# Orchard Solar 250 kWp UK — Use Case & TCO

**Headline verdict:** NPV = **+£270,228.23** over a 25-year horizon at a 7.00% nominal discount rate (WACC); IRR = **17.20%**; simple payback = **5.79 years**; discounted payback = **7.63 years**; LCOE = **£0.1145/kWh**. Equipment family: 250 kWp DC ground-mount agrivoltaic array for a UK orchard (fixed-tilt base), Huawei SUN2000-200KTL-H2 string inverter (200 kW AC, datasheet confirmed at RFQ), LONGi Hi-MO X6 (Explorer/Scientist/Guardian variants, up to 25.5% HPBC cell efficiency; product page [LONGi Hi-MO X6](https://www.longi.com/en/products/modules-series/hi-mo-x6/)) or equivalent Jinko Tiger Neo 3.0 ([Jinko Tiger Neo 3.0](https://www.jinkosolar.com/en/site/aboutus)) / Trina NEG19RC.20 bifacial modules — see §3 for the exact bill of materials. Location: United Kingdom (GB). Evidence date: 2026-09-22. Limitation: figures are deterministic; battery storage, agricultural revenue uplift and inverter-clipping losses are excluded from the base case. Source: Tradvolt scenario TCO model, scenario ID UC-OS250-UK-R9.

Decision snapshot | Metric | Value |
| --- | --- |
| Horizon | 25 years |
| Discount rate (WACC, nominal) | 7.00% |
| Currency | GBP (£) |
| Total capex (Year 0) | £247,000.00 |
| Total undiscounted cost (25 yr) | £376,862.03 |
| PV of costs | £303,759.68 |
| Total undiscounted benefit (25 yr) | £1,273,290.48 |
| PV of benefits | £573,987.91 |
| NPV | +£270,228.23 |
| IRR | 17.20% |
| Simple payback | 5.79 yr |
| Discounted payback | 7.63 yr |
| LCOE | £0.1145 / kWh |
| Verdict | Recommended at base assumptions |

**RFQ:** [Request quote — 250 kWp UK orchard solar](/rfq/?use_case=orchard-solar-250kwp-uk&size_kwp=250&country=GB)

## 1. Scope & system definition

250 kWp DC ground-mount agrivoltaic array, fixed-tilt (single-axis tracker scenario presented for comparison only — not in base NPV), on a UK commercial orchard (top-fruit or soft-fruit). Inverter: Huawei SUN2000-200KTL-H2 (200 kW AC), DC/AC ratio ≈ 1.25. Grid-connected with export meter. Battery storage excluded from base case.

Reference product models (name as marketed; datasheets confirmed at RFQ):

- PV modules (choose one per procurement lot): LONGi Hi-MO X6 Explorer / Scientist / Guardian Anti-Dust / Guardian Anti Humidity-Heat / Artist Ultra Black variants, HPBC cell efficiency exceeds 25.5% ([LONGi Hi-MO X6 product page](https://www.longi.com/en/products/modules-series/hi-mo-x6/)); Jinko Tiger Neo 3.0 (Anti-Glare / Anti-Dust / AIDC / Fire-Resistant modules; [JinkoSolar company profile](https://www.jinkosolar.com/en/site/aboutus)); Trina NEG19RC.20 bifacial equivalent (landing [Trina Solar](https://www.trinasolar.com/us-en)). Module design qualification: IEC 61215-1:2021 ed2 ([IEC 61215-1:2021 ed2 — TC 82](https://webstore.iec.ch/en/publication/61345)). Module safety qualification: UL 61730-1 ([UL 61730-1 product page](https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1)).

- Inverter: Huawei SUN2000-200KTL-H2, 200 kW AC class (landing [Huawei FusionSolar](https://solar.huawei.com/en)). Conformance: IEC 62109-1:2010 ([IEC 62109-1:2010 — TC 82](https://webstore.iec.ch/en/publication/6470)); cite IEC 62109-2:2011 via [IEC Webstore](https://webstore.iec.ch/) with full designation at RFQ. Alternative commercial 3-phase string: Sungrow SG125HT (C&I 3-phase, [Sungrow string-inverter range](https://www.sungrowpower.com/en/products/string-inverter)).

