# Orchard ESS 150 kWh AU — Total Cost of Ownership

**Verdict (10-year horizon, Australia, evidence dated 2026-01-15):** Standalone NPV is **−274,386.54 AUD** (discounted at 7.00 %/yr), simple payback and discounted payback are **not reached** over the 10-year window, and **LCOS = 1.38 AUD/kWh**. The modelled 150 kWh containerised LFP system is a standalone negative-NPV proposition on energy-arbitrage cash terms alone; it is only commercially defensible when paired with avoided-outage value, a TOU spread materially wider than 0.20 AUD/kWh, or a state/federal grant. Limitation: figures derive from the inputs below and the bounded model assumptions declared in Section 2; they are not a quotation.

| Item | Value | Unit / Note |
| --- | --- | --- |
| Equipment | Containerised LFP ESS, 150 kWh / 150 kW class (CATL 280 Ah LFP cells in Sungrow / SolaX-class PCS enclosure) | See Section 3 for named models and datasheet URLs |
| Location | Australia (NSW tariff envelope assumed) | — |
| Horizon | 10 | years |
| Discount rate | 7.00 | % / year, real, after-tax WACC proxy |
| NPV | −274,386.54 | AUD (discounted) |
| IRR | n/a | No positive cash-flow crossing within horizon |
| Simple payback | — | Not reached in 10 years |
| Discounted payback | — | Not reached in 10 years |
| LCOS | 1.38 | AUD per kWh delivered (discounted) |
| Total undiscounted cost | 355,796.65 | AUD |
| PV of costs | 315,678.01 | AUD (discounted) |
| Total undiscounted benefit | 57,975.36 | AUD |
| PV of benefits | 41,291.47 | AUD (discounted) |
| Evidence date | 2026-01-15 | Sources cited inline |

**Contents**

1. Sources table (named documents)

2. Inputs table (cited + bounded assumptions)

3. Named equipment models

4. Capex (Year 0)

5. Opex (annual)

6. TCO summary (computed table)

7. Year-by-year cash flow (computed table)

8. Sensitivity table

9. Verdict by scenario

10. Mini cert & compliance block

11. HS code & duty block

12. CTAs

## 1. Sources Table

| Row in this page | Claim | Source type | Specific document URL |
| --- | --- | --- | --- |
| Cycle life 6,000 cycles @ 80 % DoD (CATL class) | LFP prismatic cell cycle life | OEM product page (JS-rendered; specs confirmed at RFQ) | CATL Energy Storage product landing (CATL) |
| Cycle life ≥6,000 cycles @ 80 % DoD (Deye BOS-G cross-check) | LFP modular battery cycle life | OEM product news page | Deye BOS-G high-voltage LFP battery news (Deye) |
| Cycle life ≥4,000 cycles @ 25 °C (EVE LF304) | LFP prismatic cell cycle life cross-check | OEM store (cell page) | EVE LF304 cell product page (EVE Mall) |
| Calendar fade envelope (LFP cabinet) | LFP cabinet calendar fade envelope | OEM product page | BYD Battery-Box Premium HVS/HVM product page (BYD Battery-Box) |
| RTE ≥90 % (hybrid inverter class) | Hybrid inverter AC round-trip efficiency envelope | OEM product page | Sungrow SH5/6/8/10/12T 3-phase hybrid product page (Sungrow) |
| RTE ≥97.8 % (hybrid inverter cross-check) | Hybrid inverter max efficiency cross-check | OEM product page | Fox ESS H3 PRO hybrid product page (Fox ESS) |
| FX AUD/USD reference | Indicative AUD/USD reference rate | Central bank publication | RBA historical exchange rates (CSV) and RBA indicative exchange rates page |
| NSW retailer tariff envelope (Origin) | NSW residential tariff envelope | Retailer tariff schedule | Origin Energy NSW residential variation price document (PDF) |
| Import duty (batteries 8507.60) | Customs classification for Li-ion cabinet | National customs tariff lookup | Australian Border Force current tariff classification page (ABF) |
| Import duty (PCS 8504.40) | Customs classification for static converters | National customs tariff lookup | Australian Border Force current tariff classification page (ABF) |
| UN 38.3 transport test | Lithium battery transport | UN publication | UN Manual of Tests and Criteria, Section 38.3 (UNECE) |
| IEC 62619 cell safety | Secondary Li cells for industrial use | IEC publication | IEC 62619:2022 ed2 webstore entry (IEC) |
| IEC 62485-5 stationary Li operation | Safe operation of stationary Li-ion batteries | IEC publication | IEC 62485-5:2020 webstore entry (IEC) |
| AS/NZS 5139 (BESS install) | BESS installation safety | AU safety-doc reference (CEC listing) | Clean Energy Council approved batteries list (CEC) |
| EU Battery Regulation | EU 2023/1542 regulatory frame | EU regulation | Regulation (EU) 2023/1542 (EUR-Lex) |

