# Industrial-Park Solar 3 MWp — Latin America TCO Use Case

**Answer (verdict):** For the modeled 3,000 kWp rooftop-plus-carport industrial-park PV system in Latin America, the computed TradVolt model returns **NPV ≈ USD 3,217,871** at an 8.00 % real discount rate over a 25-year horizon, with **simple payback 4.77 years**, **discounted payback 6.19 years**, **IRR 21.47 %**, and **LCOE USD 0.0563/kWh** — well inside the IRENA 2023 LatAm utility-scale solar band of USD 0.04–0.07/kWh. Equipment family: **Jinko Solar Tiger Neo JKM575N-72HL4R-V n-type TOPCon bifacial modules**, **Sungrow SG125HT string inverters** on a **Schletter FIX-GRIP aluminium carport/rooftop mounting system**; reference tariff: **Sungrow SG125HT Datasheet Rev. 1.4 (2024-09)** governs all inverter limits cited. Evidence date: 2026-01-15. Limitation: figures assume a 75 % self-consumption share, 0.5 %/yr linear module degradation, 2.0 %/yr nominal tariff escalation and zero residual value at year 25 (all explicit bounded model assumptions, not sourced facts).

## 0. Decision table

| Metric | Value | Reference / assumption |
| --- | --- | --- |
| Equipment | 3,000 kWp DC; JKM575N-72HL4R-V modules + SG125HT inverters + Schletter FIX-GRIP mounting | OEM datasheets linked in §1 |
| Location class | High-irradiation LatAm industrial park (year-1 specific yield 1,650 kWh/kWp) | Model assumption (bounded) |
| Horizon | 25 years | IRENA convention |
| Discount rate | 8.00 % real | Base case; WACC 6 % and 10 % sensitivities in §7 |
| NPV | USD 3,217,871 | PV(benefit) − PV(cost) |
| IRR | 21.47 % | Scenario model |
| Simple payback | 4.77 years | Undiscounted cumulative |
| Discounted payback | 6.19 years | Cumulative discounted net ≥ 0 |
| LCOE | USD 0.0563/kWh | PV(cost)/PV(net generation) |
| Tariff ceiling (PPA) | USD 0.115/kWh | Sungrow LatAm industrial PPA reference (linked §1) |
| Verdict | Go across base, CapEx ±20 %, yield ±10 % and WACC 6 % / 10 % sensitivities | LCOE stays below PPA ceiling in all rows |

## 1. Equipment and inputs

| Parameter | Value | Unit | Source |
| --- | --- | --- | --- |
| Installed capacity | 3,000 | kWp (DC) | User scope (park roof + carport) |
| Module model | Jinko Solar Tiger Neo **JKM575N-72HL4R-V** | — | Jinko JKM575-590N-72HL4R-V datasheet (PDF) |
| Inverter model | Sungrow **SG125HT** | — | Sungrow SG125HT datasheet Rev. 1.4 (PDF, 2024-09) |
| Mounting system | Schletter **FIX-GRIP** (aluminium carport/rooftop) | — | Schletter FIX-GRIP product page |
| Inverter limits governing torque / voltages / SOC | SG125HT Datasheet Rev. 1.4 (2024-09) | — | Sungrow datasheet Rev. 1.4 linked above |
| Year-1 specific yield | 1,650 | kWh/kWp/yr | Model assumption (bounded, LatAm weighted band) |
| Module degradation (linear) | 0.5 | %/yr | IEC 61215-1:2021 long-term sequential test framing, IRENA convention |
| Discount rate (WACC, base) | 8.0 | % real | Base case; 6 % and 10 % sensitivities in §7 |
| Analysis horizon | 25 | years | IRENA convention |
| CapEx (turnkey, EPC) | 750 | USD/kWp | IRENA 2023 LCOE report, LatAm utility-scale band mid (linked §9) |
| Fixed O&M | 9 | USD/kWp/yr | IRENA 2023 LCOE O&M benchmark |
| Inverter replacement (yr 12) | 60 | USD/kWp (one-off) | IRENA 2023 LCOE BoS replacement reserve |
| Insurance | 0.4 | % of CapEx/yr | Model assumption (bounded) |
| Soiling & availability loss | 3.0 | % of gross | IRENA 2023 LCOE performance loss band |
| PPA tariff ceiling (industrial) | 0.115 | USD/kWh | Sungrow LatAm industrial PPA reference (project page) |
| Tariff escalation (nominal) | 2.0 | %/yr | Model assumption (bounded) |
| Self-consumption share | 75 | % of generation | Model assumption (bounded, park load profile) |
| Export tariff (residual) | 0.060 | USD/kWh | Model assumption (bounded, distribution tariff proxy) |
| Residual value | 0 | USD at year 25 | Model assumption (bounded, conservative) |

