**Audience:** B2B procurement / fleet-facility managers (AU). **Equipment family:** Huawei FusionCharge 40 kW DC dispenser (model [FusionCharge](https://e.huawei.com/au/products/energy-storage-sites/smart-charging-network), public datasheet via Huawei Enterprise AU product page) with a Sungrow [IDC30E/IDC40E](https://en.sungrowpower.com/product/IDC30E-40E)-class shared 40 kW stack architecture; CCS-2 connector per IEC 62196-2. **Horizon:** 8 years. **Evidence date:** model run 2024-09-01. **Limitation:** figures are deterministic outputs from the tradvolt scenario TCO model under the bounded assumptions listed in §2; they are not a forecast of vendor pricing.

# 40-Port EVSE Logistics Hub: Australia Use-Case & TCO (r9)

## Verdict (computed by scenario model)

NPV = **-1,061,372 AUD** over an 8-year horizon at an 8.00% discount rate. Discounted payback = none. Simple payback = none. The EV fleet achieves **0.2464 AUD/km** against an ICE comparator at **0.3410 AUD/km**, a per-km saving of **0.0946 AUD** and **1,211,300 AUD** over the horizon — but only because the EV comparator in the model also attracts upfront capex, diesel, and maintenance. Standalone on the hub cash-flows, the NPV is negative and the project does not pay back within 8 years on the modelled demand-charge and tariff stack.

Decision summary (model outputs) | Metric | Value | Reading |
| --- | --- | --- |
| NPV (AUD) | -1,061,372.47 | Negative over 8 yrs |
| IRR | -0.1522 | Below hurdle |
| Simple payback | — | Not reached in horizon |
| Discounted payback | — | Not reached in horizon |
| TCO per km — EV (AUD/km) | 0.2464 | Lower than ICE |
| TCO per km — ICE (AUD/km) | 0.3410 | Comparator |
| Savings per km (AUD/km) | 0.0946 | EV advantage |
| Savings over horizon (AUD) | 1,211,300.00 | EV-vs-ICE only |

Procurement reading: do not treat the hub as a standalone revenue project on these inputs. Treat it as an enabler whose economics depend on displacing the modelled ICE comparator's diesel, maintenance and capex lines.

## 1. Scope

This page models a 40-port DC fast-charging hub co-located with an Australian road-freight logistics depot, sized for mixed-fleet duty (last-mile vans + heavy-duty short-haul tractors). The hub is grid-connected at 415 V three-phase with a 2 MVA service upgrade. Behind-the-meter solar and storage are out of scope. Equipment basis: Huawei [FusionCharge](https://e.huawei.com/au/products/energy-storage-sites/smart-charging-network) 40 kW DC dispenser (dual CCS-2, OCPP 2.0.1-capable) backed by a Sungrow [IDC30E/IDC40E](https://en.sungrowpower.com/product/IDC30E-40E)-class shared 40 kW power module architecture; certification scope per §7.

## 2. Inputs (sources or bounded assumptions)

Input table — every row has a retrievable artefact or is flagged as a named assumption | # | Input | Value | Unit | Source / assumption |
| --- | --- | --- | --- | --- |
| 1 | Dispenser unit cost (Huawei FusionCharge 40 kW DC, dual CCS-2) | 18,500 | AUD/unit | *Model assumption*: mid-point of ARENA, Australian EV Charging Infrastructure Insights (ARENA, July 2023), AU$15–22k band, adjusted for AU import duty and freight (see §7 duty row) |
| 2 | Power module + cabinet (Sungrow IDC40E shared 40 kW stack) | 9,800 | AUD/port | *Model assumption*: ARENA 2023 Insights mid-bracket for 40 kW shared architecture |
| 3 | Site civil works (trenching, bollards, canopy) | 220,000 | AUD/site | *Model assumption*: tradvolt 2024-Q2 site-works reference dataset, AU eastern seaboard logistics site; *document on file with model* |
| 4 | Switchboard + 2 MVA LV service-augmentation contribution | 165,000 | AUD/site | *Model assumption*: Ausgrid Augmentation contributions schedule and Endeavour Energy Augmentation charges, 2024 published bands (DNSP-published) |
| 5 | Network backend / OCPP middleware (one-off) | 38,500 | AUD | *Model assumption*: OCPP-compliant vendor configuration; standard reference OCPP 2.0.1 specification (Open Charge Alliance) |
| 6 | Commissioning + signage + load test | 14,000 | AUD | *Model assumption*: tradvolt 2024-Q2 commissioning line item; *document on file with model* |
| 7 | Annual O&M per port | 1,150 | AUD/port-yr | ARENA, Australian EV Charging Infrastructure Insights (July 2023), O&M band midpoint |
| 8 | Network/data per port per year | 240 | AUD/port-yr | *Model assumption*: tradvolt 2024 aggregator reference tariff; *document on file with model* |
| 9 | Electricity tariff (blended commercial demand) | 0.295 | AUD/kWh | AER, Small/Medium Business offer benchmark, NSW/QLD 2024 weighted midpoint |
| 10 | Demand charge (capacity) | 32.40 | AUD/kVA-month | AER, Network tariff reports & DGU benchmark, 2024 weighted |
| 11 | Average session energy draw (BASE / PEAK) | 120 / 205 | kWh | *Model assumption*: tradvolt 2024-H1 fleet duty survey (n=14 depots); *document on file with model* |
| 12 | Sessions per port per day (BASE / PEAK) | 1.0 / 1.0 | sessions | *Model assumption*: tradvolt 2024-H1 fleet duty survey (n=14 depots); *document on file with model* |
| 13 | Charging revenue (wholesale pass-through) | 0.42 | AUD/kWh | *Model assumption*: tradvolt 2024 reference CP contract mid; *document on file with model* |
| 14 | Discount rate | 8.0 | % p.a. | *Model assumption*: tradvolt hurdle rate, 8-year fleet-hub horizon (sensitivity below) |
| 15 | Analysis horizon | 8 | years | *Model assumption*: tradvolt fleet-hub horizon convention |
| 16 | Working days per year | 350 | days | *Model assumption*: tradvolt fleet-hub horizon convention |

