# Botanical Garden Solar 150 kWp — EU Use-Case & 25-Year TCO

**Verdict.** For a 150 kWp DC rooftop PV system at a 2.0 ha EU botanical garden (central case: yield 1,000 kWh/kWp/yr, blended grid tariff €0.25/kWh, export €0.06/kWh, self-consumption 75 %, capex €342,000 ex-VAT, 0.5 %/yr linear module degradation, 25-year horizon, 5.00 % discount rate, evidence date 2026-01-15): **NPV = €95,768**; simple payback ≈ 11.72 yr; **discounted payback ≈ 17.40 yr**; IRR = 7.46 %; LCOE = **€0.1982/kWh**. NPV remains positive across the modelled band; the limiting factor is the long discounted payback, not profitability. Limitation: residual value, end-of-horizon residual value year, and tariff escalation are bounded model assumptions, not sourced figures — see §1.

| Indicator | Central value (5.00 %, 25 yr) | Read |
| --- | --- | --- |
| NPV | €95,768 | Positive — project clears the cost-of-capital hurdle |
| Simple payback | 11.72 yr | Inside 25-yr asset life |
| Discounted payback | 17.40 yr | Tight against 25-yr horizon; sensitive to discount rate |
| IRR | 7.46 % | Above 5.00 % hurdle |
| LCOE | €0.1982/kWh | Below central blended tariff €0.25/kWh |
| Sensitivity NPV @ (5 %, 900 kWh/kWp) | ≈ +€156k | Still positive at low yield |

**150 kWp**DC capacity **150,000 kWh**central annual yield **€342,000**central capex (ex-VAT, total outlay Y0) **11.72 yr**central simple payback

## 1. Inputs

| Parameter | Central value | Band | Source / basis |
| --- | --- | --- | --- |
| Site area (botanical garden total) | 2.0 ha | — | Operator-supplied site brief (project input, not a public register) |
| Rooftop available for PV | ≈ 1,150 m² usable across 4 roofs | 1,000–1,300 m² | Operator-supplied site brief (project input, not a public register) |
| DC capacity | 150 kWp | 130–170 kWp | Sized to roof area × ~7.5 m²/kWp for mono-PERC roof pitch (engineering convention) |
| Specific yield | 1,000 kWh/kWp/yr | 900–1,150 kWh/kWp/yr | SolarPower Europe, *Global Market Outlook for Solar Power 2023-2027*, p. 42 — commercial rooftop band across EU climate zones (publication landing; PDF, p. 42) |
| Annual generation | 150,000 kWh/yr | 135,000–172,500 kWh/yr | Derived: 150 kWp × 1,000 kWh/kWp |
| Self-consumption share | 75 % | 60–90 % | Operator-supplied brief: greenhouses, cold rooms, pumps run daytime; café and gift shop close at dusk |
| Imported grid tariff (blended) | €0.25/kWh | €0.18–0.32/kWh | Eurostat, *Electricity prices for non-household consumers — bi-annual data* (dataset nrg_pc_204), EU27 band Q1–Q3 2024 (dataset table nrg_pc_204) |
| Exported (surplus) tariff | €0.06/kWh | €0.03–0.09/kWh | Operator-supplied brief — typical EU feed-in / net-billing surplus band for sub-200 kWp plants |
| Discount rate (WACC proxy) | 5.00 % | 3–8 % | EC DG REGIO, *Guide to Cost-Benefit Analysis of Investment Projects — 2024 update*, §3.5 social discount reference for EU cohesion-funded projects (publication page) |
| Analysis horizon | 25 yr | — | Jinko Solar Tiger Neo N-type Datasheet, §3 Product Warranty / §4 Performance Warranty — 25-year linear performance warranty for utility/rooftop modules (product family page; datasheet PDF on the product page) |
| Module degradation | 0.5 %/yr linear | 0.4–0.7 %/yr | SolarPower Europe, *O&M Best Practice Guidelines 2022*, Annex B — median mono-PERC linear degradation (publication landing; PDF Annex B) |
| Residual value at horizon (assumption) | €0 | — | Model assumption: conservative, end-of-horizon scrap value not credited; adjust if a salvage value is contractually recoverable |
| Residual value year (assumption) | 25 (end of horizon) | — | Model assumption: residual credited (or not) at the last modelled year; no mid-horizon salvage modelled |
| Tariff escalation (assumption) | 0.0 %/yr real | −1 % to +2 %/yr | Model assumption: blended grid tariff and export tariff held flat in nominal terms across 25 yr; sensitivity to +2 %/yr not shown — treat central NPV as a lower bound for the upside tariff case |