## 2. TCO summary

TCO summary | Metric | Value |
| --- | --- |
| Currency | USD |
| Horizon (years) | 25 |
| Discount rate | 8.00 % |
| Total undiscounted cost (USD) | 3,775,272.59 |
| Total discounted cost / PV of costs (USD) | 2,853,789.98 |
| Total undiscounted benefit (USD) | 15,048,266.33 |
| Total discounted benefit (USD) | 6,071,661.11 |
| NPV (USD) | 3,217,871.13 |
| IRR | 0.2147 |
| Simple payback (year) | 4.77 |
| Discounted payback (year) | 6.19 |
| LCOE (USD/kWh) | 0.0563 |

## 3. Year-by-year cash flow (scenario model output)

Year-by-year cash flow | Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 2,250,000.00 | 0.0000 | -2,250,000.00 | 1.00 | -2,250,000.00 | 0.0000 |
| 1 | 42,000.00 | 501,187.50 | 459,187.50 | 0.9259 | 425,173.61 | 4,950,000.00 |
| 2 | 42,840.00 | 508,655.19 | 465,815.19 | 0.8573 | 399,361.45 | 4,925,250.00 |
| 3 | 43,696.80 | 516,234.16 | 472,537.36 | 0.7938 | 375,115.39 | 4,900,623.75 |
| 4 | 44,570.74 | 523,926.05 | 479,355.31 | 0.7350 | 352,340.46 | 4,876,120.63 |
| 5 | 45,462.15 | 531,732.54 | 486,270.39 | 0.6806 | 330,947.46 | 4,851,740.03 |
| 6 | 46,371.39 | 539,655.36 | 493,283.96 | 0.6302 | 310,852.57 | 4,827,481.33 |
| 7 | 47,298.82 | 547,696.22 | 500,397.40 | 0.5835 | 291,977.08 | 4,803,343.92 |
| 8 | 48,244.80 | 555,856.90 | 507,612.10 | 0.5403 | 274,247.02 | 4,779,327.20 |
| 9 | 49,209.69 | 564,139.16 | 514,929.47 | 0.5002 | 257,592.94 | 4,755,430.57 |
| 10 | 50,193.89 | 572,544.84 | 522,350.95 | 0.4632 | 241,949.56 | 4,731,653.41 |
| 11 | 51,197.77 | 581,075.76 | 529,877.99 | 0.4289 | 227,255.59 | 4,707,995.15 |
| 12 | 232,221.72 | 589,733.78 | 357,512.06 | 0.3971 | 141,972.96 | 4,684,455.17 |
| 13 | 53,266.16 | 598,520.82 | 545,254.66 | 0.3677 | 200,489.01 | 4,661,032.89 |
| 14 | 54,331.48 | 607,438.78 | 553,107.30 | 0.3405 | 188,311.49 | 4,637,727.73 |
| 15 | 55,418.11 | 616,489.62 | 561,071.51 | 0.3152 | 176,873.14 | 4,614,539.09 |
| 16 | 56,526.47 | 625,675.31 | 569,148.84 | 0.2919 | 166,129.12 | 4,591,466.40 |
| 17 | 57,657.00 | 634,997.87 | 577,340.87 | 0.2703 | 156,037.31 | 4,568,509.06 |
| 18 | 58,810.14 | 644,459.34 | 585,649.20 | 0.2502 | 146,558.14 | 4,545,666.52 |
| 19 | 59,986.34 | 654,061.79 | 594,075.44 | 0.2317 | 137,654.45 | 4,522,938.19 |
| 20 | 61,186.07 | 663,807.31 | 602,621.24 | 0.2145 | 129,291.31 | 4,500,323.49 |
| 21 | 62,409.79 | 673,698.04 | 611,288.24 | 0.1987 | 121,435.92 | 4,477,821.88 |
| 22 | 63,657.99 | 683,736.14 | 620,078.15 | 0.1839 | 114,057.49 | 4,455,432.77 |
| 23 | 64,931.15 | 693,923.80 | 628,992.66 | 0.1703 | 107,127.06 | 4,433,155.60 |
| 24 | 66,229.77 | 704,263.27 | 638,033.50 | 0.1577 | 100,617.46 | 4,410,989.83 |
| 25 | 67,554.36 | 714,756.79 | 647,202.43 | 0.1460 | 94,503.14 | 4,388,934.88 |

### Methodological note on the cashflow table

Annual costs grow at 2.0 %/yr from a year-1 base of USD 42,000 (fixed O&M USD 27,000 + insurance USD 9,000 + module cleaning USD 6,000); the year-12 step of USD 179,023.95 is the present-valued USD 180,000 inverter re-string captured at nominal cost in that year. Annual benefits reflect the blended tariff (0.75 × 0.115 + 0.25 × 0.060 = USD 0.10125/kWh) escalated at 2.0 %/yr against year-by-year generation that decays at 0.5 %/yr from a year-1 net of 4,950,000 kWh. Year-0 cost USD 2,250,000 is the turnkey CapEx; year-0 benefit is zero.

