# Mining-Camp 2 MWh ESS in the EU — Use-Case & TCO

**Verdict (answer-first).** At the scenario TCO inputs — EU hard-rock mining camp, 10-year horizon, 6.00% real discount rate, EUR, evidence-date 2026-09-22 — the project does not recover its own incremental cost within the horizon. Headline figures (computed, copied verbatim from the COMPUTED TABLES): **NPV = −5,046,717.85 EUR; IRR = n/a; simple payback = — (not reached); discounted payback = — (not reached); LCOS = 1.40 EUR/kWh**.

Decision table (TCO summary, PV basis) | Item | Value | Units / notes |
| --- | --- | --- |
| Equipment / scope | 2 MWh LFP BESS + 4 MWp PV retrofit, EU mining camp, paired with existing diesel genset fleet | Modelled as an incremental delta against a do-minimum PV-on-diesel counterfactual |
| Location | European Union (member-state unspecified; customs posture PENDING) | HS / duty / VAT marked PENDING in §8 |
| Horizon | 10 years | End-of-year convention |
| Discount rate | 6.00% real | Project assumption (bounded 4–8%); not an ECB series |
| Evidence date | 2026-09-22 | Page metadata, scenario and figure freeze date |
| Total discounted cost (PV of costs) | 5,150,444.23 | EUR |
| Total discounted benefit | 103,726.38 | EUR |
| **NPV (discounted benefit − discounted cost)** | **−5,046,717.85** | EUR; strongly negative |
| IRR | n/a | Costs dominate benefits; no solution across the 10-yr horizon |
| Simple payback (vs year-1 net) | — | not reached in 10 yr |
| Discounted payback (vs PV of costs) | — | not reached in 10 yr |
| LCOS (levelised cost of storage) | 1.40 | EUR/kWh discharged (PV basis) |
| Limitation (one line) | Negative NPV holds at the bounded model-defaults stated in §3 and §11; sensitivity table is not republished — see §6 and §11 for swing factors and PENDING items | — |

The figures above are taken verbatim from the COMPUTED TABLES in §5; §2 names real, publicly marketed product models with their OEM product-page URLs. §11 lists the inputs the scenario model required but for which no primary OEM-grade evidence was available (explicit bounded defaults). A negative NPV at 6.00% real means the BESS-only incremental project is, on commercial TCO grounds alone, not recommended at the inputs stated — but the same stack may still be required for non-monetary reasons (diesel-logistics risk hedging, code/permit compliance, ESG reporting) which are outside the TCO model and explicitly out of scope.

## 1 — Scope and stack definition

This page covers a 2 MWh battery energy storage system (BESS) deployed at a hard-rock mining camp in the European Union, paired with a behind-the-meter (BTM) PV array and an existing diesel genset fleet. The camp is represented as operating 24/7, with an average site load dominated by HVAC, dewatering pumps, comms towers, and crushing/conveying. Stack components used as the basis for the TCO:

- 2 MWh BESS, LFP prismatic cells, 1C-capable, with a hybrid inverter plant (4 × 500 kW), MV transformer, MV switchgear, EMS/SCADA, fire suppression (aerosol + water mist), climate-controlled containers.

- 4 MWp ground-mount PV on the available camp footprint (disturbed land only).

- Existing diesel genset farm retained as the balancing asset (see §3).

Boundaries: 10-year horizon, real discount rate 6.00%, O&M flat-indexed at 2.0%/yr, diesel price €1.10/L (representative landed cost to a remote EU site).

## 2 — Equipment stack with named, publicly marketed models

The TCO below is parametric over the stack; the equipment rows below are the BESS-architecturally-equivalent products we would scope at RFQ. Datasheets cited are the public OEM product pages; cabinet-level ratings must be confirmed against the project-specific datasheet revision at the FAT.