- Mounting: K2 Systems N-Rack ground-mount system (driven-pile + S-Rack rail, [K2 N-Rack product page](https://k2-systems.com/en/product-solutions/k2-n-rack-system/)) with SingleRail 36 rail, 3.65 m, EN AW-6063 T66 aluminium, article 2004258 ([K2 SingleRail 36 catalogue entry](https://catalogue.k2-systems.com/singlerail-36/2004258)).

- String monitoring / data logger: Huawei SmartLogger 3000A (same [Huawei FusionSolar](https://solar.huawei.com/en) catalogue).

## 2. Inputs table

| Input | Value | Unit | Basis |
| --- | --- | --- | --- |
| Installed DC capacity | 250 | kWp | Site specification (model assumption) |
| UK specific yield (fixed-tilt, south) | 950 | kWh/kWp/yr | Solar Energy UK — Solar PV Cost Update H1 2025 ground-mount yield band (cited band; see Sources) |
| PV tariff escalation (nominal) | 1.5 | % per year | Model assumption (bounded default for tariff escalation) |
| Opex escalation (nominal) | 2.0 | % per year | Model assumption (bounded default for opex.escalation_pct) |
| Module degradation | 0.5 | % per year | Industry convention; module datasheet warranty band |
| Self-consumption share (orchard pump-house + cold-store) | 55 | % of generation | Model assumption (site load profile) |
| Imported grid price (avoided) | 0.28 | £/kWh | Ofgem Default Tariff Cap — energy price cap hub Ofgem energy price cap (Jan–Mar 2026 baseline) |
| Export price (SEG) | 0.08 | £/kWh | Ofgem Smart Export Guarantee — scheme page Ofgem SEG (provider-dependent band, typically 0.05–0.10 £/kWh) |
| Blended benefit price (computed) | 0.19 | £/kWh | 0.55 × £0.28 + 0.45 × £0.08 ≈ £0.19/kWh (per scenario model) |
| Installed price (turnkey, fixed-tilt, base) | 0.85 | £/Wp | Solar Energy UK, Solar PV Cost Update H1 2025 — ground-mount band (see Sources) |
| Agrivoltaic canopy premium | 0.10 | £/Wp | Fraunhofer ISE / FRAV agrivoltaic cost-premium band (model assumption, see Sources) |
| Grid connection (DNO, 250 kWp) | 9,500 | £ one-off | National Grid ESO / DNOs connection-charging band (see Sources) |
| O&M fixed-tilt (Year 1) | 2,750 | £/yr | £11/kWp × 250 kWp; Solar Energy UK O&M benchmark (see Sources) |
| Insurance | 617.50 | £/yr | 0.25% × £247,000 capex; RenewableUK insurer-survey cited band (see Sources) |
| Inverter replacement (year 12) | 22,000 | £ | Model assumption (Huawei SUN2000-200KTL-H2 replacement budget) |
| Discount rate (WACC, nominal) | 7.00 | % per year | Tradvolt reference WACC (model assumption) |
| Analysis horizon | 25 | years | Tradvolt convention |
| Residual value (terminal, year 25) | 0 | £ | Model assumption (bounded default residual_value.amount = 0; residual_value.year = 25) |

Items labelled "model assumption" are bounded defaults documented in the Tradvolt scenario TCO model (scenario UC-OS250-UK-R9). Items labelled with a publisher are taken from the cited publication's reported band; live URLs and full document titles are in §11 Sources.

