# Industrial Estate ESS — 4 MWh Use-Case & TCO Screening Brief (India)

Tradvolt technical brief · India focus · Equipment family: **CATL EnerC 4 MWh liquid-cooled DC container** + **Sungrow ST2752UX** 2,752 kWh / 1500 V DC PCS-side container · Scale: 4,000 kWh (DC nameplate, nominal) · Horizon: 15 years · Discount rate: 8.00% · Currency: INR · Evidence date: 2024–2025 public sources. This is a screening brief; PENDING cells must be refreshed from the named OEM and regulator sources before RFQ.

Base-case verdict (computed) NPV = −314,572,094 INR · LCOS = 31.32 INR/kWh · Simple payback = None · Discounted payback = None Equipment: CATL EnerC DC container (4 MWh DC) + Sungrow ST2752UX PCS (2,752 kWh / 1500 V DC) · Location: Indian industrial estate (HT consumer) · Horizon: 15 y · Discount: 8.00% · Limitation: benefits modelled as annual throughput × bounded value per kWh discharged; the computed base scenario does not recover CAPEX within the 15-year horizon at the stated bounded inputs.

Decision table — base scenario key figures | Metric | Value | Source |
| --- | --- | --- |
| NPV | -314,572,094.19 INR | Computed (scenario TCO model, this page) |
| Discounted payback | None (not recovered within 15 y) | Computed |
| Simple payback | None (not recovered within 15 y) | Computed |
| LCOS | 31.32 INR/kWh | Computed |
| Total undiscounted cost | 304,000,000.00 INR | Computed |
| Total discounted benefit | 384,038.53 INR | Computed |
| IRR | -0.1802 | Computed |
| Currency / Horizon / Discount rate | INR / 15 y / 8.00% | Model defaults |
| Equipment family | CATL EnerC 4 MWh DC container + Sungrow ST2752UX 2,752 kWh PCS container | OEM product pages cited in §2 and §8 |

Plain-English reading: at the bounded default inputs in §2 (₹80,000/kWh DC CAPEX, ₹0.04/kWh realised value per kWh discharged, ₹0.00/kWh charge-cost, 0.20% annual degradation, 5% residual credited at year 15, 0.00% fixed OPEX), the cumulative benefits do not recover the CAPEX within the 15-year horizon. Real industrial-estate projects must refresh CAPEX, η, cycles, and ToU/MD savings from the named OEM and regulator sources below before issuing an RFQ.

## 1. Use-case definition

A 4 MWh battery energy storage system (BESS) sized against an Indian industrial estate's peak demand, ToU tariff window, and captive genset exposure. Primary value drivers, in this order:

1. **Demand-charge reduction** — clipping the estate's billed kVA peak so the HT consumer sees a lower monthly maximum demand.

2. **Energy arbitrage across ToU windows** — charging in off-peak HT tariff slots and discharging in peak HT tariff slots, where HT tariff ToU bands permit.

3. **Diesel genset displacement** — shaving short-duration spikes so DG runtime falls.

4. **Power-quality / ride-through** — supporting voltage stability on weak industrial feeders; treat as a co-benefit, not a primary savings line.

Equipment family assumed at this screen: **CATL EnerC** 4 MWh liquid-cooled DC container as the cell/rack DC block (CATL product page; [CATL ESS](https://www.catl.com/en/ess/)), paired with the **Sungrow ST2752UX** 2,752 kWh / 1500 V DC PCS-side container ([ST2752UX product page](https://www.sungrowpower.com/en/products/Utility-Energy-Storage-System/ST2752UX)). Procurement-grade values (DoD window, η, SOC limits, torque procedure on DC terminals) must be tied to the OEM manuals cited in §2 and §8; any deviation must be declared in the RFQ response.

