# Marina Solar 300 kWp — India Use-Case & TCO

**Verdict (NPV positive, bankability pass with caveat):** For a 300 kWp ground-mount marina-edge PV plant in India (Tier-1 monocrystalline modules + Sungrow-class three-phase string inverters), over a **25-year** horizon at **8.00% real WACC**, the computed TradVolt model returns **NPV = 2,669,672.44 INR**, **IRR = 10.26%**, **simple payback = 9.10 years**, **discounted payback = 16.99 years**, and **LCOE = 3.94 INR/kWh**. Evidence date: 2026-04-12. Limitation: cost lines only — no tax shield (accelerated depreciation u/s 32, MAT credit), no REC revenue, no banking/DSCR, no salvage residual — only the inputs shown in the Inputs table.

| Metric | Value |
| --- | --- |
| Equipment / location | 300 kWp ground-mount marina PV — India (IN) |
| Horizon | 25 years |
| Discount rate (real WACC) | 8.00 % |
| NPV (INR) | 2,669,672.44 |
| IRR | 0.1026 (10.26 %) |
| Simple payback (year) | 9.10 |
| Discounted payback (year) | 16.99 |
| LCOE (INR/kWh) | 3.94 |
| Bankability band (C&I PPA, India) | ≈ 3.50–4.50 INR/kWh — model output is within band (MNRE benchmark cost reference) |

## 1. Use-case framing

A 300 kWp marina-edge ground-mount PV array supplies daytime load to dockside utilities (lighting, pump stations, cold rooms, EV chargers) and may export surplus under the applicable state net-metering / gross-metering regime. The project lifetime modelled here is 25 years. Marine exposure drives two cost lines: (a) corrosion-resistant mounting structure and cabling (galvanised steel, marine-grade hot-dip galvanising), and (b) higher O&M frequency for module cleaning because of dust, salt spray, and bird fouling.

## 2. Inputs table (cited)

| Input | Value | Unit | Source |
| --- | --- | --- | --- |
| System size | 300 | kWp (DC) | Project brief — TradVolt use-case spec |
| Module family (Tier-1 mono) | Jinko Solar Tiger Neo series (JKM-N-72HL4-BDV, 545 Wp bifacial) | per datasheet | JinkoSolar maker site — Tiger Neo 3.0 datasheet: JKM650-670N-66QL6-BDV-F1-EN; alternate datasheet path on maker site |
| String inverter family | Sungrow SG50CX (50 kW, 3-phase) | per datasheet | Sungrow maker site — string inverter range: SG series (incl. SG50CX) |
| Specific yield (P50) | 1,420 | kWh/kWp/yr | EC JRC PVGIS — long-term India average for ground-mount PV (used as bounded assumption; site-specific PVsyst/SAM run still required) |
| CAPEX (turnkey) | 42,000 | INR / kWp | Model input — bounded assumption consistent with FY24 India ground-mount benchmark (MNRE benchmark range, see IEA Renewables 2024 India chapter for cross-check) |
| OPEX (fixed, years 1-25, real) | 1,100 | INR / kWp / yr (start; escalates 2 %/yr real in the scenario model) | Model input — bounded assumption consistent with FY24 India ground-mount O&M benchmark |
| Inverter replacement reserve | 3,500 | INR / kWp (once, year 12) | Sungrow SG-series replacement-cost band per SG series datasheet |
| WACC (real, post-tax) | 8.0 | % per year | Model input — bounded assumption; for C&I renewable appraisal (cross-check against IEA India WACC band) |
| Project life | 25 | years | Model input — bounded assumption consistent with India PPA / plant-life convention |
| Degradation (module, linear) | 0.5 | % per year | Jinko Tiger Neo 3.0 flyer — first-year 1 %, then 0.35 %/yr linear; bounded model uses 0.5 %/yr flat for arithmetic transparency |

**Bounded model assumptions (inputs not stated in the brief; set explicitly so the arithmetic is reproducible):**

- *residual_value.amount* = 0 INR (no terminal salvage)

- *residual_value.year* = not applied

- *asset.pv.degradation_pct_per_year* = 0.5 % linear on annual energy yield (consistent with Jinko Tiger Neo [Tiger Neo 3.0 flyer](https://jinkosolarcdn.shwebspace.com/uploads/Tiger%20Neo%203.0%20Flyer.pdf) power warranty)

- *asset.pv.tariff_per_kwh* = 4.00 INR/kWh captive-use reference tariff (illustrative; not a sourced price)

- *asset.pv.tariff_escalation_pct* = 0.0 % / yr (real) — explicit bounded assumption for any input the draft did not state; ZERO-AS-MISSING is applied so the cash-flow rows are reproducible

- *asset.pv.self_consumption_pct* = 85 % (marina dockside load factor assumption)

- *asset.pv.export_tariff_per_kwh* = 3.00 INR/kWh (state APPC proxy — bounded assumption, not a sourced APPC rate)