## 2. Inputs Table (cited + bounded assumptions)

| Parameter | Value | Unit | Source / classification |
| --- | --- | --- | --- |
| Nameplate energy | 150 | kWh | System nameplate (modelled) |
| Usable energy (DoD 80 %) | 120 | kWh | System nameplate × 0.80 (modelled) |
| PCS continuous power | 150 | kW | System nameplate (1C) (modelled) |
| Round-trip efficiency (RTE) | 90 | % | OEM product page — Sungrow SH5/6/8/10/12T (Sungrow) ; cross-checked with Fox ESS H3 PRO |
| Assumed cycle life | 6,000 | full equiv. cycles | OEM product page — CATL ESS landing; cross-checked with Deye BOS-G (80 % DoD, EOL at 70 % nameplate) |
| Calendar degradation | 2.5 | % / year | Model assumption (bounded) — bounded LFP calendar fade envelope aligned to BYD Battery-Box Premium HVS/HVM envelope |
| Project horizon | 10 | years | Modelling assumption (bounded) |
| Discount rate (WACC proxy) | 7.00 | % / year | Modelling assumption, AU corporate after-tax real (bounded) |
| Cycles per year | 300 | full equiv. cycles / year | Model assumption (bounded) — `asset.ess.cycles_per_year`; drives Y1 throughput ≈ 36,000 kWh against 120 kWh usable |
| AUD/USD FX | 1.53 | AUD per USD | RBA historical exchange rates (CSV) / RBA indicative exchange rates page |
| NSW peak tariff (flat indicative) | 0.38 | AUD/kWh | Indicative retailer tariff — Origin Energy NSW residential variation price document (PDF); verify with retailer bill |
| NSW shoulder/off-peak tariff | 0.18 | AUD/kWh | Indicative retailer tariff — same source; verify with retailer bill |
| Tariff spread (peak − shoulder) | 0.20 | AUD/kWh | Derived from above two rows |
| Charge cost per kWh | 0.18 | AUD/kWh | Model assumption (bounded) — `asset.ess.charge_cost_per_kwh`, set to shoulder/off-peak tariff |
| Value per kWh discharged | 0.38 | AUD/kWh | Model assumption (bounded) — `asset.ess.value_per_kwh_discharged`, set to peak tariff |
| Residual value | 0.00 | AUD | Model assumption (bounded) — `residual_value.amount` |
| Residual value year | 10 | year | Model assumption (bounded) — `residual_value.year` |
| Opex inflation | 2.0 | % / year | Model assumption (bounded) — applied to recurring opex line items Y2–Y10 |

**Reading the inputs table:** cited rows point to a specific OEM product page, an RBA FX page, or a retailer tariff PDF; rows tagged Model assumption (bounded) are explicit bounded defaults declared because the draft did not state them. They are not sourced facts and must be confirmed by the buyer.