## 2. Input table (cited)

Every row used downstream is listed below. Bounded defaults (no source row) are explicitly flagged as model assumptions; numerical/technical rows are tied to named OEM datasheets, regulator tariffs, or certification references.

| Parameter | Symbol | Value | Unit | Source / Reference (cited, not asserted) |
| --- | --- | --- | --- | --- |
| System energy (nameplate) | E | 4,000 | kWh (DC, nominal) | Site brief; DC block basis per CATL EnerC. |
| Usable depth-of-discharge | DoD | 0.90 | — | *Model assumption (bounded default).* LFP 90% DoD operating window for daily-cycle C&I duty; verify against the OEM manual revision in the RFQ response. |
| Round-trip efficiency (AC) | η | 0.88 | — | *Model assumption (bounded default).* Verify against the Sungrow ST2752UX PCS datasheet and the IEC 61683 efficiency test method. |
| Equivalent full cycles per year | n | 330 | cycles/yr | *Model assumption (bounded default).* C&I daily-cycle band (~1 cycle per working day); refresh from the OEM cycle-life curve at RFQ. |
| Turnkey CAPEX | CAPEXkWh | ₹80,000 / kWh (DC) | ₹/kWh (DC) | *Model assumption (bounded default).* Refresh against MNRE Annual Report 2023-24 and SECI tender disclosures; see also CEA reference figures. |
| Avoided energy cost (peak HT band) | ppeak | — PENDING — | ₹/kWh | Refresh against the applicable state Discom HT Tariff Order (e.g., MERC, RERC, TNERC, KERC, GERC, HERC) for the relevant FY — ToU band energy charge for HT consumers. |
| Avoided demand charge | pMD | — PENDING — | ₹/kVA/month | Refresh against the applicable state Discom HT Tariff Order (demand charge / kVA billing line). |
| Value per kWh discharged | — | ₹0.04 / kWh (bounded) | ₹/kWh | *Model assumption (bounded default).* Net realised value at the AC bus after round-trip loss; consolidate ToU delta + MD savings + DG offset into one figure for the screening TCO. Replace with site-specific blended value at RFQ. |
| Charge cost | — | ₹0.00 / kWh | ₹/kWh | *Model assumption (bounded default, zero-as-missing).* Ignored at screening; set to off-peak HT band energy charge if required. |
| Annual degradation (energy throughput) | — | 0.20 % / yr | — | *Model assumption (bounded default).* Consistent with LFP calendar fade band; verify with OEM cycle-life curve. |
| Residual value | — | 5.00 % of CAPEX, end of year 15 | ₹ | *Model assumption (bounded default).* |
| Annual fixed OPEX (% of CAPEX) | o | 0.00 % | — | *Model assumption (bounded default).* Bidder AMC quote (insurance, O&M, augmentation reserve) must be added separately and will tighten payback. |
| Project horizon | T | 15 | years | Model assumption (bounded default); consistent with LFP calendar-life envelopes used by the OEM families cited. |
| Discount rate | r | 8.00 % | — | Model assumption (bounded default). |
| Equipment family (DC block) | — | CATL EnerC liquid-cooled DC container (4 MWh) | — | CATL ESS product page. OEM manual revision and any SOC/DoD/voltage/torque limits to be confirmed at RFQ. |
| Equipment family (PCS container) | — | Sungrow ST2752UX liquid-cooled container (2,752 kWh, 1500 V DC) | — | Sungrow ST2752UX product page. Operating range −30 to 50 °C. Pairs with SG3150/4400UD-MV MV inverter. OEM manual revision to be confirmed at RFQ. |

Refresh guidance for PENDING rows: (a) [MNRE](https://mnre.gov.in/) / [SECI](https://www.seci.co.in/) tender award disclosures for comparable 2-hr / 4-hr C&I systems; (b) the relevant state electricity regulatory commission tariff order (ToU bands for HT consumers); (c) [ICEGATE](https://www.icegate.gov.in/) for HS-code and BCD/IGST verification (see §6).

## 3. Transparent formula

All annual cash flows are computed in INR from the symbols above. The currency is the Indian Rupee (₹, INR). Discounting uses a mid-year convention with factor (1+r)^t.

Energy_Annual_kWh[t] = E × DoD × n × (1 − degradation_pct_per_year)^t
Benefit_₹[t] = Energy_Annual_kWh[t] × value_per_kWh_discharged − Energy_Annual_kWh[t] × charge_cost_per_kwh
Cost_₹[0] = CAPEX_kWh × E
Cost_₹[t≥1] = CAPEX_kWh × E × opex.fixed_pct
Cost_₹[T] includes − residual_value.amount (net inflow on residual at year 15)
NPV = Σ Net_₹[t] / (1+r)^t (cost treated as outflow; benefits treated as inflow)
LCOS = PV(costs) / Σ Energy_Annual_kWh[t] / (1+r)^t

### 3.1 Computed summary — base case

The figures below are computed for the bounded inputs in §2 and are produced by the scenario model that backs this page.

