# Import 20 kW Hybrid Inverter from China to Namibia — Resort-Hybrid-20 kW Use Case: TCO & Landed Cost

**Verdict (illustrative, 25-year horizon, 8% discount rate, evidence date 2026-09-21):** Sungrow SH20T 20 kW hybrid inverter, resort site (CN → Walvis Bay / Windhoek). **NPV ≈ USD 5,201; simple payback ≈ 10.12 years; discounted payback ≈ 19.74 years; LCOE ≈ USD 0.0912 / kWh.** All duty/VAT rows PENDING — confirm against Namibia Customs at time of import. Financial figures are scenario model output and computed.

## Decision table (key figures)

| Metric | Value |
| --- | --- |
| Equipment model (named) | Sungrow SH20T (three-phase 20 kW hybrid inverter) |
| Location | Namibia — Walvis Bay / Windhoek delivery |
| Horizon | 25 years |
| Evidence date | 2026-09-21 |
| Limitation | All duties/VAT PENDING — Namibia Customs lookup at import |
| Currency | USD |
| Discount rate | 8.00 % |
| Total undiscounted cost | USD 60,724.54 |
| Total discounted cost (PV of costs) | USD 51,433.54 |
| Total undiscounted benefit | USD 140,365.36 |
| Total discounted benefit | USD 56,634.49 |
| NPV | USD 5,200.96 |
| IRR | 0.0923 |
| Simple payback | 10.12 years |
| Discounted payback | 19.74 years |
| LCOE | USD 0.0912 / kWh |

### Get a binding quote & datasheet

Submit the RFQ form — we reply within 48 hours with CIF price, lead time, and matching cert pack for the Sungrow SH20T.

[Request Quote — replies in 48h](/rfq/?product=sungrow-sh20t&amp;dest=namibia&amp;subject=RFQ%20-%20Sungrow%20SH20T%2020kW%20to%20Namibia) [Sungrow SH20T Datasheet (PDF)](https://en.sungrowpower.com/Uploads/202407/SH5T_8T_10T_12T_15T_20T_Datasheet.pdf)

## 1. Equipment model — named & cited

| Field | Value |
| --- | --- |
| OEM | Sungrow Power Supply Co., Ltd. |
| Model family / SKU | SH20T (three-phase hybrid inverter, 20 kW) |
| Manual / datasheet title | Sungrow SH5T / SH8T / SH10T / SH12T / SH15T / SH20T Datasheet | https://en.sungrowpower.com/Uploads/202407/SH5T_8T_10T_12T_15T_20T_Datasheet.pdf |
| Product page | https://en.sungrowpower.com/product/8/residential-pv-inverter |
| Battery chemistry (paired BoS) | LFP — e.g., Sungrow SBR series battery module |
| Operating limits (per OEM datasheet) | Battery port voltage range, MPPT voltage window, max DC voltage, torque values for DC/AC/battery terminals — see OEM datasheet, revision as published at the URL above |
| Why this model (not "configurable OEM") | SH20T is a publicly marketed Sungrow SKU with a published datasheet covering exactly the 20 kW three-phase hybrid class referenced in this analysis |

## 2. TCO summary (computed — scenario model)

TCO summary | Metric | Value |
| --- | --- |
| Currency | USD |
| Horizon (years) | 25 |
| Discount rate | 8.00 % |
| Total undiscounted cost (USD) | 60,724.54 |
| Total discounted cost / PV of costs (USD) | 51,433.54 |
| Total undiscounted benefit (USD) | 140,365.36 |
| Total discounted benefit (USD) | 56,634.49 |
| NPV (USD) | 5,200.96 |
| IRR | 0.0923 |
| Simple payback (year) | 10.12 |
| Discounted payback (year) | 19.74 |
| LCOE (USD/kWh) | 0.0912 |

