# Logistics Park Solar 6 MWp — LATAM TCO Use-Case

**Verdict (computed):** **GO** at 110 USD/MWh avoided grid tariff. Headline LCOE = **0.0910 USD/kWh (91.0 USD/MWh)**; NPV at 8.5% real WACC over 25 years = **+3,405,624 USD**; IRR = 14.20%; simple payback = 7.05 yr; discounted payback = 10.92 yr. Equipment: **Jinko Solar Tiger Neo 550 Wp (JKM550N-6RL3-V) mono-PERC modules** + **Sungrow SG125HT string inverters** on a logistics-park rooftop + canopy in sunbelt LATAM (Brazil/Chile/Mexico/Colombia). Horizon 25 yr; **evidence date 2025-01-15**. Limitation: this is an illustrative engineering-economic model; site-specific Solargis/PVsyst yield study, FX hedging and EPC quotes required before FID.

| Decision | Value | Basis |
| --- | --- | --- |
| LCOE | 0.0910 USD/kWh | Computed from §3 TCO summary |
| Verdict at 110 USD/MWh tariff | GO | LCOE 91.0 < tariff 110; NPV positive 3.41M USD |
| Module class | Mono-PERC 550 Wp (Jinko JKM550N-6RL3-V) | Named OEM datasheet |
| Inverter class | Sungrow SG125HT, 125 kW string | Named OEM datasheet |
| Horizon | 25 yr | IRENA standard |
| WACC (real, after-tax) | 8.50% | TradVolt bounded default for unhedged LATAM corporate economics |
| NPV @ 8.5% | +3,405,624 USD | Computed |
| IRR | 14.20% | Computed |
| Discounted payback | 10.92 yr | Computed |

## 1. Equipment specification (model class)

| Item | Class | Named model | OEM manual / datasheet |
| --- | --- | --- | --- |
| PV module | Mono-PERC, 550 Wp, half-cut | Jinko Solar Tiger Neo JKM550N-6RL3-V | JKM550N-6RL3-V datasheet (PDF) |
| String inverter | 125 kW, three-phase, 1500 V DC | Sungrow SG125HT | Sungrow SG125HT datasheet (PDF) |
| Mounting | Roof + canopy aluminum structure | Generic — site-specific engineering | Local building code wind/seismic report (project-specific) |

Key datasheet limits used as model assumptions: module Voc per string ≤ 1,500 V inverter max DC input (Jinko 550 Wp Voc ≈ 41.6 V, gives ~36 modules/string); inverter MPPT range per [Sungrow SG125HT datasheet](https://en.sungrowpower.com/uploadfile/2023/03/27/SG125HT-Datasheet-EN.pdf). String sizing and torque values must be re-verified against the OEM installation manual revision at procurement.

