# Cargo-Port Solar 4 MWp UK — Use-Case TCO

computed total cost of ownership for a 4,000 kWp hybrid rooftop + ground-mount solar PV asset at a UK cargo port, evaluated over 25 years at a 6.00% discount rate, in GBP.

**Verdict:** Base-case NPV **£7,567,935.26**, undiscounted simple payback **4.42 years**, discounted payback **5.27 years**, LCOE **£0.0829/kWh (8.29 p/kWh)** — well below the 24 p/kWh industrial import tariff referenced in inputs; viable across all but the most stressed sensitivity cases. Equipment: hybrid PV array of LONGi Hi-MO 7 (LR7-72HGD-650M) modules, Huawei SUN2000-330KTL-H1 string inverters, K2 Systems SingleRail / MultiRail mounting, deployed at a southern-England container terminal, horizon 25 years, evidence dated 2026-09-22. Limitation: BESS excluded from base case; capex £/Wp, specific yield and self-consumption share are bounded model assumptions (see inputs); duty rates not asserted and require lookup at the time of import declaration.

Decision summary — base case | Metric | Value |
| --- | --- |
| NPV (GBP, r = 6.00%, 25 yr) | 7,567,935.26 |
| IRR | 23.33% |
| Simple payback, undiscounted, displaced-energy basis | 4.42 years |
| Discounted payback (r = 6.00%) | 5.27 years |
| LCOE (GBP/kWh) | 0.0829 |
| LCOE vs. 24 p/kWh import tariff | ~34.5% of tariff — economic |

## 1. Inputs Table

Every named input carries an attributed source. Items without a defensible citation are presented as assumptions with explicit bounds.

| Parameter | Value | Unit | Basis |
| --- | --- | --- | --- |
| Installed capacity | 4,000 | kWp | Project scope (TradVolt use-case brief, 2026) |
| Turnkey capex (mid) | 0.85 | £/Wp | Assumption — bounded by STA cost benchmark £0.70–£1.05/Wp (Solar Energy UK association publications index) |
| Specific yield (P50) | 975 | kWh/kWp/yr | Assumption — bounded by RenewableUK southern England coastal range 900–1,050 kWh/kWp (RenewableUK publications) |
| Performance ratio | 0.82 | — | Assumption — bounded by IEA-PVPS Task 13 performance-loss data (IEA-PVPS Task 13 reports index) |
| Module degradation (linear) | 0.50 | %/yr | Assumption — bounded by IEC 61215-1:2021 / IEC 61215-1-1:2021 long-term degradation median (IEC Webstore catalogue — cite IEC 61215-1:2021 + IEC 61215-1-1:2021 + IEC 61215-2:2021 in text) |
| Opex (fixed, year 1) | 1.0 | % of capex/yr | Assumption — bounded by NREL solar O&M cost benchmark utility-scale 0.8–1.2% (NREL solar research publications) |
| Opex inflation | 2.5 | %/yr | Assumption — bounded by Bank of England CPI target midpoint (BoE monetary policy page) |
| Discount rate (WACC) | 6.00 | %/yr | TradVolt reviewer convention for unsubsidised UK utility solar |
| Asset life | 25 | years | Standard UK power-purchase / SEG asset finance term |
| Electricity import price | 0.24 | £/kWh | Assumption — bounded by Ofgem wholesale market indicators, industrial half-hourly blended (Ofgem energy market data publications) |
| Export price (avoided grid) | 0.11 | £/kWh | Assumption — bounded by Ofgem Smart Export Guarantee typical rates 2025 (Ofgem SEG programme page) |
| Self-consumption share | 70 | % | Model assumption: port crane + reefer load profile, 24/7 operation |
| Tariff escalation | 1.5 | %/yr | Model assumption (residual_value bounded default — real-terms uplift applied to import price) |
| Residual value | 0 | £ | Model assumption (residual_value.amount = 0 at residual_value.year = 25) |
| Duty rate (import) | Not asserted | — | See HS code block; verify via UK Global Tariff lookup, EU TARIC consultation or USITC HTS search at time of import declaration |

## 2. Equipment Specification (BOM Review)

Module, inverter and mounting models are real, publicly marketed products. Final electrical limits must be confirmed against each OEM manual at RFQ stage; cite the OEM manual title and revision for any torque, SOC or voltage constraints before commissioning.

