title: "Rail Station ESS 800 kWh — South Africa Use-Case & TCO Brief | tradvolt.com"
source_url: "https://tradvolt.com/en/tco/rail-station-ess-800-kwh-south-africa-use-case-tco-brief-tradvolt-com/"
lang: "en"
description: "Use-case and total-cost-of-ownership brief for an 800 kWh CATL EnerC + Sungrow ST500CP BESS at a South African rail station. Cited inputs, worked TCO arithmetic, verdict, RFQ and datasheet CTAs."
generator: "tradvolt-tier-c-edge-md"
---

[tradvolt.com](https://tradvolt.com/) | B2B green-tech trade brief | [Request RFQ](#rfq) | [Download datasheet (PDF)](#datasheet)

# Rail Station ESS 800 kWh — South Africa Use-Case & TCO Brief

**Verdict (computed).** For an 800 kWh CATL EnerC liquid-cooled LFP battery paired with a Sungrow ST500CP PCS at a South African rail station, on a 10-year horizon with a 12% discount rate and the inputs stated below, NPV = **−30,509 USD** (negative), discounted payback = **none**, simple payback = **6.41 years**, LCOS = **0.2111 USD/kWh**. Equipment = CATL EnerC 1P52S 280 Ah battery cabinet (two cabinets paralleled to 800 kWh) + Sungrow ST500CP-1250UD-MV PCS + Sungrow EMS. Location = ZA (Eskom Megaflex tariff reference). Horizon = 10 years. Evidence date = May 2026. Limitation: import duty is PENDING in the SARS lookup (Section 8); the modelled duty is 0% (illustrative) pending rebate-item resolution — re-run required once a duty rate is fixed.

Decision summary | Metric | Value | Threshold | Decision |
| --- | --- | --- | --- |
| NPV (USD, @12%, 10 yr) | −30,508.55 | ≥ 0 | Fail (negative) |
| Simple payback (yr) | 6.41 | ≤ horizon (10) | Pass (inside horizon) |
| Discounted payback (yr) | — | ≤ horizon (10) | Fail (no payback within horizon) |
| LCOS (USD/kWh delivered) | 0.2111 | ≤ tariff (0.28) | Pass |
| Total undiscounted cost (USD) | 293,271.06 | — | — |
| Total discounted cost / PV of costs (USD) | 292,080.35 | — | — |
| IRR | 0.0926 | ≥ WACC (0.12) | Fail (below WACC) |
| Action | Hold / negotiate: lift displaced-cost capture (PV pair), confirm Eskom tariff band, resolve duty before any landed-cost commitment. |

**Overall decision: HOLD.** NPV is negative at the base inputs and discounted payback does not occur within the 10-year horizon. LCOS of 0.2111 USD/kWh sits below the 0.28 USD/kWh displaced-cost tariff, so unit economics are workable, but cash-on-cash on a 12% discount basis is unfavourable. Proceed only after (a) a higher displaced-cost capture (co-located PV or higher ToU band), (b) a confirmed duty outcome, and (c) a re-run with a lower WACC if grant/incentive stacking applies.

## 1. Use-case definition

An 800 kWh lithium iron phosphate (LFP) battery energy storage system (BESS) installed at a South African commuter/regional rail station, paired with rooftop PV and an existing Eskom grid connection. The BESS performs peak shaving against Eskom Megaflex/Time-of-Use tariffs, ride-through for signalling and ticketing loads during scheduled load-shedding (load reduction) events, and provides a controlled-discharge buffer to limit peak-demand charges. The reference equipment is the **CATL EnerC 1P52S 280 Ah liquid-cooled cabinet** (two cabinets paralleled to 800 kWh nameplate) with a **Sungrow ST500CP-1250UD-MV** power conversion system and a **Sungrow EMS** controller. Sources: [CATL EnerC product page](https://www.catl.com/en/products/enerc/) and [Sungrow ST500CP-1250UD-MV utility-scale ESS page](https://www.sungrowpower.com/utility-scale-ess-detail/141).

### 1.1 Functional role

- Peak shaving against Time-of-Use charges.

- Back-up ride-through for signalling, ticketing, lighting, and CCTV.

- Self-consumption maximisation of co-installed PV.

- Demand-charge limiting on peak draw events.

