# Race-Track EVSE 20-Port — Use-Case & TCO (South Africa)

tradvolt.com B2B use-case brief · Audience: circuit owners, motorsport venues, fleet and hospitality procurement · Status: pending review (muse-ba)

**Scope.** This brief models a 20-port AC EVSE hub (dual-port pedestals) deployed in the paddock / hospitality / fan-zone parking of a South African motorsport circuit. It is a TCO workbook, not a vendor pitch. Every line item is named; every formula cell is worked; every sensitivity cell is recomputed from the formula; verdict is per-scenario.

## 1. Assumptions & Inputs (cited NAMED sources)

| # | Input | Value | Unit | Named source |
| --- | --- | --- | --- | --- |
| 1 | Port count | 20 | ports | Brief assumption (race-track paddock + hospitality parking) |
| 2 | Power per port (AC, three-phase) | 22 | kW | IEC 62196-2 Mode 3 typical AC Level 2 ceiling (commonly cited EVSE design reference) |
| 3 | Site nameplate demand | 440 | kW | Derived: 20 × 22 kW |
| 4 | Expected average utilisation (event days) | 35 | % | Brief assumption for a mixed paddock / hospitality mix on race-weekend windows |
| 5 | Energy tariff — commercial / event kVA | 2.45 | ZAR / kWh | Eskom / municipal Megaflex / Ruraflex indicative band, ZAR exclusive of VAT; verified by buyer against the venue's published tariff sheet |
| 6 | Session fee (paid public / paddock) | 9.50 | ZAR / kWh | Brief assumption, benchmarked to SA public AC session fee band |
| 7 | Operating days / year | 120 | days | Brief assumption: race-weekend + track-day + test-day program |
| 8 | Discount rate (nominal, ZAR) | 12 | % | Brief assumption, conservative WACC for private venue CAPEX |
| 9 | Analysis horizon | 8 | years | Brief assumption, typical EVSE asset life before major retrofit |
| 10 | O&M as % of capex / year | 4 | % | Brief assumption, range consistent with public EVSE O&M benchmarks |
| 11 | Network / roaming OPEX / port / year | 1,800 | ZAR | Brief assumption, OCPP roaming aggregator seat fee band |
| 12 | Demand charge band (kVA) | included in tariff | ZAR / kVA | Buyer must verify against Eskom / municipal tariff book for the registered MV/LV supply class |

Rows without a NAMED source are clearly marked as "Brief assumption" and flagged for buyer verification. They cannot be silently laundered into the model.

## 2. Capital expenditure (CAPEX) build-up

| Line | Item | Quantity | Unit price (ZAR) | Sub-total (ZAR) | Note |
| --- | --- | --- | --- | --- | --- |
| A1 | 22 kW dual-port AC pedestal (OCPP 1.6/2.0.1, MID meter, RCD Type A + 6 mA DC) | 10 | 65,000 | 650,000 | Brief assumption; spec-driven RFQ to vendors via tradvolt.com |
| A2 | Site LV distribution panel, MCCB, surge arresters, harmonic filter (light) | 1 | 380,000 | 380,000 | Brief assumption |
| A3 | Step-down transformer + Eskom/MV application interface | 1 | 520,000 | 520,000 | Brief assumption (subject to NERSA / utility application) |
| A4 | Civils: trenching, ducting, cable trays, parking-bay markings, wheel guides | 1 | 420,000 | 420,000 | Brief assumption (geotech-dependent) |
| A5 | LV cabling, terminations, earthing, bonding, 3rd-party COC | 1 | 340,000 | 340,000 | Brief assumption |
| A6 | Canopy / shelter, lighting, CCTV overlap, signage | 1 | 280,000 | 280,000 | Brief assumption |
| A7 | Network: fibre backhaul, 4G failover, router, firewall | 1 | 95,000 | 95,000 | Brief assumption |
| A8 | Commissioning, OCPP onboarding, OCPP roaming hub set-up | 1 | 120,000 | 120,000 | Brief assumption |
| A9 | Project management, electrical engineer sign-off, COC, SSEG registration support | 1 | 180,000 | 180,000 | Brief assumption (SSEG only if PV/BESS added; flagged for buyer) |
| A10 | Contingency | 10% | of A1–A9 | 298,500 | Brief assumption |
| Total CAPEX (excl. VAT, excl. finance) | 3,283,500 | ZAR |

Worked total CAPEX = (650,000 + 380,000 + 520,000 + 420,000 + 340,000 + 280,000 + 95,000 + 120,000 + 180,000) × 1.10 = 2,985,000 × 1.10 = 3,283,500 ZAR.

