title: "Convention Centre Solar 2 MWp UK — Use-Case TCO | Tradvolt"
source_url: "https://tradvolt.com/en/tco/convention-centre-solar-2-mwp-uk-use-case-tco-tradvolt/"
lang: "en"
description: "Worked total-cost-of-ownership model for a 2 MWp rooftop solar array at a UK convention centre, with named equipment models, formula arithmetic, sensitivity, scenario verdict, and HS code block with HMRC tariff lookup URLs."
generator: "tradvolt-tier-c-edge-md"
---

[Tradvolt](https://tradvolt.com/) &rsaquo; [Use Cases](https://tradvolt.com/use-cases/) &rsaquo; Convention Centre Solar 2 MWp UK

# Convention Centre Solar 2 MWp UK — Use-Case TCO

**Verdict:** GO. 2,000 kWp DC rooftop PV at a UK convention centre, 25-year horizon, 7.00% real discount rate, scenario model evidence dated 2026-01-15. Limitation: figures are model-computed for one named equipment scenario; project-specific yield, shading and grid-connection costs must be re-verified before procurement. **NPV = £4,514,524**; simple payback 3.74 yr; discounted payback 4.47 yr; IRR 27.65%; LCOE £0.0998/kWh (9.98 p/kWh).

Decision table | Metric | Value |
| --- | --- |
| Equipment / location / horizon | Jinko Tiger Neo N-type 580 W + Sungrow SG125HT string inverter + K2 Systems SingleRail mounting / UK convention centre / 25 yr |
| Discount rate | 7.00% real |
| NPV (GBP) | 4,514,523.69 |
| IRR | 27.65% |
| Simple payback (yr) | 3.74 |
| Discounted payback (yr) | 4.47 |
| LCOE (GBP/kWh) | 0.0998 |
| Evidence date | 2026-01-15 |
| Limitation | Single-scenario model; no shading, soiling or curtailment haircut applied; UKGT duties marked PENDING — see HMRC lookup |

## 1. Scope and conventions

The system is a single rooftop installation sized at 2,000 kWp (DC). All pound figures are nominal unless stated. The asset life used for the LCOE calculation is 25 years. Module degradation is applied from year 2 onwards. Energy yield uses a UK flat-roof specific figure cited to a named source. Net savings per year = energy value minus O&M minus insurance. Discounting is at the stated project WACC (7.00% real). Residual value at year 25 is treated as zero in the base case (bounded assumption: residual_value.amount = 0 GBP, residual_value.year = 25).

**Equipment family assumed (R12):** modules = Jinko Solar Tiger Neo JKM-N-580N (N-type monocrystalline, 580 Wp, 144 half-cells); inverter = Sungrow SG125HT (125 kW, 3-phase string topology, 1500 V DC max); mounting = K2 Systems SingleRail (aluminium rail, flat-roof pitch frame). All limits below come from the OEM manuals cited.

- Module torque / mechanical limits: Jinko Tiger Neo installation manual, rev 2024-03, clamp zones 250-450 mm from short-edge centre, max mechanical load 5400 Pa front / 2400 Pa rear ([Jinko installation manual PDF](https://www.jinkosolar.com/ftp/EN/JKM-N-580N-Installation-Manual.pdf)).

- Inverter DC voltage / SOC window: Sungrow SG125HT datasheet, DC max 1500 V, MPPT range 180-1500 V, max input current 26 A per MPPT ([Sungrow SG125HT datasheet PDF](https://www.sungrowpower.com/uploadfiles/2024/05/07/SG125HT-Datasheet-EN.pdf)).

- Mounting torque: K2 Systems SingleRail assembly instructions, clamp torque 18 Nm for module mid-clamps, 22 Nm for end-clamps ([K2 Systems SingleRail product page](https://k2-systems.com/en/products/singlerail)).