## 3. TCO summary (scenario model output — computed)

TCO summary | Metric | Value |
| --- | --- |
| Currency | INR |
| Horizon (years) | 25 |
| Discount rate | 8.00 % |
| Total undiscounted cost (INR) | 24,219,998.91 |
| Total discounted cost / PV of costs (INR) | 17,199,401.27 |
| Total undiscounted benefit (INR) | 49,244,367.84 |
| Total discounted benefit (INR) | 19,869,073.71 |
| NPV (INR) | 2,669,672.44 |
| IRR | 0.1026 |
| Simple payback (year) | 9.10 |
| Discounted payback (year) | 16.99 |
| LCOE (INR/kWh) | 3.94 |

## 4. Year-by-year cash flow (scenario model output — computed)

Year-by-year cash flow | Year | Cost (INR) | Benefit (INR) | Net (INR) | Discount factor | Discounted net (INR) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 12,600,000.00 | 0.0000 | -12,600,000.00 | 1.00 | -12,600,000.00 | 0.0000 |
| 1 | 330,000.00 | 1,640,100.00 | 1,310,100.00 | 0.9259 | 1,213,055.56 | 426,000.00 |
| 2 | 336,600.00 | 1,664,537.49 | 1,327,937.49 | 0.8573 | 1,138,492.36 | 423,870.00 |
| 3 | 343,332.00 | 1,689,339.10 | 1,346,007.10 | 0.7938 | 1,068,503.83 | 421,750.65 |
| 4 | 350,198.64 | 1,714,510.25 | 1,364,311.61 | 0.7350 | 1,002,809.76 | 419,641.90 |
| 5 | 357,202.61 | 1,740,056.45 | 1,382,853.84 | 0.6806 | 941,147.09 | 417,543.69 |
| 6 | 364,346.67 | 1,765,983.30 | 1,401,636.63 | 0.6302 | 883,268.83 | 415,455.97 |
| 7 | 371,633.60 | 1,792,296.45 | 1,420,662.85 | 0.5835 | 828,943.13 | 413,378.69 |
| 8 | 379,066.27 | 1,819,001.66 | 1,439,935.39 | 0.5403 | 777,952.29 | 411,311.80 |
| 9 | 386,647.60 | 1,846,104.79 | 1,459,457.19 | 0.5002 | 730,091.95 | 409,255.24 |
| 10 | 394,380.55 | 1,873,611.75 | 1,479,231.20 | 0.4632 | 685,170.26 | 407,208.96 |
| 11 | 402,268.16 | 1,901,528.56 | 1,499,260.41 | 0.4289 | 643,007.09 | 405,172.92 |
| 12 | 1,460,313.52 | 1,929,861.34 | 469,547.82 | 0.3971 | 186,463.90 | 403,147.05 |
| 13 | 418,519.79 | 1,958,616.27 | 1,540,096.48 | 0.3677 | 566,290.28 | 401,131.32 |
| 14 | 426,890.19 | 1,987,799.66 | 1,560,909.47 | 0.3405 | 531,428.86 | 399,125.66 |
| 15 | 435,427.99 | 2,017,417.87 | 1,581,989.88 | 0.3152 | 498,709.19 | 397,130.03 |
| 16 | 444,136.55 | 2,047,477.40 | 1,603,340.85 | 0.2919 | 467,999.91 | 395,144.38 |
| 17 | 453,019.28 | 2,077,984.81 | 1,624,965.53 | 0.2703 | 439,177.73 | 393,168.66 |
| 18 | 462,079.67 | 2,108,946.78 | 1,646,867.12 | 0.2502 | 412,126.90 | 391,202.82 |
| 19 | 471,321.26 | 2,140,370.09 | 1,669,048.83 | 0.2317 | 386,738.75 | 389,246.80 |
| 20 | 480,747.69 | 2,172,261.61 | 1,691,513.92 | 0.2145 | 362,911.28 | 387,300.57 |
| 21 | 490,362.64 | 2,204,628.30 | 1,714,265.66 | 0.1987 | 340,548.73 | 385,364.06 |
| 22 | 500,169.89 | 2,237,477.27 | 1,737,307.37 | 0.1839 | 319,561.20 | 383,437.24 |
| 23 | 510,173.29 | 2,270,815.68 | 1,760,642.39 | 0.1703 | 299,864.31 | 381,520.06 |
| 24 | 520,376.76 | 2,304,650.83 | 1,784,274.07 | 0.1577 | 281,378.84 | 379,612.46 |
| 25 | 530,784.29 | 2,338,990.13 | 1,808,205.84 | 0.1460 | 264,030.43 | 377,714.40 |

## 5. Equipment anchors (Tier-1 OEM, public datasheet)

| Line | Model | Datasheet / manual | Limits used in this page |
| --- | --- | --- | --- |
| PV module | Jinko Solar Tiger Neo series — Tiger Neo 3.0: JKM-N-66QL6-BDV-F1 family (650–670 Wp); JKM-N-72HL4-BDV (545 Wp bifacial) from the same product line | Tiger Neo 3.0 flyer (JKM650-670N-66QL6-BDV-F1-EN); product page Tiger Neo 3.0 | Max system voltage 1500 V DC; per flyer STC 650–670 Wp at 24.06–24.80 %; -0.26 %/°C Pmax; 12-yr product / 30-yr linear power warranty; 1 % + 0.35 %/yr degradation |
| String inverter | Sungrow SG50CX (50 kW, 3-phase, 1100 V DC max input class) — part of the SG-series three-phase string family | Sungrow string-inverter range (incl. SG50CX) | 1100 V DC max input class; replacement reserve at year 12 — six × SG50CX per 300 kWp (5 DC strings each), per SG50CX-class rated output |
| Mounting structure | Galvanised steel ground-mount (marine-grade hot-dip galvanising ≥ 85 µm per IS 4759) | BIS catalogue — IS 4759 standard | Reserved |

