title: "Logistics Park Solar 6 MWp in EU — TCO & Landed Cost | Tradvolt"
source_url: "https://tradvolt.com/en/tco/logistics-park-solar-6-mwp-in-eu-tco-landed-cost-tradvolt/"
lang: "en"
description: "computed TCO / landed-cost model for a 6 MWp rooftop logistics-park PV plant in the EU: capex, opex, LCOE, NPV, IRR, payback, year-by-year cash flow. Sources cited per claim."
generator: "tradvolt-tier-c-edge-md"
---

# Logistics Park Solar 6 MWp in EU — TCO & Landed Cost

Reading time ~10 min · Vertical: Logistics & Warehousing · Geography: EU-27 · Evidence date: 2026-02-12 · Limitation: model returns one base case + sensitivity; site-specific EPC pricing, DSO curtailment-share letter, and a binding TARIC ruling must be collected at RFQ stage.

**Verdict (base case).** GO. Over a 25-year horizon at a 6.00% discount rate, the 6,000 kWp rooftop logistics-park PV project returns **NPV = 6,683,610.00 EUR**, **IRR = 16.84%**, **simple payback = 6.01 years**, **discounted payback = 7.60 years**, **LCOE = 0.0874 EUR/kWh** (≈ 8.74 ct/kWh). Equipment: rooftop PV plant. Location: EU-27 logistics park. Horizon: 25 years. Evidence date: 2026-02-12. Limitation: indicative; re-run with site-specific irradiance, EPC bid and DSO tariff.

Decision table — base case | Indicator | Value | Decision band |
| --- | --- | --- |
| NPV (EUR) | 6,683,610.00 | Positive > 0 → GO |
| IRR | 0.1684 | > 6% WACC → GO |
| Simple payback (yr) | 6.01 | < 8 yr → GO |
| Discounted payback (yr) | 7.60 | < 10 yr → GO |
| LCOE (EUR/kWh) | 0.0874 | < industrial retail 0.22 → GO |

## 1. Use case framing

A logistics and distribution park covering ~90,000 m² of warehouse rooftop in the EU-27, with installed PV capacity of 6,000 kWp DC. The plant primarily self-consumes electricity for material-handling (forklifts, conveyors, cold-chain), EV yard-equipment charging, and exports residual energy under net-metering or feed-in-tariff arrangements. The system uses monocrystalline bifacial modules on a ballasted or mechanically-fixed rooftop mounting system, with string inverters sized to a DC/AC ratio of ~1.1. Grid-code compliance is assumed per EU Regulation 2016/631 (RfG) and the relevant Member-State DSO code (e.g. VDE-AR-N 4110 in Germany, CEI 0-21 in Italy).

## 2. Inputs (every cell from a named source)

Table 2.1 — Inputs used in the TCO model  | Input | Value | Unit | Source | Status |
| --- | --- | --- | --- | --- |
| Installed capacity | 6,000 | kWp (DC) | Use-case assumption (engineering brief) | model assumption |
| Specific yield, north-EU range | 950 | kWh/kWp/yr | PVGIS-SARAH2 dataset (JRC) | cited |
| Specific yield, south-EU range | 1,200 | kWh/kWp/yr | PVGIS-SARAH2 dataset (JRC) | cited |
| Capex, low (turn-key ND-EU, >5 MWp) | 700 | EUR/kWp | SolarPower Europe — EU Market Outlook for Solar Power 2024–2028 | cited |
| Capex, base | 850 | EUR/kWp | SolarPower Europe — EU Market Outlook for Solar Power 2024–2028 | cited |
| Capex, high (constrained retrofit) | 1,150 | EUR/kWp | SolarPower Europe — EU Market Outlook for Solar Power 2024–2028 | cited |
| Opex (O&M + insurance) | 1.0 % of capex/yr | % | IRENA — Renewable Power Generation Costs in 2023 | cited |
| Inverter re-investment (year 12) | 8 % of capex | % | IRENA — Renewable Power Generation Costs in 2023 | cited |
| Module degradation | 0.5 %/yr | % | IEC 61215-1:2021 — design qualification | cited |
| Discount rate (WACC) | 6.0 % nominal | % | Tradvolt editorial assumption, mid-cap logistics balance-sheet financing | editorial |
| Economic lifetime | 25 | years | IRENA — Renewable Power Generation Costs in 2023 | cited |
| Self-consumption share | 55 % | % | Tradvolt editorial assumption for a multi-tenant logistics park on diurnal operations | editorial |
| Tariff escalation (self-consumed savings) | 1.6 %/yr nominal | % | Tradvolt editorial bounded default (illustrative; capped range 0–3 %/yr) | model assumption |
| EU industrial retail electricity, excl. VAT | 0.22 | EUR/kWh | Eurostat — electricity prices for industrial consumers (nrg_pc_204) | cited |
| Export tariff (residual self-consumed-vs-export split price) | 0.07 | EUR/kWh | Tradvolt editorial assumption (typical EU feed-in band 5–9 ct/kWh) | model assumption |

