title: "Import 580W Solar Panels from China to Czechia — Commercial Rooftop TCO & Landed Cost Blueprint | Tradvolt"
source_url: "https://tradvolt.com/en/tco/import-580w-solar-panels-from-china-to-czechia-commercial-rooftop-tco-landed-cost-blueprint-tradvolt/"
lang: "en"
description: "B2B TCO and landed-cost blueprint for importing Jinko Tiger Neo 580W modules + Sungrow string inverter from China to Czechia for a 290 kWp commercial rooftop project. 25-year horizon, EUR-denominated."
generator: "tradvolt-tier-c-edge-md"
---

[Tradvolt](/) › [Solar Import Guide](/guides/) › 580W Commercial Rooftop — Czechia

# Import 580W Solar Panels from China to Czechia — Commercial Rooftop TCO & Landed Cost Blueprint

**Verdict.** A 290 kWp commercial rooftop in Czechia built with **Jinko Tiger Neo JKM580N-72HL4-BDV** modules and **Sungrow SG250HX** string inverters, imported from China under typical CN→CZ landed-cost terms, returns **NPV = 313,001 EUR**, **simple payback = 4.70 yr**, **discounted payback = 6.10 yr**, **IRR = 21.67 %**, and **LCOE = 0.0673 EUR/kWh** over a 25-year horizon at 8.00 % discount. Equipment: Jinko Tiger Neo JKM580N-72HL4-BDV modules + Sungrow SG250HX inverters. Location: Czechia (290 kWp commercial rooftop). Horizon: 25 years. Evidence date: 2026-09-22. Limitation: numeric values come from the computed Tradvolt TCO model and the inputs in §3 only; do not transpose to other equipment, roofs or tariffs without rerunning the model.

Decision summary — 290 kWp CN→CZ commercial rooftop, 25-year horizon | Decision metric | Value | Source |
| --- | --- | --- |
| Project | 290 kWp commercial rooftop, Czechia | Inputs §3 |
| Module | Jinko Tiger Neo 580 W — JKM580N-72HL4-BDV | JinkoSolar product page |
| Inverter | Sungrow SG250HX (250 kW, 12 MPPT, 1500 V DC) | Sungrow product page |
| Horizon | 25 yr | Model assumption (bounded) |
| Discount rate | 8.00 % | Model assumption (bounded) |
| Total undiscounted cost | 220,000.00 EUR | scenario TCO model |
| PV of costs (discounted) | 220,000.00 EUR | scenario TCO model |
| Total undiscounted benefit | 1,296,174.44 EUR | scenario TCO model |
| PV of benefits (discounted) | 533,001.35 EUR | scenario TCO model |
| **NPV** | **313,001.35 EUR** | scenario TCO model |
| IRR | 0.2167 | scenario TCO model |
| Simple payback | 4.70 yr | scenario TCO model |
| Discounted payback | 6.10 yr | scenario TCO model |
| LCOE | 0.0673 EUR/kWh | scenario TCO model |

[Request Quote — replies in 48h](/rfq/)

## 1. Bundle definition (module + inverter pair)

The arithmetic in §3 is anchored on a real, publicly marketed OEM pairing. SKU-level certificate numbers and the issuing notified body are listed in §4. Substitute components only after re-running the scenario TCO model.

Equipment bundle | Role | Model | Family | OEM landing page |
| --- | --- | --- | --- |
| PV module | JKM580N-72HL4-BDV (Tiger Neo, n-type TOPCon, 580 Wp, 144 cells, 1500 V DC, mc4) | Jinko Tiger Neo 580W | JinkoSolar |
| String inverter | SG250HX (250 kW, 3-phase, 12 MPPT, 1500 V DC, IP66) | Sungrow 1500 V DC commercial string | Sungrow string inverter range |
| Mounting (informational) | K2 Systems N-Rack ground-mount / S-Rack rail (commercial flat/pitched roof) | K2 Systems | K2 Systems N-Rack system |

## 2. CapEx structure

CapEx is a single illustrative 220,000 EUR lump placed at t=0 in the scenario model. Line-item allocation below is presented as a procurement checklist; the COMMITTED TCO value is the 220,000 EUR total only — do not sum the placeholder line items to that total.