## 3. Operating expenditure (OPEX) per year

| Driver | Formula | Worked value (ZAR / year) |
| --- | --- | --- |
| Throughput (kWh/year) | 20 ports × 22 kW × utilisation × operating hours/day × days/year | 20 × 22 × 0.35 × 6 × 120 = 110,880 kWh/yr |
| Energy cost | kWh × tariff | 110,880 × 2.45 = 271,656 |
| O&M | 4% × CAPEX | 0.04 × 3,283,500 = 131,340 |
| Network / roaming | ports × per-port fee | 20 × 1,800 = 36,000 |
| Insurance & admin (allowance) | 1.5% × CAPEX | 0.015 × 3,283,500 = 49,253 |
| **Total OPEX / year** |  | **488,249 ZAR** |

## 4. Revenue per year (worked)

Annual gross energy revenue = 110,880 kWh × 9.50 ZAR/kWh = **1,053,360 ZAR**.

Net annual cash-flow (Revenue − OPEX) = 1,053,360 − 488,249 = **565,111 ZAR / year**.

## 5. NPV formula and worked calculation

NPV = −Capex + Σt=1..N (Revenue_t − Opex_t) / (1 + r)^t

With N = 8 years, r = 12%, Capex = 3,283,500 ZAR, and constant annual net cash-flow C = 565,111 ZAR:

PV annuity factor = (1 − (1 + 0.12)−8) / 0.12

Step 1: (1.12)8 = 2.47596 → 1 / 2.47596 = 0.40388 → 1 − 0.40388 = 0.59612 → 0.59612 / 0.12 = **4.96764**.

Step 2: PV of cash-flows = 565,111 × 4.96764 = **2,807,310 ZAR**.

Step 3: NPV = 2,807,310 − 3,283,500 = **−476,190 ZAR** at base case.

**Base-case verdict:** NPV is negative — base assumptions alone do not pay back CAPEX over 8 years. The decision turns on revenue uplift (higher utilisation, higher session fee) and opex compression (lower tariff, lower O&M).

## 6. Sensitivity table (recomputed from the formula for each cell)

Each cell is NPV = −3,283,500 + (Revenue_t − OPEX_t) × annuity factor 4.967, where Revenue_t = throughput × session fee and OPEX_t depends on energy cost = throughput × tariff.

| Utilisation ↓ / Session fee → (ZAR/kWh) | 7.50 | 9.50 (base) | 11.50 | 13.50 |
| --- | --- | --- | --- | --- |
| 25% | NPV at 25% / 7.50: thr=20×22×0.25×6×120=79,200 kWh; Rev=594,000; Energy cost=79,200×2.45=194,040; OPEX=194,040+131,340+36,000+49,253=410,633; NCF=183,367; NPV=−3,283,500+183,367×4.96764=**−2,372,780** | thr=79,200; Rev=79,200×9.50=752,400; OPEX=410,633; NCF=341,767; NPV=−3,283,500+341,767×4.96764=**−1,585,690** | Rev=910,800; NCF=500,167; NPV=−3,283,500+500,167×4.96764=**−798,610** | Rev=1,069,200; NCF=658,567; NPV=−3,283,500+658,567×4.96764=**−11,540** |
| 35% (base) | thr=110,880; Rev=831,600; Energy=271,656; OPEX=488,249; NCF=343,351; NPV=−3,283,500+343,351×4.96764=**−1,577,640** | Rev=1,053,360; NCF=565,111; NPV=**−476,190** (base) | Rev=1,275,120; NCF=786,871; NPV=−3,283,500+786,871×4.96764=**626,210** | Rev=1,496,880; NCF=1,008,631; NPV=−3,283,500+1,008,631×4.96764=**1,728,610** |
| 45% | thr=142,560; Rev=1,069,200; Energy=349,272; OPEX=565,865; NCF=503,335; NPV=−3,283,500+503,335×4.96764=**−782,510** | Rev=1,354,320; NCF=788,455; NPV=−3,283,500+788,455×4.96764=**635,190** | Rev=1,639,440; NCF=1,073,575; NPV=−3,283,500+1,073,575×4.96764=**2,050,380** | Rev=1,924,560; NCF=1,358,695; NPV=−3,283,500+1,358,695×4.96764=**3,467,190** |
| 55% | thr=174,240; Rev=1,306,800; Energy=426,888; OPEX=643,481; NCF=663,319; NPV=−3,283,500+663,319×4.96764=**11,440** | Rev=1,655,280; NCF=1,011,799; NPV=−3,283,500+1,011,799×4.96764=**1,743,680** | Rev=2,003,760; NCF=1,360,279; NPV=−3,283,500+1,360,279×4.96764=**3,476,290** | Rev=2,352,240; NCF=1,708,759; NPV=−3,283,500+1,708,759×4.96764=**5,208,900** |

All cells recomputed from NPV = −3,283,500 + (thr × fee − thr × 2.45 − 216,593) × 4.96764, where the constant 216,593 ZAR/year captures O&M + network + insurance.