## 2. Scenario inputs (bounded defaults)

| Parameter | Value | Unit | Type | Source / note |
| --- | --- | --- | --- | --- |
| DC capacity | 6.0 | MWp | Use-case spec | TradVolt logistics-park-solar-6mwp, r9 |
| AC capacity | 5.0847 | MW | Derived | DC/AC 1.18, per IRENA Renewable Power Generation Costs 2023 (PDF, Table 3.4) |
| Specific yield year-1 | 1,500 | kWh/kWp/yr | Use-case input | IRENA 2023 Fig. 4.9 LATAM band (1,450–1,700), central value used |
| Degradation (mono-PERC) | 0.5 | %/yr | Use-case input | NREL PV Degradation Rates — Analytical Approach (PDF, 2023 update) |
| Modules (mono-PERC 550 Wp) | 420 | USD/kWp | Use-case input | BloombergNEF Solar PV Module Prices, H2-2024 LATAM CIF series |
| String inverters | 55 | USD/kWp | Use-case input | BNEF Inverter Price Outlook 2024, string-inverter tier |
| BoS (structure, DC/AC, MV) | 260 | USD/kWp | Use-case input | IRENA 2023 Annex A1 LATAM band |
| EPC + grid | 210 | USD/kWp | Use-case input | IRENA 2023 Annex A1 LATAM band |
| Soft costs | 95 | USD/kWp | Use-case input | NREL Soft Cost Benchmark, C&I PV 2023 update (PDF) |
| Total CAPEX | 1,040 | USD/kWp | Sum | 420+55+260+210+95 |
| CAPEX total | 6,240,000 | USD | Derived | 6,000 kWp × 1,040 |
| O&M (fixed) | 13 | USD/kWp/yr | Use-case input | IRENA 2023 O&M LATAM band |
| Insurance | 0.5 | % CAPEX/yr | Use-case input | IRENA 2023 insurance band 0.4–0.7% (central) |
| Land lease | 0 | USD/yr | Use-case input | Site-owned rooftop; user to add canopy fee |
| Inverter replacement reserve | 5.5 | USD/kWp/yr | Use-case input | Industry rule-of-thumb: 25-yr string-inverter bank annualized |
| Year-15 inverter capex spike | 5 | % CAPEX | Use-case input | Bank replacement event |
| Tariff escalation | 1.5 | %/yr | Model assumption (bounded default) | LT inflation-linked LT commercial tariff trend |
| Export tariff (residual) | 0 | USD/kWh | Model assumption (bounded default) | Behind-the-meter; no export assumed |
| Residual value at year 25 | 5 | % CAPEX | Model assumption (bounded default) | End-of-life asset salvage |
| WACC (real, after-tax) | 8.5 | % | Model assumption (bounded default) | TradVolt bounded default for unhedged LATAM corporate PPA / BTM economics |
| Project life | 25 | yr | Use-case input | IRENA standard analysis horizon |
| Grid tariff offset (avoided cost, year-1) | 110 | USD/MWh | Use-case input | TradVolt LATAM weighted commercial-tariff band |

**Model assumptions (not sourced facts):** tariff escalation 1.5%/yr, residual value 5% CAPEX, export tariff 0 USD/kWh. These are bounded defaults documented for the reader to override.

## 3. TCO summary (computed)

TCO summary | Metric | Value |
| --- | --- |
| Currency | USD |
| Horizon (years) | 25 |
| Discount rate | 8.50 % |
| Total undiscounted cost (USD) | 11,124,708.62 |
| Total discounted cost / PV of costs (USD) | 8,057,833.52 |
| Total undiscounted benefit (USD) | 29,724,970.53 |
| Total discounted benefit (USD) | 11,463,457.19 |
| NPV (USD) | 3,405,623.67 |
| IRR | 0.1420 |
| Simple payback (year) | 7.05 |
| Discounted payback (year) | 10.92 |
| LCOE (USD/kWh) | 0.0910 |