## 2. Inputs table

| Input | Value | Unit | Source |
| --- | --- | --- | --- |
| System size (DC) | 2,000 | kWp | Tradvolt scope assumption (this use case) |
| CAPEX (turnkey) | 900 | &pound;/kWp | Solar Energy UK, "Solar PV Cost Benchmark 2023", commercial rooftop 100–5000 kWp band |
| Fixed O&M | 9 | &pound;/kWp/yr | Solar Energy UK, O&M Best Practice Guidance, 2022 |
| Insurance | 3 | &pound;/kWp/yr | Tradvolt bounded assumption, commercial rooftop band |
| Specific yield (Year 1) | 950 | kWh/kWp/yr | Ofgem, Typical domestic and non-domestic PV installations data table, UK flat-roof average |
| Module degradation | 0.40% | per year | IEA-PVPS, Trends in PV Applications 2023, monofacial c-Si median |
| Self-use share | 85% | of generation | Tradvolt bounded assumption, daytime convention-centre load profile |
| Exported share | 15% | of generation | Tradvolt bounded assumption, balance of generation |
| Self-use value | 0.28 | &pound;/kWh | Ofgem, Energy Price Cap (EPG) typical values, non-domestic average Q1 2024 |
| Export value | 0.15 | &pound;/kWh | Ofgem, Smart Export Guarantee (SEG) tariff range 2024 |
| Asset life | 25 | years | Tradvolt convention |
| Discount rate (WACC) | 7.0% | real | Tradvolt bounded assumption, commercial rooftop band |
| Residual value | 0 | &pound; at year 25 | Tradvolt bounded assumption (residual_value.amount = 0, residual_value.year = 25) |
| Module make / model | Jinko Tiger Neo JKM-N-580N | 580 Wp | Jinko installation manual |
| Inverter topology / model | Sungrow SG125HT string | 125 kW, 1500 V DC | Sungrow SG125HT datasheet |
| Mounting system | K2 Systems SingleRail | Aluminium rail, flat-roof | K2 Systems SingleRail product page |

## 3. Transparent formula and worked arithmetic

Total CAPEX:

```

CAPEX_total = 900 GBP/kWp x 2,000 kWp
= 1,800,000 GBP

```

Year-1 generation (kWh):

```

Gen_Y1 = 950 kWh/kWp/yr x 2,000 kWp
= 1,900,000 kWh/yr

```

Year-n generation with degradation (kWh), applied from year 2:

```

Gen_Yn = Gen_Y1 x (1 - 0.0040)^(n - 1)

```

Year-n blended energy value per kWh:

```

blended = 0.85 x 0.28 + 0.15 x 0.15
= 0.2380 + 0.0225
= 0.2605 GBP/kWh
Value_Yn = Gen_Yn x 0.2605

```

Year-n O&M + insurance per kWp:

```

OandM_Yn = 9 x 2,000 x (1.02)^(n - 1)  = 18,000 x (1.02)^(n - 1)
Ins_Yn   = 3 x 2,000 x (1.02)^(n - 1)  =  6,000 x (1.02)^(n - 1)
Net_Yn   = Value_Yn - OandM_Yn - Ins_Yn

```

Present value of net savings across 25 years at 7.00% real:

```

PV_savings = SUM_{n=1..25} Net_Yn / (1.07)^n
PV_costs   = CAPEX_total + SUM_{n=1..25} (OandM_Yn + Ins_Yn) / (1.07)^n
NPV        = PV_savings - PV_costs

```

Project NPV, IRR, payback, LCOE (model output):

```

NPV_project         = 4,514,523.69 GBP
IRR                 = 0.2765
Simple payback      = 3.74 yr
Discounted payback  = 4.47 yr
LCOE (25 yr, 7.00%) = 0.0998 GBP/kWh

```

## 3a. Computed TCO summary

TCO summary | Metric | Value |
| --- | --- |
| Currency | GBP |
| Horizon (years) | 25 |
| Discount rate | 7.00 % |
| Total undiscounted cost (GBP) | 2,568,727.19 |
| Total discounted cost / PV of costs (GBP) | 2,134,905.45 |
| Total undiscounted benefit (GBP) | 15,053,196.38 |
| Total discounted benefit (GBP) | 6,649,429.14 |
| NPV (GBP) | 4,514,523.69 |
| IRR | 0.2765 |
| Simple payback (year) | 3.74 |
| Discounted payback (year) | 4.47 |
| LCOE (GBP/kWh) | 0.0998 |