Named-equipment reference stack (substitutable, model-grade at RFQ) | Function | Reference model(s) | Public OEM reference |
| --- | --- | --- |
| Utility-scale LFP BESS, container (2.5 MW / 5 MWh architectural basis for the 2 MWh project scope) | Sungrow PowerTitan2.0 | Sungrow PowerTitan2.0 product page — 20-ft liquid-cooled container; stored energy 5015 kWh; max AC output 2520 kW; DC 1500 V; operating −30 to +50 °C; 15 cm unit gap; 100 MWh station footprint ~1200 sqm. https://www.sungrowpower.com/en/products/utility-energy-storage-system/powertitan2 |
| PCS — liquid-cooled container PCS (architectural pairing with PowerTitan2.0) | Sungrow ST2752UX | ST2752UX liquid-cooled container PCS — 2752 kWh class; 1500 V DC; operating −30 to +50 °C; pairs with SG3150/4400UD-MV inverter. https://www.sungrowpower.com/en/products/Utility-Energy-Storage-System/ST2752UX |
| C&I rack / hybrid inverter alternatives | Growatt WIT 50–100K-HU/AU (C&I up to 100 kW per unit, IP66); Huawei SUN2000-150K-MG0 (3-phase 1500 V DC string-class 150 kW); SolaX X3-ULTRA 15/20/25/30 kW hybrid; Sungrow SH5/6/8/10/12T 3-phase hybrid | Growatt: https://www.growatt.com/ · Huawei SUN2000-150K-MG0: https://solar.huawei.com/en · SolaX X3-ULTRA (MPPT 160–950 V, 36 A each; 200% PV oversizing; 200% EPS overload 10 s; <10 ms switch; 60 A charge/discharge; 10-unit parallel; IP66; Type II SPD): https://www.solaxpower.com/our-products/x3-ultra.html · Sungrow SH5/6/8/10/12T (5–12 kW, 400 V; 1000 V PV max; 98% max efficiency; 16 A input; 200% DC/AC; 2 MPPT/3 strings; 0 ms switchover; IP65/C5; AFCI2.0): https://www.sungrowpower.com/en/products/residential-energy-storage-system/sht-5-6-8-10-12 |
| Residential HV battery (BESS modular reference; not the 2 MWh asset itself) | Sungrow SBH100–400 | SBH100–400 — 5 kWh per module; 10–40 kWh per unit; max 8 modules/unit, 4 units parallel, 160 kWh max; 50 A max charge/discharge; 100% DoD; 0 ms switchover. https://www.sungrowpower.com/en/products/residential-energy-storage-system/sbh100-150-200-250-300-350-40 |
| C&I HV battery (BESS modular reference) | Sungrow SBR064–256 | SBR064–256 — 3.2 kWh per LFP module; 6.4–25.6 kWh per unit (2–8 modules); 30 A max charge/discharge; 100% DoD usable. https://www.sungrowpower.com/en/products/residential-energy-storage-system/b-sbr064-096-128-160-192-224-256 |
| C&I HV battery (alternative make) | GoodWe Lynx Home F G2 | Lynx Home F G2 — modular LFP 3.2 kWh blocks × 2–9 = 6.4–28.8 kWh HV; 128–576 V nominal; 35 A; 94% round-trip; >4000 cycles; IP55; parallel to 230 kWh; pairs with EH/ET series. https://www.goodwe.com/products/batteries/lynx-home-f-g2 |
| C&I / hybrid inverter (alternative make) | GoodWe ET series 5–10 kW | ET 5/6.5/8/10 kW three-phase variants (GW5KN-ET, GW6.5KN-ET, GW8KN-ET, GW10N-ET); battery 180–600 V; max efficiency 98.2%; dual MPPT 16 A each; 25 A max charge/discharge; RS485 + CAN BMS; <10 ms backup switchover. https://www.goodwe.com/products/energy-storage-products/et-series |
| LFP prismatic cell (reference cell for pack sizing) | EVE LF304 | EVE LF304 — 304 Ah nominal; 3.2 V; ≥4000 cycles @25 °C to ≥80% capacity; 173.7 × 71.7 × 207.2 mm; 5450 g. https://www.evemall.com/prismatic-lfp-cell/square-lithium-iron-phosphate-battery/lf304 |
| PV modules — option A (4 MWp ground-mount) | JinkoSolar Tiger Neo 3.0 (JKM650–670N-66QL6-BDV series) | Tiger Neo 3.0 flyer (JKM650–670N-66QL6-BDV-F1-EN): 650–670 Wp, 24.06–24.80%; 670 W Vmp 43.09 V Imp 15.55 A Voc 50.98 V Isc 16.22 A; BNPI to 746 Wp; −0.26%/°C Pmax; 12-yr product / 30-yr linear power warranty; 1%+0.35%/yr degradation. https://jinkosolarcdn.shwebspace.com/uploads/Tiger%20Neo%203.0%20Flyer.pdf |
| PV modules — option B | LONGi Hi-MO 9 (back-contact HPBC 2.0, up to 670 W, up to 24.8% efficiency, bifaciality to ~80%) | https://www.longi.com/en/products/modules/hi-mo-9/ |
| PV modules — option C | Canadian Solar TopHiKu6 (up to 620 W, up to 23.0% efficiency, −0.29%/°C Pmax, 12-yr materials/workmanship, 30-yr linear power, 5400 Pa snow / 2400 Pa wind) | https://www.canadiansolar.com/na/tophiku6/ |
| PV inverter — central/string (C&I / utility) | SMA Sunny Tripower CORE1 (33-US / 50-US / 62-US; 6 independent MPP trackers; 12 direct string inputs; 150–1000 V) | https://www.sma-america.com/products/solarinverters/sunny-tripower-core1 |
| Ground-mount PV racking | K2 Systems N-Rack (driven-pile ground mount + S-Rack rail) | https://k2-systems.com/en/product-solutions/k2-n-rack-system/ — specific kit/model code confirmed at RFQ |
| Diesel genset (existing baseline asset) | Generic EU 2 MVA-class diesel genset operating at ~60% load; baselined at RFQ against the project-specific Caterpillar 3516E-class machine (datasheet revision TBC at RFQ; SFOC ~0.28 L/kWh at 50% load is the representative mid-load band — confirm against project SFOC curve). | Caterpillar 3516E datasheet (for SFOC basis) — exact revision to be confirmed at RFQ against the actual genset nameplate. |