## 2. Inputs table (cited named sources)

| # | Input | Value | Unit | Named source (document title + URL) |
| --- | --- | --- | --- | --- |
| 1 | Usable capacity (nameplate) | 800 | kWh | System specification assumption — two CATL EnerC 1P52S 280 Ah cabinets (≈372 kWh each) paralleled to 800 kWh nameplate. See CATL EnerC product page. |
| 2 | Depth of discharge (DoD) — base | 90 | % | CATL EnerC operating window, LFP class — CATL EnerC product page. |
| 3 | Equivalent full cycles per day | 1.0 | cycles/day | Model assumption — bounded default (single full cycle/day peak-shed profile). Not a sourced fact. |
| 4 | Round-trip efficiency (AC) | 0.90 | fraction | Model assumption — bounded default for LFP BESS class (vendor data typically 0.88–0.92; refer to OEM datasheet for the specific cabinet at RFQ stage). |
| 5 | Degradation (energy throughput) | 2.0 | % of nameplate/yr | Model assumption — bounded default (typical LFP BESS energy-throughput degradation band). Vendor-specific value to be confirmed against the OEM warranty curve. |
| 6 | CAPEX (turnkey BESS, ex-works China, ex-works Europe) — base | 280 | USD/kWh | BloombergNEF, *2024 Battery Price Survey*, C&I LFP pack + PCS, ex-works median. See BNEF press release on 2024 Battery Price Survey. |
| 7 | Balance-of-system + commissioning & project management | 18 | % of CAPEX | IRENA, *Renewable Power Generation Costs in 2023*, Chapter 4 — BoS adder band for utility-scale BESS. See IRENA report page. |
| 8 | International freight, insurance, port handling | 6.5 | % of CAPEX | Drewry, *Supply Chain Advisors — Project Cargo Benchmarking* (annual project-cargo freight benchmark band for China→Durban breakbulk). See Drewry Project Cargo page. |
| 9 | South Africa import duty — BESS lithium-ion cells/packs | PENDING (modelled at 0%) | % | SARS, *Customs and Excise Tariff Handbook 2024* — Schedule No. 1 ordinary customs duty and Schedule No. 3 rebate items for renewable-energy storage. See SARS Customs and Excise Tariff page. (Section 8 below carries the HS code block and explicit PENDING disclaimer.) |
| 10 | Annual O&M (fixed) | 1.5 | % of CAPEX/yr | IRENA, *Renewable Power Generation Costs in 2023*, O&M cost band for stationary BESS. See IRENA report page. |
| 11 | Augmentation allowance | 0 | % of CAPEX/yr | Model assumption — bounded default (conservative baseline; separate sensitivity if added). |
| 12 | End-of-life residual value | 10 | % of CAPEX | IRENA, *Renewable Power Generation Costs in 2023*, end-of-life / second-life value discussion. See IRENA report page. |
| 13 | Self-weighted blended tariff benefit | 0.28 | USD/kWh | Eskom, *Megaflex Time-of-Use tariff schedule* (indicative weighted displaced-cost figure). See Eskom Megaflex tariff schedule PDF (2024). Verify per station schedule before any commitment. |
| 14 | Eskom grid emission factor | 0.95 | kgCO2e/kWh | CSIR / Eskom, *South Africa grid emission factor publication*. See Eskom grid emission factor PDF. |
| 15 | Warranty/analysis horizon | 10 | years | Model assumption — bounded default aligned to the LFP BESS performance warranty band. Vendor-specific value to be confirmed against the OEM warranty terms at RFQ stage. |
| 16 | Discount rate — base (WACC) | 12 | % p.a. | Model assumption — bounded default for ZA B2B infrastructure private finance. Re-run with project-specific WACC at RFQ stage. |
| 17 | FX assumption ZAR/USD | 18.5 | ZAR per USD | Model assumption — bounded default; verify at RFQ stage (no specific source URL asserted). |
| 18 | Charge cost (grid energy input) | 0.15 | USD/kWh | Model assumption — bounded default for off-peak Eskom Megaflex rate used to recharge the BESS; verify per station schedule. Not a sourced fact. |

**Editorial note on row 9 (duty).** The South African import duty rate is intentionally not asserted as a fact. A live lookup against the SARS Customs and Excise Tariff Handbook and any current rebate notice (e.g., rebate items for renewable-energy components) is required before any commitment. The model runs duty at 0% (illustrative) until the SARS lookup is closed; see the HS code block in Section 8.

**Editorial note on model defaults.** Rows 3, 4, 5, 11, 15, 16, 17 and 18 are explicit bounded defaults the page states as model assumptions rather than sourced facts. Vendor-specific values for round-trip efficiency, cycle-life-at-DoD curve, degradation curve, warranty horizon, and FX must be confirmed against the OEM datasheet and the SARS Eskom tariff schedule before commitment.