## 3. Equipment reference families (illustrative envelope — final selection at RFQ)

The single equipment model for this 6 MWp site is fixed at RFQ stage against an EPC bid and the DSO grid-code letter. The families named below are illustrative envelopes used to bracket capex / inverter count / mounting layout. They are **not** certified as the installed configuration; compliance items in §8 must be re-issued against the actual selected model before FID.

- Modules (illustrative envelope): [LONGi Hi-MO 9](https://www.longi.com/en/products/modules/hi-mo-9/) (up to 670 W, up to 24.8% efficiency, HPBC 2.0 back-contact, 12-yr product / 30-yr power warranty, bifaciality up to 80%); also [LONGi Hi-MO X6](https://www.longi.com/en/products/modules-series/hi-mo-x6/) family (Explorer / Scientist / Guardian / Artist Ultra Black variants, HPBC cell efficiency >25.5%).

- Modules (illustrative envelope): [JinkoSolar Tiger Neo 3.0](https://www.jinkosolar.com/en/site/aboutus) (Anti-Glare / Anti-Dust / AIDC / Fire-Resistant variants).

- String inverters (illustrative envelope): [Sungrow string inverter range](https://www.sungrowpower.com/en/products/string-inverter) (incl. SG125HT C&I 3-phase); and [Huawei FusionSolar](https://solar.huawei.com/en) commercial string-inverter families.

- Mounting system (illustrative envelope): [K2 Systems CrossRail System](https://k2-systems.com/en-us/product-solutions/crossrail-system/) pitched/flat-roof rail family.

- Optional AC-coupled storage (not in this base case): [BYD Energy Storage](https://www.bydenergy.com/) MC Cube / Battery-Box Premium HVS/HVM LFP cabinets; [CATL EnerC](https://www.catl.com/en/ess/) commercial LFP. Cabinet ratings to be confirmed at RFQ.

## 4. computed TCO results (scenario model)

TCO summary | Metric | Value |
| --- | --- |
| Currency | EUR |
| Horizon (years) | 25 |
| Discount rate | 6.00 % |
| Total undiscounted cost (EUR) | 7,141,545.29 |
| Total discounted cost / PV of costs (EUR) | 6,090,383.34 |
| Total undiscounted benefit (EUR) | 26,099,424.88 |
| Total discounted benefit (EUR) | 12,773,993.34 |
| NPV (EUR) | 6,683,610.00 |
| IRR | 0.1684 |
| Simple payback (year) | 6.01 |
| Discounted payback (year) | 7.60 |
| LCOE (EUR/kWh) | 0.0874 |

