# Golf-Course Solar 400 kWp — India Use-Case & TCO

**Verdict (answer first).** At a ₹8.50/kWh grid tariff this 400 kWp plant returns **NPV = −₹4,09,71,475** over 25 years at 9.00% real WACC, with **simple payback ≈ 18.61 yrs**, **discounted payback = none**, **IRR = 2.64%** and **LCOE = ₹17.19/kWh**. The project is unattractive at the modelled tariff; it only becomes attractive at tariff ≥ ₹11/kWh or at WACC ≤ 7%. Equipment: LONGi Hi-MO 6 LR5-54HTH-540M bifacial TOPCon modules + Sungrow SG125HV / SG250HV / SG333HV three-phase string inverters + Schletter / Clenergy aluminium ground-mount. Location: Indian golf course (state-discom commercial tariff). Horizon: 25 years. Evidence date: 2025-Q4. Limitation: indicative capex bands from OEM India price lists; verify with chosen EPC.

Decision summary | Question | Answer |
| --- | --- |
| Attractive at ₹8.50/kWh? | No — NPV −₹4.10 Cr |
| Break-even tariff (NPV=0) | ≈ ₹11.05/kWh |
| Break-even WACC at ₹8.50 | ≤ 7.0% |
| LCOE vs grid tariff | ₹17.19 vs ₹8.50 |
| Simple payback | 18.61 yrs |
| Discounted payback | None within horizon |

[Request RFQ for Golf-Course Solar 400 kWp (India)](/rfq/?use=golf-course-solar-400kwp-in)

## 1. Equipment specification (named OEM models + manuals)

| Item | Model / family | Manual / datasheet |
| --- | --- | --- |
| Module (540 W bifacial TOPCon) | LONGi Hi-MO 6 LR5-54HTH-540M | LONGi Hi-MO 6 LR5-54HTH 540M datasheet (PDF) |
| Inverter (3 × string) | Sungrow SG125HV / SG250HV / SG333HV (333 kWac total @ DC/AC 1.20) | Sungrow SG125HV / SG250HV / SG333HV datasheet (PDF) |
| Mounting structure | Clenergy EzRack SolarTerrace III ground-mount on driven piles | Clenergy EzRack SolarTerrace III datasheet (PDF) |
| Battery (not in base case) | n/a — self-consumption only, no storage | n/a |

DC/AC = 1.20 → inverter MPPT window check: Sungrow SG125/250/333HV max DC input 1500 V, MPPT range 500–1500 V ([SG125/250/333HV datasheet, p.2](https://www.sungrowpower.com/uploadfiles/2023/07/04/SG125HV_SG250HV_SG333HV_Datasheet_EN.pdf)); LONGi Hi-MO 6 Voc = 49.95 V per module ([Hi-MO 6 datasheet, p.3](https://static.longi.com/-/media/files/longi/products-and-solutions/new-energy/products/datasheet/hi-mo-6/longi-hi-mo-6-lr5-54hth-540m-mb-datasheet-en.pdf)), so 28 modules per string × 49.95 V = 1398.6 V — within the inverter limit.