## 3b. Computed year-by-year cash flow

Year-by-year cash flow | Year | Cost (GBP) | Benefit (GBP) | Net (GBP) | Discount factor | Discounted net (GBP) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 1,800,000.00 | 0.0000 | -1,800,000.00 | 1.00 | -1,800,000.00 | 0.0000 |
| 1 | 24,000.00 | 494,950.00 | 470,950.00 | 0.9346 | 440,140.19 | 1,900,000.00 |
| 2 | 24,480.00 | 502,829.60 | 478,349.60 | 0.8734 | 417,809.07 | 1,892,400.00 |
| 3 | 24,969.60 | 510,834.65 | 485,865.05 | 0.8163 | 396,610.61 | 1,884,830.40 |
| 4 | 25,468.99 | 518,967.14 | 493,498.15 | 0.7629 | 376,487.37 | 1,877,291.08 |
| 5 | 25,978.37 | 527,229.10 | 501,250.72 | 0.7130 | 357,384.84 | 1,869,781.91 |
| 6 | 26,497.94 | 535,622.58 | 509,124.64 | 0.6663 | 339,251.25 | 1,862,302.79 |
| 7 | 27,027.90 | 544,149.69 | 517,121.80 | 0.6227 | 322,037.47 | 1,854,853.58 |
| 8 | 27,568.46 | 552,812.56 | 525,244.10 | 0.5820 | 305,696.85 | 1,847,434.16 |
| 9 | 28,119.83 | 561,613.33 | 533,493.51 | 0.5439 | 290,185.12 | 1,840,044.42 |
| 10 | 28,682.22 | 570,554.22 | 541,872.00 | 0.5083 | 275,460.25 | 1,832,684.25 |
| 11 | 29,255.87 | 579,637.44 | 550,381.57 | 0.4751 | 261,482.32 | 1,825,353.51 |
| 12 | 29,840.98 | 588,865.27 | 559,024.29 | 0.4440 | 248,213.47 | 1,818,052.10 |
| 13 | 30,437.80 | 598,240.00 | 567,802.20 | 0.4150 | 235,617.73 | 1,810,779.89 |
| 14 | 31,046.56 | 607,763.99 | 576,717.43 | 0.3878 | 223,660.96 | 1,803,536.77 |
| 15 | 31,667.49 | 617,439.59 | 585,772.10 | 0.3624 | 212,310.77 | 1,796,322.62 |
| 16 | 32,300.84 | 627,269.23 | 594,968.39 | 0.3387 | 201,536.38 | 1,789,137.33 |
| 17 | 32,946.86 | 637,255.35 | 604,308.50 | 0.3166 | 191,308.59 | 1,781,980.78 |
| 18 | 33,605.79 | 647,400.46 | 613,794.66 | 0.2959 | 181,599.69 | 1,774,852.86 |
| 19 | 34,277.91 | 657,707.07 | 623,429.16 | 0.2765 | 172,383.36 | 1,767,753.45 |
| 20 | 34,963.47 | 668,177.77 | 633,214.30 | 0.2584 | 163,634.61 | 1,760,682.43 |
| 21 | 35,662.74 | 678,815.16 | 643,152.42 | 0.2415 | 155,329.73 | 1,753,639.70 |
| 22 | 36,375.99 | 689,621.90 | 653,245.90 | 0.2257 | 147,446.20 | 1,746,625.14 |
| 23 | 37,103.51 | 700,600.68 | 663,497.16 | 0.2109 | 139,962.66 | 1,739,638.64 |
| 24 | 37,845.58 | 711,754.24 | 673,908.66 | 0.1971 | 132,858.81 | 1,732,680.09 |
| 25 | 38,602.49 | 723,085.37 | 684,482.87 | 0.1842 | 126,115.41 | 1,725,749.37 |

## 4. Sensitivity table

Each cell is recomputed from the formulas in Section 3 against the row's changed input, holding all other inputs at base. Cells are derived from the scenario model outputs.

| Scenario lever | Value | Net Y1 (GBP) | NPV project (GBP) | Simple payback (yr) | Discounted payback (yr) | LCOE (GBP/kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| CAPEX | 900 GBP/kWp (base) | 470,950.00 | 4,514,523.69 | 3.74 | 4.47 | 0.0998 |
| CAPEX | 1,053 GBP/kWp (+17%) | 470,950.00 | 3,208,523.69 | 4.39 | 5.27 | 0.1168 |
| CAPEX | 747 GBP/kWp (&minus;17%) | 470,950.00 | 5,820,523.69 | 3.10 | 3.67 | 0.0829 |
| Specific yield | 850 kWh/kWp/yr (&minus;11%) | 422,103.42 | 3,176,964.93 | 4.27 | 5.13 | 0.1061 |
| Specific yield | 1,050 kWh/kWp/yr (+11%) | 519,796.58 | 5,852,082.45 | 3.46 | 4.11 | 0.0940 |
| Discount rate | 5.00% real | 470,950.00 | 5,884,773.19 | 3.74 | 4.05 | 0.0843 |
| Discount rate | 9.00% real | 470,950.00 | 3,486,799.71 | 3.74 | 4.96 | 0.1130 |
| Self-use share | 70% (export 30%) | 448,837.50 | 3,713,289.14 | 4.01 | 4.79 | 0.0998 |
| Self-use share | 95% (export 5%) | 486,956.50 | 4,360,257.59 | 3.70 | 4.41 | 0.0998 |
| O&M | 15 GBP/kWp/yr (+67%) | 434,950.00 | 3,450,304.31 | 4.14 | 4.93 | 0.0998 |
| O&M | 5 GBP/kWp/yr (&minus;44%) | 494,950.00 | 5,511,677.55 | 3.64 | 4.33 | 0.0998 |

Reading guide: LCOE moves with CAPEX, yield and discount rate (in the O&M and self-use rows LCOE is unchanged at 0.0998 because O&M is operating cost excluded from the LCOE denominator and the energy denominator is unchanged). Discounted payback is reported alongside simple payback because the draft's R11 review flagged that simple payback alone mis-states risk when CAPEX or discount rate shifts.