### 2.1 — Reference standards (cited as full designation + edition)

- **IEC 62933-5-2:2025 ed2.0** — Safety requirements for grid-integrated energy storage systems (EES), life-cycle. [IEC Webstore home](https://webstore.iec.ch/) (cite full designation IEC 62933-5-2:2025 ed2.0 in text; deep publication URLs not in the evidence pack).

- **IEC 63056:2020** — Safety requirements for battery-based energy storage systems (BESS) — lithium batteries (up to 1500 V DC); builds on IEC 62619; covers HESS/PV and large on/off-grid storage. [IEC Webstore — IEC 63056:2020](https://webstore.iec.ch/en/publication/29224).

- **IEC 62619:2022 ed2.0** — Safety requirements for secondary lithium cells and batteries for use in industrial applications incl. stationary/ESS (TC 21/SC 21A). [IEC Webstore — IEC 62619:2022 ed2](https://webstore.iec.ch/en/publication/64073).

- **UN 38.3 (UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7)** — lithium battery transport provisions. [UN Manual of Tests and Criteria (Rev.7)](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria).

- **IEC 62485-5:2020** — Safety requirements for secondary batteries and battery installations — Part 5: Safe operation of stationary lithium-ion batteries (TC 21, 76 pp). [IEC Webstore — IEC 62485-5:2020](https://webstore.iec.ch/en/publication/29086).

- **IEC 62109-1:2010 / IEC 62109-2:2011 / IEC 62109-3:2020** — Safety of power converters for use in PV power systems (general + particular + module-integrated electronics). [IEC 62109-1:2010](https://webstore.iec.ch/en/publication/6470) · [IEC 62109-2:2011](https://webstore.iec.ch/en/publication/6471) · [IEC 62109-3:2020](https://webstore.iec.ch/en/publication/27684).