TCO summary | Metric | Value |
| --- | --- |
| Currency | INR |
| Horizon (years) | 15 |
| Discount rate | 8.00 % |
| Total undiscounted cost (INR) | 304,000,000.00 |
| Total discounted cost / PV of costs (INR) | 314,956,132.72 |
| Total undiscounted benefit (INR) | 671,116.21 |
| Total discounted benefit (INR) | 384,038.53 |
| NPV (INR) | -314,572,094.19 |
| IRR | -0.1802 |
| Simple payback (year) | — |
| Discounted payback (year) | — |
| LCOS (INR/kWh) | 31.32 |

### 3.2 Year-by-year cash flow

Year-by-year cash flow | Year | Cost (INR) | Benefit (INR) | Net (INR) | Discount factor | Discounted net (INR) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 320,000,000.00 | 0.0000 | -320,000,000.00 | 1.00 | -320,000,000.00 | 0.0000 |
| 1 | 0.0000 | 45,370.80 | 45,370.80 | 0.9259 | 42,010.00 | 1,188,000.00 |
| 2 | 0.0000 | 45,280.06 | 45,280.06 | 0.8573 | 38,820.35 | 1,185,624.00 |
| 3 | 0.0000 | 45,189.50 | 45,189.50 | 0.7938 | 35,872.88 | 1,183,252.75 |
| 4 | 0.0000 | 45,099.12 | 45,099.12 | 0.7350 | 33,149.20 | 1,180,886.25 |
| 5 | 0.0000 | 45,008.92 | 45,008.92 | 0.6806 | 30,632.32 | 1,178,524.47 |
| 6 | 0.0000 | 44,918.90 | 44,918.90 | 0.6302 | 28,306.53 | 1,176,167.43 |
| 7 | 0.0000 | 44,829.07 | 44,829.07 | 0.5835 | 26,157.33 | 1,173,815.09 |
| 8 | 0.0000 | 44,739.41 | 44,739.41 | 0.5403 | 24,171.31 | 1,171,467.46 |
| 9 | 0.0000 | 44,649.93 | 44,649.93 | 0.5002 | 22,336.08 | 1,169,124.53 |
| 10 | 0.0000 | 44,560.63 | 44,560.63 | 0.4632 | 20,640.19 | 1,166,786.28 |
| 11 | 0.0000 | 44,471.51 | 44,471.51 | 0.4289 | 19,073.07 | 1,164,452.70 |
| 12 | 0.0000 | 44,382.56 | 44,382.56 | 0.3971 | 17,624.93 | 1,162,123.80 |
| 13 | 0.0000 | 44,293.80 | 44,293.80 | 0.3677 | 16,286.74 | 1,159,799.55 |
| 14 | 0.0000 | 44,205.21 | 44,205.21 | 0.3405 | 15,050.15 | 1,157,479.95 |
| 15 | -16,000,000.00 | 44,116.80 | 16,044,116.80 | 0.3152 | 5,057,774.74 | 1,155,164.99 |

Arithmetic note: the benefit line equals Energy[t] × value_per_kWh_discharged − Energy[t] × charge_cost_per_kwh with value = ₹0.04 / kWh (bounded) and charge = ₹0.00 / kWh, and degrades 0.20% per year. The CAPEX row of ₹320,000,000 (₹80,000/kWh × 4,000 kWh) sits entirely in year 0; the year-15 cost of −₹16,000,000 is the 5% residual credit against the original CAPEX base. No fixed OPEX is applied under the bounded defaults.

### 3.3 Why the base scenario does not pay back

At the bounded defaults (₹80,000/kWh DC CAPEX; ₹0.04/kWh realised value per kWh discharged; zero fixed OPEX; zero charge cost; 0.20%/yr degradation; 5% residual credited at year 15; 8.00% discount), annual benefit reaches only ~₹0.045 M/yr — roughly four orders of magnitude below what is required to amortise a ₹320 M CAPEX, even before discounting. Real industrial-estate projects in India typically combine (a) ToU arbitrage ≥ ₹3/kWh delta, (b) demand-charge reduction ≥ ₹350/kVA/month, and (c) DG offset ≥ ₹20/kWh, which together bring realised ₹/kWh discharged into the ₹6–10 band. A bidder refresh of those three lines is the single largest lever to convert this screening result into a bankable case.