## 3. Named Equipment Models

| Subsystem | Named model / family | OEM | Datasheet / product page URL | Key limits cited |
| --- | --- | --- | --- | --- |
| Battery cells (primary) | CATL 280 Ah LFP prismatic cell (3.2 V nominal) | CATL | CATL Energy Storage product landing (CATL) — exact model designation confirmed at RFQ (CATL ESS pages JS-rendered) | Cycle life 6,000 @ 80 % DoD; nominal voltage 3.2 V; charge 0.5C / discharge 1C |
| Battery cells (cross-check) | EVE LF304 304 Ah LFP prismatic cell | EVE Energy | EVE LF304 cell product page (EVE Mall) | 304 Ah nominal; 3.2 V; ≥4,000 cycles @ 25 °C to ≥80 %; 173.7 × 71.7 × 207.2 mm; 5,450 g |
| Battery cabinet / BMS (cross-check) | Deye BOS-G high-voltage LFP battery | Ningbo Deye Inverter Technology Co., Ltd. | Deye BOS-G high-voltage LFP news (Deye) | 5.12 kWh / 51.2 V / 100 Ah per module; 20.48–61.44 kWh from 4–12 modules; 19-inch rack; ≥6,000 cycles; intelligent BMS with aerosol fire extinguishing |
| Battery cabinet / BMS (alt cross-check) | BYD Battery-Box Premium HVS / HVM | BYD | BYD Battery-Box Premium HVS/HVM product page (BYD Battery-Box) | HVS: 2–5 modules series, 5.1–12.8 kWh usable; 3 stacks parallel max 38.4 kWh. HVM: 3–8 modules, 8.1–21.7 kWh; 3 parallel max 65.0 kWh. Cobalt-free LFP. |
| PCS / hybrid inverter (primary) | Sungrow SH5/6/8/10/12T three-phase hybrid inverter | Sungrow | Sungrow SH5/6/8/10/12T 3-phase hybrid product page (Sungrow) | 5–12 kW AC at 400 V; 1,000 V PV max; 98 % max efficiency; 16 A input; 200 % DC/AC; 2 MPPT/3 strings; 0 ms switchover; IP65/C5; AFCI2.0; pairs SBH100-400 / SBR064-256 |
| PCS / hybrid inverter (cross-check) | Fox ESS H3 PRO hybrid inverter | Fox ESS | Fox ESS H3 PRO hybrid product page (Fox ESS) | Max efficiency 97.8 %; MPPT 99.9 %; high-voltage batteries; IP65 |
| PCS / hybrid inverter (alt cross-check) | SolaX X3-ULTRA 15/20/25/30 kW hybrid inverter | SolaX Power | SolaX X3-ULTRA hybrid product page (SolaX Power) | 15/20/25/30 kW hybrid; MPPT 160–950 V, 36 A each; 200 % PV oversizing; 200 % EPS overload 10 s; <10 ms switch; 60 A charge/discharge; 10-unit parallel; IP66; Type II SPD |
| Container / enclosure | 10-ft ISO containerised BESS enclosure with HVAC | Generic (project pack) | Not OEM-branded; conforms to ISO 668 1C (10-ft) | — |

The modelled "150 kWh / 150 kW class containerised LFP" is realised as a stack of approximately 7–8 battery cabinets (e.g., BYD Battery-Box Premium HVS or Deye BOS-G-class modules, configurable in parallel to ≈ 150 kWh) fronted by one Sungrow SH5/6/8/10/12T, Fox ESS H3 PRO or SolaX X3-ULTRA-class PCS in a 10-ft ISO container with HVAC, aerosol fire suppression and EMS/SCADA gateway. System-level limits (max charge/discharge current, SOC window, voltage window) are those of the OEM datasheet revision cited above and must be re-confirmed against the supplier declaration prior to procurement.

## 4. Capex (Year 0)

| Line item | AUD (ex-GST) | Note |
| --- | --- | --- |
| Battery modules (LFP, 150 kWh) | 75,000 | Indicative distributor pricing for 2025-vintage LFP cells (CATL / EVE class) |
| PCS / hybrid inverter 150 kW class | 45,000 | Sungrow SH5/6/8/10/12T / Fox ESS H3 PRO / SolaX X3-ULTRA class (sized for 1C duty) |
| BOS (switchgear, cabling, AC/DC) | 18,000 | Indicative |
| Containerised enclosure + HVAC | 22,000 | 10-ft ISO container, climate-controlled |
| Fire suppression + ventilation | 9,500 | Aerosol / clean-agent system |
| EMS / SCADA gateway | 7,500 | Vendor energy-management software licence |
| Transport to site (intra-NSW) | 5,000 | Indicative logistics quote (UN 38.3 compliant) |
| Install, commissioning, training | 14,000 | EPC contractor day-rate × estimated days |
| Engineering, permits, network study | 8,000 | Indicative |
| Contingency 10 % | 20,400 | Sum of above × 0.10 |
| **Capex subtotal (ex-GST, ex-duty)** | **224,400** | Sum of all line items incl. contingency |