Year-by-year cash flow | Year | Cost (EUR) | Benefit (EUR) | Net (EUR) | Discount factor | Discounted net (EUR) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 5,100,000.00 | 0.0000 | -5,100,000.00 | 1.00 | -5,100,000.00 | 0.0000 |
| 1 | 51,000.00 | 869,250.00 | 818,250.00 | 0.9434 | 771,933.96 | 5,700,000.00 |
| 2 | 52,020.00 | 882,201.83 | 830,181.83 | 0.8900 | 738,858.87 | 5,671,500.00 |
| 3 | 53,060.40 | 895,346.63 | 842,286.23 | 0.8396 | 707,199.76 | 5,643,142.50 |
| 4 | 54,121.61 | 908,687.30 | 854,565.69 | 0.7921 | 676,896.07 | 5,614,926.79 |
| 5 | 55,204.04 | 922,226.74 | 867,022.70 | 0.7473 | 647,889.80 | 5,586,852.15 |
| 6 | 56,308.12 | 935,967.92 | 879,659.80 | 0.7050 | 620,125.44 | 5,558,917.89 |
| 7 | 57,434.28 | 949,913.84 | 892,479.55 | 0.6651 | 593,549.88 | 5,531,123.30 |
| 8 | 58,582.97 | 964,067.55 | 905,484.59 | 0.6274 | 568,112.23 | 5,503,467.69 |
| 9 | 59,754.63 | 978,432.16 | 918,677.53 | 0.5919 | 543,763.82 | 5,475,950.35 |
| 10 | 60,949.72 | 993,010.80 | 932,061.08 | 0.5584 | 520,458.04 | 5,448,570.60 |
| 11 | 62,168.72 | 1,007,806.66 | 945,637.95 | 0.5268 | 498,150.27 | 5,421,327.74 |
| 12 | 471,412.09 | 1,022,822.98 | 551,410.89 | 0.4970 | 274,034.32 | 5,394,221.10 |
| 13 | 64,680.33 | 1,038,063.04 | 973,382.71 | 0.4688 | 456,359.80 | 5,367,250.00 |
| 14 | 65,973.94 | 1,053,530.18 | 987,556.24 | 0.4423 | 436,797.08 | 5,340,413.75 |
| 15 | 67,293.42 | 1,069,227.78 | 1,001,934.36 | 0.4173 | 418,072.20 | 5,313,711.68 |
| 16 | 68,639.29 | 1,085,159.28 | 1,016,519.99 | 0.3936 | 400,149.32 | 5,287,143.12 |
| 17 | 70,012.07 | 1,101,328.15 | 1,031,316.08 | 0.3714 | 382,994.10 | 5,260,707.41 |
| 18 | 71,412.31 | 1,117,737.94 | 1,046,325.63 | 0.3503 | 366,573.69 | 5,234,403.87 |
| 19 | 72,840.56 | 1,134,392.23 | 1,061,551.67 | 0.3305 | 350,856.64 | 5,208,231.85 |
| 20 | 74,297.37 | 1,151,294.68 | 1,076,997.31 | 0.3118 | 335,812.85 | 5,182,190.69 |
| 21 | 75,783.32 | 1,168,448.97 | 1,092,665.65 | 0.2942 | 321,413.50 | 5,156,279.74 |
| 22 | 77,298.98 | 1,185,858.86 | 1,108,559.87 | 0.2775 | 307,631.02 | 5,130,498.34 |
| 23 | 78,844.96 | 1,203,528.16 | 1,124,683.19 | 0.2618 | 294,438.98 | 5,104,845.85 |
| 24 | 80,421.86 | 1,221,460.72 | 1,141,038.86 | 0.2470 | 281,812.12 | 5,079,321.62 |
| 25 | 82,030.30 | 1,239,660.49 | 1,157,630.19 | 0.2330 | 269,726.25 | 5,053,925.01 |

Reconciliation check: cumulative undiscounted net column at year 25 = −5,100,000 + Σ(t=1..25) Nett; NPV = Σ(t=0..25) Discounted-nett = 6,683,610.00 EUR (headline). Simple payback = 6.01 years (undiscounted cumulative net crosses zero between years 6 and 7); discounted payback = 7.60 years (discounted cumulative net crosses zero between years 7 and 8).

## 5. Scenario set — LCOE band

Table 5.1 — LCOE scenarios (reproduced from scenario model)  | Scenario | Capex EUR/kWp | Yield kWh/kWp/yr | r % | LCOE ct/kWh | Self-consumed savings, undiscounted year-1 (EUR/yr) |
| --- | --- | --- | --- | --- | --- |
| S1 — southern, low capex, soft WACC | 700 | 1,200 | 4 | 4.71 | 871,200 |
| S2 — southern, base | 850 | 1,200 | 6 | 6.72 | 871,200 |
| S3 — northern, base | 850 | 950 | 6 | 8.48 | 689,700 |
| S4 — northern, base, high WACC | 850 | 950 | 8 | 9.98 | 689,700 |
| S5 — constrained retrofit | 1,150 | 950 | 6 | 11.48 | 689,700 |

Self-consumed savings row states undiscounted year-1 savings (55% × annual generation × 0.22 EUR/kWh), reported on an undiscounted basis for an apples-to-apples view against the LCOE band. The computed NPV in §4 uses the discounted cash flow above.

## 6. Sensitivity — LCOE (ct/kWh) vs yield and discount rate

Table 6.1 — capex fixed at 850 EUR/kWp; LCOE in ct/kWh  | Yield (kWh/kWp/yr) ↓ \ r % → | 4 | 6 | 8 |
| --- | --- | --- | --- |
| 900 | 8.21 | 9.07 | 10.66 |
| 950 | 7.78 | 8.48 | 9.98 |
| 1,000 | 7.39 | 8.06 | 9.48 |
| 1,100 | 6.72 | 7.33 | 8.62 |
| 1,200 | 5.68 | 6.72 | 7.90 |

## 7. Verdict-by-scenario

**S1 (southern, low capex, soft WACC)** — GO. LCOE ≈ 4.71 ct/kWh, a wide spread below industrial retail 22 ct/kWh. Strong siting-grade; bid lock-in the EPC price.

**S2 (southern, base)** — GO. LCOE ≈ 6.72 ct/kWh; commercial-grade recommendation.

**S3 (northern, base)** — CONDITIONAL. LCOE ≈ 8.48 ct/kWh below industrial band but tight; proceed only with a bankable EPC and PVGIS-validated yield ≥ 950 kWh/kWp/yr.

**S4 (northern, high WACC)** — CONDITIONAL. At r = 8%, LCOE ≈ 9.98 ct/kWh still leaves a positive spread against 22 ct/kWh retail; desk-check non-grid revenue (capacity payment, flexibility) before FID.

**S5 (constrained retrofit)** — NO-GO. LCOE ≈ 11.48 ct/kWh barely clears grid parity on self-consumption; without subsidy or PPA, do not build as a stand-alone solar asset.

## 8. Certification & compliance pointers (to be re-issued against actual selected equipment at RFQ)

### Compliance pointers (generic; re-bind to selected model + manual revision at RFQ)

- Module design qualification and safety: [IEC 61215-1:2021 (Ed 2.0)](https://webstore.iec.ch/en/publication/61345) and [UL 61730-1 (PV module safety qualification — Part 1)](https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1).

- PCE / inverter safety: [IEC 62109-1:2010 (general)](https://webstore.iec.ch/en/publication/6470) and [IEC 62109-2:2011 (DC-AC inverter particular)](https://webstore.iec.ch/en/publication/6471); used jointly per the IEC 62109 series.

- Mounting / DC cabling per IEC 62548 and HD 60364 series (low-voltage electrical installations).

- Grid code: [EU Regulation 2016/631 (RfG)](https://eur-lex.europa.eu/eli/reg/2016/631/oj); Member-State DSO codes (e.g. [VDE-AR-N 4110](https://www.vde-verlag.de/standards/254900/vde-ar-n-4110-anwendungsregel-2018-11.html) DE; [CEI 0-21](https://www.ceiweb.it/it/normazione/norme-cei-0-21-0-16.aspx) IT).

- Structural adequacy per Eurocode (EN 1991-1-1, EN 1991-1-3) by a chartered engineer.

- Fire safety per IEC 62474 / national transposition (e.g. VDE-AR-E 2100-712 in DE).

- HSE: working-at-height, fall-arrest, lone-worker per national OSHA equivalents (e.g. BG Bau, INAIL).

### Equipment limits (final values fixed only after model is selected)

- Module limits: max system voltage per OEM datasheet (typically 1,500 V DC); mechanical load envelope per [IEC 61215-1:2021](https://webstore.iec.ch/en/publication/61345).

- Inverter limits: MPPT voltage window, max DC short-circuit current, and Q(U) reactive-power capability per the OEM datasheet and [EU 2016/631](https://eur-lex.europa.eu/eli/reg/2016/631/oj).

- Battery limits (if storage is added later): SOC operating window per the OEM product manual (e.g. [BYD Battery-Box Premium HVS/HVM installation manual](https://www.bydenergy.com/); [CATL EnerC product manual](https://www.catl.com/en/ess/)) and [IEC 62485-5:2020 (safe operation of stationary lithium-ion batteries)](https://webstore.iec.ch/en/publication/29086).

Manufacturer declarations of conformity and notified-body certificates are collected at RFQ stage; Tradvolt does not represent any specific certificate number as fact. The equipment envelope in §3 is illustrative; §8 must be re-issued against the actual model + manual revision selected for this site before FID.

## 9. HS code block — duty pending binding TARIC ruling

### Goods classification — duty PENDING

| Component | HS subheading | EU CN code indicative | Duty rate (EU MFN indicative) | Status |
| --- | --- | --- | --- | --- |
| Crystalline silicon PV modules | 8541.43 | 85414300 | 0 % (per EU CN 2024) | PENDING |
| Power inverters (PV) | 8504.40 | 85044090 sub-line | 2.7 % (EU MFN indicative 2024) | PENDING |
| Mounting structures, aluminium/steel | 7610 / 7308 | 76109090 / 73089099 | 3 % indicative | PENDING |
| DC cables, PV-rated | 8544.60 | 85446090 | 3.7 % indicative | PENDING |

#### Lookup instructions

1. Open the [European Commission TARIC consultation](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en).

2. Enter the eight-digit CN code and the destination Member State.

3. Verify: WTO MFN duty, any anti-dumping measure, any anti-subsidy/countervailing measure, any PV-component suspension in force.

4. Confirm any inward-processing relief or other CARGO benefit available to the project SPV.

5. Capture the TARIC reference number and, where the value justifies it, request a Binding Tariff Information (BTI) ruling from the national customs authority.

Disclaimer: values above are indicative CN-line baselines from the public EU TARIC dataset. Final payable duty is determined by the customs authority of clearance at import. Anti-dumping / countervailing measures can override MFN and must be checked by a licensed customs broker before each shipment.

## 10. Risk callouts

- DSO curtailment reduces NPV — request a curtailment-share letter from the operator before FID.

- Roof rights: confirm building permit and roof-warranty alignment for the full 25 years; sub-metering per EU Directive 2012/27/EU.

- Tax treatment (PPA, leasing, CAPEX) materially changes §5 sensitivity — bring tax counsel into the bid loop.

- HS code risk: a binding TARIC ruling (BTI) removes reclassification risk; budgets assume the indicative CN-line duties above.

## 11. CTAs

[Request an RFQ for a 6 MWp logistics-park PV plant](/rfq/)

Editorial notice: this document is a transparent engineering-economics model, not investment advice. Numbers above are reproduced verbatim from the scenario model tables in §4. Re-validate at every site RFQ.