## 3. TCO summary (scenario model output)

TCO summary | Metric | Value |
| --- | --- |
| Currency | GBP |
| Horizon (years) | 25 |
| Discount rate | 7.00 % |
| Total undiscounted cost (GBP) | 376,862.03 |
| Total discounted cost / PV of costs (GBP) | 303,759.68 |
| Total undiscounted benefit (GBP) | 1,273,290.48 |
| Total discounted benefit (GBP) | 573,987.91 |
| NPV (GBP) | 270,228.23 |
| IRR | 0.1720 |
| Simple payback (year) | 5.79 |
| Discounted payback (year) | 7.63 |
| LCOE (GBP/kWh) | 0.1145 |

## 4. Year-by-year cash flow (scenario model output)

Year-by-year cash flow | Year | Cost (GBP) | Benefit (GBP) | Net (GBP) | Discount factor | Discounted net (GBP) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 247,000.00 | 0.0000 | -247,000.00 | 1.00 | -247,000.00 | 0.0000 |
| 1 | 3,367.50 | 45,125.00 | 41,757.50 | 0.9346 | 39,025.70 | 237,500.00 |
| 2 | 3,434.85 | 45,572.87 | 42,138.02 | 0.8734 | 36,804.97 | 236,312.50 |
| 3 | 3,503.55 | 46,025.18 | 42,521.63 | 0.8163 | 34,710.32 | 235,130.94 |
| 4 | 3,573.62 | 46,481.98 | 42,908.36 | 0.7629 | 32,734.58 | 233,955.28 |
| 5 | 3,645.09 | 46,943.31 | 43,298.22 | 0.7130 | 30,871.03 | 232,785.51 |
| 6 | 3,717.99 | 47,409.22 | 43,691.23 | 0.6663 | 29,113.31 | 231,621.58 |
| 7 | 3,792.35 | 47,879.76 | 44,087.41 | 0.6227 | 27,455.42 | 230,463.47 |
| 8 | 3,868.20 | 48,354.97 | 44,486.77 | 0.5820 | 25,891.70 | 229,311.15 |
| 9 | 3,945.56 | 48,834.89 | 44,889.33 | 0.5439 | 24,416.82 | 228,164.60 |
| 10 | 4,024.47 | 49,319.57 | 45,295.10 | 0.5083 | 23,025.73 | 227,023.77 |
| 11 | 4,104.96 | 49,809.07 | 45,704.11 | 0.4751 | 21,713.69 | 225,888.66 |
| 12 | 26,187.06 | 50,303.43 | 24,116.36 | 0.4440 | 10,707.95 | 224,759.21 |
| 13 | 4,270.80 | 50,802.69 | 46,531.88 | 0.4150 | 19,309.08 | 223,635.42 |
| 14 | 4,356.22 | 51,306.90 | 46,950.68 | 0.3878 | 18,208.28 | 222,517.24 |
| 15 | 4,443.34 | 51,816.13 | 47,372.78 | 0.3624 | 17,170.08 | 221,404.65 |
| 16 | 4,532.21 | 52,330.40 | 47,798.19 | 0.3387 | 16,190.90 | 220,297.63 |
| 17 | 4,622.86 | 52,849.78 | 48,226.92 | 0.3166 | 15,267.41 | 219,196.14 |
| 18 | 4,715.31 | 53,374.31 | 48,659.00 | 0.2959 | 14,396.44 | 218,100.16 |
| 19 | 4,809.62 | 53,904.05 | 49,094.43 | 0.2765 | 13,575.02 | 217,009.66 |
| 20 | 4,905.81 | 54,439.05 | 49,533.24 | 0.2584 | 12,800.33 | 215,924.61 |
| 21 | 5,003.93 | 54,979.36 | 49,975.43 | 0.2415 | 12,069.72 | 214,844.99 |
| 22 | 5,104.01 | 55,525.03 | 50,421.02 | 0.2257 | 11,380.69 | 213,770.76 |
| 23 | 5,206.09 | 56,076.12 | 50,870.03 | 0.2109 | 10,730.87 | 212,701.91 |
| 24 | 5,310.21 | 56,632.67 | 51,322.46 | 0.1971 | 10,118.05 | 211,638.40 |
| 25 | 5,416.41 | 57,194.75 | 51,778.34 | 0.1842 | 9,540.12 | 210,580.21 |

The Year 0 line is capex of £247,000 (PV modules + agrivoltaic canopy premium + DNO grid connection; see §2). The Year 12 cost spike of £26,187.06 reflects the £22,000 inverter replacement plus the baseline annual opex+insurance (~£4,187.06 in that year after 2.0%/yr opex escalation). Residual value at year 25 is set to £0 per the bounded default. Year 1 net benefit at 950 kWh/kWp × 250 kWp = 237,500 kWh × blended ~£0.19/kWh ≈ £45,125 matches the cash-flow table, and the sum of discounted nets reconciles to the computed NPV of +£270,228.23 in §3.

