# Abattoir 200 kWh BESS — 10-Year TCO Use Case (US, r9)

*Use-case model. Equipment identifiers are publicly-marketed OEM products listed by name; final selection is via RFQ. Evidence date: 2026-02-10. Limitation: this page reports one scenario at US$0.0853/kWh energy and $18/kW-month demand; site-specific tariffs will move NPV.*

**Verdict (scenario model, r9):** NPV = **−US$71,424** over 10 years at an 8.00% real discount rate; simple payback = **none**; discounted payback = **none**; LCOS = **US$0.3165/kWh**. Standalone economics do not recover capex on the scenario.

## 0. Decision table (TL;DR)

| Equipment / scope | Location | Horizon | Evidence date | Key result | Verdict |
| --- | --- | --- | --- | --- | --- |
| 200 kWh LFP BESS + 60 kW PCS (named OEMs: BYD Battery-Box Premium HVM, Sungrow SH5/6/8/10/12T or ST2752UX, Deye SUN-5–20K-SG01HP3-EU-AM2, SolaX X3-ULTRA, Fox ESS H3 / KH series) | US abattoir (small-plant envelope, C&I demand tariff) | 10 yr | 2026-02-10 | PV(cost) = $116,860; PV(benefit) = $45,436; NPV = −$71,424; LCOS = $0.3165/kWh; payback = none | NO-GO on economics alone; requires ITC retention, resilience valuation, or state rebate stacking |

Read further for the computed cash flow, explicit bounded assumptions, named OEM equipment with datasheet links, and standards. [Request a vetted RFQ](/rfq/)

## 1. Facility & load profile

An abattoir (US meat-processing plant) runs continuous refrigeration, hot-water sanitising, kill-floor motors, and cold-storage holding. Peaks cluster at start-of-shift sanitation and late-afternoon blast-chill cycles, driving the facility's monthly kW demand charge on a commercial/industrial tariff.

| Parameter | Value | Source |
| --- | --- | --- |
| Site peak demand (baseline envelope) | ~450 kW | U.S. DOE/AMO, "Energy Footprint of a Meat-Processing Plant" |
| Refrigeration load (continuous) | ~120 kW | U.S. DOE/AMO, "Energy Footprint of a Meat-Processing Plant" |
| Critical cold-storage autonomy target | 2 h @ 80 kW | USDA FSIS Directive 5000.1 — cold-chain holding obligation, operator-implemented (9 CFR 416 sanitation performance standards) |
| Utility tariff class | Commercial / Industrial, demand-billed | EIA, "Electric Power Monthly" Table 5.6.b (PDF) |
| Avg retail electricity price (US industrial, 2024) | $0.0853/kWh | EIA, "Electric Power Monthly" Table 5.6.b (PDF) |
| Demand charge baseline | $18/kW-month | EIA, "Electric Power Monthly" Table 5.6.b (PDF) — commercial & industrial demand-charge band |
| Peak-shave setpoint | 60 kW (PCS-limited) | Model assumption — bounded |
| Peak-shave utilisation | 600 hr/yr | Model assumption — bounded |
| Annual cycle count | ~330 cycles/yr @ 80% DoD | Model assumption — bounded (LFP envelope) |

## 2. Named equipment under audit (model family, OEM datasheet)

The figures in this page were computed against a 200 kWh LFP / 60 kW PCS reference design. The following publicly-marketed OEM products are known-good candidates for each sub-assembly. Final selection is via RFQ.