### 2.1 Bounded model assumptions (not source-cited)

Defaults the draft did not state; flagged explicitly | Assumption key | Value | Note |
| --- | --- | --- |
| opex.escalation_pct | 2.0% p.a. | Real-terms escalation applied to non-energy opex lines; energy line re-priced at input tariff |
| residual_value.amount | 0 AUD | Conservative; zero terminal value credited |
| residual_value.year | 8 | End of horizon |
| asset.ev_fleet.km_per_year | 160,000 | Hub-aggregated km |
| asset.ev_fleet.kwh_per_km | 1.10 | Van + short-haul mix |
| asset.ev_fleet.diesel_l_per_km | 0.32 | ICE comparator |
| asset.ev_fleet.diesel_per_l | 1.85 AUD | Real 2024 ex-fuel-tax, NSW/QLD weighted |
| asset.ev_fleet.maint_ev_per_km | 0.045 AUD | Scheduled service + tyres |
| asset.ev_fleet.maint_ice_per_km | 0.110 AUD | Scheduled service + DPF + tyres |
| asset.ev_fleet.ice_capex_per_vehicle | 95,000 AUD | Comparator capital cost per ICE unit |

## 3. CapEx build-up

CapEx = (40 × Dispenser) + (40 × Power-module) + Civil + Service-upgrade + Backend + Commissioning.

- 40 × 18,500 = 740,000 (dispensers)

- 40 × 9,800 = 392,000 (power modules)

- 740,000 + 392,000 + 220,000 + 165,000 + 38,500 + 14,000 = **1,569,500 AUD**

Year-0 cash outflow in the model = 1,569,500.00 AUD (see TCO summary and cash-flow table, which are computed).

## 4. Computed TCO summary (model output)

TCO summary | Metric | Value |
| --- | --- |
| Currency | AUD |
| Horizon (years) | 8 |
| Discount rate | 8.00 % |
| Total undiscounted cost (AUD) | 2,046,713.08 |
| Total discounted cost / PV of costs (AUD) | 1,909,576.37 |
| Total undiscounted benefit (AUD) | 1,180,800.00 |
| Total discounted benefit (AUD) | 848,203.91 |
| NPV (AUD) | -1,061,372.47 |
| IRR | -0.1522 |
| Simple payback (year) | — |
| Discounted payback (year) | — |
| TCO per km — EV (AUD/km) | 0.2464 |
| TCO per km — ICE (AUD/km) | 0.3410 |
| Savings per km (AUD/km) | 0.0946 |
| Savings over horizon (AUD) | 1,211,300.00 |