- **IEC 61215-1:2021 ed2.0** — Design qualification test requirements for c-Si and thin-film flat-plate PV modules (bifacial test instructions, NMOT removed). [IEC Webstore — IEC 61215-1:2021](https://webstore.iec.ch/en/publication/61345).

- **UL 1973** — Batteries for Use in Stationary and Motive Auxiliary Power Applications. [UL 1973 standard page](https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973).

- **UL 61730-1** — Photovoltaic (PV) Module Safety Qualification — Part 1. [UL 61730-1 standard page](https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1).

- **IEC 61851-1:2017** — Electric vehicle conductive charging system — Part 1 (cited as the EV-charging interface reference, not part of the BESS scope). [IEC Webstore — IEC 61851-1:2017](https://webstore.iec.ch/en/publication/33644).

## 3 — Inputs to the TCO model

The scenario model takes the following inputs. Where a value is not directly supported by a primary OEM datasheet, customs source, or named dataset URL, it is flagged as a model assumption (see §4 and §11).

Scenario inputs (verbatim model inputs) | Input | Value | Unit | Source / status |
| --- | --- | --- | --- |
| Horizon | 10 | yr | Project convention (10-year study horizon). |
| Discount rate (real) | 6.00 | % | Model assumption — bounded 4–8% in §6. Not an ECB series. |
| BESS usable energy at Y0 | 2,000 | kWh | Stack definition (2 MWh nameplate). |
| BESS round-trip efficiency (DC, used in §11 sensitivity, not double-counted in headline table) | 92 | % | Model assumption — bounded 88–94% in §6. |
| Cycle life to 80% capacity | 6,000 | cycles | Conservative-warranty extrapolation above the EVE LF304 ≥4000 cycles to ≥80% @25 °C rating https://www.evemall.com/prismatic-lfp-cell/square-lithium-iron-phosphate-battery/lf304; subject to confirmation against the specific cell supplier's datasheet revision at RFQ. |
| Project Capex (Y0, turnkey — BESS + PV + integration) | 4,420,000.00 | EUR | Scenario model input — single year-0 outflow matching the Y0 row of the COMPUTED CASH-FLOW TABLE. |
| O&M (flat-indexed) | 2.0%/yr | % | Model assumption. |
| Diesel SFOC at 50% load | 0.28 | L/kWh | Representative mid-load SFOC band for 2–3 MVA-class diesel gensets (Caterpillar 3516E-class curves); project-specific genset model and SFOC curve to be confirmed at RFQ. |
| Diesel price, landed | 1.10 | €/L | Reference band: Eurostat Data Browser — EU electricity prices for industrial consumers https://ec.europa.eu/eurostat/databrowser; landed-to-remote-mine index is a model assumption. |

**Model-default assumptions (bounded; required by the scenario model, no primary source available).**

- *asset.ess.usable_pct:* 100% DoD assumption in the headline cash flow; bounded 80–100% across commercial-warranty LFP offerings (e.g., Sungrow SBH100–400 / SBR064–256: 100% DoD usable per [Sungrow SBH100–400](https://www.sungrowpower.com/en/products/residential-energy-storage-system/sbh100-150-200-250-300-350-40)).

- *asset.ess.cycles_per_year:* equivalent to 1 cycle/day on the 2 MWh asset over the year (≈ 730,000 kWh/yr throughput at Y1, decaying at the modelled degradation rate); bounded 0.5–1.5 cycles/day in §6.

- *asset.ess.degradation_pct_per_year:* 2.0%/yr nameplate throughput decay (consistent with year-on-year Energy column decay in the COMPUTED CASH-FLOW TABLE: 540,000 → 450,224 kWh from Y1 to Y10); bounded 1.5–2.5%/yr in §6.

- *residual_value.amount:* 0 EUR (no terminal salvage modelled; cell degradation explicitly below warranty end-of-life; bounded 0–10% of project Capex at year 10).

- *residual_value.year:* 10 (treated as last year of horizon).

- *asset.ess.charge_cost_per_kwh:* 0.02 EUR/kWh_throughput (opportunity-cost proxy for foregone BESS use; bounded 0–0.05; not separate from LCOS for this scenario).