## 5. Opex (annual)

| Line item | AUD/year (Y1) | Note |
| --- | --- | --- |
| Preventative maintenance (incl. parts) | 4,500 | Quarterly site visit, remote monitoring |
| Remote monitoring subscription | 1,200 | Vendor cloud platform |
| Insurance surcharge | 1,800 | Annual policy uplift for battery |
| Augmentation reserve (capacity top-up) | 3,000 | Reserve fund for cell-top-up at Year 7–8 |
| Network charges (if export-limited) | 1,500 | Stand-by, demand, network access |
| **Opex subtotal (Y1)** | **12,000** | Sum of all line items, inflated at 2.0 %/yr from Y2 |

## 6. TCO Summary (computed table)

TCO summary | Metric | Value |
| --- | --- |
| Currency | AUD |
| Horizon (years) | 10 |
| Discount rate | 7.00 % |
| Total undiscounted cost (AUD) | 355,796.65 |
| Total discounted cost / PV of costs (AUD) | 315,678.01 |
| Total undiscounted benefit (AUD) | 57,975.36 |
| Total discounted benefit (AUD) | 41,291.47 |
| NPV (AUD) | -274,386.54 |
| IRR | n/a |
| Simple payback (year) | — |
| Discounted payback (year) | — |
| LCOS (AUD/kWh) | 1.38 |

## 7. Year-by-Year Cash Flow (computed table)

Year-by-year cash flow | Year | Cost (AUD) | Benefit (AUD) | Net (AUD) | Discount factor | Discounted net (AUD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 224,400.00 | 0.0000 | -224,400.00 | 1.00 | -224,400.00 | 0.0000 |
| 1 | 12,000.00 | 6,480.00 | -5,520.00 | 0.9346 | -5,158.88 | 36,000.00 |
| 2 | 12,240.00 | 6,318.00 | -5,922.00 | 0.8734 | -5,172.50 | 35,100.00 |
| 3 | 12,484.80 | 6,160.05 | -6,324.75 | 0.8163 | -5,162.88 | 34,222.50 |
| 4 | 12,734.50 | 6,006.05 | -6,728.45 | 0.7629 | -5,133.10 | 33,366.94 |
| 5 | 12,989.19 | 5,855.90 | -7,133.29 | 0.7130 | -5,085.94 | 32,532.76 |
| 6 | 13,248.97 | 5,709.50 | -7,539.47 | 0.6663 | -5,023.87 | 31,719.44 |
| 7 | 13,513.95 | 5,566.76 | -7,947.19 | 0.6227 | -4,949.11 | 30,926.46 |
| 8 | 13,784.23 | 5,427.59 | -8,356.63 | 0.5820 | -4,863.64 | 30,153.30 |
| 9 | 14,059.91 | 5,291.90 | -8,768.01 | 0.5439 | -4,769.22 | 29,399.46 |
| 10 | 14,341.11 | 5,159.61 | -9,181.50 | 0.5083 | -4,667.41 | 28,664.48 |

## 8. Sensitivity Table

| Variable | −20 % | Base | +20 % | Effect on 10-yr LCOS (AUD/kWh) |
| --- | --- | --- | --- | --- |
| Capex | 179,520 | 224,400 | 269,280 | LCOS moves roughly ±0.10 AUD/kWh around 1.38 |
| Discount rate | 5.6 % | 7.0 % | 8.4 % | LCOS rises ~+3 % at +1.4 pp, falls ~−2 % at −1.4 pp |
| Cycle life (EOL threshold) | 4,800 | 6,000 | 7,200 | LCOS inverse: +20 % cycles ⇒ ~−6 % LCOS |
| Annual benefit | 0.8 × base | 1.0 × base | 1.2 × base | NPV swing dominates; payback moves ±2 yrs (none in 10 yrs at base) |
| Degradation rate | 2.0 %/yr | 2.5 %/yr | 3.0 %/yr | Year-10 delivered energy: ≈ 30,600 / 28,664 / ≈ 26,700 kWh |

## 9. Verdict by Scenario (10-yr horizon)

| Scenario | NPV (AUD) | LCOS (AUD/kWh) | Verdict |
| --- | --- | --- | --- |
| Base — TOU arbitrage (0.20 AUD/kWh spread) | −274,386.54 | 1.38 | Negative-NPV under stated assumptions. Viable only if paired with resilience, subsidy, or a materially wider TOU spread. |
| Tariff arbitrage (wider spread required) | NPV improves linearly with spread | 1.38 (unchanged) | Still negative at a 0.20 AUD/kWh spread; would need a sustained ≥ ~0.50 AUD/kWh spread, or additional value-stacking, to approach break-even. |
| Outage resilience value (avoided-loss) | −274,386.54 on cash terms alone | 1.38 | Standalone negative on cash terms alone. Justified only on an avoided-loss basis (crop value at risk, insurance credit, contractual SLA). |

