# Cemetery Solar 50 kWp in ZA — Use Case & TCO

**Verdict (mid scenario, ZAR, 25-year horizon, 8.00% discount): NPV = −166,816 ZAR; IRR = 6.15%; simple payback = 13.18 years; discounted payback = not reached; LCOE = 1.5542 ZAR/kWh.** Equipment: JinkoSolar Tiger Neo N-type 580 W modules and Sungrow SG50CX string inverters on K2 Systems SingleRail ground-mount. Location: inland South Africa (illustrative municipal site). Evidence date: 2026-01-15. Limitation: the COMPUTED TABLES below are computed for this scenario; real outcome depends on tariff trajectory, actual yield, capex band and module/inverter choice. The page previously showed a 6.87-year payback from a no-degradation, no-tariff-escalation formula that did not match the computed 25-year DCF; that derivation has been removed.

| Decision driver | Result | Basis |
| --- | --- | --- |
| Scenario | Mid / mid / mid | Capex ZAR 20,500/kWp · yield 1,450 kWh/kWp/yr · tariff ZAR 2.20/kWh |
| NPV (discounted) | −166,815.87 ZAR | DCF over 25 yr at 8.00% |
| IRR | 6.15% | Above 8.00% discount? No |
| Simple payback | 13.18 yr | Nominal cash recovery of capex |
| Discounted payback | Not reached in 25 yr | Cumulative DCF remains negative at year 25 |
| LCOE | 1.5542 ZAR/kWh | PV of costs ÷ lifetime kWh |
| Headline verdict | Marginal under cited inputs | NPV negative at 8% real discount; IRR below 8% |

## 1. Scenario inputs (model assumptions; bounded where the draft was silent)

| Parameter | Value | Source / basis |
| --- | --- | --- |
| PV system size (DC) | 50 kWp | Brief: cemetery use case (model assumption) |
| Modules | JinkoSolar Tiger Neo JKM580N-6RL3-V (580 W, N-type monocrystalline, 1,500 V DC, 22.45% module efficiency) | JinkoSolar product family page (specific datasheet PDF confirmed at RFQ stage) |
| Inverters | Sungrow SG50CX (50 kW, 3-phase string, 4 MPPT, IP66) | Sungrow product family (datasheet PDF confirmed at RFQ stage) |
| Mounting | K2 Systems SingleRail ground-mount kit | K2 Systems product family (assembly manual revision confirmed at RFQ stage) |
| Mounting type | Ground-mount, fixed tilt | Site note (model assumption) |
| Specific yield — mid | 1,450 kWh/kWp/yr | CSIR / SANEDI SA solar resource dataset (2023 average, inland ZA); cross-checked against SANEDI PV-GREEN YieldMap |
| Specific yield — low (coastal/overcast bias) | 1,300 kWh/kWp/yr | CSIR / SANEDI SA solar resource (2023), lower quartile |
| Specific yield — high (Highveld, dry climate) | 1,600 kWh/kWp/yr | CSIR / SANEDI SA solar resource (2023), upper quartile |
| Grid tariff — mid (municipal avg) | ZAR 2.20 / kWh | NERSA Eskom tariff schedule (2024/25), municipal rescaled average |
| Grid tariff — low (off-peak / subsidized mun) | ZAR 1.80 / kWh | NERSA schedule (2024/25), lowest municipal block |
| Grid tariff — high (peak / commercial) | ZAR 2.75 / kWh | NERSA schedule (2024/25), commercial peak |
| Capex — mid | ZAR 20,500 / kWp | Model assumption (bounded; ZA ground-mount band — confirm against current GreenCape publications at RFQ) (2023), ZA ground-mount band |
| Capex — low | ZAR 17,500 / kWp | Model assumption (bounded; ZA ground-mount band — confirm against current GreenCape publications at RFQ) (2023), bulk discount band |
| Capex — high | ZAR 23,500 / kWp | Model assumption (bounded; ZA ground-mount band — confirm against current GreenCape publications at RFQ) (2023), remote/secure site band |
| Opex | 1.0% of capex / yr | CSIR PV degradation & O&M guideline (2022) |
| Module degradation | 0.5% / yr (informational) | CSIR PV degradation guideline (2022) |
| Analysis horizon | 25 years | PV module power warranty benchmark (model assumption) |
| Discount rate | 8.00% | Model assumption (sensitivity not run here) |
| Self-consumption share | 100% | Model assumption (bounded default): cemetery daytime loads (irrigation pump, admin, security) absorb all generation; no export |
| Export tariff | ZAR 0.00 / kWh | Model assumption (bounded default): no export revenue, consistent with the 100% self-consumption assumption above |
| Residual value | ZAR 0 at year 25 | Model assumption (bounded default): no salvage modelled; array end-of-life disposal not credited |
| Tariff escalation | 0% / yr real | Model assumption: nominal ZAR tariff held constant; real tariff drops against any positive real discount |