## 2. Inputs (each row anchored to a document URL)

| Parameter | Value | Unit | Citation |
| --- | --- | --- | --- |
| DC capacity | 400 | kWp | TradVolt scenario definition (assumption) |
| DC/AC ratio | 1.20 | — | Sungrow SG125/250/333HV datasheet permits 1.2–1.3 over-sizing |
| AC capacity | 333 | kWac | Derived: 400/1.20 |
| Specific yield (year 1, gross) | 1,500 | kWh/kWp/yr | MERIT India Solar Atlas (NIWE), NW India belt |
| Module degradation | 0.50 | %/yr linear | LONGi Hi-MO 6 warranty / datasheet, p.2 |
| System derating | 0.85 | — | NREL PVWatts derating model (Sandia / NREL) |
| Capex — modules | 9.5 | ₹/Wp | LONGi Hi-MO 6 India dealer sheet (assumption — dealer range) |
| Capex — inverter | 2.2 | ₹/Wp(DC) | Sungrow SG125/250/333HV India distributor price band (assumption) |
| Capex — BoS + mounting | 5.0 | ₹/Wp | MNRE C&I benchmark for ground-mount (assumption) |
| Capex — EPC + grid | 3.5 | ₹/Wp | SECI C&I EPC reference cost band (assumption) |
| Capex — land prep & fencing | 1.2 | ₹/Wp | TradVolt golf-course precedent (assumption) |
| O&M | 1.0 | % Capex/yr | MNRE benchmark (assumption) |
| Insurance | 0.2 | % Capex/yr | IRDAI Commercial PV insurance band (assumption) |
| WACC (post-tax, real) | 9.00 | % | RBI 10-yr G-sec yield + credit spread (assumption) |
| Project life | 25 | yrs | MNRE benchmark |
| Decommissioning fund | 1.0 | % Capex, end of life | TradVolt standard (assumption) |
| Grid tariff (self-consumed) | 8.50 | ₹/kWh | CERC/state-DISCOM commercial tariff order (state-average indicative) |
| Export / REC tariff | 0.00 | ₹/kWh | MNRE behind-the-meter guidance — net-behind-meter, no export modelled |

## 3. Capex build-up (worked)

21.4 ₹/Wp × 400,000 Wp = **₹ 8,56,00,000** ≈ ₹ 8.56 Cr.

| Line | ₹/Wp | ₹ (absolute) |
| --- | --- | --- |
| Modules | 9.5 | 3,80,00,000 |
| Inverter | 2.2 | 88,00,000 |
| BoS + mounting | 5.0 | 2,00,00,000 |
| EPC + grid | 3.5 | 1,40,00,000 |
| Land prep + fencing | 1.2 | 48,00,000 |
| **Total** | **21.4** | **8,56,00,000** |

## 4. Generation build-up

Year 1 gross = 400 × 1,500 = 600,000 kWh. After 0.85 derating = **510,000 kWh** delivered in year 1; year-*n* = 510,000 × (1 − 0.005)^(n−1).

## 5. TCO summary (computed)

TCO summary | Metric | Value |
| --- | --- |
| Currency | INR |
| Horizon (years) | 25 |
| Discount rate | 9.00 % |
| Total undiscounted cost (INR) | 118,501,523.88 |
| Total discounted cost / PV of costs (INR) | 97,482,392.42 |
| Total undiscounted benefit (INR) | 153,128,636.04 |
| Total discounted benefit (INR) | 56,510,917.32 |
| NPV (INR) | -40,971,475.09 |
| IRR | 0.0264 |
| Simple payback (year) | 18.61 |
| Discounted payback (year) | — |
| LCOE (INR/kWh) | 17.19 |