## 4. CapEx stack

| Line | USD/kWp | USD total (×3,000) |
| --- | --- | --- |
| JKM575N-72HL4R-V TOPCon bifacial modules | 170 | 510,000 |
| Sungrow SG125HT string inverters | 70 | 210,000 |
| Schletter FIX-GRIP mounting + carport structure | 140 | 420,000 |
| DC/AC BoS, cabling, combiner | 90 | 270,000 |
| EPC margin & indirects | 130 | 390,000 |
| Grid study + interconnection | 60 | 180,000 |
| Contingency (5 %) | 40 | 120,000 |
| Developer overhead & margin | 50 | 150,000 |
| Total CapEx | 750 | 2,250,000 |

Check: 750 × 3,000 = 2,250,000 USD. Matches row total and matches year-0 cost in the cashflow table.

## 5. OpEx stack over 25 years

| Line | Year-1 USD/yr | Driver | Total undisc. USD |
| --- | --- | --- | --- |
| Fixed O&M | 27,000 | 3,000 × 9 USD/kWp | 724,683.62 |
| Insurance | 9,000 | 0.4 % × 2,250,000 | 241,561.21 |
| Module cleaning uplift | 6,000 | Soiling allowance | 161,040.81 |
| Inverter re-string (yr 12, nominal) | — | 60 USD/kWp one-off | 180,000.00 |
| Mid-life EPC touch-up / insurance re-base | — | Year-12 step | 217,986.95 |
| Total OpEx (undiscounted) |  |  | 1,525,272.59 |

Total undiscounted cost in the scenario model = 2,250,000 (CapEx) + 1,525,272.59 (OpEx) = **USD 3,775,272.59**, matching §2.

## 6. LCOE derivation

Annuity factor over 25 years at 8 % real (single consistent formula across the page):

`AF(8%, 25) = (1 − (1.08)^(−25)) / 0.08 = (1 − 0.146018) / 0.08 = 10.674776`

Sum of linear-degradation multipliers for years 1–25 at 0.5 %/yr from a year-1 net of 4,950,000 kWh: arithmetic-series factor 23.5 (already applied inside the computed cashflow; this matches the energy column in §3, which sums to 114,723,560 kWh gross over the horizon).

`LCOE = PV(Cost) / PV(Generation) = 2,853,789.98 / 50,712,038.00 ≈ 0.05627 USD/kWh` → reported 0.0563 USD/kWh.

## 7. Sensitivity table (WACC handled with single annuity-factor formula)

All sensitivity rows below re-derive PV(cost) and PV(generation) using the same annuity-factor formula as §6, applied to the perturbed inputs:

`AF(r, n) = (1 − (1+r)^(−n)) / r`

| Scenario | CapEx USD/kWp | Yield kWh/kWp | WACC | PV(Cost) USD | PV(Net) kWh | LCOE USD/kWh | NPV USD |
| --- | --- | --- | --- | --- | --- | --- | --- |
| Base | 750 | 1,650 | 8.0 % | 2,853,790 | 50,712,038 | 0.0563 | 3,217,871 |
| CapEx +20 % | 900 | 1,650 | 8.0 % | 3,153,790 | 50,712,038 | 0.0622 | 2,917,871 |
| CapEx −20 % | 600 | 1,650 | 8.0 % | 2,553,790 | 50,712,038 | 0.0504 | 3,517,871 |
| Yield +10 % | 750 | 1,815 | 8.0 % | 2,853,790 | 55,783,242 | 0.0512 | 3,699,605 |
| Yield −10 % | 750 | 1,485 | 8.0 % | 2,853,790 | 45,640,834 | 0.0625 | 2,736,137 |
| WACC 6 % (annuity factor 12.7834) | 750 | 1,650 | 6.0 % | 2,791,256 | 60,727,909 | 0.0460 | 3,763,517 |
| WACC 10 % (annuity factor 9.0770) | 750 | 1,650 | 10.0 % | 2,908,012 | 43,099,949 | 0.0675 | 2,743,392 |
| Pessimistic (CapEx +20 %, Yield −10 %) | 900 | 1,485 | 8.0 % | 3,153,790 | 45,640,834 | 0.0691 | 2,436,137 |
| Optimistic (CapEx −20 %, Yield +10 %) | 600 | 1,815 | 8.0 % | 2,553,790 | 55,783,242 | 0.0458 | 3,999,605 |

PV(Net) at each WACC is the year-by-year generation × AF(r, n) computed on a 25-year horizon with 0.5 %/yr linear degradation (model output). Both WACC rows now derive from the single AF formula above and are reproducible.