## 3. Year-by-year cash flow (computed — scenario model)

Year-by-year cash flow | Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 45,350.00 | 0.0000 | -45,350.00 | 1.00 | -45,350.00 | 0.0000 |
| 1 | 480.00 | 4,674.91 | 4,194.91 | 0.9259 | 3,884.18 | 54,999.00 |
| 2 | 489.60 | 4,744.57 | 4,254.97 | 0.8573 | 3,647.95 | 54,724.00 |
| 3 | 499.39 | 4,815.27 | 4,315.87 | 0.7938 | 3,426.08 | 54,450.38 |
| 4 | 509.38 | 4,887.01 | 4,377.63 | 0.7350 | 3,217.69 | 54,178.13 |
| 5 | 519.57 | 4,959.83 | 4,440.26 | 0.6806 | 3,021.97 | 53,907.24 |
| 6 | 529.96 | 5,033.73 | 4,503.77 | 0.6302 | 2,838.14 | 53,637.71 |
| 7 | 540.56 | 5,108.73 | 4,568.18 | 0.5835 | 2,665.49 | 53,369.52 |
| 8 | 551.37 | 5,184.85 | 4,633.48 | 0.5403 | 2,503.33 | 53,102.67 |
| 9 | 562.40 | 5,262.11 | 4,699.71 | 0.5002 | 2,351.03 | 52,837.16 |
| 10 | 573.64 | 5,340.51 | 4,766.87 | 0.4632 | 2,207.98 | 52,572.97 |
| 11 | 585.12 | 5,420.09 | 4,834.97 | 0.4289 | 2,073.64 | 52,310.11 |
| 12 | 596.82 | 5,500.85 | 4,904.03 | 0.3971 | 1,947.46 | 52,048.56 |
| 13 | 608.76 | 5,582.81 | 4,974.05 | 0.3677 | 1,828.95 | 51,788.31 |
| 14 | 620.93 | 5,665.99 | 5,045.06 | 0.3405 | 1,717.65 | 51,529.37 |
| 15 | 633.35 | 5,750.42 | 5,117.07 | 0.3152 | 1,613.11 | 51,271.72 |
| 16 | 646.02 | 5,836.10 | 5,190.08 | 0.2919 | 1,514.93 | 51,015.37 |
| 17 | 658.94 | 5,923.05 | 5,264.12 | 0.2703 | 1,422.73 | 50,760.29 |
| 18 | 672.12 | 6,011.31 | 5,339.19 | 0.2502 | 1,336.13 | 50,506.49 |
| 19 | 685.56 | 6,100.88 | 5,415.32 | 0.2317 | 1,254.79 | 50,253.96 |
| 20 | 699.27 | 6,191.78 | 5,492.51 | 0.2145 | 1,178.41 | 50,002.69 |
| 21 | 713.25 | 6,284.04 | 5,570.78 | 0.1987 | 1,106.67 | 49,752.67 |
| 22 | 727.52 | 6,377.67 | 5,650.15 | 0.1839 | 1,039.29 | 49,503.91 |
| 23 | 742.07 | 6,472.70 | 5,730.63 | 0.1703 | 976.01 | 49,256.39 |
| 24 | 756.91 | 6,569.14 | 5,812.23 | 0.1577 | 916.58 | 49,010.11 |
| 25 | 772.05 | 6,667.02 | 5,894.97 | 0.1460 | 860.77 | 48,765.06 |

Discount factor = 1 / (1 + 0.08)year. Net = Benefit − Cost. Discounted net = Net × Discount factor. Energy column = annual PV generation (kWh) used in the benefit calculation.

## 4. Use case profile

| Parameter | Value |
| --- | --- |
| Site | Namibian resort (e.g., Erongo / Zambezi region) |
| Load | Lodges, kitchen cold-chain, lighting, water pumping |
| PV array (typical pairing) | ~25–30 kWp monocrystalline |
| Battery (LFP) | ~40–60 kWh LFP rack |
| Inverter role | PV + battery + diesel-genset AC-coupling, three-phase 400 V |
| Operating hours target | ≥ 12 h/day autonomous, with genset back-up |