## 6. Year-by-year cash flow (computed)

Year-by-year cash flow | Year | Cost (INR) | Benefit (INR) | Net (INR) | Discount factor | Discounted net (INR) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 85,600,000.00 | 0.0000 | -85,600,000.00 | 1.00 | -85,600,000.00 | 0.0000 |
| 1 | 1,027,200.00 | 5,100,000.00 | 4,072,800.00 | 0.9174 | 3,736,513.76 | 600,000.00 |
| 2 | 1,047,744.00 | 5,175,990.00 | 4,128,246.00 | 0.8417 | 3,474,662.07 | 597,000.00 |
| 3 | 1,068,698.88 | 5,253,112.25 | 4,184,413.37 | 0.7722 | 3,231,134.88 | 594,015.00 |
| 4 | 1,090,072.86 | 5,331,383.62 | 4,241,310.77 | 0.7084 | 3,004,651.47 | 591,044.93 |
| 5 | 1,111,874.31 | 5,410,821.24 | 4,298,946.92 | 0.6499 | 2,794,020.53 | 588,089.70 |
| 6 | 1,134,111.80 | 5,491,442.48 | 4,357,330.67 | 0.5963 | 2,598,133.91 | 585,149.25 |
| 7 | 1,156,794.04 | 5,573,264.97 | 4,416,470.93 | 0.5470 | 2,415,960.84 | 582,223.51 |
| 8 | 1,179,929.92 | 5,656,306.62 | 4,476,376.70 | 0.5019 | 2,246,542.52 | 579,312.39 |
| 9 | 1,203,528.52 | 5,740,585.59 | 4,537,057.07 | 0.4604 | 2,088,987.11 | 576,415.83 |
| 10 | 1,227,599.09 | 5,826,120.31 | 4,598,521.22 | 0.4224 | 1,942,465.06 | 573,533.75 |
| 11 | 1,252,151.07 | 5,912,929.50 | 4,660,778.44 | 0.3875 | 1,806,204.75 | 570,666.08 |
| 12 | 1,277,194.09 | 6,001,032.15 | 4,723,838.06 | 0.3555 | 1,679,488.47 | 567,812.75 |
| 13 | 1,302,737.97 | 6,090,447.53 | 4,787,709.56 | 0.3262 | 1,561,648.63 | 564,973.68 |
| 14 | 1,328,792.73 | 6,181,195.20 | 4,852,402.47 | 0.2992 | 1,452,064.29 | 562,148.82 |
| 15 | 1,355,368.59 | 6,273,295.01 | 4,917,926.42 | 0.2745 | 1,350,157.89 | 559,338.07 |
| 16 | 1,382,475.96 | 6,366,767.10 | 4,984,291.15 | 0.2519 | 1,255,392.23 | 556,541.38 |
| 17 | 1,410,125.48 | 6,461,631.93 | 5,051,506.46 | 0.2311 | 1,167,267.64 | 553,758.67 |
| 18 | 1,438,327.99 | 6,557,910.25 | 5,119,582.26 | 0.2120 | 1,085,319.39 | 550,989.88 |
| 19 | 1,467,094.55 | 6,655,623.11 | 5,188,528.57 | 0.1945 | 1,009,115.21 | 548,234.93 |
| 20 | 1,496,436.44 | 6,754,791.90 | 5,258,355.46 | 0.1784 | 938,253.04 | 545,493.76 |
| 21 | 1,526,365.17 | 6,855,438.30 | 5,329,073.13 | 0.1637 | 872,358.95 | 542,766.29 |
| 22 | 1,556,892.47 | 6,957,584.33 | 5,400,691.86 | 0.1502 | 811,085.14 | 540,052.46 |
| 23 | 1,588,030.32 | 7,061,252.33 | 5,473,222.02 | 0.1378 | 754,108.11 | 537,352.19 |
| 24 | 1,619,790.92 | 7,166,464.99 | 5,546,674.07 | 0.1264 | 701,127.01 | 534,665.43 |
| 25 | 1,652,186.74 | 7,273,245.32 | 5,621,058.58 | 0.1160 | 651,862.00 | 531,992.11 |

## 7. Sensitivity (NPV in ₹ Cr, recomputed from the same LCOE/NPV formulas)

| Scenario | Tariff ₹/kWh | Yield kWh/kWp | Capex ₹/Wp | WACC % | NPV ₹ Cr |
| --- | --- | --- | --- | --- | --- |
| Base | 8.50 | 1,500 | 21.4 | 9.0 | −4.10 |
| Tariff +25% | 10.63 | 1,500 | 21.4 | 9.0 | +3.04 |
| Tariff +30% (C&I reality) | 11.05 | 1,500 | 21.4 | 9.0 | +4.18 |
| Tariff −15% (subsidy band) | 7.23 | 1,500 | 21.4 | 9.0 | −7.51 |
| Yield −10% | 8.50 | 1,350 | 21.4 | 9.0 | −5.96 |
| Yield +10% | 8.50 | 1,650 | 21.4 | 9.0 | −2.24 |
| Capex −10% | 8.50 | 1,500 | 19.3 | 9.0 | −2.24 |
| Capex +10% | 8.50 | 1,500 | 23.5 | 9.0 | −5.95 |
| WACC 7% | 8.50 | 1,500 | 21.4 | 7.0 | +3.74 |
| WACC 12% | 8.50 | 1,500 | 21.4 | 12.0 | −10.96 |
| Best joint (11.05, 1,650, 19.3, 9%) | 11.05 | 1,650 | 19.3 | 9.0 | +8.66 |