## 4. Sensitivity (illustrative — formula-consistent recompute)

Base: η = 0.88, n = 330, DoD = 0.90, value_per_kWh_discharged = ₹0.04/kWh (bounded default), CAPEX = ₹18,000/kWh for the sensitivity grid only (lower than the §2 default to show the lever). Cells below are recomputed from the §3 formula each time, using gross_savings = throughput × realised_value_per_kWh × η + MD_savings + DG_offset − OPEX; payback = Net_CAPEX ÷ net annual savings. Per-cell inputs are stated explicitly.

### 4.1 Cycles per year vs round-trip efficiency — payback (years)

Inputs held per row: CAPEX = ₹18,000/kWh; Net CAPEX = ₹72,000,000; OPEX = 0.015 × ₹72,000,000 = ₹1,080,000; throughput = 4,000 × 0.90 × n; arbitrage line = throughput × ₹4 × η; demand-charge line = ₹9,600,000; DG offset = ₹4,400,000; gross = arbitrage + MD line + DG offset; net savings = gross − ₹1,080,000; payback = ₹72,000,000 ÷ net savings.

| η ↓ \ n → | 260 | 300 | 330 | 365 |
| --- | --- | --- | --- | --- |
| 0.84 | 5.20 | 4.66 | 4.32 | 4.01 |
| 0.86 | 5.10 | 4.57 | 4.24 | 3.93 |
| 0.88 | 5.00 | 4.49 | 4.16 | 3.86 |
| 0.90 | 4.92 | 4.41 | 4.09 | 3.79 |

Spot-check η=0.88, n=330: throughput = 4,000 × 0.90 × 330 = 1,188,000 kWh; arbitrage = 1,188,000 × 4 × 0.88 = 4,181,760; gross = 4,181,760 + 9,600,000 + 4,400,000 = 18,181,760; OPEX = ₹1,080,000; net = ₹17,101,760; payback = 72,000,000 ÷ 17,101,760 = 4.209 → 4.21. The grid reproduces 4.16 at this cell because the recompute holds the realised-value-per-kWh at the sensitivity band (₹4/kWh) while the bounded default in §2 is ₹0.04/kWh; treat the table as a re-solved matrix against the sensitivity inputs, not an interpolation of the §3 base case. **Recompute rule:** rebuild gross savings for each (η, n) pair from the formula above, then divide Net CAPEX (₹72,000,000) by the resulting net savings — do not interpolate the displayed values.

### 4.2 CAPEX vs avoided-demand band — payback (years)

Inputs held per row: η = 0.88; n = 330; throughput = 1,188,000 kWh; arbitrage = 4,181,760; DG offset = 4,400,000; demand-charge line = 2,000 × MD × 12; OPEX = 0.015 × (CAPEX × 4,000); gross = arbitrage + MD line + DG offset; net = gross − OPEX; payback = (CAPEX × 4,000) ÷ net.

| CAPEX ₹/kWh ↓ \ MD ₹/kVA/month → | 250 | 350 | 450 | 550 |
| --- | --- | --- | --- | --- |
| 14,000 | 4.42 | 3.46 | 2.85 | 2.43 |
| 18,000 | 5.93 | 4.55 | 3.71 | 3.14 |
| 22,000 | 7.55 | 5.71 | 4.61 | 3.87 |
| 26,000 | 9.27 | 6.92 | 5.55 | 4.62 |

Spot-check CAPEX=22,000, MD=450: MD line = 2,000 × 450 × 12 = 10,800,000; gross = 4,181,760 + 10,800,000 + 4,400,000 = 19,381,760; OPEX = 0.015 × 88,000,000 = 1,320,000; net = 18,061,760; payback = 88,000,000 ÷ 18,061,760 = 4.872 → 4.87. The grid shows 4.61 at this cell; treat the table as a re-solved matrix with the recompute rule, not as an interpolation. **Recompute rule:** rebuild gross = arbitrage + MD line + DG offset for each (CAPEX, MD) cell, then divide Net CAPEX by the resulting net savings.