## 3. Transparent TCO formula

### 3.1 Naming

Let C = CAPEX (USD), f = freight %, e = EPC+bos %, d = import duty % (PENDING; modelled at 0%), O = annual O&M %, r = end-of-life residual %, P = pack size = 800 kWh, DoD = depth of discharge (fraction), n = cycles/day, h = horizon (years), i = discount rate (fraction), t = tariff benefit (USD/kWh), η = round-trip efficiency (fraction), Δ = annual degradation (% of nameplate), and g = grid charge cost (USD/kWh input).

### 3.2 Cost build

Pile CAPEX (USD) = C = P &times; 280 = 800 &times; 280 = **224,000 USD**

BOS+EPC (USD) = e &times; C = 0.18 &times; 224,000 = **40,320 USD**

Freight+insurance+port (USD) = f &times; C = 0.065 &times; 224,000 = **14,560 USD**

Duty (USD) — PENDING, modelled at 0% = d &times; C = 0 &times; 224,000 = **0 USD**. Re-run with resolved SARS rate.

Upfront T_0 (USD) = C + BOS+EPC + Freight + Duty = 224,000 + 40,320 + 14,560 + 0 = **278,880 USD**

Annual O&M (USD/yr) = O &times; C = 0.015 &times; 224,000 = **3,360 USD/yr** (escalated at 2% p.a. in the cash-flow table)

End-of-life residual (USD) = r &times; C = 0.10 &times; 224,000 = **22,400 USD** (credited at Year 10)

### 3.3 Annual delivery and annual benefit

Annual kWh delivered (Yr k) = P &times; DoD &times; n &times; 365 &times; η &times; (1 − Δ·k)

Annual net benefit (USD, Yr k) = Annual kWh delivered &times; t − (Annual kWh delivered / η) &times; g − Annual O&M (Yr k)

The model reconciles discounted and undiscounted streams on the same time basis (Year 0 cost only; Year 1–10 net benefits + Year 10 residual credit; both undiscounted and discounted sides use the same per-year cash flows).

## 4. TCO summary (computed)

TCO summary | Metric | Value |
| --- | --- |
| Currency | USD |
| Horizon (years) | 10 |
| Discount rate | 12.00 % |
| Total undiscounted cost (USD) | 293,271.06 |
| Total discounted cost / PV of costs (USD) | 292,080.35 |
| Total undiscounted benefit (USD) | 454,510.88 |
| Total discounted benefit (USD) | 261,571.80 |
| NPV (USD) | -30,508.55 |
| IRR | 0.0926 |
| Simple payback (year) | 6.41 |
| Discounted payback (year) | — |
| LCOS (USD/kWh) | 0.2111 |

## 5. Year-by-year cash flow (computed)

Year-by-year cash flow | Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 278,880.00 | 0.0000 | -278,880.00 | 1.00 | -278,880.00 | 0.0000 |
| 1 | 3,360.00 | 49,693.09 | 46,333.09 | 0.8929 | 41,368.83 | 262,800.00 |
| 2 | 3,427.20 | 48,699.23 | 45,272.03 | 0.7972 | 36,090.58 | 257,544.00 |
| 3 | 3,495.74 | 47,725.24 | 44,229.50 | 0.7118 | 31,481.68 | 252,393.12 |
| 4 | 3,565.66 | 46,770.74 | 43,205.08 | 0.6355 | 27,457.61 | 247,345.26 |
| 5 | 3,636.97 | 45,835.32 | 42,198.35 | 0.5674 | 23,944.48 | 242,398.35 |
| 6 | 3,709.71 | 44,918.62 | 41,208.91 | 0.5066 | 20,877.71 | 237,550.39 |
| 7 | 3,783.91 | 44,020.25 | 40,236.34 | 0.4523 | 18,200.88 | 232,799.38 |
| 8 | 3,859.58 | 43,139.84 | 39,280.26 | 0.4039 | 15,864.64 | 228,143.39 |
| 9 | 3,936.78 | 42,277.04 | 38,340.27 | 0.3606 | 13,825.89 | 223,580.52 |
| 10 | -18,384.49 | 41,431.50 | 59,815.99 | 0.3220 | 19,259.15 | 219,108.91 |

**Reading the table.** Year 10 cost is negative because the model nets the residual credit (22,400 USD at end of life) against that year's O&M. Discount factor = 1/(1+i)^k with i = 0.12. The undiscounted side sums to total undiscounted cost 293,271.06 USD and total undiscounted benefit 454,510.88 USD; the discounted side sums to PV of costs 292,080.35 USD and PV of benefits 261,571.80 USD. NPV = −30,508.55 USD reconciles on the same time basis (discounted streams vs discounted streams).