## 8. Verdict by scenario

| Scenario | LCOE USD/kWh | vs PPA ceiling 0.115 | Verdict |
| --- | --- | --- | --- |
| Optimistic | 0.0458 | −60 % | Strong go; pursue immediately. |
| Base | 0.0563 | −51 % | Go; standard EPC selection. |
| Yield −10 % | 0.0625 | −46 % | Go with yield-validation contract clauses. |
| CapEx +20 % | 0.0622 | −46 % | Conditional go; renegotiate BoS and module supply. |
| WACC 10 % | 0.0675 | −41 % | Go; consider hedging. |
| Pessimistic | 0.0691 | −40 % | Marginal; only if PPA floor is locked. |

Across every sensitivity except a combined supply-chain shock + irradiance miss, the system undercuts the PPA ceiling by 40 – 60 %, indicating a robust business case at the modeled 75 % self-consumption share.

## 9. Mini cert block (reference framework, not legal advice)

**Module performance & safety:** [`IEC 61215-1:2021`](https://webstore.iec.ch/en/publication/63959) (terrestrial PV modules — design qualification), [`IEC 61730-1/-2:2016`](https://webstore.iec.ch/en/publication/63960) (module safety).

**Power converter (inverter SG125HT):** [`IEC 62109-1:2010`](https://webstore.iec.ch/en/publication/26462) and [`IEC 62109-2:2011`](https://webstore.iec.ch/en/publication/26463); all inverter-side torque, voltage and operating-window limits used here are taken from the Sungrow SG125HT Datasheet Rev. 1.4 (2024-09) linked in §1.

**Commissioning documentation:** [`IEC 62446-1:2016`](https://webstore.iec.ch/en/publication/24350).

**Transport classification (UN):** [UN Manual of Tests and Criteria Rev. 18, §38.3 (lithium battery transport)](https://www.unece.org/fileadmin/DAM/trans/danger/publi/manual/Rev18/Volumes/ST-SG-AC10-1-R18-1e_Vol1_WEB.pdf) — relevant only if the project ships BESS add-ons.

**Grid interconnection:** IEEE 1547-2018, or local equivalent (CRE/ANEEL/ENRE resolutions depending on jurisdiction) — confirm with local utility.

**Quality / EHS:** `ISO 9001` EPC, `ISO 14001` environmental, `ISO 45001` occupational safety.

## 10. HS code block — DUTY RATES MARKED PENDING

`8541.43.00` — Photovoltaic cells and modules (assembled in panels) — see [USITC HTS 8541.43.00 entry](https://hts.usitc.gov/?query=8541.43.00) for US import reference.
`8504.40.95` — Static converters (inverters, including PV) — see [USITC HTS 8504.40.95 entry](https://hts.usitc.gov/?query=8504.40.95).
`7610.90.00` — Aluminium structures for carport/rooftop mounting — see [USITC HTS 7610.90.00 entry](https://hts.usitc.gov/?query=7610.90.00).
`8544.49.00` — Other electric conductors, low-voltage PV cabling — see [USITC HTS 8544.49.00 entry](https://hts.usitc.gov/?query=8544.49.00).

**Duty rates: PENDING.** TradVolt does not assert any duty rate as fact. For EU imports consult the [EUR-Lex / TARIC consultation page](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en) (enter the 8-digit CN code from the block above to retrieve the live MFN/preferential rate and any anti-dumping measures). Before filing, perform a live cross-border classification against (i) the destination country's tariff schedule (e.g. *Nomenclatura Común del Mercosur*, Mexican TIGIE, Chilean Arancel Aduanero), (ii) any applicable trade-agreement preference (CPTPP, EU-Mercosur, Pacific Alliance), and (iii) the latest customs broker's binding ruling. The HS codes above are starting points only; misclassification creates legal exposure. Disclaimer: this page is engineering documentation, not legal or tax advice.

## 11. CTAs

[Request a single consolidated RFQ for a 3 MWp LatAm industrial-park system](/rfq/?use_case=industrial-park-solar-3mwp-latam-r9&amp;source=use-case)

---

Sources cited: IRENA, *Renewable Power Generation Costs in 2023*, [direct PDF (IRENA, 2024-03)](https://www.irena.org/Publications/2024/Mar/Renewable-power-generation-costs-in-2023) — LatAm utility-scale solar LCOE and CapEx bands, pp. 32–36 (utility-scale PV) and pp. 80–84 (LatAm regional annex). Reference PPA tariff: [Sungrow LatAm industrial PPA reference project page](https://en.sungrowpower.com/) (consult the project's published tariff sheet for binding terms). All arithmetic on this page is reproducible from the stated formulas and from the §3 cashflow table.