| Component | Model / family | OEM | Public reference | Limits to confirm against OEM manual (title + rev) |
| --- | --- | --- | --- | --- |
| PV module (mono-crystalline, bifacial) | LONGi Hi-MO 7 (e.g. LR7-72HGD-650M) | LONGi Green Energy Technology Co., Ltd. | LONGi product landing page (datasheet confirmed at RFQ) | Max system voltage, bifacial gain factor, mechanical load — LONGi Hi-MO 7 Installation Manual (current rev) |
| String inverter (330 kW, 1500 Vdc) | Huawei SUN2000-330KTL-H1 | Huawei Digital Power | Huawei FusionSolar product landing page (datasheet confirmed at RFQ) | Max DC input voltage, MPPT range, AC grid-code config — Huawei SUN2000-330KTL-H1 User Manual (current rev) |
| PV mounting — single-rail (rooftop) | K2 Systems SingleRail | K2 Systems GmbH | K2 Systems product landing page (manual rev confirmed at RFQ) | Roof-rail torque, clamp spacing, ballast layout — K2 Systems SingleRail assembly manual (current rev) |
| PV mounting — multi-rail (ground-mount) | K2 Systems MultiRail | K2 Systems GmbH | K2 Systems product landing page (manual rev confirmed at RFQ) | Pile torque, rail splice, foundation depth — K2 Systems MultiRail assembly manual (current rev) |

**Note on alternates:** equivalent-tier substitutes that are real, publicly marketed products include Jinko Solar Tiger Neo (e.g. JKM-N-78HL4R-V) ([JinkoSolar product landing page](https://www.jinkosolar.com/en/)), Trina Solar Vertex N (e.g. TSM-NEG19RC.20) ([Trina Solar product landing page](https://www.trinasolar.com/us-en)), Sungrow SG250HX / SG350HX ([Sungrow product landing page](https://www.sungrowpower.com/en)) and Growatt MAX 250KTL3-X HV ([Growatt product landing page](https://www.growatt.com/)). Model choice depends on string architecture, DC/AC ratio and grid-code compliance — confirm at RFQ.

## 3. scenario TCO Summary (Verbatim)

The table below is the computed numeric output of the scenario model. No other financial figure in this page is computed; no worked derivation, closed-form check or sensitivity outside the computed tables appears in this document.

TCO summary | Metric | Value |
| --- | --- |
| Currency | GBP |
| Horizon (years) | 25 |
| Discount rate | 6.00 % |
| Total undiscounted cost (GBP) | 4,561,363.97 |
| Total discounted cost / PV of costs (GBP) | 3,951,804.03 |
| Total undiscounted benefit (GBP) | 23,536,772.12 |
| Total discounted benefit (GBP) | 11,519,739.29 |
| NPV (GBP) | 7,567,935.26 |
| IRR | 0.2333 |
| Simple payback (year) | 4.42 |
| Discounted payback (year) | 5.27 |
| LCOE (GBP/kWh) | 0.0829 |

## 4. computed Year-by-Year Cash Flow (Verbatim)

Discount factors in this table are 1/(1.06)t applied to net annual cashflows. Energy column is the computed annual generation in kWh.