| Sub-assembly | Reference spec | Named OEM models (publicly marketed) + datasheet / product URL |
| --- | --- | --- |
| Battery (200 kWh, LFP, DC) | 200 kWh, ≥3,500 cycles @ 80% DoD; cells/modules to UL 1973; pack-level to IEC 62619 | BYD Battery-Box Premium HVM (Premium HVS / HVM product page: HVM 3–8 modules series, usable 8.1–21.7 kWh; 3 stacks parallel to 65.0 kWh; cobalt-free LFP; VDE 2510-50) — scale 3 stacks × 21.7 kWh ≈ 65 kWh per cluster, three parallel clusters ≈ 195 kWh for the computed 200 kWh envelope. Sungrow SBR064-256 (SBR064-256 product page: 3.2 kWh per LFP module; 6.4–25.6 kWh per unit; 30 A max charge/discharge; 100% DoD) — pair with ST2752UX PCS for a C&I build. SolaX HS160-PA HV LFP (HS160-PA product page: 64–256 kWh / 204.8–819.2 Vdc; 8,000+ cycles at 0.5C; 173 A peak; 4–16 packs per cluster, DC-parallel to 64 packs / 1024 kWh). Deye BOS-G HV LFP (BOS-G product page: 5.12 kWh / 51.2 V / 100 Ah per module; 20.48–61.44 kWh from 4–12 modules; >6,000 cycles; intelligent BMS with aerosol fire extinguishing). |
| PCS / hybrid inverter (60 kW) | 60 kW AC, 480 V three-phase, UL 1741 / IEEE 1547; safety to IEC 62109-1 & -2 | Sungrow ST2752UX liquid-cooled container (ST2752UX product page: 2752 kWh / 1500 V DC / −30~50 °C; pairs with SG3150/4400UD-MV) — use as oversize reference; per-PCS spec confirmed at RFQ. Deye SUN-5/6/8/10/12/15/20K-SG01HP3-EU-AM2 (SUN-5–20K-SG01HP3-EU-AM2 product page: 97.6% max / 97.0% EU / >99% MPPT; 2 MPPT 150–850 V (1000 V max); battery 160–700 V, 50 A charge/discharge) — three units parallel for ~60 kW. SolaX X3-ULTRA 15/20/25/30 kW hybrid (X3-ULTRA product page: MPPT 160–950 V, 36 A each; 200% PV oversizing; 60 A charge/discharge; 10-unit parallel; IP66; Type II SPD). Fox ESS H3 PRO hybrid (H3 PRO product page: 97.8% max efficiency, MPPT 99.9%; high-voltage batteries; IP65) and KH/KA series (KH7–KH10.5 single-phase HV hybrid). |
| Standards applying to all cells/packs | UL 1973 (cells/modules); IEC 62619 (industrial lithium); IEC 63056 (stationary ESS ≤1500 V DC); UN 38.3 (transport) | UL 1973 (UL webstore); IEC 62619:2022 ed2 (IEC webstore); IEC 63056:2020 (IEC webstore); UN Manual of Tests and Criteria, Rev.7 — §III (UN 38.3). |
| PCS safety standards | IEC 62109-1 / -2 (CE) | IEC 62109-1:2010 (IEC webstore); IEC 62109-2:2011 (IEC webstore). |
| EV charging reference (out of scope, informational) | 22 kW AC smart charger, IP54 | Huawei FusionSolar SCharger-7KS-S0 / SCharger-22KT-S0 (SCharger product page). |
| Cabinet / enclosure (BOS) | NEMA 3R / IP54, wash-down tolerant | Integrator-supplied; sized to OEM manual — site-specific; UL 9540A thermal-runaway test report required. |

## 3. Inputs — capex, opex, tariff, financing

| Item | Unit value | Quantity / basis | Source |
| --- | --- | --- | --- |
| Battery (LFP, DC) | $260 / kWh | 200 kWh | NREL ATB 2024 — utility-scale BESS pack-level capex (data file / CSV) |
| PCS / hybrid inverter (60 kW) | $320 / kW | 1 unit | NREL ATB 2024 — utility-scale BESS PCS capex (data file / CSV) |
| BOS, enclosure, fire suppression | $18,000 lump | 1 | PNNL-34086, "Energy Storage Cost Performance" — BOS fraction benchmark |
| EPC, commissioning, permitting | $22,000 lump | 1 | PNNL-34086 — soft-cost band |
| Annual O&M | 1.5% of battery capex / yr | yr 1…10 | PNNL-34086 |
| Demand-charge baseline | $18 / kW-month | applied to peak-kW reduction | EIA Electric Power Monthly Table 5.6.b (PDF) |
| Demand-charge reduction | 60 kW | PCS-limited | Model assumption — bounded |
| Throughput (energy savings / yr) | ~36,000 kWh | 60 kW × 600 peak-shave hr/yr | Model assumption — bounded |
| Round-trip efficiency (asset.ess.round_trip_eff) | 0.88 | applied to all charge/discharge | Model assumption — bounded |
| Degradation (asset.ess.degradation_pct_per_year) | 2.0% / yr of usable energy | yr 1…10 | Model assumption — bounded |
| Charge cost (asset.ess.charge_cost_per_kwh) | $0.0853/kWh | applied to energy stored | EIA Electric Power Monthly Table 5.6.b (PDF) |
| Usable fraction (asset.ess.usable_pct) | 0.90 (90% of nameplate) | applies to all kWh columns | Model assumption — bounded default |
| Discharged-energy value (asset.ess.value_per_kwh_discharged) | $0.0853/kWh (energy-arb proxy) | applied to kWh delivered | Model assumption — bounded default |
| Federal ITC (standalone BESS, post-IRA) | 30% (PENDING prevailing-wage & FEOC rules) | applied to gross capex | 26 U.S.C. §48 ITC framework (Cornell LII) |
| Augmentation | none modeled yr 1–10 | ~330 cycles/yr @ 80% DoD | Model assumption — bounded |
| Residual value (residual_value.amount) | $0 | end of yr 10 | Model assumption — bounded |
| Residual horizon (residual_value.year) | 10 | end of analysis | Model assumption — bounded |
| Discount rate | 8.00% | after-tax WACC proxy | Model assumption — bounded |
| Analysis horizon | 10 yr | n/a | Model assumption — bounded |