## 5. Scenarios & verdict

### Scenario A — Fixed-tilt, base price (computed base case)

Capex £247,000; NPV **+£270,228.23**; simple payback **5.79 yr**; discounted payback **7.63 yr**; IRR **17.20%**; LCOE **£0.1145/kWh**. **Verdict: recommended** at the computed base assumptions in §2.

### Scenario B — Single-axis tracker (+13.7% yield, +23.5% installed price)

Indicative only — not the computed base case. Tracker uplift on yield is partly offset by higher capex, higher O&M (£15/kWp/yr vs £11/kWp/yr) and higher insurance. **This page does not publish an computed NPV for Scenario B.** The previous draft's figure of "+£262,400" cannot be reproduced from the computed cash-flow model in §4 and is therefore not asserted on this page. Procurement should request a tracker-specific re-quote via the RFQ link.

### Scenario C — Low price (£0.75/Wp), low yield (850 kWh/kWp/yr)

Indicative only — not the computed base case. Lower installed price (£0.75/Wp) is credible only on volume procurement; yield 850 kWh/kWp/yr corresponds to a poorly-oriented UK site. **This page does not publish an computed NPV for Scenario C.** The previous draft's figure of "+£312,400" cannot be reproduced from the computed cash-flow model and is therefore not asserted on this page. Procurement should request a tracker-specific re-quote via the RFQ link.

### Scenario D — High price (£1.05/Wp), low yield (850 kWh/kWp/yr)

Indicative only — not the computed base case. Combination is uneconomic under the scenario model. **This page does not publish an computed NPV for Scenario D.** The previous draft's figure of "−£102,200" cannot be reproduced from the computed cash-flow model and is therefore not asserted on this page. Procurement should request a tracker-specific re-quote via the RFQ link.

Scenario B / C / D sensitivity envelopes are available on request to B2B buyers via the RFQ form.

## 6. Key assumptions & limits

- No battery storage in base case. (If a battery is later added, candidate LFP packs include Deye BOS-G high-voltage series, 5.12 kWh per module at 51.2 V / 100 Ah, systems 20.48–61.44 kWh from 4–12 modules, 19-inch rack, >6000 cycles, intelligent BMS with aerosol fire extinguishing — see [Deye BOS-G product note](https://www.deyeinverter.com/news/industry-news/powering-the-future-deye-s-highvoltage-lithium-battery-solutions-for-reliable-energy-storage.html); Sungrow SBR064-256 LFP, 3.2 kWh per module, 6.4–25.6 kWh per unit, 30 A max charge/discharge — see [Sungrow SBR064-256 product page](https://www.sungrowpower.com/en/products/residential-energy-storage-system/b-sbr064-096-128-160-192-224-256). Confirm exact spec and warranty at RFQ.)

- No inflation in opex (real terms) beyond the bounded default opex.escalation_pct input (2.0%/yr nominal, applied to cost side).

- 55% self-consumption assumes on-site irrigation, cold-store and pack-house load during daylight.

- DNO connection cost is band-referenced; site-specific quotes may vary 30–50%.

- Agrivoltaic canopy premium is a bounded default; not all UK sites require it.

- Residual value at year 25 = £0 (bounded default; revise per site at RFQ).

- Module safety qualification assumed: UL 61730-1 ([UL 61730-1 product page](https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1)) and IEC 61215-1:2021 ed2 ([IEC 61215-1:2021 ed2 — TC 82](https://webstore.iec.ch/en/publication/61345)) for design qualification and type approval.

## 7. Product certifications

No product certifications are asserted as fact on this TCO page beyond the standards named in §1 (UL 61730-1 for module safety qualification, IEC 61215-1:2021 ed2 for module design qualification, IEC 62109-1:2010 for inverter safety). All other certifications (e.g. MCS for UK installations, IEC 61215 for module performance, IEC 62619:2022 ed2 for stationary lithium-battery safety) are site- and procurement-lot specific and must be confirmed by the EPC and by the buyer's site-specific RFQ response. Tradvolt does not represent any certification as held by any specific OEM until the corresponding certificate number and date are returned with the RFQ.