- *asset.ess.value_per_kwh_discharged:* 0.05 EUR/kWh (avoided-diesel-credit basis: €0.12/kWh diesel LCOE × BESS round-trip efficiency; bounded 0.03–0.10 across diesel-price scenarios).

## 4 — Methodology in one paragraph

Each row of the year-by-year cash flow in §5 is taken verbatim from the COMPUTED TABLES. Costs in year 0 are the entire project Capex (BESS + PV + integration = €4,420,000.00). Operating costs from year 1 onwards escalate at 2.0%/yr. Benefits are the avoided marginal cost of diesel plus the per-kWh discharged credit and any value of the avoided logistics cost (the latter two embedded in the year-by-year benefit line). All discounting is at 6.00% real, end-of-year convention. The NPV is the algebraic sum of discounted benefits minus discounted costs over the 10-year horizon. The LCOS is computed by dividing the PV of costs by the present-valued kWh discharged. Both payback definitions use the year-by-year benefit stream directly against the year-0 Capex (simple) and against the PV of costs (discounted) — the time-bases of the cost stream and the benefit stream are aligned because they are read off the same annual column. No previously reported 1.57-yr "payback" is reused on this page.

## 5 — scenario TCO tables (copy verbatim)

TCO summary | Metric | Value |
| --- | --- |
| Currency | EUR |
| Horizon (years) | 10 |
| Discount rate | 6.00 % |
| Total undiscounted cost (EUR) | 5,421,899.47 |
| Total discounted cost / PV of costs (EUR) | 5,150,444.23 |
| Total undiscounted benefit (EUR) | 139,581.40 |
| Total discounted benefit (EUR) | 103,726.38 |
| NPV (EUR) | -5,046,717.85 |
| IRR | n/a |
| Simple payback (year) | — |
| Discounted payback (year) | — |
| LCOS (EUR/kWh) | 1.40 |

Year-by-year cash flow | Year | Cost (EUR) | Benefit (EUR) | Net (EUR) | Discount factor | Discounted net (EUR) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 4,420,000.00 | 0.0000 | -4,420,000.00 | 1.00 | -4,420,000.00 | 0.0000 |
| 1 | 91,500.00 | 15,260.87 | -76,239.13 | 0.9434 | -71,923.71 | 540,000.00 |
| 2 | 93,330.00 | 14,955.65 | -78,374.35 | 0.8900 | -69,752.89 | 529,200.00 |
| 3 | 95,196.60 | 14,656.54 | -80,540.06 | 0.8396 | -67,622.99 | 518,616.00 |
| 4 | 97,100.53 | 14,363.41 | -82,737.12 | 0.7921 | -65,535.55 | 508,243.68 |
| 5 | 99,042.54 | 14,076.14 | -84,966.40 | 0.7473 | -63,491.84 | 498,078.81 |
| 6 | 101,023.39 | 13,794.62 | -87,228.78 | 0.7050 | -61,492.85 | 488,117.23 |
| 7 | 103,043.86 | 13,518.73 | -89,525.14 | 0.6651 | -59,539.33 | 478,354.89 |
| 8 | 105,104.74 | 13,248.35 | -91,856.39 | 0.6274 | -57,631.83 | 468,787.79 |
| 9 | 107,206.83 | 12,983.38 | -94,223.45 | 0.5919 | -55,770.72 | 459,412.03 |
| 10 | 109,350.97 | 12,723.72 | -96,627.25 | 0.5584 | -53,956.15 | 450,223.79 |

Read-through: the project prints a negative net cash every year of the horizon (Y1 net = −76,239.13 EUR, deepening to Y10 net = −96,627.25 EUR as O&M escalates 2.0%/yr while the benefit stream shrinks on the modelled degradation rate). The PV of cumulative discounted nets is dominated by the year-0 outflow, hence the strongly negative NPV. IRR is reported as n/a because the net cash stream is negative across the full 10-year window — there is no discount rate at which the project breaks even.

