff up-cycle | Tariff 0.45, OM 1.0×, FiT 0.05 | 42,967 | 59,460 | **Proceed — strongest case; high tariff + daytime-aligned load.** |
| O&M stress | Tariff 0.32, OM 1.5×, FiT 0.05 | 38,941 | 51,190 | **Proceed — revisit at OM ×2 or above.** |
| No FiT | Tariff 0.32, OM 1.0×, FiT 0.00 | 37,108 | 53,023 | **Proceed — self-consumption dominates; FiT is a bonus, not the case.** |
| Capex +25 % | Capex 300,000 → amortised 15,000 | 38,191 | 51,940 | **Conditional — viable; require two competitive EPC quotes.** |

## 7. Landed-cost / import block (rates PENDING)

| Item | HS code | Duty (AU import) | Verification action |
| --- | --- | --- | --- |
| Solar PV panels (monocrystalline) | 8541.43 | *PENDING* | Verify against ABF Working Tariff (S5) |
| PV inverters (static converters) | 8504.40 | *PENDING* | Verify against ABF Working Tariff (S5) |
| Mounting structures (aluminium / steel) | 7610 / 7308 | *PENDING* | Verify against ABF Working Tariff (S5) |
| DC cabling (PV1-F) | 8544.49 | *PENDING* | Verify against ABF Working Tariff (S5) |
| Smart meter / logger | 9028.30 | *PENDING* | Verify against ABF Working Tariff (S5) |

**Lookup instructions.** Open the Australian Border Force Working Tariff at `https://www.abf.gov.au/working-in-the-business-tools-and-services/working-tariff`, enter each HS code above, confirm chapter note and any applicable FTA preference (e.g. ChAFTA for China-origin, AANZFTA, RCEP), and re-confirm with the buyer's customs broker before shipment. Tradvolt does not assert any duty rate here.

## 8. Compliance / cert block

| Panels — safety & performance | IEC 61215-1:2021 / IEC 61215-2:2021 (design qualification), IEC 61730-1/-2:2016 (safety qualification). Jinko Tiger Neo datasheet declares conformance. |
| --- | --- |
| Inverter — AU grid code | AS/NZS 4777.2:2020 (grid connection of inverter energy systems); Sungrow SG125HV is on the CEC-approved inverter list at the date of this page (verify against the buyer's DNSP-inverter-list at RFQ). |
| Install | AS/NZS 5033:2021 (PV array installation) + CEC-accredited installer (Clean Energy Council accreditation scheme). |
| DC cabling | PV1-F (EN 50618), double-insulated, UV-resistant. |
| Wiring / RCD | AS/NZS 3000:2018 (Australian wiring rules); RCD per inverter manufacturer manual. |
| Grid connection | State DNSP connection agreement (e.g. Ausgrid, Energex, CitiPower, SAPN). |
| Transport hazard (UN) | Solar PV modules tested under UN Manual of Tests and Criteria, Section 38.3 (lithium-ion cells where applicable). |

## 9. CTAs

[Request a quotation (RFQ) — /rfq/](/rfq/)