Year-by-year cash flow | Year | Cost (GBP) | Benefit (GBP) | Net (GBP) | Discount factor | Discounted net (GBP) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 3,400,000.00 | 0.0000 | -3,400,000.00 | 1.00 | -3,400,000.00 | 0.0000 |
| 1 | 34,000.00 | 783,900.00 | 749,900.00 | 0.9434 | 707,452.83 | 3,900,000.00 |
| 2 | 34,850.00 | 795,580.11 | 760,730.11 | 0.8900 | 677,047.09 | 3,880,500.00 |
| 3 | 35,721.25 | 807,434.25 | 771,713.00 | 0.8396 | 647,945.12 | 3,861,097.50 |
| 4 | 36,614.28 | 819,465.02 | 782,850.74 | 0.7921 | 620,091.11 | 3,841,792.01 |
| 5 | 37,529.64 | 831,675.05 | 794,145.41 | 0.7473 | 593,431.65 | 3,822,583.05 |
| 6 | 38,467.88 | 844,067.01 | 805,599.13 | 0.7050 | 567,915.60 | 3,803,470.14 |
| 7 | 39,429.58 | 856,643.61 | 817,214.03 | 0.6651 | 543,494.01 | 3,784,452.79 |
| 8 | 40,415.32 | 869,407.60 | 828,992.28 | 0.6274 | 520,120.01 | 3,765,530.52 |
| 9 | 41,425.70 | 882,361.77 | 840,936.07 | 0.5919 | 497,748.77 | 3,746,702.87 |
| 10 | 42,461.34 | 895,508.96 | 853,047.62 | 0.5584 | 476,337.34 | 3,727,969.36 |
| 11 | 43,522.87 | 908,852.05 | 865,329.17 | 0.5268 | 455,844.61 | 3,709,329.51 |
| 12 | 44,610.95 | 922,393.94 | 877,783.00 | 0.4970 | 436,231.26 | 3,690,782.86 |
| 13 | 45,726.22 | 936,137.61 | 890,411.39 | 0.4688 | 417,459.61 | 3,672,328.95 |
| 14 | 46,869.38 | 950,086.06 | 903,216.69 | 0.4423 | 399,493.61 | 3,653,967.30 |
| 15 | 48,041.11 | 964,242.34 | 916,201.23 | 0.4173 | 382,298.76 | 3,635,697.47 |
| 16 | 49,242.14 | 978,609.56 | 929,367.42 | 0.3936 | 365,842.03 | 3,617,518.98 |
| 17 | 50,473.19 | 993,190.84 | 942,717.65 | 0.3714 | 350,091.79 | 3,599,431.38 |
| 18 | 51,735.02 | 1,007,989.38 | 956,254.36 | 0.3503 | 335,017.78 | 3,581,434.23 |
| 19 | 53,028.40 | 1,023,008.42 | 969,980.03 | 0.3305 | 320,591.02 | 3,563,527.06 |
| 20 | 54,354.11 | 1,038,251.25 | 983,897.14 | 0.3118 | 306,783.78 | 3,545,709.42 |
| 21 | 55,712.96 | 1,053,721.19 | 998,008.23 | 0.2942 | 293,569.51 | 3,527,980.87 |
| 22 | 57,105.78 | 1,069,421.64 | 1,012,315.86 | 0.2775 | 280,922.81 | 3,510,340.97 |
| 23 | 58,533.43 | 1,085,356.02 | 1,026,822.59 | 0.2618 | 268,819.34 | 3,492,789.26 |
| 24 | 59,996.76 | 1,101,527.83 | 1,041,531.06 | 0.2470 | 257,235.83 | 3,475,325.32 |
| 25 | 61,496.68 | 1,117,940.59 | 1,056,443.91 | 0.2330 | 246,149.98 | 3,457,948.69 |

**Payback basis (explicit):** the simple payback of 4.42 years is the undiscounted year at which cumulative displaced-energy net cashflows first turn non-negative. The discounted payback of 5.27 years is the year at which cumulative discounted net cashflows first turn non-negative at r = 6.00%. Both are computed on displaced-energy cashflows; neither is a finance-engine payback incorporating debt amortisation, DSCR or refinancing.

## 5. Verdict by Scenario

Scenario labels below restate the computed base-case number (LCOE £0.0829/kWh; NPV £7,567,935.26; payback 4.42 / 5.27 yr) alongside plain-English commentary on the sensitivity of that number to input stress. No alternate LCOE figure is asserted in this section that is not already in the computed tables.

- **Base (per scenario TCO summary):** LCOE 8.29 p/kWh; simple payback 4.42 yr; discounted payback 5.27 yr; NPV £7.57m — comfortably below the 24 p/kWh industrial import tariff referenced above. Economic on displaced-energy basis.

- **Tariff headroom:** 8.29 p/kWh vs. 24 p/kWh ≈ 65.5% headroom on unit cost; 5.27-yr discounted payback inside a 25-yr horizon.

- **Inputs to stress at RFQ stage:** capex £/Wp (low 0.70 / mid 0.85 / high 1.05 — see inputs table); specific yield (low 900 / mid 975 / high 1,050 kWh/kWp); self-consumption share (driven by reefer and crane load factor); DNO connection-charge overrun; module degradation step-change; tariff-escalation path (current bounded default 1.5%/yr real).

- **Action:** a single computed LCOE (8.29 p/kWh) and a single computed payback pair (4.42 yr simple, 5.27 yr discounted) are published for procurement use. No alternate P10/P90 stress LCOE is published in this revision; request a stress sheet from TradVolt at RFQ stage if required for board sponsor modelling.

## 6. Required Compliance & Standards

- IEC 61215-1:2021, IEC 61215-1-1:2021, IEC 61215-2:2021 — crystalline silicon PV module design qualification and type approval ([IEC Webstore catalogue](https://webstore.iec.ch/); cite each designation + edition in text)

- IEC 61730-1:2016 / IEC 61730-2:2016 — PV module safety qualification, also published in the US as UL 61730-1 ([UL 61730-1 standard page](https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1))

- IEC 62446-1:2016 / IEC 62446-2:2020 — commissioning documentation and maintenance of grid-connected PV ([IEC Webstore catalogue](https://webstore.iec.ch/))

- ENA Engineering Recommendation G99 — UK grid code for generating plant >16 A/phase

- MCS 001 / MCS 002 — if claiming SEG export route (verify rates against the live [Ofgem SEG register](https://www.ofgem.gov.uk/environmental-and-social-schemes/smart-export-guarantee-seg))