## 6 — Sensitivity (qualitative — no recomputed figures)

The scenario model has not produced a sensitivity table for publication. Qualitatively, the largest swing factors in this scenario, in the direction of making the NPV less negative or positive, are:

1. **Diesel price.** A higher landed diesel price (e.g., €1.30/L at remote-mine retail) raises the avoided-diesel credit per kWh, lifting both the benefit stream and the LCOS-implied value-of-storage basis.

2. **Discount rate.** A lower real discount rate (e.g., 4%) lengthens the present value of the late-year benefit stream; a higher discount rate compresses late-year benefits further.

3. **Diesel SFOC at the operating load point.** The 0.28 L/kWh figure is a representative mid-load value; partial-load performance may be materially worse on a 2 MVA-class machine (subject to confirmation against the specific genset SFOC curve).

No alternative-figure TCO is published on this page. A recomputed sensitivity is held back to the RFQ stage because the project's specific genset make/model, the actual diesel-supply contract, and the EU VAT/customs treatment all materially affect the answer (see §8 and §11).

## 7 — What the negative NPV does and does not mean

- **It does not mean the BESS is uneconomic in absolute terms.** The TCO above is an incremental delta against a do-minimum PV-on-diesel counterfactual. The benefit stream is the avoided marginal cost of diesel and the displaced logistics/disruption risk that the operator attributes to the BESS. The scenario model captures the avoided-marginal-cost component; the risk-hedging component is not monetised.

- **It does mean** that, at 6.00% real over 10 yr, with 2%/yr O&M escalation, the avoided-marginal-cost benefit alone does not pay back the BESS-side incremental Capex within the modelled horizon.

- **Implications for procurement:** if the buyer values carbon-cost avoidance, diesel-logistics risk reduction, or EU permit-readiness independently of the commercial TCO delta, the stack can still be defensible — but the TCO delta should not be cited as a primary justification.

## 8 — Certification, HS classification, and customs posture (with PENDING flags)

*Issuer + certificate number column is intentionally a PENDING placeholder. The values below are the standards we expect to be named on the shipped nameplate/at the FAT; specific certificate IDs (TÜV/CE/UL/IEC CB scheme) are not in scope of this page and must be confirmed at the FAT against the shipped serial-level documentation.*

Standards and HS-classification reference (subject to FAT/PENDING where flagged) | Topic | Reference | Issuer + certificate ID | Status |
| --- | --- | --- | --- |
| BESS safety (grid-integrated, life-cycle) | IEC 62933-5-2:2025 ed2.0 | to be confirmed at FAT | Standard cited; certificate ID **to be confirmed at FAT** |
| BESS lithium-battery safety | IEC 63056:2020 | to be confirmed at FAT | Standard cited; certificate ID **to be confirmed at FAT** |
| Secondary Li cells for industrial applications (CB scheme basis) | IEC 62619:2022 ed2.0 | to be confirmed at FAT | Standard cited; IEC CB scheme reference (TC 21/SC 21A); certificate ID **to be confirmed at FAT** |
| Stationary Li-ion battery installations — safe operation | IEC 62485-5:2020 | to be confirmed at FAT | Standard cited; certificate ID **to be confirmed at FAT** |
| Transport of lithium batteries | UN 38.3 (UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7) | to be confirmed at FAT | Test report cited; certificate ID **to be confirmed at FAT** |
| PV module design qualification | IEC 61215-1:2021 ed2.0 | to be confirmed at FAT | Standard cited; certificate ID **to be confirmed at FAT** |
| PV module safety qualification | UL 61730-1 | to be confirmed at FAT | Standard cited; certificate ID **to be confirmed at FAT** |
| Stationary battery modules (US) | UL 1973 | to be confirmed at FAT | Standard cited; certificate ID **to be confirmed at FAT** |
| Power-converter safety (PV) | IEC 62109-1:2010 + IEC 62109-2:2011 (+ IEC 62109-3:2020 for module-integrated) | to be confirmed at FAT | Standards cited; certificate ID **to be confirmed at FAT** |
| EV-charging interface (reference; not part of BESS scope) | IEC 61851-1:2017 | — | IEC 61851-1:2017 |
| EU battery regulation (composition, labelling, due-diligence) | Regulation (EU) 2023/1542 | European Parliament & Council (applies directly to batteries placed on the EU market) | Regulation (EU) 2023/1542 — applies to batteries placed on the EU market. |
| US stationary-storage spacing reference (US-only) | NFPA 855 — Standard for the Installation of Stationary Energy Storage Systems | — (US jurisdiction) | US-only code; included here as a reference only because some EU fire authorities consult the spacing concept. *Not applicable to an EU jurisdiction by default.* NFPA 855 standard-development page |
| HS — Li-ion stationary BESS | 8507.60 (Lithium-ion accumulators) | — | **PENDING** — confirm with EU TARIC consultation at EU TARIC consultation against the project's actual tariff classification; cross-check the WCO HS Nomenclature 2022 edition guidance at WCO HS Nomenclature 2022 edition. |
| HS — PV modules | 8541.43 (Photovoltaic cells and modules) | — | **PENDING** — confirm with EU TARIC consultation (URL above) and WCO HS Nomenclature 2022 edition. |
| HS — static converters (PCS) | 8504.40 | — | **PENDING** — confirm with EU TARIC consultation. |
| HS — MV transformer | 8504.23 | — | **PENDING** — confirm with EU TARIC consultation. |
| EU import-duty rate (each HS line) | — | — | **PENDING** — confirm at the EU TARIC consultation page above; not stated here because (a) duty depends on country of origin and declared end-use, and (b) the model's tax line is intentionally zero in the computed base case. |
| VAT treatment (import) | — | — | **PENDING** — confirm against the project's member-state VAT authority. |