CapEx line-item checklist (placeholder unit prices — RFQ to bind) | Line item | Quantity | Unit price (EUR) | Subtotal (EUR) | Source / note |
| --- | --- | --- | --- | --- |
| Jinko Tiger Neo JKM580N-72HL4-BDV | 500 pcs (290 kWp) | RFQ | RFQ | JinkoSolar product page |
| Sungrow SG250HX string inverter | 1 pc (250 kW) | RFQ | RFQ | Sungrow product page |
| K2 Systems racking + rail kit (commercial roof) | 1 lot | RFQ | RFQ | K2 Systems |
| DC cabling, AC cabling, conduit, mc4 | 1 lot | RFQ | RFQ | Per BoS layout |
| Combiner box, SPD, AC/DC disconnects, rapid shutdown | 1 lot | RFQ | RFQ | Per BoS layout |
| Monitoring / data logger (Sungrow iSolarCloud gateway) | 1 lot | RFQ | RFQ | Sungrow |
| Sea freight CN → Hamburg/Bremerhaven (FCL) | 1 shipment | RFQ | RFQ | FIATA forwarder quote |
| Inland haulage port → project site, CZ | 1 shipment | RFQ | RFQ | Forwarder quote |
| Marine insurance (Institute Cargo Clauses (A)) — model assumption, bounded | 1 policy | bounded assumption | bounded assumption | IUA policy clauses library |
| EU customs duty (HS 8541.43 — see §5) | 1 lot | TARIC lookup | TARIC lookup | EU TARIC consultation |
| Czech VAT (DPH) | 1 lot | Finanční správa lookup | lookup | Finanční správa |
| Customs broker fee | 1 lot | RFQ | RFQ | Broker quote |
| EPC install, commissioning, grid hook-up | 1 project | RFQ | RFQ | EPC quote |
| **Total CapEx committed to TCO model** |  |  | **220,000.00 EUR** | scenario TCO model input |

### Claim rows — CapEx structure & bundle

| Claim | Src: NAME | URL | accessed |
| --- | --- | --- | --- |
| Jinko Tiger Neo 580 W product family exists and is publicly marketed. | JinkoSolar — Tiger Neo product page | https://www.jinkosolar.com/en/ | 2026-09-22 |
| Sungrow SG250HX is a publicly marketed 250 kW three-phase, 1500 V DC string inverter in the Sungrow commercial string inverter range. | Sungrow Power — string inverter range | https://www.sungrowpower.com/en/products/string-inverter | 2026-09-22 |
| K2 Systems markets rail-based PV mounting systems for commercial roofs (N-Rack / S-Rack). | K2 Systems — N-Rack system page | https://k2-systems.com/en/product-solutions/k2-n-rack-system/ | 2026-09-22 |
| CapEx is presented as an illustrative 220,000 EUR lump in the scenario TCO model. | Tradvolt scenario TCO model | https://tradvolt.com/rfq/ (model inputs disclosed on request) | 2026-09-22 |
| Marine cargo insurance under Institute Cargo Clauses (A) is the canonical all-risks marine cargo cover. | IUA — Institute Cargo Clauses (A) clauses library | https://www.iua.co.uk/clauses | 2026-09-22 |
| CN→EU PV module shipments are commonly booked CIF Hamburg/Bremerhaven with inland haulage, DAP project-site CZ, or CIP Praha per ICC Incoterms 2020. | ICC — Incoterms 2020 rules | https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | 2026-09-22 |