## 5. CapEx (landed into Namibia)

| Line | Description | USD (illustrative) |
| --- | --- | --- |
| EXW unit (1 pc) | Sungrow SH20T 20 kW three-phase hybrid inverter | PENDING — RFQ |
| Quantity | 1 pc (typical resort install) | 1 |
| Sea freight CN → Walvis Bay | 1 pc in wooden crate, LCL or 20′ GP (verify dims) | PENDING — RFQ |
| Insurance | 0.3 % of CIF (typical) | PENDING — RFQ |
| CIF value | EXW + freight + insurance | PENDING — RFQ |
| Import duty | Namibia Customs — PENDING — lookup | PENDING |
| VAT | Namibia VAT — PENDING — lookup | PENDING |
| Customs broker + WH handling | Walvis Bay or Windhoek ICD | ~ USD 250–450 |
| Road transport to site | Walvis Bay → resort (variable) | PENDING — RFQ |
| Install + commissioning | By Namibian EPC partner, not Tradvolt scope | By buyer |
| **Indicative landed cost (DDP-like, ex-installation)** | CIF + duty + VAT + broker + inland | PENDING — RFQ |

## 6. OpEx (annual) — bounded defaults

| Item | Frequency | USD / year (illustrative) |
| --- | --- | --- |
| Firmware updates / remote monitoring | Included by Sungrow (iSolarCloud) — verify SKU | 0 |
| Preventive service (filter, fans, torque) | Annual by local EPC | ~ 120–250 |
| Spare parts (fans, contactors) | Annual allowance | ~ 80–150 |
| Insurance (asset) | Annual | ~ 0.5 % of landed CapEx |
| Diesel genset fuel (residual, post-hybrid) | Reduced vs. diesel-only | Site-specific |
| **Total OpEx ex-fuel** | Year 1–25 | **~ 200–400 + insurance** |

## 7. Model inputs — every numeric input with source row

| Input | Value | Type | Source / lookup path |
| --- | --- | --- | --- |
| Discount rate (WACC) | 8.00 % | Model assumption | Scenario model default — bounded assumption |
| Horizon | 25 years | Model assumption | Scenario model default — bounded assumption |
| Year 0 CapEx (USD) | 45,350.00 | Model assumption | Scenario model default — bounded assumption |
| Year 1 OpEx (USD) | 480.00 | Model assumption | Scenario model default — bounded assumption |
| OpEx escalation | 2.00 % / yr | Model assumption | Scenario model default — bounded assumption |
| Diesel price (NAD/L) | 25.00 (base); 22.00 (low); 28.00 (high) | PENDING — lookup | Lookup path: Namibia Petroleum Corporation / Ministry of Mines and Energy publications at import time — https://www.mme.gov.na/divisions/energy |
| Namibia PV yield | 2,200 kWh/kWp/yr | Model assumption (bounded) | Placeholder default — confirm against a country-specific irradiance dataset such as the Global Solar Atlas (https://globalsolaratlas.info/download/namibia) or Solargis country file |
| Year-1 benefit (USD) | 4,674.91 | Model assumption | Scenario model default — bounded assumption |
| Benefit escalation | 1.49 % / yr | Model assumption | Scenario model default — bounded assumption |
| Year-1 energy (kWh) | 54,999.00 | Model assumption | Scenario model default — bounded assumption |
| PV degradation | 0.50 % / yr | Model assumption (bounded default) | Typical industry default for monocrystalline modules — confirm against module manufacturer datasheet (e.g., LONGi, Jinko, Trina) at RFQ |
| Residual value (amount) | PENDING — RFQ | Model assumption (bounded default) | Scenario model default = 0 — bounded assumption |
| Residual value (year) | PENDING — RFQ | Model assumption (bounded default) | Scenario model default = end of horizon — bounded assumption |
| asset.pv.degradation_pct_per_year | 0.50 % | Model assumption (bounded default) | Industry-typical default — bounded assumption |
| asset.pv.tariff_per_kwh (self-consumption) | PENDING — buyer input | Model assumption (bounded default) | Not stated in draft — bounded assumption set to displaced-diesel-equivalent in the model |
| asset.pv.tariff_escalation_pct | 1.49 % | Model assumption (bounded default) | Scenario model default — bounded assumption |
| asset.pv.self_consumption_pct | PENDING — buyer input | Model assumption (bounded default) | Not stated in draft — bounded assumption set by model; buyer to confirm against site load profile |
| asset.pv.export_tariff_per_kwh | PENDING — buyer input | Model assumption (bounded default) | Not stated in draft — Namibia export tariff to be confirmed with ECB / Nampower; bounded assumption set to 0 in the model (no export revenue assumed) |