## 8. HS code & duty (advisory)

| Component | HS code (UK) | MFN duty | Lookup |
| --- | --- | --- | --- |
| PV modules / cells | 8541.43 | 0% | UK Global Tariff lookup |
| Mounting structure (aluminium / steel) | 7610.90 / 7308.30 | Lookup | UK Global Tariff lookup |
| Inverter (static converter) | 8504.40 | Lookup | UK Global Tariff lookup |
| Cabling (insulated) | 8544.42 | Lookup | UK Global Tariff lookup |

The importer must verify live duty rates against the [UK Global Tariff](https://www.trade-tariff.service.gov.uk/) using the codes above. Tradvolt does not assert duty rates as fact beyond the published 0% MFN on HS 8541.43 for crystalline PV cells/modules. For non-UK destinations use the appropriate national tariff lookup (e.g. [USITC HTS](https://hts.usitc.gov/), [EU TARIC](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en), [Japan Customs tariff schedule (English)](https://www.customs.go.jp/english/tariff/), [Australian Border Force current tariff](https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff), [South African Revenue Service tariff](https://www.sars.gov.za/customs-and-excise/tariff/), [Central Board of Indirect Taxes and Customs (India)](https://www.cbic.gov.in/), [ICEGATE (India)](https://www.icegate.gov.in/)).

## 9. Logistics & Incoterms reference

Default procurement basis: [ICC Incoterms® 2020](https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/). Recommend FOB or CIF for GB port of entry. Wood packaging must comply with [IPPC ISPM 15](https://www.ippc.int/en/core-activities/standards-setting/ispms/). Lithium batteries (if any) classified per [IATA Dangerous Goods Regulations](https://www.iata.org/en/programs/cargo/dgr/), [ICAO Dangerous Goods](https://www.icao.int/safety/dangerousgoods/Pages/default.aspx) and tested per the [UN Manual of Tests and Criteria](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria) (UN 38.3, ST/SG/AC.10/11/Rev.7). Stationary lithium battery safety per IEC 62619:2022 ed2 ([IEC 62619:2022 ed2 — TC 21/SC 21A](https://webstore.iec.ch/en/publication/64073)) and IEC 62485-5:2020 ([IEC 62485-5:2020 — TC 21](https://webstore.iec.ch/en/publication/29086)). EU battery regulation context: Regulation (EU) 2023/1542 ([EUR-Lex official document page](https://eur-lex.europa.eu/eli/reg/2023/1542/oj)). Forwarding per [FIATA](https://fiata.org/) standard documents.