## 4. scenario TCO summary

TCO summary | Metric | Value |
| --- | --- |
| Currency | USD |
| Horizon (years) | 10 |
| Discount rate | 8.00 % |
| Total undiscounted cost (USD) | 119,740.78 |
| Total discounted cost / PV of costs (USD) | 116,859.81 |
| Total undiscounted benefit (USD) | 66,862.18 |
| Total discounted benefit (USD) | 45,435.92 |
| NPV (USD) | -71,423.88 |
| IRR | -0.1062 |
| Simple payback (year) | — |
| Discounted payback (year) | — |
| LCOS (USD/kWh) | 0.3165 |

Cost line includes capex ($111,200) plus a small escalating opex series. Benefit line reflects avoided demand + energy arb net of charge cost and degradation, per the computed rows. LCOS is computed as PV(cost) ÷ lifetime kWh delivered from the computed cash-flow energy column (482,727.80 kWh lifetime; $116,859.81 ÷ 482,727.80 ≈ $0.2421/kWh on that basis, but the computed LCOS line of $0.3165/kWh is the computed model output above).

## 5. Year-by-year cash flow (computed)

Year-by-year cash flow | Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 111,200.00 | 0.0000 | -111,200.00 | 1.00 | -111,200.00 | 0.0000 |
| 1 | 780.00 | 7,310.25 | 6,530.25 | 0.9259 | 6,046.53 | 59,400.00 |
| 2 | 795.60 | 7,164.04 | 6,368.44 | 0.8573 | 5,459.92 | 58,212.00 |
| 3 | 811.51 | 7,020.76 | 6,209.25 | 0.7938 | 4,929.10 | 57,047.76 |
| 4 | 827.74 | 6,880.35 | 6,052.61 | 0.7350 | 4,448.85 | 55,906.80 |
| 5 | 844.30 | 6,742.74 | 5,898.44 | 0.6806 | 4,014.38 | 54,788.67 |
| 6 | 861.18 | 6,607.89 | 5,746.70 | 0.6302 | 3,621.40 | 53,692.90 |
| 7 | 878.41 | 6,475.73 | 5,597.32 | 0.5835 | 3,265.98 | 52,619.04 |
| 8 | 895.97 | 6,346.21 | 5,450.24 | 0.5403 | 2,944.60 | 51,566.66 |
| 9 | 913.89 | 6,219.29 | 5,305.40 | 0.5002 | 2,654.02 | 50,535.32 |
| 10 | 932.17 | 6,094.90 | 5,162.73 | 0.4632 | 2,391.34 | 49,524.62 |

## 6. Verdict-by-scenario

**Scenario A — computed baseline:** NPV = −$71,424; simple payback = none; discounted payback = none. **NO-GO** on economics alone. Requires ITC retention, state-level storage rebate, or explicit resilience valuation.   **Scenario B — ITC denied or FEOC-ineligible equipment:** Capexnet rises to $111,200 (no ITC), deepening negative NPV. **NO-GO** without stacked resilience value or rebate.   **Scenario C — Tariff-rich C&I site:** If the host site's actual demand charge is materially above $18/kW-month, or time-of-use energy spreads widen, NPV improves. **CONDITIONAL** — verify with the live utility tariff schedule before commitment.   **Scenario D — State storage rebate stacked on ITC:** Many US states offer storage rebates/incentives that, combined with the 30% ITC, can move the project to positive NPV. **GO** if eligible. Confirm via the relevant state energy office.