**Reading the verdict:** the three scenarios are modelled against the same hardware, opex, discount rate and degradation curve; only the benefit function differs. The computed tables in Sections 6 and 7 reflect the bounded assumptions declared in Section 2. Commercial viability improves materially when (a) a state or federal grant is captured, (b) the site has a high-value crop with genuine outage-risk exposure, or (c) the system is value-stacked across multiple daily TOU windows.

## 10. Mini Cert & Compliance Block

**Indicative compliance map — verify before procurement:**

- AS/NZS 5139 — Safety of battery energy storage systems (installations); product must appear on the Clean Energy Council approved batteries list to qualify for connection and SRES pathways — [CEC approved batteries list (CEC)](https://cleanenergycouncil.org.au/industry-programs/products-program/batteries)

- AS/NZS 4777.2 — Grid connection of energy systems via inverters (Australia); product must appear on the CEC approved inverters list — [CEC Products Program hub (CEC)](https://cleanenergycouncil.org.au/industry-programs/products-program)

- IEC 62619:2022 ed2 — Secondary lithium cells and batteries for use in industrial applications including stationary/ESS (TC 21/SC 21A) — [IEC 62619:2022 ed2 webstore entry (IEC)](https://webstore.iec.ch/en/publication/64073)

- IEC 62485-5:2020 — Safety requirements for secondary batteries and battery installations, Part 5: Safe operation of stationary lithium-ion batteries (TC 21) — [IEC 62485-5:2020 webstore entry (IEC)](https://webstore.iec.ch/en/publication/29086)

- IEC 62109-1:2010 / IEC 62109-2:2011 — Safety of power converters for use in PV power systems, Parts 1 and 2 (TC 82) — [IEC 62109-1:2010 (IEC)](https://webstore.iec.ch/en/publication/6470) and [IEC 62109-2:2011 (IEC)](https://webstore.iec.ch/en/publication/6471)

- UN 38.3 — Transport of lithium batteries (mandatory for sea/air freight); ST/SG/AC.10/11/Rev.7 — [UN Manual of Tests and Criteria, Section 38.3 (UNECE)](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria)

- Regulation (EU) 2023/1542 — EU Battery Regulation — [Regulation (EU) 2023/1542 (EUR-Lex)](https://eur-lex.europa.eu/eli/reg/2023/1542/oj)

- CEC accreditation — required for inverter listing under SRES rebate pathways, where applicable.

All certs and listings must be confirmed against the actual supplier declaration and the latest revision of each standard.

## 11. HS Code & Duty Block (PENDING broker confirmation)

**Indicative classification (PENDING broker confirmation):**

| Component | HS code (provisional) | Duty rate | GST |
| --- | --- | --- | --- |
| Lithium-ion storage batteries (cabinet / rack mounted) | 8507.60 | PENDING — verify via ABF current tariff classification page (ABF) | 10 % (standard) |
| PCS / hybrid inverter | 8504.40 | PENDING — verify via ABF current tariff classification page (ABF) | 10 % |
| BOS switchgear | 8537.10 | PENDING — verify via ABF current tariff classification page (ABF) | 10 % |
| ISO container enclosure | 8609.00 | PENDING — verify via ABF current tariff classification page (ABF) | 10 % |

**Lookup instructions:** confirm final classification and applicable duty rate via the *Australian Border Force* Working Tariff and a licensed customs broker before any import. Verify whether the system qualifies for any free-trade-agreement preference (e.g., AANZFTA, RCEP, ChAFTA) based on country of origin. Check whether a *Tariff Concession Order* or *Advance Ruling* applies to the specific goods.

**Disclaimer:** we do not assert any duty rate as fact. All customs treatment is the responsibility of the importer and their appointed customs broker.

## 12. CTAs

[Request a quoted RFQ via TradVolt](/rfq/) [Permalink to this TCO page](https://tradvolt.com/use-cases/orchard-ess-150kwh-au-r9/)