## 3. TCO model — inputs, cash-flow table, summary

### 3.1 Model inputs (the only inputs the scenario TCO model used)

Model inputs (bounded assumptions where the draft did not state a value) | Input | Value | Unit | Class |
| --- | --- | --- | --- |
| Module | Jinko Tiger Neo JKM580N-72HL4-BDV (580 Wp) | — | OEM selection |
| Inverter | Sungrow SG250HX (250 kW, 1500 V DC, 12 MPPT) | — | OEM selection |
| Module count | 500 | pcs | Model assumption (bounded) |
| System size | 500 × 580 / 1000 = 290 | kWp | Computed |
| Specific yield (CZ commercial roof) | 1,100 | kWh/kWp/yr | Model assumption (bounded — PVGIS-class) |
| Self-consumption ratio | 70 | % | Model assumption (bounded — commercial day-load profile) |
| Import tariff | 0.18 | EUR/kWh | Model assumption (bounded — CZ commercial band) |
| Export tariff / compensation | 0.06 | EUR/kWh | Model assumption (bounded) |
| PV module annual degradation | 0.5 | %/yr | Model assumption (bounded — TOPCon class) |
| Tariff escalation | 1.0 | %/yr | Model assumption (bounded) |
| CapEx (illustrative lump at t=0) | 220,000.00 | EUR | Model assumption (bounded) |
| Fixed annual opex | 0.00 | EUR/yr | Model assumption (bounded — fixed opex dropped for this summary) |
| Replacement reserve at year 12 | DROPPED-ITEM | EUR | Model assumption (bounded — inverter mid-life replacement dropped) |
| Residual value | 0.00 | EUR at horizon end | Model assumption (bounded — residual dropped) |
| Horizon | 25 | years | Model assumption (bounded) |
| Discount rate | 8.00 | % | Model assumption (bounded) |
| Yield year 1 | 319,000.00 | kWh | Computed (290 × 1,100) |
| Year-1 benefit | 45,936.00 | EUR | Computed (223,300 × 0.18 + 95,700 × 0.06) |

### 3.2 scenario TCO summary (copy verbatim)

TCO summary | Metric | Value |
| --- | --- |
| Currency | EUR |
| Horizon (years) | 25 |
| Discount rate | 8.00 % |
| Total undiscounted cost (EUR) | 220,000.00 |
| Total discounted cost / PV of costs (EUR) | 220,000.00 |
| Total undiscounted benefit (EUR) | 1,296,174.44 |
| Total discounted benefit (EUR) | 533,001.35 |
| NPV (EUR) | 313,001.35 |
| IRR | 0.2167 |
| Simple payback (year) | 4.70 |
| Discounted payback (year) | 6.10 |
| LCOE (EUR/kWh) | 0.0673 |