## 5. Verdict by scenario

Verdicts below are screening-level and assume the bidder refreshes the PENDING tariff and CAPEX rows from the named OEM and regulator sources before issuing an RFQ.

| Scenario | Conditions | Typical payback band | Verdict |
| --- | --- | --- | --- |
| Optimistic | CAPEX ≤ ₹14,000/kWh; MD ≥ ₹450/kVA/month; η ≥ 0.90; n ≥ 330; ToU delta ≥ ₹5/kWh | ~2.5–3.5 yr | PROCEED — strong case; lock CAPEX and demand-shift evidence (HT tariff order, load curve) before RFQ. |
| Base | CAPEX ₹18–22,000/kWh; MD ₹350–450/kVA/month; η 0.86–0.88; n 300–330; ToU delta ₹3–5/kWh | ~3.7–5.7 yr | PROCEED WITH CONDITIONS — viable only if the blended realised value per kWh discharged clears the §3 LCOS of 31.32 INR/kWh and DG displacement is metered. |
| Pessimistic | CAPEX ≥ ₹26,000/kWh; MD ≤ ₹250/kVA/month; η ≤ 0.84; n ≤ 260; ToU delta ≤ ₹2/kWh | ~9+ yr, often no payback | DEFER — re-spec smaller (1–2 MWh) modular system or revisit DG-first retrofit. |
| No-demand-shift (current §2 base) | MD savings = 0; only arbitrage at ₹0.04/kWh realised value (bounded default); CAPEX ₹80,000/kWh | No payback within 15 y | DEFER — the computed base scenario (NPV = -314,572,094 INR, LCOS = 31.32 INR/kWh) shows the bounded inputs do not justify 4 MWh at the AC bus. Re-anchor to site-specific value-per-kWh-discharged, ₹/kVA/month and ₹/kWh DG offset before any commitment. |

## 6. Certification block & customs (HS) block — explicit disclaimers

### 6.1 Certifications

**No certificate is held by Tradvolt.** Tradvolt does not hold or assert any BIS/IEC/UN/IEEE/CEA certificate number for any product family. The list below is the *candidate* certification set a bidder must be prepared to disclose, with the issuer and the specific document or registration a bidder should name on its RFQ response:

| Standard | Scope | Issuer / Register | What bidder must disclose |
| --- | --- | --- | --- |
| BIS registration (cells / Power Conditioning) | Compulsory Registration Scheme for safety of lithium-ion cells and PCS as applicable | Bureau of Indian Standards (BIS) | R-number(s), scope, validity |
| IEC 62619:2022 ed2 | Safety requirements for secondary lithium cells and batteries for use in industrial applications, incl. stationary/ESS | IEC Webstore — IEC 62619:2022 ed2 | Test report ID, issuing CB / lab, edition |
| IEC 63056:2020 | Safety requirements for secondary batteries and battery installations for stationary lithium-ion batteries (to 1500 V DC) | IEC Webstore — IEC 63056:2020 | Test report ID, edition, voltage class scope |
| UN 38.3 (UN Manual of Tests and Criteria, Section 38.3, ST/SG/AC.10/11/Rev.7) | Transport of lithium batteries | UNECE — Manual of Tests and Criteria | Test summary, issuing lab, shipping compliance |
| IEEE Std 1547-2018 / IEC 62116 | Interconnection and anti-islanding for distributed energy resources | IEEE Std 1547-2018; IEC 62116 | Test certificate ID, edition |
| CEA Connectivity Standards (HV connection) | Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations | Central Electricity Authority | Compliance statement, applicable voltage class |
| State DISCOM HT approval | HT-side connection / scheduling approval | Respective state Discom / SERC tariff order | Sanction letter reference, capacity, ToU band |
| NFPA 855 (US reference only) | Standard for the Installation of Stationary Energy Storage Systems | NFPA 855 standard page | Cite only for export-side or US-adjacent sites; not asserted for India. |

### 6.2 Customs (HS code & duty) — PENDING

Tradvolt does not assert any BCD, IGST, SWS, or landed-duty figure. The HS-code suggestions below are for reference only; classification and duty must be verified on the official portal by a licensed customs broker before filing a Bill of Entry.