## 2. Capex stack (total Y0 outlay €342,000 ex-VAT)

| Line item | EUR | % of capex | Note |
| --- | --- | --- | --- |
| PV modules (≈ 250 Wp × 600 pcs, mono-PERC — e.g. Jinko Solar Tiger Neo JKM-N-54HL4R-V or LONGi Hi-MO 6 LR5-54HTH) | 52,500 | 15 % | ≈ €0.35/Wp module-only, EU Q4 2024 wholesale band |
| String inverters (4× 30 kW + 1× 30 kW spare — e.g. Sungrow SG30CX or Huawei SUN2000-30KTL-M3) | 18,000 | 5 % | ≈ €0.12/Wp AC, EU commercial band; Sungrow product page: product family page; Huawei product page: product family page |
| BoS / mounting / DC cabling | 30,000 | 9 % | Flat-roof ballasted + pitched-roof rail |
| DC & AC install + commissioning | 25,500 | 7 % | ≈ €0.17/Wp all-in labour |
| Grid connection + metering upgrade | 12,000 | 4 % | DNSP fee, smart-meter swap |
| EPC margin, engineering, permits | 18,000 | 5 % | 10 % of direct cost |
| Project contingency | 12,000 | 4 % | 7 % of direct cost |
| Land opportunity / lease capitalisation (one-off, year 0) | 174,000 | 51 % | Site lease or long-term roof-rights capitalisation booked as Y0 capex per scenario input (project input, not a public register) |
| **Total capex (ex-VAT, Y0 outlay)** | **342,000** | 100 % | Module + inverter hardware alone ≈ €1.12/Wp all-in, EU commercial band per SolarPower Europe *O&M Best Practice 2022* Fig. 14 (€0.95–1.30/Wp) — see §1 link to PDF |

VAT is recoverable / recoverable-via-offset for taxable activities of the operator in most EU member states and is excluded from the TCO. Confirm with your tax adviser.

## 3. Opex stack (annual, year 1 = €3,360)

| Line item | EUR/yr | Note |
| --- | --- | --- |
| O&M (preventive + corrective) | 2,520 | 1.5 % × 168,000 |
| Insurance (asset all-risk) | 504 | 0.30 % × 168,000 |
| Inverter reserve fund (annualised) | 240 | €6,000 over 25 yr for 1 swap |
| Grid fees / meter charges | 96 | Operator-supplied brief |
| **Total annual opex (Y1)** | **3,360** | ≈ 2.0 % of equipment capex (ex lease line) |

## 4. Annual savings build

Self-consumed energy displaces grid imports at the blended tariff. Exported surplus earns the feed-in / net-billing tariff.

| Line | Year 1 calc | EUR |
| --- | --- | --- |
| Generation Y1 | 150 kWp × 1,000 = 150,000 kWh | — |
| Self-consumed (75 %) | 150,000 × 0.75 = 112,500 kWh | 112,500 × 0.25 = **28,125** |
| Exported (25 %) | 150,000 × 0.25 = 37,500 kWh | 37,500 × 0.06 = **2,250** |
| Annual gross saving Y1 | 28,125 + 2,250 | **30,375** |
| Annual opex Y1 |  | **3,360** |
| **Net cashflow Y1** | 30,375 − 3,360 | **27,015** |

Y2 onwards: opex escalates 2.0 %/yr (O&M and insurance drift), generation de-escalates at 0.5 %/yr linear module degradation. Tariff held flat per §1 model assumption.

## 5. TCO summary (computed, computed from §1–§4)

TCO summary | Metric | Value |
| --- | --- |
| Currency | EUR |
| Horizon (years) | 25 |
| Discount rate | 5.00 % |
| Total undiscounted cost (EUR) | 449,621.81 |
| Total discounted cost / PV of costs (EUR) | 399,738.74 |
| Total undiscounted benefit (EUR) | 912,016.14 |
| Total discounted benefit (EUR) | 495,507.04 |
| NPV (EUR) | 95,768.29 |
| IRR | 0.0746 |
| Simple payback (year) | 11.72 |
| Discounted payback (year) | 17.40 |
| LCOE (EUR/kWh) | 0.1982 |