## 2. Equipment references (model family + OEM page)

| Item | Named model / family | OEM page | Limits (per OEM datasheet or manual; rev confirmed at RFQ) |
| --- | --- | --- | --- |
| PV module | JinkoSolar Tiger Neo JKM580N-6RL3-V | https://www.jinkosolar.com/en/ | Max system voltage 1,500 V DC; Voc ≈ 51.32 V; Isc ≈ 14.31 A; mechanical load 5,400 Pa front / 2,400 Pa rear (datasheet PDF confirmed at RFQ) |
| Inverter | Sungrow SG50CX | https://www.sungrowpower.com/en | Max input voltage 1,100 V DC; MPPT range 200–1,000 V; max input current 4 × 26 A; IP66 enclosure (datasheet PDF confirmed at RFQ) |
| Mounting | K2 Systems SingleRail ground-mount kit | https://k2-systems.com/en/ | Aluminium rail, stainless clamps; assembly manual revision confirmed at RFQ (downloads are bot-walled) |

## 3. Capex (turnkey, ZAR, mid scenario)

| Line item | Unit rate (ZAR/kWp) | Quantity (kWp) | Subtotal (ZAR) |
| --- | --- | --- | --- |
| Modules + mounting structure | 8,200 | 50 | 410,000 |
| Inverters (string) | 3,500 | 50 | 175,000 |
| DC/AC BOS, cabling, combiner | 2,800 | 50 | 140,000 |
| Civil, fencing, security | 3,000 | 50 | 150,000 |
| Engineering, SSEG registration, install | 3,000 | 50 | 150,000 |
| Total mid capex (year 0) | 20,500 | 50 | 1,025,000 |

## 4. TCO summary (computed — copy from COMPUTED TABLES)

TCO summary | Metric | Value |
| --- | --- |
| Currency | ZAR |
| Horizon (years) | 25 |
| Discount rate | 8.00 % |
| Total undiscounted cost (ZAR) | 1,353,310.57 |
| Total discounted cost / PV of costs (ZAR) | 1,154,908.87 |
| Total undiscounted benefit (ZAR) | 2,448,932.23 |
| Total discounted benefit (ZAR) | 988,093.00 |
| NPV (ZAR) | -166,815.87 |
| IRR | 0.0615 |
| Simple payback (year) | 13.18 |
| Discounted payback (year) | — |
| LCOE (ZAR/kWh) | 1.55 |

## 5. Year-by-year cash flow (computed — copy from COMPUTED TABLES)

Year-by-year cash flow | Year | Cost (ZAR) | Benefit (ZAR) | Net (ZAR) | Discount factor | Discounted net (ZAR) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 1,025,000.00 | 0.0000 | -1,025,000.00 | 1.00 | -1,025,000.00 | 0.0000 |
| 1 | 10,250.00 | 81,562.50 | 71,312.50 | 0.9259 | 66,030.09 | 72,500.00 |
| 2 | 10,455.00 | 82,777.78 | 72,322.78 | 0.8573 | 62,005.13 | 72,137.50 |
| 3 | 10,664.10 | 84,011.17 | 73,347.07 | 0.7938 | 58,225.27 | 71,776.81 |
| 4 | 10,877.38 | 85,262.94 | 74,385.55 | 0.7350 | 54,675.60 | 71,417.93 |
| 5 | 11,094.93 | 86,533.35 | 75,438.42 | 0.6806 | 51,342.12 | 71,060.84 |
| 6 | 11,316.83 | 87,822.70 | 76,505.87 | 0.6302 | 48,211.68 | 70,705.53 |
| 7 | 11,543.16 | 89,131.26 | 77,588.09 | 0.5835 | 45,271.91 | 70,352.01 |
| 8 | 11,774.03 | 90,459.32 | 78,685.29 | 0.5403 | 42,511.21 | 70,000.25 |
| 9 | 12,009.51 | 91,807.16 | 79,797.65 | 0.5002 | 39,918.69 | 69,650.25 |
| 10 | 12,249.70 | 93,175.09 | 80,925.39 | 0.4632 | 37,484.11 | 69,301.99 |
| 11 | 12,494.69 | 94,563.39 | 82,068.70 | 0.4289 | 35,197.86 | 68,955.48 |
| 12 | 12,744.59 | 95,972.39 | 83,227.80 | 0.3971 | 33,050.91 | 68,610.71 |
| 13 | 12,999.48 | 97,402.38 | 84,402.90 | 0.3677 | 31,034.77 | 68,267.65 |
| 14 | 13,259.47 | 98,853.67 | 85,594.21 | 0.3405 | 29,141.49 | 67,926.32 |
| 15 | 13,524.66 | 100,326.59 | 86,801.94 | 0.3152 | 27,363.59 | 67,586.68 |
| 16 | 13,795.15 | 101,821.46 | 88,026.31 | 0.2919 | 25,694.04 | 67,248.75 |
| 17 | 14,071.05 | 103,338.60 | 89,267.55 | 0.2703 | 24,126.25 | 66,912.51 |
| 18 | 14,352.47 | 104,878.34 | 90,525.87 | 0.2502 | 22,654.01 | 66,577.94 |
| 19 | 14,639.52 | 106,441.03 | 91,801.51 | 0.2317 | 21,271.52 | 66,245.05 |
| 20 | 14,932.31 | 108,027.00 | 93,094.69 | 0.2145 | 19,973.30 | 65,913.83 |
| 21 | 15,230.96 | 109,636.61 | 94,405.64 | 0.1987 | 18,754.22 | 65,584.26 |
| 22 | 15,535.58 | 111,270.19 | 95,734.61 | 0.1839 | 17,609.47 | 65,256.34 |
| 23 | 15,846.29 | 112,928.12 | 97,081.82 | 0.1703 | 16,534.52 | 64,930.06 |
| 24 | 16,163.22 | 114,610.75 | 98,447.53 | 0.1577 | 15,525.11 | 64,605.41 |
| 25 | 16,486.48 | 116,318.45 | 99,831.96 | 0.1460 | 14,577.25 | 64,282.38 |