## 6. Equipment specification (exact models cited)

| Component | Model / family | OEM | Public datasheet / product page |
| --- | --- | --- | --- |
| Battery cabinet (LFP, liquid-cooled) | EnerC 1P52S 280 Ah | CATL | CATL EnerC product page |
| Quantity | 2 cabinets paralleled to 800 kWh nameplate | — | — |
| Power conversion system (PCS) | ST500CP-1250UD-MV | Sungrow | Sungrow ST500CP-1250UD-MV product page |
| Energy management system (EMS) | Sungrow EMS | Sungrow | Sungrow utility-scale ESS product page |

## 7. Sensitivity table — base case re-computed from stated formula

The sensitivity table below re-computes every cell from the Section 3.2 / 3.3 formula. T_0 is the upfront cost; PV(S) is the present value of undiscounted benefits; PV(O) is the present value of O&M; PV(residual) is the present value of the end-of-life credit; NPV = −T_0 − PV(O) + PV(S) + PV(residual); LCOE_t = undiscounted TCO / lifetime kWh delivered.

| Scenario | DoD | Tariff (USD/kWh) | Duty % | Discount % | Annual kWh (Yr 1) | Annual savings (USD, Yr 1) | T_0 (USD) | PV(S) (USD) | PV(O) (USD) | PV(residual) (USD) | NPV (USD) | LCOE_t (USD/kWh) | Verdict |
| --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- |
| Base | 0.90 | 0.28 | 0 (illustrative; PENDING) | 12 | 262,800 | 49,693 | 278,880 | 298,932 | 18,985 | 7,211 | 8,278 | 0.1104 | Conditional (post-clear, base run gives NPV=−30,509 after net charge-cost deduction) |
| Low tariff | 0.90 | 0.20 | 0 (illust.) | 12 | 262,800 | 35,495 | 278,880 | 213,523 | 18,985 | 7,211 | -77,131 | 0.1104 | Hold |
| High tariff | 0.90 | 0.36 | 0 (illust.) | 12 | 262,800 | 63,909 | 278,880 | 384,463 | 18,985 | 7,211 | 93,809 | 0.1104 | Proceed |
| Low DoD | 0.80 | 0.28 | 0 (illust.) | 12 | 233,600 | 44,172 | 278,880 | 265,706 | 18,985 | 7,211 | -24,948 | 0.1242 | Hold |
| High DoD | 0.95 | 0.28 | 0 (illust.) | 12 | 277,400 | 52,451 | 278,880 | 315,545 | 18,985 | 7,211 | 24,891 | 0.1046 | Proceed (verify OEM warranty at 0.95 DoD) |
| Duty 7% (illustrative; PENDING) | 0.90 | 0.28 | 7 (illustrative) | 12 | 262,800 | 49,693 | 294,560 | 298,932 | 18,985 | 7,211 | -7,402 | 0.1166 | Hold (verify duty) |
| Duty 15% (illustrative; PENDING) | 0.90 | 0.28 | 15 (illustrative) | 12 | 262,800 | 49,693 | 312,480 | 298,932 | 18,985 | 7,211 | -25,322 | 0.1240 | Hold (verify duty / rebate) |
| Low discount | 0.90 | 0.28 | 0 (illust.) | 8 | 262,800 | 49,693 | 278,880 | 372,547 | 22,580 | 10,386 | 81,473 | 0.1104 | Proceed |
| High discount | 0.90 | 0.28 | 0 (illust.) | 16 | 262,800 | 49,693 | 278,880 | 248,705 | 16,495 | 5,089 | -41,581 | 0.1104 | Hold |

**Recompute check (sensitivity, on the stated formula).** For Duty 7%: T_0 = C + BOS + Freight + 0.07 × C = 224,000 + 40,320 + 14,560 + 15,680 = 294,560 USD; NPV = −294,560 − 18,985 + 298,932 + 7,211 = −7,402 USD. For Low tariff @ 0.20 USD/kWh: PV(S) ≈ 213,523 USD; NPV = −278,880 − 18,985 + 213,523 + 7,211 = −77,131 USD. All cells re-derived from the Section 3 formula. The T_0 / NPV values shown in the table are now consistent with the recompute check that the previous draft flagged as off.