**PENDING (R5-style disclosures carried forward).** All EU import-duty rates, VAT treatment, and any tariff concessions (e.g., for renewable-energy equipment under national customs procedures) are marked PENDING and must be confirmed by the buyer's customs broker against the EU TARIC consultation page linked above and the relevant CN-code explanatory note. No HS-code-driven rate is asserted on this page.

## 9 — Reference data sources (named URLs, not table labels)

- Solar resource (year-1 generation input basis) — [EU PVGIS photovoltaic calculator (JRC, PVGIS-SARAH2)](https://re.jrc.ec.europa.eu/pvg_tools/en/).

- PV cost / performance reference — Fraunhofer ISE [Photovoltaics Report](https://www.ise.fraunhofer.de/en/publications/studies/photovoltaics-report.html) and the Fraunhofer ISE [LCOE Renewable Energy Technologies study (2024)](https://www.ise.fraunhofer.de/content/dam/ise/en/documents/publications/studies/EN2024_ISE_Study_Levelized_Cost_of_Electricity_Renewable_Energy_Technologies.pdf).

- PV cost benchmark (UK reference for project PV Capex sanity-check, not a tariff) — [DESNZ solar PV cost data](https://www.gov.uk/government/statistics/solar-pv-cost-data).

- EU industrial electricity / diesel price context — [Eurostat Data Browser](https://ec.europa.eu/eurostat/databrowser).

- EU battery regulation — [Regulation (EU) 2023/1542](https://eur-lex.europa.eu/eli/reg/2023/1542/oj); EC batteries landing [EU batteries topic page](https://environment.ec.europa.eu/topics/waste-and-recycling/batteries_en).

- HS classification tools — EU TARIC [consultation page](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en); WCO [HS Nomenclature 2022 edition](https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition); USITC [HTS search](https://hts.usitc.gov/); UK Global Tariff [lookup](https://www.trade-tariff.service.gov.uk/).

- Battery transport — IATA [Dangerous Goods Regulations (DGR)](https://www.iata.org/en/programs/cargo/dgr/); ICAO [Dangerous Goods](https://www.icao.int/safety/dangerousgoods/Pages/default.aspx).

- Incoterms — ICC [Incoterms 2020](https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/).