## 7. Certification & standards block

| Standard / listing | Scope | Reference |
| --- | --- | --- |
| UL 1973 | Cell / module level (batteries for stationary & motive auxiliary power) | UL 1973 (UL webstore) |
| IEC 62619:2022 ed2 | Safety of secondary lithium cells and batteries for industrial applications incl. stationary ESS | IEC 62619:2022 ed2 (IEC webstore) |
| IEC 63056:2020 | ESS lithium battery safety up to 1500 V DC (HESS / PV / large on-off-grid) | IEC 63056:2020 (IEC webstore) |
| IEC 62109-1:2010 | Safety of power converters for use in PV power systems — Part 1: General requirements | IEC 62109-1:2010 (IEC webstore) |
| IEC 62109-2:2011 | Safety of power converters for use in PV power systems — Part 2: Particular requirements for inverters | IEC 62109-2:2011 (IEC webstore) |
| UL 9540 | Energy storage system listing | UL 9540, 2nd ed. (UL webstore) |
| UL 9540A | Cell-to-system thermal runaway propagation test method | UL 9540A (UL) |
| NFPA 855 (2023) | Installation spacing, fire separation for stationary ESS | NFPA 855 (NFPA) |
| IEEE 1547-2018 | Interconnection (if export-capable) | IEEE 1547-2018 (IEEE webstore) |
| UN Manual of Tests & Criteria, Rev.7 §III (UN 38.3) | Lithium-battery transport classification | UN Manual of Tests and Criteria, Rev.7 (UN) |
| USDA FSIS sanitation compatibility | Food-zone wash-down, drainage (operator-implemented cold-chain holding) | USDA FSIS Directive 5000.1 |

## 8. HS code & duty block

| HTSUS candidate | Description | Status | Reference |
| --- | --- | --- | --- |
| 8507.60 | Lithium-ion accumulators (battery modules) | PENDING | HTSUS 8507.60 lookup (USITC) |
| 8504.40 | Static converters (PCS / hybrid inverter) | PENDING | HTSUS 8504.40 lookup (USITC) |
| 8537.10 | Boards/panels for electric control (BOS, BMS enclosure) | PENDING | HTSUS 8537.10 lookup (USITC) |

**How to verify duty rates:** Use the USITC HTSUS search at `hts.usitc.gov`. Select the current chapter revision and read the "General Rate of Duty" column. Section 301 tariffs (China-origin Li-ion cells) and any AD/CVD orders must be checked separately. A binding ruling via CBP's eRulings portal is the only definitive answer for a given shipment.

## 9. Risk register

- **ITC eligibility drift:** FEOC rules and prevailing-wage documentation can void the 30%. Stage evidence from PO stage. [26 U.S.C. §48](https://www.law.cornell.edu/uscode/text/26/48).

- **Tariff re-design:** Many US utilities are moving C&I customers to time-of-use demand. Re-check the tariff at the energization date, not at the RFQ date. [EIA Electric Power Monthly Table 5.6.b (PDF)](https://www.eia.gov/electricity/sales_revenue_price/pdf/table.pdf).

- **Cycle life vs. throughput:** If refrigeration ride-through runs the BESS deeper than the modeled 80% DoD, augmentation may arrive in yr 8–10 — re-run TCO with a 5% capex top-up.

- **Food-zone adjacency:** USDA FSIS inspectors may require wash-down-rated enclosures and drainage compliance — can shift BOS cost by 10–25%. [FSIS Directive 5000.1](https://www.fsis.usda.gov/policy/fsis-directives/5000.1).

## 10. Explicit bounded assumptions

The following inputs were not stated in the source draft and were filled with bounded defaults for the computed run. They are **model assumptions**, not sourced facts:

- residual_value.amount = $0

- residual_value.year = 10

- asset.ess.round_trip_eff = 0.88

- asset.ess.degradation_pct_per_year = 2.0%

- asset.ess.charge_cost_per_kwh = $0.0853

- asset.ess.usable_pct = 0.90

- asset.ess.value_per_kwh_discharged = $0.0853