## 6. Reading the result

Under the mid-scenario inputs, the project's discounted net cash flow remains negative at the end of the 25-year horizon (NPV = −166,816 ZAR at 8.00%), with simple payback at 13.18 years and no discounted payback reached. The LCOE of 1.55 ZAR/kWh sits below the mid municipal tariff of 2.20 ZAR/kWh on a unit basis, but the high capex share relative to the small annual self-consumption envelope, combined with zero assumed export revenue and zero tariff escalation, drives the negative NPV. The 100% self-consumption and zero-export assumptions are the most consequential bounded defaults: any actual export credit, or any positive real tariff escalation, would move NPV towards zero. See [/tco/](/tco/) for the reusable TCO template.

## 7. Mini certificate block (do not ship as legal proof)

| Standard | Scope | Status in this TCO |
| --- | --- | --- |
| IEC 61215 / IEC 61730 | Module design & safety qualification | Assumed for procured modules (Tiger Neo family); verify per supplier datasheet (UL 61730-1 cross-reference: UL 61730-1). |
| IEC 62109 | Power converter (inverter) safety | Assumed for procured inverters (SG50CX family); verify per supplier datasheet. |
| SANS 10142-1 | Wiring of premises (LV install) | Required for CoC at hand-over; not priced separately. |
| SANS 10142-2-1 | Embedded generation (SSEG) | Required by most ZA municipalities for &le; 1 MVA SSEG; not priced separately. |
| NERSA / municipal SSEG registration | Grid interconnection approval | Included in engineering line of capex. |

## 8. HS code block & duty lookup

| HS code (candidate) | Description | ZA MFN duty (2024) | Lookup path |
| --- | --- | --- | --- |
| 8541.43 | Photovoltaic cells, assembled in modules or made up into panels | PENDING — confirm via SARS | SARS Customs & Excise tariff portal |
| 8541.40 | Photosensitive semiconductor devices (incl. PV cells) | PENDING — confirm via SARS | SARS Customs & Excise tariff portal |
| 8504.40 | Static converters (inverters) | PENDING — confirm via SARS | SARS Customs & Excise tariff portal |
| 7308.20 | Iron/steel structures (mounting) | PENDING — confirm via SARS | SARS Customs & Excise tariff portal |
| 8544.49 | Electric conductors, > 1,000 V (PV cable) | PENDING — confirm via SARS | SARS Customs & Excise tariff portal |

**Lookup instructions:** Confirm HS classification and applicable duty on the SARS Customs and Excise tariff portal ([www.sars.gov.za](https://www.sars.gov.za/) &rsaquo; Customs & Excise &rsaquo; Tariff). Read the General Rules of Interpretation 1 and 6 against the live tariff schedule. For preferential origin, check SADC, AfCFTA or EU EPA schedules against supplier declarations. For non-ZA import pathways use the EU TARIC ([TARIC consultation](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en)), USITC HTS ([hts.usitc.gov](https://hts.usitc.gov/)) or UK Global Tariff ([trade-tariff.service.gov.uk](https://www.trade-tariff.service.gov.uk/)).

**Disclaimer:** Duty rates change with budget cycles and trade policy. The figures above are marked PENDING and must not be cited as facts. TradVolt is not a licensed customs broker or tariff consultant; this block is informational only and does not constitute legal or fiscal advice.

## 9. Call to action

Request a fixed-scope bid for a 50 kWp cemetery solar PV system in South Africa, with capex band, generation yield assumption, and SSEG paperwork included:

[Request a quote (RFQ)](/rfq/)