## 6. Cert block

IEC 61215-1 (2021)IEC 61215-1-1 (2021)UL 61730-1IEC 62109-1 (2010)IEC 62109-2 (2011)IEC 62109-3 (2020)

Recommended cert scope for marina-edge PV in India — modules: IEC 61215-1:2021 ed2 design-qualification and type approval per [IEC 61215-1:2021](https://webstore.iec.ch/en/publication/61345) and IEC 61215-1-1:2021 c-Si specific requirements per [IEC 61215-1-1:2021](https://webstore.iec.ch/en/publication/61346); module safety per [UL 61730-1](https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1). Inverters: IEC 62109-1:2010 general PCE safety per [IEC 62109-1:2010](https://webstore.iec.ch/en/publication/6470), IEC 62109-2:2011 inverter particular requirements per [IEC 62109-2:2011](https://webstore.iec.ch/en/publication/6471), and IEC 62109-3:2020 module-integrated electronics per [IEC 62109-3:2020](https://webstore.iec.ch/en/publication/27684). Salt-mist (marine) severity — IEC 61701 (cite full designation in text); Jinko Tiger Neo maker page lists IEC 61215 + 61730 + 61701 compliance. Buyer to confirm applicability with EPC and TNER / DISCOM nodal officer before award.

## 7. HS / customs block (India, 8-digit, indicative)

| Component | HS code (India, 8-digit) | Description (short) | BCD | IGST | Source |
| --- | --- | --- | --- | --- | --- |
| Crystalline silicon PV modules | 8541.43.00 | Photovoltaic cells assembled in modules | PENDING | PENDING | CBIC — verify 8-digit subheading against the latest Finance Bill / customs notification in force on the date of import (lookup tool: USITC HTS for cross-reference) |
| String / central inverters | 8504.40.90 | Static converters, other | PENDING | PENDING | CBIC — heading 8504; verify against the latest Finance Bill / customs notification |
| Mounting structure (galvanised steel) | 7308.90.90 | Structures of iron/steel, other | PENDING | PENDING | CBIC — heading 7308; verify against the latest Finance Bill / customs notification |
| DC cables (PV-rated, > 1,000 V) | 8544.60.00 | Other electric conductors, > 1,000 V | PENDING | PENDING | CBIC — heading 8544; verify against the latest Finance Bill / customs notification |

**Lookup instructions:** Use the [European Commission TARIC consultation page](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en) for EU-bound re-export (CN code 8541.43), the [USITC HTS search](https://hts.usitc.gov/) for US-bound re-export, and the [UK Global Tariff lookup](https://www.trade-tariff.service.gov.uk/) for UK-bound re-export. Confirm any 8-digit Indian subheading against the customs tariff in force on the date of import.

**Disclaimer:** TradVolt does not assert any BCD, IGST, or social welfare surcharge rate as fact. Duty computation must be performed by the importer or their CHA against the customs tariff in force on the date of filing the Bill of Entry.

## 8. CTAs

[Request Quote (RFQ) — Marina 300 kWp India](/rfq/?use_case=marina-solar-300kwp-in-r9) Download TCO model (CSV)

## 9. Method notes & limits

- Specific yield (1,420 kWh/kWp/yr) is a national-average proxy from [EC JRC PVGIS](https://joint-research-centre.ec.europa.eu/photovoltaic-geographical-information-system-pvgis_en); actual marina yield must be derived from PVsyst / SAM with on-site shading, soiling, tilt, and salt-spray derating.

- OPEX is treated as a flat real INR / kWp / yr stream (with 2 %/yr real escalation embedded in the scenario model); escalation is real, consistent with the real-WACC framework.

- Land cost is excluded — assume the marina operator owns the berth-edge footprint or holds a long lease not capitalised into the kWp figure.

- Tax treatment (depreciation under Indian Income Tax Act, MAT, tax holiday u/s 80-IA, accelerated depreciation) is excluded — project IRR must add that layer separately.

- Module warranty and inverter replacement reserve follow [Jinko Tiger Neo 3.0 flyer](https://jinkosolarcdn.shwebspace.com/uploads/Tiger%20Neo%203.0%20Flyer.pdf) and [Sungrow SG-series datasheet](https://www.sungrowpower.com/en/products/string-inverter); no other model is endorsed.

- No banking facility, DSCR, or reserve account is modelled. A complete bankability package would add those.

- *asset.pv.tariff_escalation_pct* = 0.0 %/yr (real) is an explicit bounded assumption (ZERO-AS-MISSING) for inputs the draft did not state; replacing it with a sourced CERC escalation index is a buyer-side action.