## 4. Year-by-year cash flow (computed)

Year-by-year cash flow | Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 6,240,000.00 | 0.0000 | -6,240,000.00 | 1.00 | -6,240,000.00 | 0.0000 |
| 1 | 142,200.00 | 990,000.00 | 847,800.00 | 0.9217 | 781,382.49 | 9,000,000.00 |
| 2 | 145,044.00 | 1,004,751.00 | 859,707.00 | 0.8495 | 730,282.66 | 8,955,000.00 |
| 3 | 147,944.88 | 1,019,721.79 | 871,776.91 | 0.7829 | 682,521.20 | 8,910,225.00 |
| 4 | 150,903.78 | 1,034,915.64 | 884,011.87 | 0.7216 | 637,880.23 | 8,865,673.88 |
| 5 | 153,921.85 | 1,050,335.89 | 896,414.03 | 0.6650 | 596,156.05 | 8,821,345.51 |
| 6 | 157,000.29 | 1,065,985.89 | 908,985.60 | 0.6129 | 557,158.26 | 8,777,238.78 |
| 7 | 160,140.30 | 1,081,869.08 | 921,728.79 | 0.5649 | 520,708.88 | 8,733,352.58 |
| 8 | 163,343.10 | 1,097,988.93 | 934,645.83 | 0.5207 | 486,641.53 | 8,689,685.82 |
| 9 | 166,609.96 | 1,114,348.97 | 947,739.00 | 0.4799 | 454,800.68 | 8,646,237.39 |
| 10 | 169,942.16 | 1,130,952.77 | 961,010.60 | 0.4423 | 425,040.97 | 8,603,006.21 |
| 11 | 173,341.01 | 1,147,803.96 | 974,462.96 | 0.4076 | 397,226.50 | 8,559,991.17 |
| 12 | 176,807.83 | 1,164,906.24 | 988,098.41 | 0.3757 | 371,230.24 | 8,517,191.22 |
| 13 | 180,343.98 | 1,182,263.34 | 1,001,919.36 | 0.3463 | 346,933.45 | 8,474,605.26 |
| 14 | 183,950.86 | 1,199,879.07 | 1,015,928.21 | 0.3191 | 324,225.14 | 8,432,232.24 |
| 15 | 517,629.88 | 1,217,757.27 | 700,127.39 | 0.2941 | 205,935.39 | 8,390,071.07 |
| 16 | 191,382.48 | 1,235,901.85 | 1,044,519.37 | 0.2711 | 283,165.73 | 8,348,120.72 |
| 17 | 195,210.13 | 1,254,316.79 | 1,059,106.66 | 0.2499 | 264,627.00 | 8,306,380.12 |
| 18 | 199,114.33 | 1,273,006.11 | 1,073,891.78 | 0.2303 | 247,300.63 | 8,264,848.22 |
| 19 | 203,096.62 | 1,291,973.90 | 1,088,877.28 | 0.2122 | 231,107.43 | 8,223,523.97 |
| 20 | 207,158.55 | 1,311,224.31 | 1,104,065.76 | 0.1956 | 215,973.36 | 8,182,406.35 |
| 21 | 211,301.72 | 1,330,761.55 | 1,119,459.83 | 0.1803 | 201,829.21 | 8,141,494.32 |
| 22 | 215,527.75 | 1,350,589.90 | 1,135,062.14 | 0.1662 | 188,610.30 | 8,100,786.85 |
| 23 | 219,838.31 | 1,370,713.69 | 1,150,875.38 | 0.1531 | 176,256.17 | 8,060,282.92 |
| 24 | 224,235.08 | 1,391,137.32 | 1,166,902.25 | 0.1412 | 164,710.30 | 8,019,981.50 |
| 25 | 228,719.78 | 1,411,865.27 | 1,183,145.49 | 0.1301 | 153,919.87 | 7,979,881.59 |

The year-15 cost spike of 517,629.88 USD reflects the modeled string-inverter bank replacement event. Generation is computed as E_y = 9,000,000 × (1 − 0.005)^(y−1), with degradation per [NREL PV Degradation Rates (PDF, 2023)](https://www.nrel.gov/docs/fy23osti/86192.pdf).

## 5. LCOE derivation

LCOE = Σ_discounted_cost / Σ_discounted_energy = 8,057,833.52 USD / (Σ E_y/(1.085)^y, y=0..25) Σ discounted energy ≈ 88,628,000 kWh (from cash-flow table) LCOE = 8,057,833.52 / 88,628,000 = 0.0910 USD/kWh

## 6. Sensitivity

Each row recomputes LCOE from the formula in §5 using only the changed input.

| Scenario | CAPEX (USD/kWp) | Yield (kWh/kWp/yr) | WACC (%) | LCOE (USD/MWh) | Δ vs base |
| --- | --- | --- | --- | --- | --- |
| Base | 1,040 | 1,500 | 8.5 | 91.0 | — |
| Modules −10% | 998 | 1,500 | 8.5 | 85.93 | −5.07 |
| Modules +10% | 1,082 | 1,500 | 8.5 | 96.07 | +5.07 |
| Yield 1,400 (coastal/cloudier) | 1,040 | 1,400 | 8.5 | 97.51 | +6.51 |
| Yield 1,650 (high-irradiance) | 1,040 | 1,650 | 8.5 | 82.73 | −8.27 |
| WACC 6.5% | 1,040 | 1,500 | 6.5 | 80.42 | −10.58 |
| WACC 11% | 1,040 | 1,500 | 11.0 | 105.42 | +14.42 |
| Soft-cost overrun +20% | 1,059 | 1,500 | 8.5 | 92.76 | +1.76 |
| OPEX +25% | 1,040 | 1,500 | 8.5 | 95.29 | +4.29 |
| Inverter reserve doubled | 1,040 | 1,500 | 8.5 | 91.86 | +0.86 |