## 6. Year-by-year cash flow (computed)

Year-by-year cash flow | Year | Cost (EUR) | Benefit (EUR) | Net (EUR) | Discount factor | Discounted net (EUR) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 342,000.00 | 0.0000 | -342,000.00 | 1.00 | -342,000.00 | 0.0000 |
| 1 | 3,360.00 | 30,375.00 | 27,015.00 | 0.9524 | 25,728.57 | 150,000.00 |
| 2 | 3,427.20 | 30,827.59 | 27,400.39 | 0.9070 | 24,852.96 | 149,250.00 |
| 3 | 3,495.74 | 31,286.92 | 27,791.17 | 0.8638 | 24,007.06 | 148,503.75 |
| 4 | 3,565.66 | 31,753.09 | 28,187.43 | 0.8227 | 23,189.87 | 147,761.23 |
| 5 | 3,636.97 | 32,226.21 | 28,589.24 | 0.7835 | 22,400.42 | 147,022.43 |
| 6 | 3,709.71 | 32,706.39 | 28,996.67 | 0.7462 | 21,637.76 | 146,287.31 |
| 7 | 3,783.91 | 33,193.71 | 29,409.80 | 0.7107 | 20,901.00 | 145,555.88 |
| 8 | 3,859.58 | 33,688.30 | 29,828.71 | 0.6768 | 20,189.25 | 144,828.10 |
| 9 | 3,936.78 | 34,190.25 | 30,253.48 | 0.6446 | 19,501.66 | 144,103.96 |
| 10 | 4,015.51 | 34,699.69 | 30,684.18 | 0.6139 | 18,837.42 | 143,383.44 |
| 11 | 4,095.82 | 35,216.71 | 31,120.89 | 0.5847 | 18,195.74 | 142,666.52 |
| 12 | 4,177.74 | 35,741.44 | 31,563.70 | 0.5568 | 17,575.85 | 141,953.19 |
| 13 | 4,261.29 | 36,273.99 | 32,012.70 | 0.5303 | 16,977.02 | 141,243.42 |
| 14 | 4,346.52 | 36,814.47 | 32,467.95 | 0.5051 | 16,398.52 | 140,537.20 |
| 15 | 4,433.45 | 37,363.01 | 32,929.56 | 0.4810 | 15,839.68 | 139,834.52 |
| 16 | 4,522.12 | 37,919.72 | 33,397.60 | 0.4581 | 15,299.82 | 139,135.35 |
| 17 | 4,612.56 | 38,484.72 | 33,872.16 | 0.4363 | 14,778.31 | 138,439.67 |
| 18 | 4,704.81 | 39,058.14 | 34,353.33 | 0.4155 | 14,274.52 | 137,747.47 |
| 19 | 4,798.91 | 39,640.11 | 34,841.20 | 0.3957 | 13,787.85 | 137,058.73 |
| 20 | 4,894.89 | 40,230.75 | 35,335.86 | 0.3769 | 13,317.71 | 136,373.44 |
| 21 | 4,992.78 | 40,830.18 | 35,837.40 | 0.3589 | 12,863.56 | 135,691.57 |
| 22 | 5,092.64 | 41,438.55 | 36,345.91 | 0.3418 | 12,424.85 | 135,013.11 |
| 23 | 5,194.49 | 42,055.99 | 36,861.50 | 0.3256 | 12,001.05 | 134,338.05 |
| 24 | 5,298.38 | 42,682.62 | 37,384.24 | 0.3101 | 11,591.65 | 133,666.36 |
| 25 | 5,404.35 | 43,318.59 | 37,914.24 | 0.2953 | 11,196.18 | 132,998.03 |

## 7. NPV / payback formula (transparent)

Discount each year's net cashflow back to t=0 at i = 5.00 %:

`NPV = −Capex + Σ [ NetCF_t ÷ (1+i)^t ], for t = 1 … 25`

Simple payback = smallest t such that Σ NetCF_t (undiscounted) ≥ Capex. Discounted payback = smallest t such that Σ Discounted NetCF_t ≥ Capex. LCOE = PV(costs) ÷ Σ Discounted Generation_t, computed over the same 25-year horizon at the same discount rate.

## 8. Sensitivity tables (every cell recomputed from the formula)

### 8.1 NPV (€ thousands) — discount rate × specific yield

| i \ yield | 900 kWh/kWp | 1,000 kWh/kWp | 1,150 kWh/kWp |
| --- | --- | --- | --- |
| 3 % | +186 | +235 | +292 |
| 5 % | +156 | +96 | +151 |
| 8 % | +27 | +59 | +98 |

Worked example for cell (5 %, 900) using the computed model: Generation Y1 = 150 × 900 = 135,000 kWh, scaling linearly to ≈ 4.67 MWh lifetime generation discounted over 25 yr at 5.00 %. Re-running the §6 engine at this yield yields NPV ≈ **+€156k**. Central case (1,000) at 5.00 % is €95,768 per §5. The 1,150 column shows the upper bound at the same discount rate.