### 3.3 Year-by-year cash flow (copy verbatim)

Year-by-year cash flow | Year | Cost (EUR) | Benefit (EUR) | Net (EUR) | Discount factor | Discounted net (EUR) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 220,000.00 | 0.0000 | -220,000.00 | 1.00 | -220,000.00 | 0.0000 |
| 1 | 0.0000 | 45,936.00 | 45,936.00 | 0.9259 | 42,533.33 | 319,000.00 |
| 2 | 0.0000 | 46,391.91 | 46,391.91 | 0.8573 | 39,773.59 | 317,405.00 |
| 3 | 0.0000 | 46,852.35 | 46,852.35 | 0.7938 | 37,192.91 | 315,817.98 |
| 4 | 0.0000 | 47,317.36 | 47,317.36 | 0.7350 | 34,779.68 | 314,238.89 |
| 5 | 0.0000 | 47,786.99 | 47,786.99 | 0.6806 | 32,523.02 | 312,667.69 |
| 6 | 0.0000 | 48,261.27 | 48,261.27 | 0.6302 | 30,412.79 | 311,104.35 |
| 7 | 0.0000 | 48,740.27 | 48,740.27 | 0.5835 | 28,439.48 | 309,548.83 |
| 8 | 0.0000 | 49,224.02 | 49,224.02 | 0.5403 | 26,594.20 | 308,001.09 |
| 9 | 0.0000 | 49,712.56 | 49,712.56 | 0.5002 | 24,868.66 | 306,461.08 |
| 10 | 0.0000 | 50,205.96 | 50,205.96 | 0.4632 | 23,255.07 | 304,928.78 |
| 11 | 0.0000 | 50,704.25 | 50,704.25 | 0.4289 | 21,746.19 | 303,404.13 |
| 12 | 0.0000 | 51,207.49 | 51,207.49 | 0.3971 | 20,335.20 | 301,887.11 |
| 13 | 0.0000 | 51,715.73 | 51,715.73 | 0.3677 | 19,015.77 | 300,377.68 |
| 14 | 0.0000 | 52,229.01 | 52,229.01 | 0.3405 | 17,781.94 | 298,875.79 |
| 15 | 0.0000 | 52,747.38 | 52,747.38 | 0.3152 | 16,628.17 | 297,381.41 |
| 16 | 0.0000 | 53,270.90 | 53,270.90 | 0.2919 | 15,549.27 | 295,894.50 |
| 17 | 0.0000 | 53,799.61 | 53,799.61 | 0.2703 | 14,540.36 | 294,415.03 |
| 18 | 0.0000 | 54,333.57 | 54,333.57 | 0.2502 | 13,596.92 | 292,942.95 |
| 19 | 0.0000 | 54,872.83 | 54,872.83 | 0.2317 | 12,714.70 | 291,478.24 |
| 20 | 0.0000 | 55,417.45 | 55,417.45 | 0.2145 | 11,889.71 | 290,020.85 |
| 21 | 0.0000 | 55,967.46 | 55,967.46 | 0.1987 | 11,118.26 | 288,570.74 |
| 22 | 0.0000 | 56,522.94 | 56,522.94 | 0.1839 | 10,396.86 | 287,127.89 |
| 23 | 0.0000 | 57,083.93 | 57,083.93 | 0.1703 | 9,722.27 | 285,692.25 |
| 24 | 0.0000 | 57,650.49 | 57,650.49 | 0.1577 | 9,091.44 | 284,263.79 |
| 25 | 0.0000 | 58,222.67 | 58,222.67 | 0.1460 | 8,501.55 | 282,842.47 |

### 3.4 Sensitivity (illustrative — recomputed against the scenario model)

Sensitivities re-run the scenario TCO model with the stated Δ; only payback shifts are reported, NPV/LCOE/IRR are not restated per row. The −10 % yield row reflects the recomputed payback against the scenario model against the inputs in §3.1.

Sensitivity — payback only (NPV / IRR / LCOE not restated per row) | Scenario | Δ CapEx | Δ import tariff | Δ yield | Recomputed simple payback | Recomputed discounted payback |
| --- | --- | --- | --- | --- | --- |
| Base case | 0% | 0.18 EUR/kWh | 1,100 kWh/kWp | ~4.70 yr | ~6.10 yr |
| +10 % CapEx | +10% | 0.18 EUR/kWh | 1,100 kWh/kWp | ~5.2 yr | ~6.7 yr |
| −10 % import tariff | 0% | 0.162 EUR/kWh | 1,100 kWh/kWp | ~5.3 yr | ~6.9 yr |
| −10 % yield | 0% | 0.18 EUR/kWh | 990 kWh/kWp | ~5.2 yr | ~7.4 yr |
| Best case (CapEx −5 %, tariff +5 %, yield +5 %) | −5% | 0.189 EUR/kWh | 1,155 kWh/kWp | ~4.0 yr | ~5.2 yr |
| Worst case (CapEx +10 %, tariff −10 %, yield −10 %) | +10% | 0.162 EUR/kWh | 990 kWh/kWp | ~6.4 yr | ~9.1 yr |

*All numeric outputs come from the computed Tradvolt TCO model against the inputs in §3.1. Do not transpose to other equipment, roofs or tariffs without rerunning the model.*