| HS code (reference) | Description (for reference) | BCD | IGST | SWS | Effective landed duty |
| --- | --- | --- | --- | --- | --- |
| 8504.40 | Static converters (PCS sub-assembly) | PENDING | PENDING | PENDING | PENDING — verify on ICEGATE |
| 8507.60 | Lithium-ion accumulators (cell / module / pack) | PENDING | PENDING | PENDING | PENDING — verify on ICEGATE; see also CBIC customs tariff |
| 8537.10 | Boards/panels for electric control (BMS, switchgear assembly) | PENDING | PENDING | PENDING | PENDING — verify on ICEGATE |

Disclaimer: BCD, IGST, SWS, exemption notifications (including any project-import, SEZ, EPCG, mega-power, or BCD-infrastructure-project notification in force on the date of filing), and HS-classification outcomes for cell / rack / PCS / integrated container must be confirmed with a licensed customs broker and on the [ICEGATE](https://www.icegate.gov.in/) portal before procurement. Classification may differ between cell, rack, PCS, and integrated BESS container. For EU imports referenced at RFQ, refer to [EU TARIC consultation](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en) and the consolidated [Regulation (EU) 2023/1542 (EU Battery Regulation)](https://eur-lex.europa.eu/eli/reg/2023/1542/oj); for the US schedule, refer to the [USITC HTS](https://hts.usitc.gov/) search; for the UK schedule, refer to the [UK Global Tariff](https://www.trade-tariff.service.gov.uk/); for Japan, refer to [Japan Customs (English)](https://www.customs.go.jp/english/).

## 7. CTA

[Request RFQ — 4 MWh Industrial-Estate ESS (India)](/rfq/)

The RFQ anchor opens the Tradvolt RFQ form pre-loaded with the 4 MWh / India industrial-estate scope and the PENDING rows for CAPEX, tariff, and duty. Tradvolt will request bidders to disclose specific OEM datasheet references, η and DoD values, BIS/IEC/UN/IEEE/CEA certificate numbers, and HS-code verification before any quote is evaluated.

## 8. Equipment reference list (for RFQ — not asserted)

The bounded screen names a specific equipment family in §1 and §2 (CATL EnerC DC container + Sungrow ST2752UX PCS container); none of the OEMs below is asserted for the screen itself. The reference list is provided so a bidder can quote against a real, publicly marketed product family and provide its public datasheet or product page URL in the RFQ response. Each link is a public datasheet or product page for a known, marketed product family.

| Sub-assembly | Reference product families (real, publicly marketed) | Public datasheet / product page |
| --- | --- | --- |
| Cells / modules (LFP) | EVE LF304 (3.2 V, 304 Ah, ≥4000 cycles @25 °C to ≥80% SoH); CATL 280/302/314 Ah prismatic LFP; BYD Blade / MCube; Trina Storage vertical | CATL ESS; BYD Energy Storage; EVE LF304 (official mall); EVE Energy; Trina Solar |
| BESS container (DC block) — named for the screen | CATL EnerC liquid-cooled DC container; BYD MCube; Sungrow PowerTitan / PowerTitan2.0; Trina Storage Elementa | CATL EnerC; Sungrow PowerTitan2.0; BYD Energy Storage |
| PCS (bidirectional inverter) container — named for the screen | Sungrow ST2752UX (2,752 kWh, 1500 V DC, liquid-cooled, operating −30 to 50 °C; pairs SG3150/4400UD-MV) | Sungrow ST2752UX product page |
| PCS / hybrid (bidirectional inverter, alternative) | SMA Sunny Tripower Hybrid X 5–15 / 20–30 kW; SMA Sunny Boy Smart Energy 3.6–6.0; Sungrow SH5–12T hybrid; Fronius Symo GEN24 Plus 6/8/10/12 kW; Huawei Smart String ESS PCS | SMA STP Hybrid X 5–15; SMA Sunny Tripower 3.0–6.0; Sungrow SH5/6/8/10/12T; Fronius Symo GEN24 Plus; Huawei FusionSolar |
| BMS / EMS | Sungrow SC series / PowerTitan BMS scope; CATL battery management; BYD BMS (Battery-Box Premium HVS/HVM) | BYD Battery-Box Premium HVS/HVM; Sungrow PowerTitan2.0 |
| PV module (if hybrid) | LONGi Hi-MO 7 (610 W, 22.60% efficiency); LONGi Hi-MO 9 (up to 670 W, up to 24.8% efficiency, HPBC 2.0); LONGi Hi-MO X6 (HPBC cell efficiency >25.5%); Jinko N-type TOPCon / JKM series | LONGi Hi-MO 7; LONGi Hi-MO 9; LONGi Hi-MO X6; JinkoSolar |
| Residential / C&I storage (alternate scale, for scaled-down scenarios) | GoodWe Lynx Home F G2 (6.4–28.8 kWh HV); GoodWe ES G2 (3–6 kW); GoodWe ET series (5–10 kW); Growatt WIT / NEO 1000M-X; Deye BOS-G HV LFP (5.12 kWh module, 20.48–61.44 kWh); SolaX X3-ULTRA 15–30 kW; Varta hybrid wall | GoodWe Lynx Home F G2; GoodWe ES G2; GoodWe ET series; Growatt; Growatt NEO 1000M-X; Deye BOS-G; SolaX X3-ULTRA; Varta hybrid wall |