All blue cells are model assumptions (bounded defaults), not sourced facts. All yellow cells are PENDING and require buyer / regulator lookup before relying on the TCO.

## 8. Compliance & certifications

| Standard | Scope | Document / issuer |
| --- | --- | --- |
| IEC 62109-1 / -2 | Safety of power converters for use in photovoltaic power systems | IEC Webstore — IEC 62109-1:2010 / IEC 62109-2:2011 (https://webstore.iec.ch/publication/6391); certificate IDs must appear on the OEM datasheet |
| IEC 61727 / IEC 62116 | Grid interconnection & anti-islanding | IEC Webstore — IEC 61727:2004 (https://webstore.iec.ch/publication/3280) and IEC 62116:2014 (https://webstore.iec.ch/publication/22737); certificate IDs on OEM datasheet |
| CE marking | EU conformity (EMC + LVD) | EU Regulation 765/2008 (https://eur-lex.europa.eu/eli/reg/2008/765/oj) and Decision 768/2008/EC (https://eur-lex.europa.eu/eli/dec/2008/768/oj); verify on datasheet |
| Namibia ECB / Nampower grid code | Local utility approval | Electricity Act, 2007 (Namibia), administered by the Electricity Control Board — https://www.ecb.org.na/ — buyer to confirm connection requirements at RFQ |
| Battery transport (UN 38.3) | Lithium battery transport safety | UN Manual of Tests and Criteria, Part III, 38.3 — https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria — required for sea-freight (Walvis Bay) |

Tradvolt does not assert any certificate number, test lab, or ranking on this page. Confirm the exact certificate IDs from the OEM datasheet supplied with the RFQ reply.

## 9. Duty / HS / VAT block (Namibia)

| Item | Reference | SoT |
| --- | --- | --- |
| HS national line (typical chapter 85.04 — static converters / inverters) | PENDING — lookup | Lookup path: USITC HTS (https://hts.usitc.gov/?query=inverter) for the US/WCO 6-digit baseline; confirm against the official Namibia Customs & Excise tariff at import (https://www.customs.gov.na/) |
| Import duty | PENDING — lookup | Namibia Customs & Excise (https://www.customs.gov.na/) |
| VAT | PENDING — lookup | Namibia Revenue Agency — VAT Act reference (https://www.namra.org/) |
| EPZ / renewable-energy rebate eligibility | PENDING — lookup | Ministry of Industrialisation & Trade / Namibia Investment Promotion & Development Board (https://www.nipdb.com/) |

All duty and VAT rates on this page are marked PENDING — lookup. Confirm the exact HS national line, duty rate, VAT rate, and any rebates at the time of import.

## 10. FAQ

### What is the typical payback for a 20 kW resort hybrid system in Namibia?

On the scenario model outputs above, illustrative simple payback is **10.12 years** and discounted payback (8 % WACC) is **19.74 years** over a 25-year horizon. NPV ≈ **USD 5,201**; LCOE ≈ **USD 0.0912 / kWh**. These are NOT a quote.

### Which HS code applies to a 20 kW hybrid inverter imported into Namibia?

The exact HS national line must be confirmed against the official Namibia Customs tariff at the time of import. All duty/VAT rows above are PENDING — lookup.

### Which certifications should I request for Namibia-bound shipments?

At minimum: IEC 62109-1/-2 (safety), IEC 61727 / IEC 62116 (grid interconnection), and CE marking. Confirm certificate numbers on the Sungrow SH20T datasheet before issuing the PO.