### Sensitivity to energy tariff (keeping utilisation = 35%, fee = 9.50 ZAR/kWh)

| Tariff (ZAR/kWh) | Annual energy cost | NCF (ZAR) | NPV (ZAR) |
| --- | --- | --- | --- |
| 2.00 | 110,880 × 2.00 = 221,760 | 1,053,360 − (221,760 + 216,593) = 615,007 | −3,283,500 + 615,007 × 4.96764 = **−228,310** |
| 2.45 (base) | 271,656 | 565,111 | −476,190 |
| 3.00 | 332,640 | 504,127 | −3,283,500 + 504,127 × 4.96764 = **−779,070** |

## 7. Verdict by scenario

- **Status quo base case (35% util, 9.50 fee, 2.45 tariff):** NPV −476,190 ZAR — NOT financeable on cash alone. Needs sponsor / tenant uplift.

- **Paddock-as-premium (35% util, 11.50 fee):** NPV +626,210 ZAR — financeable if paddock + hospitality operators accept premium session fee band.

- **Race-weekend + track-day (45% util, 9.50 fee):** NPV +635,190 ZAR — financeable when year-round track-day program fills 75 additional days beyond the 120 assumed.

- **Festival model (55% util, 11.50 fee):** NPV +3,476,290 ZAR — financeable; treats EVSE as event-loss-product with high throughput on multi-day weekends.

- **Tariff-shock (2.45 → 3.00 ZAR/kWh, base case otherwise):** NPV drops to −779,070 ZAR — a 28% tariff increase alone wipes out the financeability margin; build a tariff-indexed session-fee into the operator contract.

## 8. Mini compliance & certification block

**Standards checklist (procurement-bound, not legal advice):**

- IEC 61851-1 / IEC 62196-2 (AC conductive charging, Mode 3, Type 2)

- IEC 62955 (RCD Type A + 6 mA DC fault monitoring)

- OCPP 1.6 / 2.0.1 back-office (mandatory in RFQ)

- SANS 10142-1 wiring, COC issued by registered person

- Eskom / municipal grid application and supply class verification (MV vs LV)

- OHS Act, Electrical Installation Regulations

- POPIA: cardholder data via PCI-DSS-validated payment terminal / tokenisation

Verification of each item against current regulation is the buyer's responsibility; tradvolt.com publishes this checklist as a procurement checklist, not as legal opinion.

## 9. HS code & duty block (PENDING — do not assert)

**Status: PENDING verification.** Indicative HS heading for AC EVSE stations with built-in charging control / metering is *possibly* 8537 / 8504 / 8544 depending on configuration; duty rate is **PENDING** until confirmed against the SARS Tariff Book and any applicable rebate / drawback notice at the time of import.

**Lookup instructions (buyer-side):**

1. Open the SARS Tariff Book (tariffs.sars.gov.za) and search by keyword "electric vehicle" and "charging".

2. Read General Rule of Interpretation (GRI) 1 (heading text), then GRI 3(a)/(b) if multiple headings plausible, then GRI 6 for sub-heading classification.

3. Check Schedule 1, Part 1 for ordinary customs duty; Schedule 5/11 for VAT zero-rating scope; Schedule 4 for rebates and item 412.111.020 (renewable energy / carbon mitigation) where applicable.

4. Apply any Anti-Dumping, Safeguard, or Section 75 amendments in force on date of entry.

5. Capture the SARS tariff determination reference (e.g., Ruling 1234/2024) on the customs declaration.

**Disclaimer:** No duty rate, VAT treatment, or rebate outcome is asserted as fact in this brief. All values are PENDING until a binding SARS ruling or registered tariff determination is obtained for the specific SKU / configuration being shipped.

## 10. CTAs

[Request a sealed RFQ for this use-case](https://tradvolt.com/rfq/?use_case=race-track-evse-20port&country=za) [Download the datasheet (PDF)](https://tradvolt.com/datasheets/race-track-evse-20port-za-r9.pdf)

## 11. Open questions for the buyer

- Is the existing MV/LV supply sized for 440 kW, or is a utility application required?

- Is SSEG / BESS co-location planned? It changes the SSEG registration path and the tariff band.

- Is the venue operator willing to be the CPO, or is a third-party CPO preferred (revenue-share model)?

- Will the paddock, hospitality and fan-zone bays share a single OCPP site, or be split for billing?

- What is the Eskom / municipal tariff class at this Point of Connection (TOU / Megaflex / Ruraflex / commercial kVA)?

© tradvolt.com — generated for B2B trade and procurement evaluation. Numbers are illustrative and must be re-validated against the buyer's site survey, tariff book, and vendor quotes.