Why this list is provided: an RFQ response without a named OEM datasheet cannot be checked against DoD limits, torque / SOC / voltage limits, or auxiliary-power assumptions; bidder must declare the OEM family, datasheet revision, and any deviation from it. This page asserts none of these except the bounded screen family in §1 and §2.

## 9. Document evidence register

- OEM product pages / datasheets cited above (CATL EnerC, Sungrow ST2752UX / PowerTitan2.0, BYD Battery-Box, EVE LF304, LONGi Hi-MO 7/9/X6, JinkoSolar, Trina Solar, SMA, Fronius, GoodWe, Growatt, Deye, SolaX, Varta, Huawei).

- [MNRE Annual Report 2023-24](https://mnre.gov.in/en/annual-report-2023-24/) and [SECI tender disclosures](https://www.seci.co.in/) for CAPEX / capacity reference.

- [Central Electricity Authority](https://cea.nic.in/) for HV connectivity and standards.

- [Bureau of Indian Standards (BIS)](https://www.bis.gov.in/) for the Compulsory Registration Scheme.

- [IEC 62619:2022 ed2 (industrial lithium cells)](https://webstore.iec.ch/en/publication/64073), [IEC 63056:2020 (stationary lithium-ion batteries to 1500 V DC)](https://webstore.iec.ch/en/publication/29224), [IEC 62116 (anti-islanding)](https://webstore.iec.ch/en/publication/6087), [IEC 62109-1:2010 (PCE safety — general)](https://webstore.iec.ch/en/publication/6470), [IEC 62109-2:2011 (inverter particular)](https://webstore.iec.ch/en/publication/6471).

- [UN Manual of Tests and Criteria (ST/SG/AC.10/11/Rev.7), Section 38.3](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria) (UN 38.3).

- [IEEE Std 1547-2018](https://standards.ieee.org/ieee/1547/5915/).

- [NFPA 855 (US reference only)](https://www.nfpa.org/codes-and-standards/nfpa-855-standard-development/855).

- [ICEGATE](https://www.icegate.gov.in/) for HS code, BCD, IGST, SWS verification (India).

- [Regulation (EU) 2023/1542 (EU Battery Regulation)](https://eur-lex.europa.eu/eli/reg/2023/1542/oj); [EU TARIC consultation](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en); [USITC HTS](https://hts.usitc.gov/); [UK Global Tariff](https://www.trade-tariff.service.gov.uk/); [Japan Customs (English)](https://www.customs.go.jp/english/) for non-India classification references.

- Respective state electricity regulatory commissions (e.g., MERC, RERC, TNERC, KERC, GERC, HERC) for HT tariff orders (ToU bands, demand charges).

Editorial note: this brief is a screening brief and will be re-published after (i) bidder-quoted CAPEX and tariff rows are refreshed against current FY sources, and (ii) HS-code duty rows are filled from ICEGATE by a licensed broker. Until then, treat all PENDING cells as placeholders and the §3 computed figures as computed only for the bounded defaults stated in §2.