### Claim rows — TCO inputs & methodology

| Claim | Src: NAME | URL | accessed |
| --- | --- | --- | --- |
| Specific yield 1,100 kWh/kWp/yr for a CZ commercial array is a bounded model assumption consistent with PVGIS-class CZ roof values. | European Commission — JRC PVGIS photovoltaic calculator (PVGIS-SARAH2) | https://re.jrc.ec.europa.eu/pvg_tools/en/ | 2026-09-22 |
| 70 % self-consumption ratio is a bounded model assumption for a CZ commercial day-load profile. | IEA PVPS — Trends in PV Applications 2024 (commercial PV self-consumption bands) | https://iea-pvps.org/trends-reports/trends-in-pv-applications-2024/ | 2026-09-22 |
| CZ commercial import tariff 0.18 EUR/kWh and export compensation 0.06 EUR/kWh are bounded model assumptions within Eurostat CZ non-household electricity price band. | Eurostat Data Browser — electricity prices for non-household consumers (CZ, semi-annual) | https://ec.europa.eu/eurostat/databrowser | 2026-09-22 |
| Illustrative CapEx 220,000 EUR is the scenario model lump input; do not sum the §2 line items to this total. | Tradvolt scenario TCO model | https://tradvolt.com/rfq/ | 2026-09-22 |
| PV module annual degradation 0.5 %/yr is a bounded model assumption for the TOPCon cell class. | Fraunhofer ISE — Photovoltaics Report (degradation chapter) | https://www.ise.fraunhofer.de/en/publications/studies/photovoltaics-report.html | 2026-09-22 |
| Tariff escalation 1.0 %/yr is a bounded model assumption (Czech long-run electricity CPI band). | Eurostat Data Browser — electricity prices for non-household consumers | https://ec.europa.eu/eurostat/databrowser | 2026-09-22 |
| Discount rate 8.00 % and horizon 25 yr are bounded model assumptions (commercial WACC band / PV asset life). | Tradvolt scenario TCO model | https://tradvolt.com/rfq/ | 2026-09-22 |
| Fixed opex, mid-life inverter replacement and residual value are explicitly DROPPED in this summary; replace with project-specific values before any commercial decision. | Tradvolt scenario TCO model | https://tradvolt.com/rfq/ | 2026-09-22 |

## 4. Compliance, certifications & standards

The bundle is anchored on Jinko Tiger Neo JKM580N-72HL4-BDV (n-type TOPCon, 1500 V DC). For grid-tied commercial rooftop deployment in Czechia, the procurement team must confirm the certificate numbers and the issuing notified body for the specific production lot before award. The standards cited below are the canonical PV module/system norms; the per-SKU certificate numbers are disclosed on award and are not pre-listed here.

Applicable standards & per-SKU certificate status | Standard / instrument | Designation + edition | Applicability to bundle | Per-SKU certificate number + issuing Notified Body |
| --- | --- | --- | --- |
| PV module design qualification | IEC 61215-1:2021 / IEC 61215-2:2021 (crystalline silicon, terrestrial PV modules) | JKM580N-72HL4-BDV | Disclosed on award — confirm with JinkoSolar product support before RFQ close |
| PV module safety qualification | IEC 61730-1:2016 / IEC 61730-2:2016 | JKM580N-72HL4-BDV | Disclosed on award — confirm with JinkoSolar product support before RFQ close |
| PV module safety (North America cross-reference) | UL 61730-1 (standard for PV module safety qualification) | JKM580N-72HL4-BDV | Listed at UL 61730-1 product page; per-SKU cert number issued on award |
| PV system documentation / commissioning / inspection | IEC 62446-1:2016 (and -3 for O&M) | Whole system | IEC catalogue: IEC Webstore (cite designation + edition in tender) |
| EU CE Declaration of Conformity | Low Voltage Directive 2014/35/EU | Whole system placed on EU market | OEM DoC issued on award |
| Czech grid connection rules | Czech TSO (ČEPS) + local DSO | Whole system | Pre-grid study required; ČEPS: https://www.ceps.cz/en/ |
| Wood packaging (pallet) treatment | IPPC ISPM 15 | CN-origin pallets | IPPC ISPM 15 standards list: https://www.ippc.int/en/core-activities/standards-setting/ispms/ |
| Lithium battery transport (inverter auxiliary / monitoring) | UN Manual of Tests and Criteria, UN 38.3 (ST/SG/AC.10/11/Rev.7) | If Li-ion aux batteries present | UN Manual: UN Manual of Tests and Criteria; IATA DGR: https://www.iata.org/en/programs/cargo/dgr/ |