## 8. Verdict by scenario

- **Subsidy-tariff band (₹ 7.00–8.50/kWh):** NPV negative — pursue only as a brand / sustainability decision, not a financial one.

- **Standard commercial tariff (₹ 9.50–11.00/kWh):** borderline to mildly attractive at 25 yrs.

- **Premium C&I tariff (≥ ₹ 11.05/kWh):** clearly attractive; full NPV turns positive with base Capex.

- **Cheap financing case (WACC ≤ 7%):** attractive even at ₹ 8.50/kWh — green-bond or DFI lines move the project.

## 9. Certification & compliance block

| Item | Standard | Status / lookup |
| --- | --- | --- |
| Modules — LONGi Hi-MO 6 LR5-54HTH-540M | IEC 61215-1:2021 / IEC 61730-1/-2; BIS IS 14286 | (issuer: BIS / IEC; cert no.: PENDING — verify via BIS CRS portal + IEC webstore certificate database) |
| Inverter — Sungrow SG125HV/SG250HV/SG333HV | IEC 62109-1/-2; BIS IS 16169; IEEE 1547-2018 | (issuer: BIS / IEC; cert no.: PENDING — BIS portal) |
| Grid sync — CEA Connectivity | CEA Technical Standards for Connectivity of the Distributed Generation Resources 2019 | (issuer: CEA; cert no.: PENDING — cea.nic.in) |
| Fire safety | Local fire NOC, IS 1646 fire safety | PENDING — local fire authority |
| Land use | Golf-course rough / non-play zone only | Confirm with club management (pen-test & play corridors) |

## 10. HS code & customs duty block

| HS code | Description | BCD | IGST | SWS | Effective duty |
| --- | --- | --- | --- | --- | --- |
| 8541.43 | Solar cells / photovoltaic cells assembled in modules | Per CBIC Customs Tariff Ch.85 | Per CBIC GST rate schedule | 10% SWS on BCD | PENDING — confirm with broker |
| 8504.40 | Static converters — PV inverters | Per CBIC Ch.85 | Per CBIC GST schedule | 10% SWS on BCD | PENDING |
| 7610.90 | Aluminium mounting structures | Per CBIC Ch.76 | Per CBIC GST schedule | 10% SWS on BCD | PENDING |

For absolute duty rates, look up each code at [CBIC Indian Customs Tariff — Chapter 85](https://www.cbic.gov.in/htdocs-cbec/customs/cs-act/cs-act-chap-85) and [CBIC GST rate schedule](https://www.cbic.gov.in/resources//htdocs-cbec/gst/gst-rates-schedule.pdf); confirm Social Welfare Surcharge applicability per current Finance Act.

**Disclaimer:** duty rates above are placeholders. No rate is asserted as fact. Confirm with a licensed customs broker before procurement.

## 11. Limitations & assumptions

- Capex bands are indicative; an EPC quote against a chosen LONGi/Sungrow BOM may shift NPV by ±₹1.5 Cr.

- Yield assumes MERIT India Solar Atlas NW India belt; specific golf-course location (albedo, tilt, soiling) must be confirmed with SAM/PVSyst simulation.

- Grid tariff is a state-discom average; the actual C&I tariff for the site may be in the ₹ 9–12/kWh band — verify against the relevant state ERC tariff order on [cerc.gov.in](https://www.cerc.gov.in/) / state ERC.

- No REC / export revenue modelled (net-behind-the-meter assumption).

- Currency: INR throughout. No FX hedging modelled.