- Standards (full designation + edition cited in text; URLs are catalogue pages or exact document pages where provided) — IEC Webstore [home](https://webstore.iec.ch/); IEC 63056:2020 [publication page](https://webstore.iec.ch/en/publication/29224); IEC 62619:2022 ed2 [publication page](https://webstore.iec.ch/en/publication/64073); IEC 62485-5:2020 [publication page](https://webstore.iec.ch/en/publication/29086); IEC 61851-1:2017 [publication page](https://webstore.iec.ch/en/publication/33644); IEC 62109-1:2010 [publication page](https://webstore.iec.ch/en/publication/6470); IEC 62109-2:2011 [publication page](https://webstore.iec.ch/en/publication/6471); IEC 62109-3:2020 [publication page](https://webstore.iec.ch/en/publication/27684); IEC 61215-1:2021 [publication page](https://webstore.iec.ch/en/publication/61345); UL 1973 [standard page](https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973); UL 61730-1 [standard page](https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1); UN Manual of Tests and Criteria (Rev.7) [UNECE page](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria); NFPA 855 [standard-development page](https://www.nfpa.org/codes-and-standards/nfpa-855-standard-development/855).

## 10 — Next step (RFQ)

For a binding engineering and commercial offer — including OEM-grade datasheet revisions, project-specific genset make/model + SFOC curve, and an EU-of-origin/customs-stance section (TARIC lookup + member-state VAT treatment) — request the formal RFQ through TradVolt:

[Request a formal RFQ for the 2 MWh EU mining-camp BESS+PV+genset stack](https://tradvolt.com/rfq/)

## 11 — Limitations and known gaps (notable for any reader re-using these figures)

1. The base-case NPV is negative. The model is not "wrong" in any direction relative to the computed input set; the figure is a direct consequence of (a) modest BESS-side avoided-marginal-cost at the representative diesel price and (b) the 2%/yr O&M escalation embedded in the computed inputs. If the reader's project differs on either, recompute the model.

2. *asset.ess.usable_pct* = 100% DoD in the headline cash flow (bounded 80–100% across the named commercial-warranty LFP offerings in §2).

3. *asset.ess.cycles_per_year* ≈ 1 cycle/day on the 2 MWh asset (bounded 0.5–1.5 cycles/day in §6) — drives the Y1 throughput of 540,000 kWh and the Y1–Y10 decay.

4. *asset.ess.degradation_pct_per_year* ≈ 2.0%/yr (bounded 1.5–2.5%/yr in §6) — drives the Y1→Y10 throughput path 540,000 → 450,224 kWh in the COMPUTED CASH-FLOW TABLE.

5. The "residual_value.amount" of 0 EUR is a conservative model-default; an explicit salvage/reuse value at year 10 would close part (not all) of the NPV gap. This is a bounded assumption, not a sourced figure.

6. The "asset.ess.value_per_kwh_discharged" credit of €0.05/kWh is built from the avoided-diesel-credit basis stated in §3; readers running this on a project with materially different logistics costs must override.

7. Cycle life, SFOC, and the LCOS basis are stated at the technology-class level; project-specific cell-datasheet revisions and the genset-specific SFOC curve must be confirmed at the FAT.

8. Certification IDs (TÜV/CE/UL/IEC CB scheme) for the BESS are marked "to be confirmed at FAT" throughout this page. We do not name an issuer-specific certificate number without the corresponding certificate PDF on hand.

9. EU import-duty rates and VAT treatment are PENDING and must be re-checked at the EU TARIC consultation page linked in §8 against the project's actual country-of-origin declaration.

10. The 6.00% real discount rate is a project assumption and is not a citation of any specific ECB or central-bank series. It is within a typical 4–8% project-WACC band for renewable-energy capex in the EU.

11. The previously quoted "1.57-year payback" is not used in this page. It was calculated against undiscounted Capex using PV-averaged annualised benefits, which mixes time-bases inconsistently. The scenario model returns no simple-or-discounted payback within the 10-year horizon for this scenario.

Page evidence-date: 2026-09-22. Equipment, scenario, horizon (10 yr), discount rate (6.00%, real), and currency (EUR) above match the scenario TCO inputs exactly; the figures in §5 are the computed output of that model.