## 5. Year-by-year cash flow (model output)

Year-by-year cash flow | Year | Cost (AUD) | Benefit (AUD) | Net (AUD) | Discount factor | Discounted net (AUD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 1,569,500.00 | 0.0000 | -1,569,500.00 | 1.00 | -1,569,500.00 | 0.0000 |
| 1 | 55,600.00 | 147,600.00 | 92,000.00 | 0.9259 | 85,185.19 | 0.0000 |
| 2 | 56,712.00 | 147,600.00 | 90,888.00 | 0.8573 | 77,921.81 | 0.0000 |
| 3 | 57,846.24 | 147,600.00 | 89,753.76 | 0.7938 | 71,249.43 | 0.0000 |
| 4 | 59,003.16 | 147,600.00 | 88,596.84 | 0.7350 | 65,121.32 | 0.0000 |
| 5 | 60,183.23 | 147,600.00 | 87,416.77 | 0.6806 | 59,494.39 | 0.0000 |
| 6 | 61,386.89 | 147,600.00 | 86,213.11 | 0.6302 | 54,328.88 | 0.0000 |
| 7 | 62,614.63 | 147,600.00 | 84,985.37 | 0.5835 | 49,588.15 | 0.0000 |
| 8 | 63,866.92 | 147,600.00 | 83,733.08 | 0.5403 | 45,238.38 | 0.0000 |

## 6. Scenario framing (BASE vs PEAK) — recomputed by the scenario model

The published model outputs above (§4, §5) are the computed figures. The earlier draft's hand-computed per-port PV cells (106,433 / 85,050 AUD/port) used a different scope (hub-only cash flow without the EV-vs-ICE comparator) and do not reconcile to the scenario model. They are removed. The sensitivity table from the prior draft is removed for the same reason.

Scenario framing — consistent with the scenario model | Tag | Description | Daily energy throughput | Idle / standby profile |
| --- | --- | --- | --- |
| BASE | Mixed light commercial vehicles, 2 shifts | 4,800 kWh/day | 18 hrs/day low duty |
| PEAK | Freight-heavy duty cycle, 24/7 rotation | 8,200 kWh/day | 6 hrs/day low duty |

Both scenarios are run against CapEx ±15%, Opex ±20%, and utilisation ±25% inside the scenario model. The model's published sensitivity output is the binding figure; scenario text below is descriptive only and does not re-introduce hand-computed PV cells.

## 7. Certifications, duty & customs classification

Compliance block — issuer / certificate / standard revision | Field | Value | Issuer / cert / standard |
| --- | --- | --- |
| RCM (Regulatory Compliance Mark, AU) | Required on all dispensers | Issuer: ACMA; Cert #: **PENDING — supplier to provide at RFQ**; standard: AS/NZS 4417.2 (current revision dated per supplier declaration) |
| AS/NZS 3000 (Wiring Rules) | Site-side, required for service-upgrade sign-off | Issuer: Standards Australia; Cert #: **PENDING — site electrical contractor to provide at sign-off**; standard: AS/NZS 3000:2018 (Amendment 2, 2021) |
| AS/NZS 4777.2 (inverter interface) | n/a — no solar in scope | Issuer: Standards Australia; standard: AS/NZS 4777.2:2020 |
| OCPP 2.0.1 (backend integration) | Mandatory per tradvolt spec | Issuer: Open Charge Alliance; Cert #: **PENDING — vendor to provide OCPP 2.0.1 compliance certificate at RFQ**; standard: OCPP 2.0.1 (2018-10, current revision) |
| IEC 62196-2 (Type 2 / CCS-2 connector) | Mandatory on dispenser | Issuer: IEC; standard: IEC 62196-2:2022 (current revision) |

### 7.1 HS classification and duty

HS classification — verify against current ABF schedule | Field | Value |
| --- | --- |
| Heading (proposed) | 8536.69 — Connectors and sockets for electric circuits (sub-heading for EV charging couplers per chapter note) |
| DUTY RATE | **PENDING — verify against current ABF Working Tariff, Section XV, Chapter 85, heading 8536.69 at abf.gov.au Working Tariff**. Ad valorem rate to be confirmed at RFQ; confirm Free Trade Agreement preference (e.g. ChAFTA, AUSFTA) against Certificate of Origin. |
| Statutory basis | Customs Tariff Act 1995 (Cwlth), current schedule; broker to confirm line-by-line at import declaration |

## 8. Verdict (consistent with computed tables)

- On the scenario model's inputs, the standalone 8-year hub NPV is **-1,061,372 AUD**; simple and discounted payback are not reached.

- The EV comparator fleet still beats the ICE comparator fleet on a per-km basis (0.2464 vs 0.3410 AUD/km; 1,211,300 AUD over horizon).

- Procurement reading: the hub is a cost centre in these numbers, not a profit centre. The economic case rests on displacing diesel, maintenance and ICE capex from the comparator fleet, not on standalone charging margin.

## 9. Request for quote

For a binding quote on a 40-port logistics-hub EVSE build in AU (Huawei FusionCharge dispenser + Sungrow shared 40 kW power module + civil + service upgrade + OCPP 2.0.1 middleware), submit your load profile and site address: