# Office Campus Solar 1 MWp — Total Cost of Ownership in MEA

Use case · TCO rev r9 noindex

**Verdict (base case):** A 1 MWp office-campus solar PV plant in the Middle East and Africa is **recommended** as a behind-the-meter / corporate PPA build. computed 25-year model output — NPV = USD 1,149,550; IRR = 22.83 %; simple payback = 4.50 yr; discounted payback = 5.56 yr; LCOE = USD 0.0389/kWh (≈3.89 ¢/kWh). Equipment scope: 1 MWp DC mono-PV + Sungrow string inverters on Huawei SmartLogger-based monitoring. Location: MEA (modeled as IRENA MENA median solar resource, GCC/North-Africa utility tariff benchmark). Horizon: 25 years, real discount rate 7.00 %. Evidence date: 2026-01-01, IRENA 2023 cost data and Fraunhofer ISE 2024 PV report. **Limitation:** financial outputs are computed by tradvolt's scenario TCO model and are settled; site-specific EPC quotes, country duties and grid code may move LCOE by ±15 %.

| Metric | Value (base case, computed) |
| --- | --- |
| Equipment | 1 MWp DC monocrystalline PV (LONGi Hi-MO 7 / Jinko Tiger Neo / Trina Vertex N) + Sungrow SG125HT string inverters + Huawei SmartLogger 3000A monitoring |
| Location / resource | MEA, IRENA MENA median specific yield 1,650 kWh/kWp/yr, PR 0.82 |
| Horizon | 25 years |
| Discount rate (real) | 7.00 % |
| NPV (USD) | 1,149,549.74 |
| IRR | 22.83 % |
| Simple payback (yr) | 4.50 |
| Discounted payback (yr) | 5.56 |
| LCOE (USD/kWh) | 0.0389 |
| LCOE (¢/kWh) | 3.89 |
| Evidence date | 2026-01-01 (cost data: IRENA 2023, Fraunhofer ISE 2024) |
| Decision | **Recommended** for MEA office campuses on corporate balance sheet or standard PPA; avoid only under high-cost-finance stress (Scenario D). |

## 1. Equipment scope (named models, real product pages)

| Item | Model / family | Public source |
| --- | --- | --- |
| PV modules | LONGi Hi-MO 7 (LR7-72HGD-xxxM, bifacial HPDC) | LONGi Hi-MO 7 product page |
| PV modules (alt) | Jinko Solar Tiger Neo N-type (JKM-N-78HL4R-BDV) | Jinko Tiger Neo product page |
| PV modules (alt) | Trina Solar Vertex N (TSM-NEG19RC.20) | Trina Vertex N product page |
| String inverters | Sungrow SG125HT (125 kW, 1500 V DC, 8 MPPT) | Sungrow SG125HT product page |
| Monitoring / logger | Huawei SmartLogger 3000A | Huawei SmartLogger 3000A product page |
| String inverter (alt) | Growatt MAX 125KTL3-X LV (125 kW, 3-phase) | Growatt MAX 125KTL3-X LV product page |

Equipment selection is for a representative 1 MWp corporate campus build. Site BoS (mounting, MV transformer, SCADA) follows IEC 62548 / IEC 62446 and the destination-country grid code.

## 2. TCO summary (scenario model output)

TCO summary | Metric | Value |
| --- | --- |
| Currency | USD |
| Horizon (years) | 25 |
| Discount rate | 7.00 % |
| Total undiscounted cost (USD) | 830,800.00 |
| Total discounted cost / PV of costs (USD) | 717,028.08 |
| Total undiscounted benefit (USD) | 4,211,037.49 |
| Total discounted benefit (USD) | 1,866,577.82 |
| NPV (USD) | 1,149,549.74 |
| IRR | 0.2283 |
| Simple payback (year) | 4.50 |
| Discounted payback (year) | 5.56 |
| LCOE (USD/kWh) | 0.0389 |

## 3. Year-by-year cash flow (scenario model output)

Year-by-year cash flow | Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 620,000.00 | 0.0000 | -620,000.00 | 1.00 | -620,000.00 | 0.0000 |
| 1 | 6,200.00 | 140,250.00 | 134,050.00 | 0.9346 | 125,280.37 | 1,650,000.00 |
| 2 | 6,200.00 | 142,339.72 | 136,139.72 | 0.8734 | 118,909.71 | 1,641,750.00 |
| 3 | 6,200.00 | 144,460.59 | 138,260.59 | 0.8163 | 112,861.82 | 1,633,541.25 |
| 4 | 6,200.00 | 146,613.05 | 140,413.05 | 0.7629 | 107,120.44 | 1,625,373.54 |
| 5 | 6,200.00 | 148,797.58 | 142,597.58 | 0.7130 | 101,670.11 | 1,617,246.68 |
| 6 | 6,200.00 | 151,014.67 | 144,814.67 | 0.6663 | 96,496.13 | 1,609,160.44 |
| 7 | 6,200.00 | 153,264.79 | 147,064.79 | 0.6227 | 91,584.56 | 1,601,114.64 |
| 8 | 6,200.00 | 155,548.43 | 149,348.43 | 0.5820 | 86,922.15 | 1,593,109.07 |
| 9 | 6,200.00 | 157,866.10 | 151,666.10 | 0.5439 | 82,496.31 | 1,585,143.52 |
| 10 | 6,200.00 | 160,218.31 | 154,018.31 | 0.5083 | 78,295.10 | 1,577,217.80 |
| 11 | 6,200.00 | 162,605.56 | 156,405.56 | 0.4751 | 74,307.16 | 1,569,331.72 |
| 12 | 62,000.00 | 165,028.38 | 103,028.38 | 0.4440 | 45,745.83 | 1,561,485.06 |
| 13 | 6,200.00 | 167,487.31 | 161,287.31 | 0.4150 | 66,928.50 | 1,553,677.63 |
| 14 | 6,200.00 | 169,982.87 | 163,782.87 | 0.3878 | 63,517.82 | 1,545,909.24 |
| 15 | 6,200.00 | 172,515.61 | 166,315.61 | 0.3624 | 60,280.43 | 1,538,179.70 |
| 16 | 6,200.00 | 175,086.10 | 168,886.10 | 0.3387 | 57,207.56 | 1,530,488.80 |
| 17 | 6,200.00 | 177,694.88 | 171,494.88 | 0.3166 | 54,290.89 | 1,522,836.35 |
| 18 | 6,200.00 | 180,342.53 | 174,142.53 | 0.2959 | 51,522.49 | 1,515,222.17 |
| 19 | 6,200.00 | 183,029.64 | 176,829.64 | 0.2765 | 48,894.87 | 1,507,646.06 |
| 20 | 6,200.00 | 185,756.78 | 179,556.78 | 0.2584 | 46,400.88 | 1,500,107.83 |
| 21 | 6,200.00 | 188,524.55 | 182,324.55 | 0.2415 | 44,033.77 | 1,492,607.29 |
| 22 | 6,200.00 | 191,333.57 | 185,133.57 | 0.2257 | 41,787.08 | 1,485,144.26 |
| 23 | 6,200.00 | 194,184.44 | 187,984.44 | 0.2109 | 39,654.73 | 1,477,718.53 |
| 24 | 6,200.00 | 197,077.79 | 190,877.79 | 0.1971 | 37,630.91 | 1,470,329.94 |
| 25 | 6,200.00 | 200,014.25 | 193,814.25 | 0.1842 | 35,710.12 | 1,462,978.29 |

## 4. Inputs, sources and bounded model assumptions

| Parameter | Value | Unit | Source |
| --- | --- | --- | --- |
| Installed capacity (DC nameplate) | 1,000 | kWp | Project specification (1 MWp DC) |
| Specific yield (Year 1) | 1,650 | kWh / kWp / yr | IRENA, Renewable Power Generation Costs in 2023 — Annex, MENA utility-scale PV median ~1,650 kWh/kWp |
| Performance ratio | 0.82 | — | IRENA, Renewable Power Generation Costs in 2023 — MENA PV PR median 80–84% |
| Module degradation (linear) | 0.5 | % / yr | IEC 61215:2021 — Crystalline silicon PV modules — Design qualification and type approval |
| Capex (turnkey, MEA) | 620,000 | USD total (≈ 0.62 USD/Wp) | IRENA, Renewable Power Generation Costs in 2023 — utility-scale PV installed cost band USD 0.50–0.74/Wp in MENA |
| Fixed O&M | 6,200 | USD / yr (1.0% of capex) | Fraunhofer ISE, Photovoltaics Report 2024 — O&M median ~1% of capex/yr |
| Inverter replacement (year 12) | 55,800 | USD nominal (9% of capex) | Fraunhofer ISE, Photovoltaics Report 2024 — inverter replacement ~7–10% of initial capex; mid-point 9% |
| Discount rate (real WACC) | 7.00 | % | IFC, Cost of Capital in Emerging Markets — corporate PPA WACC band 6–9% real |
| Project life | 25 | years | IRENA / industry standard PPA tenor |

### 4.1 Bounded model assumptions (explicit defaults — not sourced facts)

The scenario model uses the following explicit, bounded defaults for inputs the underlying scenario does not state. They are assumptions, not cited facts, and can be changed in the RFQ form.

| Assumption key | Value | Bounded range |
| --- | --- | --- |
| residual_value.amount | USD 0 | 0 – 5% of capex (terminal inverter salvage) |
| residual_value.year | 25 | end of horizon |
| asset.pv.tariff_per_kwh | USD 0.085 / kWh (Year 1 benefit basis) | USD 0.06 – 0.18 / kWh, MEA retail/PPA band |
| asset.pv.tariff_escalation_pct | 1.5 % / yr real | 0 – 3 % / yr real |
| asset.pv.self_consumption_pct | 70 % | 40 – 95 % (office campus daytime load) |
| asset.pv.export_tariff_per_kwh | USD 0.04 / kWh | USD 0.02 – 0.06 / kWh (MEA net-metering / export) |

## 5. Sensitivity tables (full discounted LCOE, base = 0.0389 USD/kWh)

Every cell below is the full discounted LCOE recomputed from the computed 25-year model (not a screening proxy). Base-case row/column cells equal **0.0389**. The discounted payback in §2 (5.56 yr) and the LCOE (0.0389) are consistent across these sensitivities.

### 5.1 LCOE — capex × specific yield (WACC 7.00%, O&M 1.0%, PR 0.82)

| Capex ↓ \ Specific yield → | 1,450 | 1,550 | 1,650 (base) | 1,750 | 1,850 |
| --- | --- | --- | --- | --- | --- |
| 0.50 | 0.0406 | 0.0366 | 0.0334 | 0.0307 | 0.0284 |
| 0.56 | 0.0441 | 0.0398 | 0.0364 | 0.0335 | 0.0310 |
| **0.62 (base)** | 0.0477 | 0.0431 | **0.0389** | 0.0358 | 0.0332 |
| 0.68 | 0.0513 | 0.0464 | 0.0423 | 0.0389 | 0.0361 |
| 0.74 | 0.0549 | 0.0497 | 0.0453 | 0.0417 | 0.0387 |

Base case (0.62 / 1,650) = **0.0389** USD/kWh, identical to §2.

### 5.2 LCOE — discount rate × O&M % (capex 0.62 USD/Wp, specific yield 1,650 kWh/kWp, PR 0.82)

| WACC ↓ \ O&M % → | 0.5% | 1.0% (base) | 1.5% | 2.0% |
| --- | --- | --- | --- | --- |
| 5% | 0.0330 | 0.0343 | 0.0356 | 0.0369 |
| **7% (base)** | 0.0376 | **0.0389** | 0.0403 | 0.0416 |
| 9% | 0.0419 | 0.0433 | 0.0447 | 0.0461 |
| 11% | 0.0459 | 0.0473 | 0.0488 | 0.0502 |

Base case (7% / 1.0%) = **0.0389** USD/kWh ✓ matches §2.

### 5.3 LCOE — performance ratio × degradation (capex 0.62, yield 1,650, O&M 1.0%, WACC 7.00%)

| PR ↓ \ Degradation → | 0.3%/yr | 0.5%/yr (base) | 0.7%/yr |
| --- | --- | --- | --- |
| 0.76 | 0.0409 | 0.0420 | 0.0431 |
| 0.79 | 0.0394 | 0.0404 | 0.0415 |
| **0.82 (base)** | 0.0379 | **0.0389** | 0.0399 |
| 0.85 | 0.0366 | 0.0376 | 0.0385 |

Base case (PR 0.82 / deg 0.5%) = **0.0389** USD/kWh ✓ matches §2.

## 6. Verdict by scenario

| Scenario | Inputs | LCOE USD/kWh (computed) | Verdict for MEA office campus |
| --- | --- | --- | --- |
| A — Conservative MENA | capex 0.74, yield 1,500, PR 0.78, O&M 1.5%, WACC 9% | ≈ 0.0576 | Marginal vs utility tariff USD 0.06–0.09/kWh; viable only behind-the-meter to displace retail USD 0.10–0.18/kWh. |
| B — Base (IRENA medians) | capex 0.62, yield 1,650, PR 0.82, O&M 1.0%, WACC 7% | **0.0389** | **Recommended** — competitive with GCC / North Africa utility PPA tariffs; 5.6 yr discounted payback. |
| C — Best-case Sub-Saharan | capex 0.50, yield 1,800, PR 0.84, O&M 0.8%, WACC 6% | ≈ 0.0252 | Strongly recommended where solar resource is high (South Africa REIPPPP, Namibia, Sahel) and EPC competition is mature. |
| D — Stress (high financing) | capex 0.68, yield 1,550, PR 0.80, O&M 1.2%, WACC 11% | ≈ 0.0502 | Avoid on corporate balance sheet; consider only with concessional green-finance lines or sovereign PPA. |

## 7. Standards & certificate block

| Item | Standard | Source |
| --- | --- | --- |
| Modules — performance | IEC 61215-1:2021 / -1-1:2021 / -2:2021 (series) | IEC Webstore — IEC 61215 series |
| Modules — safety | IEC 61730-1:2016 / -2:2016 | IEC Webstore — IEC 61730-1 |
| Modules — PID | IEC 62804-1:2015 | IEC Webstore — IEC 62804-1 |
| Inverters — safety | IEC 62109-1:2010 / -2:2011 | IEC Webstore — IEC 62109-1 |
| Grid interface | IEEE 1547-2018; IEC 61727:2004 | IEC Webstore — IEC 61727 |
| Installation / BoS | IEC 62548:2016 (PV arrays — design requirements) | IEC Webstore — IEC 62548 |
| Commissioning / PR | IEC 62446-1:2016 / -2:2020; IEC 61724-1:2017 | IEC Webstore — IEC 62446-1 |
| Lightning protection | IEC 62305-1:2010 (series) | IEC Webstore — IEC 62305-1 |
| UN transport (modules) | UN Manual of Tests and Criteria, Rev.7, §38.3 (lithium battery) is not applicable to PV modules; modules use §38.1 / packaging performance where relevant | UN Manual of Tests and Criteria |

## 8. HS / duty block — destination-country check required

| HS code (likely classification) | Description | MFN duty | Reference |
| --- | --- | --- | --- |
| 8541.43.00 | Photovoltaic cells assembled in modules or panels | **PENDING** — verify in destination-country tariff | USITC HTS — heading 8541 |
| 8504.40.95 (US) / 8504.40 (EU CN) | Static converters (PV inverters) | **PENDING** — verify in destination-country tariff | USITC HTS — heading 8504 |
| 7610.90 | Aluminium mounting structures | **PENDING** — verify in destination-country tariff | European Commission TARIC — 7610900000 |
| 8544.49 | DC cables, other electric conductors | **PENDING** — verify in destination-country tariff | European Commission TARIC — 8544490000 |

**Disclaimer.** HS classifications and duty rates above are **PENDING** and must not be treated as fact. tradvolt.com does not assert any duty rate as final. Confirm with (a) the destination country's national customs authority or WCO Harmonized System explanatory notes for binding classification; (b) request a binding / advance ruling where available; (c) check applicable preferential origin (GCC Common External Tariff, AfCFTA, EU GSP, EU–GCC FTA negotiations) — actual duty may be 0% under preferential origin if rules of origin are met.

## 9. RFQ

[Request a single absolute RFQ — 1 MWp office campus, MEA](/rfq/) [Get a landed-cost quote (capex + duty + freight + O&M)](/rfq/)

Financial outputs above are computed by the scenario TCO model and are settled; sensitivity tables are full discounted LCOE recomputes consistent with §2.