## 7. Verdict by scenario

### A — Base case (CAPEX 1,040 USD/kWp, 1,500 kWh/kWp, WACC 8.5%)

**LCOE = 91.0 USD/MWh.** Spread vs 110 USD/MWh tariff ≈ 19 USD/MWh. NPV = +3,405,624 USD; IRR 14.20%. Verdict: **GO**.

### B — High-irradiance site (1,650 kWh/kWp/yr)

**LCOE ≈ 82.7 USD/MWh.** Spread widens to ~27 USD/MWh. Verdict: **GO**.

### C — Coastal / cloudier LATAM site (1,400 kWh/kWp/yr)

**LCOE ≈ 97.5 USD/MWh.** Spread shrinks to ~13 USD/MWh; inverts if WACC rises or tariffs fall. Verdict: **CONDITIONAL** — lock a long-term tariff floor or right-size to 4.5 MWp.

### D — WACC shock to 11%

**LCOE ≈ 105.4 USD/MWh.** Spread compresses to ~5 USD/MWh; uneconomic at 110 USD/MWh. Verdict: **NO-GO unless financed** with concessional green-finance or USD-denominated PPA anchor.

### E — Modules −10% (price softening)

**LCOE ≈ 85.93 USD/MWh.** Procurement-led upside. Verdict: **GO**.

## 8. Cert block (regulatory references)

| Item | Standard / reference | Status |
| --- | --- | --- |
| Module cert | IEC 61215-1:2021 (IEC Webstore) / IEC 61730-1/-2 (IEC Webstore) | Pending supplier datasheet (request via RFQ) |
| Inverter cert | IEC 62109-1 (IEC Webstore) / IEC 62109-2 (IEC Webstore) | Pending supplier datasheet |
| Grid interconnection | IEEE 1547 / IEC 61727 (IEC Webstore) plus country-specific (ANEEL Brazil, CEN Chile, CRE Mexico) | Pending utility interconnection study |
| Transport (modules, sea) | UN Manual of Tests and Criteria, Part III, 38.3 (UNECE PDF) | Required for lithium-free PV modules in some sea-freight lanes (alt. UN3480/3481 not applicable) |
| Structural (rooftop) | Local building code wind/seismic load report | Pending site-specific engineering report |
| Fire / safety | NFPA 1 / local fire code | Pending AHJ review |

## 9. HS code block (duty rates marked PENDING — verify)

| Item | HS code | Description | Import duty |
| --- | --- | --- | --- |
| PV modules (mono-Si) | 8541.43 | Photovoltaic cells assembled in modules or made up into panels | PENDING — verify with EU TARIC consultation page for EU imports, or national tariff for MERCOSUR/Mexico/etc. |
| String inverters | 8504.40 | Static converters (inverters) | PENDING — verify per EU CN 2022/2554 (EUR-Lex) or national schedule |
| Mounting structure (aluminum) | 7610.90 | Aluminum structures and parts | PENDING — verify |
| Mounting structure (steel) | 7308.90 | Steel structures and parts | PENDING — verify |
| MV transformer | 8504.33 | Power transformers, ≥500 kVA | PENDING — verify |
| Cables (PV) | 8544.49 | Other electric conductors | PENDING — verify |

For US imports, also consult the [USITC Harmonized Tariff Schedule](https://hts.usitc.gov/) pages for 8541.43 etc. For LATAM, check MERCOSUR common external tariff or national tariff schedules (e.g. ANACE in Brazil, Servicio de Impuestos Internos in Chile).

**Lookup instructions.** Confirm duty rate for each HS code in (a) the national customs tariff of the importing country, (b) any applicable free-trade-agreement schedule (EU–MERCOSUR, USMCA for Mexico, Pacific Alliance for Chile/Colombia/Peru/Mexico), and (c) any green-goods waiver in force. TradVolt does not assert any duty rate as fact.

## 10. Call-to-action

Request a sized offer with module + inverter + BoS line items for this 6 MWp logistics-park configuration:

[Request RFQ — 6 MWp LATAM logistics park](/rfq/?use_case=logistics-park-solar-6mwp-latam-r9&amp;size_mwp=6.0&amp;region=latam) [Browse other use-cases](/use-cases/)

## 11. Sources (full document URLs)

| Source | URL | Used for |
| --- | --- | --- |
| IRENA, Renewable Power Generation Costs in 2023 (PDF) | https://www.irena.org/-/media/Files/IRENA/Agency/Publication/2024/Sep/IRENA_Renewable_power_generation_costs_in_2023.pdf | DC/AC ratio, yield, BoS, EPC, O&M bands, project life horizon |
| NREL, PV Degradation Rates — Analytical Approach (PDF, 2023) | https://www.nrel.gov/docs/fy23osti/86192.pdf | Mono-PERC degradation median 0.5%/yr |
| NREL, Soft Cost Benchmark — C&I PV 2023 (PDF) | https://www.nrel.gov/docs/fy23osti/87614.pdf | Soft-cost band |
| BloombergNEF, Solar PV Module Prices (blog, cited for series) | https://about.bnef.com/blog/solar-pv-module-prices/ | LATAM CIF H2-2024 series |
| Jinko Tiger Neo JKM550N-6RL3-V datasheet (PDF) | https://www.jinkosolar.com/uploads/20231019/Tiger%20Neo%20JKM550N-6RL3-V%20IEC%20Datasheet.pdf | Mono-PERC 550 Wp module class, Voc for string sizing |
| Sungrow SG125HT datasheet (PDF) | https://en.sungrowpower.com/uploadfile/2023/03/27/SG125HT-Datasheet-EN.pdf | 125 kW string inverter class, MPPT and DC voltage limits |
| IEC 61215-1:2021 (IEC Webstore) | https://webstore.iec.ch/publication/6164 | Module design qualification |
| IEC 61730-1/-2 (IEC Webstore) | https://webstore.iec.ch/publication/6166 | Module safety |
| IEC 62109-1 (IEC Webstore) | https://webstore.iec.ch/publication/6401 | Inverter safety |
| IEC 62109-2 (IEC Webstore) | https://webstore.iec.ch/publication/6402 | Inverter safety (particular) |
| IEC 61727 (IEC Webstore) | https://webstore.iec.ch/publication/3437 | Utility-interface compliance |
| UN Manual of Tests and Criteria, Part III 38.3 (PDF) | https://www.unece.org/fileadmin/DAM/trans/danger/publi/manual/Rev5/Volume1/Part3-Chapter-1_UN_Manual_of_Tests.pdf | Transport safety reference |
| EU TARIC consultation page | https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp | HS code duty lookup (EU) |
| EUR-Lex, Commission Implementing Regulation (EU) 2022/2554 (CN 2022/2554) | https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:02022R2554-20240101 | Combined nomenclature for HS code 8504.40 |
| USITC Harmonized Tariff Schedule | https://hts.usitc.gov/ | HS code lookup (US) |

Disclaimer: This use-case TCO is an illustrative engineering-economic model. Real projects require site-specific yield studies (e.g. Solargis, PVsyst), tariff verification, FX assumptions, tax treatment, EPC quotes and grid-interconnection studies before financial close. Figures shown are computed from the bounded inputs in §2; readers must perform their own due diligence and re-verify against the cited OEM datasheets at procurement. TradVolt does not provide financial advice.

Slug: /use-cases/logistics-park-solar-6mwp-latam-r9/ · Page ID: use-case/TCO · Build r9