## 5. Verdict by scenario

- **Base scenario:** NPV = &pound;4,514,524; simple payback 3.74 yr; discounted payback 4.47 yr; LCOE 9.98 p/kWh; IRR 27.65%. — Verdict: **GO**. Returns comfortably clear the 7% hurdle.

- **CAPEX +17% (supply-chain shock, &pound;1,053/kWp):** NPV = &pound;3,208,524; LCOE 11.68 p/kWh; discounted payback 5.27 yr. — Verdict: **GO** if financing is locked before procurement and a fixed-price EPC contract is used.

- **CAPEX &minus;17% (scale discount, &pound;747/kWp):** NPV = &pound;5,820,524; LCOE 8.29 p/kWh; discounted payback 3.67 yr. — Verdict: **STRONG GO**.

- **Yield &minus;11% (low-irradiance site, 850 kWh/kWp):** NPV = &pound;3,176,965; simple payback 4.27 yr; discounted payback 5.13 yr. — Verdict: **GO**, but commissioning a yield assessment before contract is mandatory.

- **Yield +11% (high-irradiance, pitch-optimised, 1,050 kWh/kWp):** NPV = &pound;5,852,082; discounted payback 4.11 yr. — Verdict: **STRONG GO**.

- **Discount 5.00% real:** NPV = &pound;5,884,773; discounted payback 4.05 yr. — Verdict: **STRONG GO**.

- **Discount 9.00% real:** NPV = &pound;3,486,800; discounted payback 4.96 yr. — Verdict: **GO**; remains accretive across the sensitivity band tested.

- **Self-use 70% (poor load match):** NPV = &pound;3,713,289; discounted payback 4.79 yr. — Verdict: **GO**; still accretive but load-shifting via HVAC scheduling is recommended to lift self-use.

- **Self-use 95% (excellent load match):** NPV = &pound;4,360,258; discounted payback 4.41 yr. — Verdict: **STRONG GO**.

- **O&M 15 GBP/kWp/yr (+67%, premium service contract):** NPV = &pound;3,450,304; discounted payback 4.93 yr. — Verdict: **GO**; the uplift does not flip the project under the tested band.

- **O&M 5 GBP/kWp/yr (&minus;44%, minimal service contract):** NPV = &pound;5,511,678; discounted payback 4.33 yr. — Verdict: **STRONG GO**; verify warranty conditions before adopting.

## 6. Call to action

**Request a quote:** [https://tradvolt.com/rfq/](/rfq/)

## 7. Mini certification block

- Modules: Jinko Tiger Neo JKM-N-580N — [IEC 61215](https://www.tuv.com/), [IEC 61730](https://www.tuv.com/); BloombergNEF Tier-1 list, Q4 2024 ([BloombergNEF Tier-1 module list](https://about.bnef.com/blog/tier-1-module-list/)).

- Inverter: [IEC 62109-1/-2](https://webstore.iec.ch/publication/6449); Sungrow SG125HT datasheet.

- Installation: [BS EN 62446](https://shop.bsigroup.com/) commissioning documentation; [IET Code of Practice for Grid-Connected Solar PV, 2nd edition](https://shop.theiet.org/).

- Mounting: [MCS 012](https://www.mcscertified.com/standards) for pitched-roof and flat-roof mounting systems; K2 Systems SingleRail assembly instructions.

- Grid connection: [G99 application](https://www.energynetworks.org/industry-hub/engineering-recommendations/g99) via local Distribution Network Operator.

## 8. HS code block (duty rates marked PENDING)

| Component | HS code (UK) | Duty rate (UK) | Lookup URL | Notes |
| --- | --- | --- | --- | --- |
| Crystalline silicon PV modules (Jinko Tiger Neo JKM-N-580N) | 8541.43.00 | PENDING — lookup | HMRC Trade Tariff 8541.43.00.00 | Confirm current UK Global Tariff rate, anti-dumping/safeguard status, and UKGT preferences before quoting. |
| String / central inverters (Sungrow SG125HT) | 8504.40.95 | PENDING — lookup | HMRC Trade Tariff 8504.40.95.90 | Confirm current UK Global Tariff rate before quoting. |
| Mounting and racking (K2 Systems SingleRail, aluminium) | 7610.90.90 | PENDING — lookup | HMRC Trade Tariff 7610.90.90.90 | Confirm current UK Global Tariff rate before quoting. |
| DC cables (PV-rated) | 8544.49.20 | PENDING — lookup | HMRC Trade Tariff 8544.49.20.00 | Confirm current UK Global Tariff rate before quoting. |

**Lookup instructions:** use the HMRC Trade Tariff service at [https://www.trade-tariff.service.gov.uk/](https://www.trade-tariff.service.gov.uk/) to retrieve the live duty and VAT treatment for each code. Reconcile against any applicable measures (anti-dumping, safeguards, UKGT preferences) at the time of import.