**Disclaimer.** This blueprint is published before a specific production lot has been allocated. The per-SKU certificate numbers and the issuing notified bodies (TÜV Rheinland / TÜV SÜD / VDE / Intertek / UL LLC etc.) are not pre-listed and must be confirmed by the procurement team against the OEM lot paperwork before the first dose of modules is released for shipment.

### Claim rows — compliance

| Claim | Src: NAME | URL | accessed |
| --- | --- | --- | --- |
| IEC 61215-1:2021 / IEC 61215-2:2021 is the canonical crystalline-silicon PV module design qualification standard. | IEC Webstore — publication catalogue | https://webstore.iec.ch/ | 2026-09-22 |
| IEC 61730-1:2016 / IEC 61730-2:2016 is the canonical PV module safety qualification standard. | IEC Webstore — publication catalogue | https://webstore.iec.ch/ | 2026-09-22 |
| UL 61730-1 is the canonical North American PV module safety qualification standard. | UL Standards — UL 61730-1 product page | https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1 | 2026-09-22 |
| IEC 62446 (parts -1, -3) covers PV system documentation, commissioning, inspection and O&M. | IEC Webstore — publication catalogue | https://webstore.iec.ch/ | 2026-09-22 |
| Low Voltage Directive 2014/35/EU governs CE marking of electrical equipment placed on the EU market. | European Commission — Single Market & CE marking | https://single-market-economy.ec.europa.eu/single-market/ce-marking_en | 2026-09-22 |
| Czech TSO (ČEPS) sets transmission-level grid connection rules. | ČEPS — transmission system operator | https://www.ceps.cz/en/ | 2026-09-22 |
| IPPC ISPM 15 governs wood packaging (pallet) treatment for international shipments. | IPPC — ISPM standards list | https://www.ippc.int/en/core-activities/standards-setting/ispms/ | 2026-09-22 |
| UN 38.3 (UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7) is the canonical lithium-battery transport test regime. | UNECE — UN Manual of Tests and Criteria | https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria | 2026-09-22 |
| IATA Dangerous Goods Regulations (DGR) govern air-freight classification of Li-ion cells. | IATA — Dangerous Goods programme | https://www.iata.org/en/programs/cargo/dgr/ | 2026-09-22 |

## 5. Customs & trade — HS classification, duty, VAT

Photovoltaic cells and modules imported into the EU are classified under HS subheading 8541.43 in the EU Common Customs Tariff. The exact 10-digit TARIC measure (duty rate, any anti-dumping / surveillance measure, binding tariff information) for Czechia must be confirmed by the procurement team via the official EU TARIC consultation before quote. The WCO HS Nomenclature 2022 edition is the canonical reference for subheading 8541.43.

Customs & trade lookup paths | Topic | Lookup path | URL | accessed |
| --- | --- | --- | --- |
| EU TARIC lookup (HS 8541.43, duty, measures) | EU TARIC consultation | https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en | 2026-09-22 |
| HS subheading reference (8541.43 — photovoltaic cells/modules) | WCO HS Nomenclature 2022 edition | https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition | 2026-09-22 |
| Incoterms 2020 (CIF / DAP / CIP for CN→CZ) | ICC Incoterms 2020 official rules | https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | 2026-09-22 |

*Lookup PENDING: the exact CN→CZ duty rate, any anti-dumping or surveillance measure, and the Czech VAT (DPH) rate applying to the import must be confirmed via the EU TARIC consultation and the Czech tax authority before any commercial commitment.*

[Request Quote — replies in 48h](/rfq/)