## 10. Next steps

**RFQ:** [Request quote — 250 kWp UK orchard solar](/rfq/?use_case=orchard-solar-250kwp-uk&size_kwp=250&country=GB)

## 11. Sources

| Publisher | Document | Edition / Date | URL |
| --- | --- | --- | --- |
| RenewableUK | Solar Photovoltaic Deployment in the UK (annual statistics, specific-yield band; insurance-survey band) | Annual statistics, 2024–2025 | RenewableUK (cite publication title + year when republishing) |
| Solar Energy UK | Solar PV Cost Update H1 2025 (ground-mount installed-price band; O&M benchmark; specific-yield band) | H1 2025 | Solar Energy UK — Solar PV Cost Update H1 2025 (cite title + edition) |
| Solar Energy UK | Best Practice Guidelines for Solar PV (tracker yield-uplift band) | Current edition | Solar Energy UK — Best Practice Guidelines |
| Fraunhofer ISE / Forschungsverbund Agrar- und Versorgungstechnik (FRAV) | Agrivoltaics Cost Premium Guidance | Current edition | Fraunhofer ISE (cite agrivoltaic cost-premium band) |
| National Grid ESO | Connection Charging Methodology (DNO band reference) | Current statement | National Grid ESO — Connection Charging Methodology |
| Ofgem | Energy price cap hub (Default Tariff Cap; avoided grid-import price level) | Current quarter (Jan–Mar 2026 baseline) | Ofgem energy price cap hub |
| Ofgem | Smart Export Guarantee (SEG) reference rates | Current | Ofgem — Smart Export Guarantee |
| IEC | IEC 62109-1:2010 — Safety of power converters for use in photovoltaic power systems, Part 1: General requirements (TC 82) | 2010 | IEC 62109-1:2010 — TC 82 |
| IEC | IEC 62109-2:2011 — Part 2: Particular requirements for inverters | 2011 | IEC Webstore — cite IEC 62109-2:2011 |
| IEC | IEC 61215-1:2021 ed2 — Terrestrial PV modules — Design qualification and type approval — Part 1: Test requirements (TC 82) | 2021 ed2 | IEC 61215-1:2021 ed2 — TC 82 |
| IEC | IEC 62619:2022 ed2 — Safety requirements for secondary lithium cells and batteries for use in industrial applications incl. stationary/ESS (TC 21/SC 21A) | 2022 ed2 | IEC 62619:2022 ed2 — TC 21/SC 21A |
| IEC | IEC 62485-5:2020 — Safety requirements for secondary batteries and battery installations — Part 5: Safe operation of stationary lithium-ion batteries (TC 21) | 2020 | IEC 62485-5:2020 — TC 21 |
| UL | UL 61730-1 Photovoltaic (PV) Module Safety Qualification — Part 1 | Current edition | UL 61730-1 product page |
| UNECE | UN Manual of Tests and Criteria (UN 38.3 lithium-battery provisions), ST/SG/AC.10/11/Rev.7 | Rev.7 | UN Manual of Tests and Criteria |
| ICAO | ICAO Dangerous Goods (battery air-transport provisions) | Current | ICAO Dangerous Goods |
| European Commission | Regulation (EU) 2023/1542 — EU Battery Regulation | 2023 | EUR-Lex — Regulation (EU) 2023/1542 |
| HMRC / UK Border Force | UK Global Tariff (HS 8541.43, 8504.40, 7610.90, 7308.30, 8544.42) | Live | UK Global Tariff lookup |
| European Commission | TARIC consultation | Live | EU TARIC consultation |
| USITC | Harmonized Tariff Schedule of the United States | Live | USITC HTS search |
| Japan Customs | Tariff schedule (English) | Live | Japan Customs tariff schedule |
| Australian Border Force | Current tariff classification | Live | ABF current tariff |
| South African Revenue Service | Customs and Excise Tariff | Live | SARS Customs & Excise Tariff |
| Central Board of Indirect Taxes and Customs (India) | Indian Customs tariff / ICEGATE | Live | CBIC India / ICEGATE |
| ICC | Incoterms® 2020 | 2020 | ICC Incoterms 2020 |
| IPPC | ISPM 15 (wood packaging) | Current | IPPC ISPMs |
| IATA | Dangerous Goods Regulations (DGR) | Annual edition | IATA DGR |
| FIATA | Standard freight-forwarding documents | Current | FIATA |
| IEA | Renewables market data (background) | Annual | IEA |

OEM product pages (reference; datasheets confirmed at RFQ): LONGi Hi-MO X6 ([LONGi Hi-MO X6](https://www.longi.com/en/products/modules-series/hi-mo-x6/)), JinkoSolar Tiger Neo 3.0 ([JinkoSolar company profile](https://www.jinkosolar.com/en/site/aboutus)), Trina Solar ([trinasolar.com/us-en](https://www.trinasolar.com/us-en)), Huawei FusionSolar ([solar.huawei.com/en](https://solar.huawei.com/en)), Sungrow string-inverter range incl. SG125HT ([Sungrow string-inverter range](https://www.sungrowpower.com/en/products/string-inverter)), K2 Systems N-Rack + SingleRail 36 ([N-Rack](https://k2-systems.com/en/product-solutions/k2-n-rack-system/) / [SingleRail 36 catalogue entry](https://catalogue.k2-systems.com/singlerail-36/2004258)).