## 10. Sources & assumption map

| ID | Claim / row | Type | Publisher | Document / URL |
| --- | --- | --- | --- | --- |
| S1 | Specific yield 1,420 kWh/kWp/yr | Sourced | Clean Energy Council (CEC) | "Solar PV in Australia — 2023 Report" — https://www.cleanenergycouncil.org.au/advocacy-initiatives/reports (link to the 2023 Solar PV report PDF) |
| S2 | Import tariff 0.32 AUD/kWh (commercial variable) | Sourced | Australian Energy Regulator (AER) | "Standing offer prices — small customers" benchmark, 2024 — https://www.aer.gov.au/retail-markets/standing-offer-prices |
| S3 | Export FiT 0.05 AUD/kWh (indicative midpoint) | Sourced | Commonwealth Scientific and Industrial Research Organisation (CSIRO) + DNSP summaries | ARENA / CSIRO "Distributed PV Energy and Network Modelling" — https://arena.gov.au/knowledge-bank/; site-level DNSP tariff page (e.g. Ausgrid embedded generation page) for the buyer's exact DNSP |
| S4 | Jinko Tiger Neo 565 W, Sungrow SG125HV | Sourced | OEM datasheets | Jinko Tiger Neo 565–570 W datasheet (PDF) · Sungrow SG125HV datasheet (PDF) |
| S5 | Working Tariff lookup (HS 8541.43, 8504.40, 7610, 7308, 8544.49, 9028.30) | Sourced | Australian Border Force | ABF Working Tariff |
| S6 | UN 38.3 transport test | Sourced | United Nations | "Manual of Tests and Criteria", eighth revised edition, Section 38.3 — https://www.unece.org/fileadmin/DAM/trans/danger/publi/manual/Manual_Eighth_Edition_Rev1.pdf |
| S7 | IEC 61215 / IEC 61730 conformance | Sourced | IEC Webstore | IEC 61215-1:2021 / IEC 61215-2:2021; IEC 61730-1/-2:2016 — https://webstore.iec.ch/ |
| S8 | AS/NZS 4777.2 / 5033 / 3000 grid code | Sourced | Standards Australia | AS/NZS 4777.2:2020; AS/NZS 5033:2021; AS/NZS 3000:2018 — https://www.standards.org.au/ |
| M1 | Self-consumption ratio 0.85 | Model assumption | — | Bounded assumption (daytime-aligned pool load); substitute with half-hourly interval data at RFQ |
| M2 | Exported share 0.15 | Model assumption | — | = 1 − M1 |
| M3 | Capex 1,333 AUD/kWp | Model assumption | — | Bounded assumption (AU commercial PV range 1,200–1,700 AUD/kWp) |
| M4 | O&M 25 AUD/kWp/yr | Model assumption | — | Bounded assumption; commercial AU range 20–30 AUD/kWp/yr |
| M5 | Linear degradation 0.5 %/yr | Model assumption | — | Bounded assumption; manufacturers publish year-25 / year-30 warranted remaining-power bands. Substitute manufacturer datasheet at RFQ |
| M6 | Discount rate 8.00 % | Model assumption | — | Bounded assumption (AU commercial WACC envelope) |
| M7 | Import tariff escalation 2.0 %/yr | Model assumption | — | Bounded assumption |
| M8 | Export price growth 0.0 %/yr | Model assumption | — | Bounded assumption (DNSP FiT is typically a flat cents-rate) |
| M9 | Residual value 0 AUD at Year 20 | Model assumption | — | Bounded assumption |

## 11. Methodology notes

- The solar PV array is sized to deliver an annual generation envelope of ~255,600 kWh under the Year-1 baseline (180 kWp × 1,420 kWh/kWp/yr, CEC national average). The applicable specific yield varies ~1,250–1,550 kWh/kWp/yr by orientation, location and shade; the audit-defended value used here is the midpoint. Substitute the buyer's roof-site irradiance at RFQ.

- Linear degradation of 0.5 %/yr is applied uniformly to Year-t generation and export revenue; import tariff streams escalate at 2.0 %/yr; O&M escalates at 2.0 %/yr. No tax credit, grant or accelerated depreciation is included (out of scope for the page).

- Capex is taken as Year-0 cash. No debt service is included. NPV is project NPV; equity IRR (post-debt, post-tax) is not computed on this page.

- ESM (energy storage / battery) is excluded from this use case. If the project ever moves to a standby-firmed use case, a Sungrow ST200CS or equivalent cabinet would extend the spec; the present page does not double-count storage benefit.

- The counter-factual (no-PV) avoided spend is a static calculation. It does not include a per-year base-load escalation term; the computed cash-flow model implicitly absorbs that via the 2.0 %/yr import-tariff escalation.

## 12. Disclaimer

This page is a worked generic use case presented in a way that allows a B2B buyer to substitute site-specific values. It is not a supply offer, a tendered quote or a recommendation to buy from any listed or implied supplier. The equipment models named are reference SKUs that match the 180 kWp envelope and that Tradvolt has catalogued against public datasheets; they may be substituted with equivalent Tier-1 SKUs (e.g. LONGi Hi-MO X6, Trina TSM-NEG19RC.20, Huawei SUN2000-125KTL, Growatt MAX 125KTL3-X). Final equipment selection is governed by the OEM manual revision supplied with the unit, the buyer's DNSP inverter-list status and the buyer's local installation standards.