### Does Tradvolt publish a fixed retail price?

No. Pricing depends on SKU, qty, Incoterm, cert pack, and destination — submit the RFQ form for a binding quote.

### Can OpEx savings exceed diesel generator running costs?

In Namibian resort sites the displaced fuel is typically diesel. The savings shown are ILLUSTRATIVE and depend on a verified diesel price and average runtime — both must be confirmed by the buyer.

## 11. RFQ & datasheet

### Need the datasheet first?

Download the Sungrow SH20T datasheet to evaluate dimensions, MPPT count, battery port rating, and supported communication protocols before requesting a quote.

[Request Quote — replies in 48h](/rfq/?product=sungrow-sh20t&amp;dest=namibia&amp;subject=RFQ%20-%20Sungrow%20SH20T%2020kW%20to%20Namibia) [Sungrow SH20T Datasheet (PDF)](https://en.sungrowpower.com/Uploads/202407/SH5T_8T_10T_12T_15T_20T_Datasheet.pdf)

## 12. Sources & claim rows

| Claim | Source | URL | Accessed |
| --- | --- | --- | --- |
| 20 kW three-phase hybrid inverter specification (Sungrow SH20T) | Sungrow SH5T/SH8T/SH10T/SH12T/SH15T/SH20T Datasheet | https://en.sungrowpower.com/Uploads/202407/SH5T_8T_10T_12T_15T_20T_Datasheet.pdf | 2026-09-21 |
| Sungrow residential PV inverter product family | Sungrow Power Supply Co., Ltd. — product page | https://en.sungrowpower.com/product/8/residential-pv-inverter | 2026-09-21 |
| IEC 62109 (safety of power converters for use in PV power systems) | IEC Webstore publication page | https://webstore.iec.ch/publication/6391 | 2026-09-21 |
| IEC 61727 (PV utility-interface characteristics) | IEC Webstore publication page | https://webstore.iec.ch/publication/3280 | 2026-09-21 |
| IEC 62116 (anti-islanding test procedure) | IEC Webstore publication page | https://webstore.iec.ch/publication/22737 | 2026-09-21 |
| CE marking framework (EU) | EUR-Lex — Regulation (EC) No 765/2008 | https://eur-lex.europa.eu/eli/reg/2008/765/oj | 2026-09-21 |
| CE marking framework — Decision 768/2008/EC | EUR-Lex — Decision No 768/2008/EC | https://eur-lex.europa.eu/eli/dec/2008/768/oj | 2026-09-21 |
| UN Manual of Tests and Criteria, Part III, 38.3 (lithium battery transport) | UNECE | https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria | 2026-09-21 |
| Namibia utility / grid-code authority | Electricity Control Board (ECB), Namibia — Electricity Act, 2007 | https://www.ecb.org.na/ | 2026-09-21 |
| Namibia Customs & Excise (import duty / HS lookup) | Namibia Customs & Excise — official portal | https://www.customs.gov.na/ | 2026-09-21 |
| USITC HTS baseline for inverter HS line (reference only) | USITC Harmonized Tariff Schedule search | https://hts.usitc.gov/?query=inverter | 2026-09-21 |
| Namibia VAT administration | Namibia Revenue Agency (NAMRA) | https://www.namra.org/ | 2026-09-21 |
| Diesel price reference (Namibia) | Ministry of Mines and Energy (Namibia) — Petroleum division | https://www.mme.gov.na/divisions/energy | 2026-09-21 |
| Namibia PV yield (2,200 kWh/kWp/yr) — bounded assumption | Global Solar Atlas — Namibia country file | https://globalsolaratlas.info/download/namibia | 2026-09-21 |

All non-cited numerical inputs (EXW unit price, freight, insurance, broker, inland, diesel price, duty rate, VAT rate) are marked PENDING on this page and must be confirmed against the OEM datasheet, a Tradvolt RFQ reply, and the official Namibia Customs tariff at time of import. Financial figures in the TCO summary and cash-flow tables are the computed output of the scenario model.