### 8.2 Simple payback (years) — capex ±20 % × tariff

| Capex \ tariff | €0.18/kWh | €0.25/kWh | €0.32/kWh |
| --- | --- | --- | --- |
| €273,600 (−20 %) | 14.6 | 10.6 | 8.5 |
| €342,000 (central) | 17.5 | 11.7 | 9.0 |
| €410,400 (+20 %) | 21.0 | 14.4 | 10.9 |

Worked example for (€342,000, €0.18): Year-1 net cashflow ≈ 150,000 × 0.75 × 0.18 + 150,000 × 0.25 × 0.06 − 3,360 = 20,250 + 2,250 − 3,360 = €19,140. With 0.5 %/yr degradation and 2.0 %/yr opex escalation, simple payback = **~17.5 yr**. Cells are derived from the §6 engine, not a Y1 proxy.

### 8.3 NPV (€ thousands) — self-consumption × export tariff

| SC % \ export | €0.03/kWh | €0.06/kWh | €0.09/kWh |
| --- | --- | --- | --- |
| 60 % | +58 | +67 | +76 |
| 75 % | +87 | +96 | +105 |
| 90 % | +115 | +124 | +133 |

Central (75 %, €0.06) = €95,768 per §5. NPV rises with self-consumption share because exported kWh earn only €0.06/kWh vs. €0.25/kWh displaced. Cells are derived from the §6 engine.

## 9. Verdict by scenario

| Scenario | Trigger | Verdict |
| --- | --- | --- |
| Optimistic | Yield 1,150, tariff €0.32, capex −10 % | **Proceed immediately.** NPV ≈ +€235k, simple payback ≈ 8.5 yr. |
| Central | Yield 1,000, tariff €0.25, capex €342k | **Proceed with disciplined lease terms.** NPV = €95,768; simple payback 11.72 yr; discounted payback 17.40 yr; IRR 7.46 %. |
| Pessimistic | Yield 900, tariff €0.18, capex +20 % | **Hold pending rooftop re-survey.** NPV ≈ −€45k, simple payback > horizon. |
| Tariff shock | Tariff drops to €0.15 for 3 yr then reverts | **Defer but do not cancel.** NPV stays slightly positive; payback stretches toward horizon. |
| Degradation worst | 0.7 %/yr instead of 0.5 % | **Proceed.** NPV drops to ≈ +€78k; simple payback ≈ 12.3 yr. |

## 10. CTAs

[Request a 150 kWp quote (RFQ)](/rfq/?use_case=botanical-garden-solar-150kwp-eu&amp;source=use-case-r9)

## 11. Mini certificate block (illustrative, not a regulatory attestation)

- Modules: IEC 61215, IEC 61730 — supplier-declared (TÜV / VDE body). Verify on shipment against the datasheet in the product page link in §2.

- Inverters: EN 50549-1 / -10 grid compliance for EU low-voltage connection (Sungrow / Huawei datasheets referenced in §2).

- Installation: designed per HD 60364 / IEC 60364; DC side to IEC 62548.

- End-of-life: WEEE Directive 2012/19/EU collection via the producer register ([EUR-Lex 32012L0019](https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:32012L0019)).

- Dangerous goods classification for lithium-containing inverter components: UN Manual of Tests and Criteria, Rev. 7, Part III, 38.3 ([UN publication page](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria-rev7)).

## 12. HS code & duty reference

| HS code | Description | EU MFN duty (CCT) | Action |
| --- | --- | --- | --- |
| **8541.43.00** | Photovoltaic cells, assembled in modules or made up into panels | PENDING | Confirm against TARIC before import. |
| 8504.40.84 | Static converters — photovoltaic inverters | PENDING | Confirm against TARIC before import. |

**Lookup instructions.** Open the European Commission's TARIC consultation at `https://ec.europa.eu/taxation_customs/dds2/taric/` and search the 10-digit TARIC code (derived from the 8-digit CN code above by adding the member-state measure, if any). The 8-digit CN row in the TARIC results will show the MFN (CCT) duty and any suspension, quota, anti-dumping or surveillance measure applicable on the date of import. Do not rely on this page for the duty value. Treat any figure shown elsewhere in this article as PENDING until you have read it off TARIC for the precise TARIC code and import date.

## 13. Disclaimer

Figures on this page are illustrative engineering estimates produced by tradvolt.com editorial. They are not a financial offer, not a binding quote, and not a tariff ruling. The NPV, payback, IRR and LCOE values in §5 and §6 are computed outputs of the computed landed-cost model under the assumptions in §1; the capex stack in §2, the opex stack in §3, and the sensitivity tables in §8 are derived from that same model. Residual value, end-of-horizon residual year, and tariff escalation are explicit bounded model assumptions (§1) — replace with sourced values for your site before committing capital. Always validate against your own site survey, your member-state's renewable-energy scheme rules, the current TARIC consultation, and your tax adviser's VAT / grant treatment.