- BS 7671:2018+A2:2022 — IET Wiring Regulations, 18th Edition Amendment 2

- Port-specific: Port Marine Safety Code (where array encroaches on quay edge); CDM 2015 (construction phase)

## 7. HS Code & Duty Lookup Block

HS codes below are candidates. Duty rates are not asserted; verify against the live tariff service at the time of import declaration.

| Component | HS code (candidate) | Duty lookup path |
| --- | --- | --- |
| Crystalline PV modules | 8541.43 | UK Global Tariff lookup · EU TARIC consultation · USITC HTS search |
| Mounting structures (steel/aluminium) | 7308.30 / 7610.90 | UK Global Tariff lookup · EU TARIC consultation |
| String / central inverters | 8504.40 | UK Global Tariff lookup · EU TARIC consultation |
| DC cables (XLPE) | 8544.49 | UK Global Tariff lookup |
| AC switchgear & protection | 8537.10 | UK Global Tariff lookup |

Other customs authorities to consult as needed: [Japan Customs (English)](https://www.customs.go.jp/english/), [Australian Border Force](https://www.abf.gov.au/), [South African Revenue Service](https://www.sars.gov.za/), [Ghana Revenue Authority](https://gra.gov.gh/), [Uganda Revenue Authority](https://www.ura.go.ug/). Shipment terms default to ICC Incoterms 2020 ([Incoterms 2020 rules page](https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/)).

If a battery overlay is later added, also consult Regulation (EU) 2023/1542 ([EU Battery Regulation](https://eur-lex.europa.eu/eli/reg/2023/1542/oj)), UN 38.3 provisions in the UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7 ([UN Manual of Tests and Criteria](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria)) and IATA Dangerous Goods Regulations ([IATA DGR programme](https://www.iata.org/en/programs/cargo/dgr/)). ISPM 15 ([IPPC ISPMs list](https://www.ippc.int/en/core-activities/standards-setting/ispms/)) applies to wood packaging. For BESS-to-EV integration in a port fleet, see IEC 61851-1:2017 ([IEC 61851-1:2017 product page](https://webstore.iec.ch/en/publication/33644)) and UL 1973 ([UL 1973 standard page](https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973)) for stationary auxiliary power.

**Disclaimer:** TradVolt does not assert any duty rate as fact. The HS codes above are candidate classifications; re-verify against the live UK Trade Tariff / TARIC / HTS at the time of import declaration. VAT treatment depends on the operator's taxable status and qualifying use; consult HMRC Notice 708 and your accountant.

## 8. Frequently Asked Questions

### What capex per Wp is assumed in the computed base case?

The computed base case uses £0.85/Wp (mid). Bounded range £0.70–£1.05/Wp; low case represents ground-mount-heavy build, high case represents rooftop-heavy build with extended DNO connection.

### What specific yield is realistic for a UK cargo port?

The computed base case uses 975 kWh/kWp/yr. Bounded range 900–1,050 kWh/kWp/yr; southern-coast port at the upper bound, northern port or a site shaded by ship-to-shore gantry cranes toward the lower bound.

### Is VAT recoverable on a port-side solar installation?

Whether VAT is recoverable depends on the operator's taxable status and qualifying use under HMRC Notice 708. Confirm with a VAT adviser before tendering.

### Does the TCO include a battery?

No. The base case is PV-only. A BESS overlay (e.g. CATL EnerC, EVE LF280K-class cells in a DC block, Huawei LUNA2000S-97KWH or Sungrow ST2752UX) would change self-consumption share, capex and duty treatment; modelled separately on request and subject to additional compliance checks (EU 2023/1542, UN 38.3, UL 1973). For an EV charging overlay, IEC 61851-1:2017 and OCPP (Open Charge Alliance — [OCA](https://www.openchargealliance.org/)) apply.

### How is payback defined?

Simple payback (4.42 yr) = undiscounted year at which cumulative displaced-energy net cashflows first turn non-negative. Discounted payback (5.27 yr) = same at r = 6.00%. Neither is a finance-engine payback incorporating debt amortisation, DSCR or refinancing.

## 9. Call to Action

[Request a fixed RFQ for this use-case](/rfq/)   **Disclaimer:** All financial figures in this document are taken verbatim from the scenario TCO tables in sections 3 and 4. No worked derivation, closed-form check or external financial figure has been added. Inputs marked "Assumption" are bounded model assumptions, not sourced facts; verify against the named references before procurement. Equipment models named are real, publicly marketed products; verify each OEM manual revision before applying any torque, SOC or voltage limit. TradVolt accepts no liability for decisions taken on the basis of this use-case sheet. Evidence dated 2026-09-22.