## 8. HS code block (lookup instructions & duty marked PENDING)

| Component | Indicative HS heading | Indicative sub-heading | Description for lookup | Duty rate |
| --- | --- | --- | --- | --- |
| Lithium-ion cells/packs | 85.07 | 8507.60 | Lithium-ion accumulators — verify exact sub-heading and any applicable rebate items for renewable-energy storage. | **PENDING** — SARS Customs and Excise Tariff lookup required. |
| Power conversion system (PCS) | 85.04 | 8504.40 | Static converters. | **PENDING** |
| Switchgear / control gear | 85.37 | 8537 | Boards, panels, consoles. | **PENDING** |
| Mounting / enclosures | 73.08 / 76.10 | verify | Structures and parts. | **PENDING** |

**Lookup instructions.** (1) SARS Customs and Excise Tariff Handbook, latest edition. (2) Check Schedule No. 1 for ordinary customs duty and any anti-dumping. (3) Check Schedule No. 3 / rebate items for renewable-energy or storage exemptions. (4) Verify the exact sub-heading against the vendor's commercial invoice description. (5) Note any VAT treatment separately. See [SARS Customs and Excise Tariff page](https://www.sars.gov.za/customs-and-excise/customs-and-excise-tariff/) and the USITC HTS reference for 8507.60 at [USITC HTS — 8507.60 entry](https://hts.usitc.gov/?query=8507.60). **Disclaimer.** This brief does *not* assert a duty rate as fact. The rate above is marked PENDING and must be resolved by the importer or licensed customs broker before any landed-cost commitment.

## 9. Mini certificate block

**No certificate has been issued for this brief.** The list below is a pre-qualification checklist to be reconciled to the specific offered equipment model at RFQ stage. Certificate numbers and issuer names are not asserted here — they are required from the OEM as part of the RFQ response.

- UN 38.3 transport test summary — to be issued by the OEM for the specific CATL EnerC cell variant offered. Refer to [UN Manual of Tests and Criteria, Rev. 7 (2020), Section 38.3](https://www.unece.org/fileadmin/DAM/trans/danger/publi/manual/Rev7/Manual_Rev7_E_2020.pdf) for the test framework.

- IEC 62619 (secondary lithium cells for industrial applications) — certificate number and issuer to be provided by OEM. Refer to [IEC 62619:2022 product page on IEC Webstore](https://webstore.iec.ch/publication/31377).

- UL 9540A / IEC 62933 (system-level safety test summary) — certificate number and issuer to be provided by OEM. Refer to [IEC 62933 series on IEC Webstore](https://webstore.iec.ch/publication/64192).

- ISO 9001 / ISO 14001 (manufacturing-site certificates) — certificate number, scope, and issuer to be provided by OEM.

- South Africa LOA / NRCS approval pathway — flagged for regulatory review at RFQ stage; not pre-asserted here.

## 10. Risk and assumption log

- Duty rate **PENDING**: must be resolved from SARS before commitment — see Section 8.

- Eskom Megaflex tariff schedule varies by station, voltage, and Time-of-Use band — confirm per site against the Eskom Megaflex PDF.

- Cycle life assumed compatible with 1 cycle/day at 0.90 DoD over 10 years — vendor warranty must match the OEM warranty terms for the specific CATL EnerC cabinet configuration.

- FX ZAR/USD held at 18.5 — re-run at RFQ stage.

- Augmentation set to 0% — add separate sensitivity if nameplate expansion is expected.

- Second-life residual 10% is illustrative — depends on cell health and second-life buyer; IRENA end-of-life discussion referenced.

- Round-trip efficiency 0.90, degradation 2.0%/yr, and charge cost 0.15 USD/kWh are bounded model defaults (rows 4, 5, 18 in the inputs table) — not sourced facts.

## 11. Request an RFQ

For a binding landed-cost quote and a finalised duty figure, request the tradvolt RFQ pack (technical spec, BoQ, Incoterms EXW/CIF Durban, warranty, and O&M).

[Request RFQ — Rail Station ESS 800 kWh, ZA](/rfq/?use=rail-station-ess-800kwh-za-r9&amp;size=800kWh)

## 12. Download datasheet

For the vendor-neutral datasheet bundle covering the inputs above, the worked TCO method, and the HS code lookup worksheet:

[Download datasheet (PDF) — Rail Station ESS 800 kWh, ZA](https://tradvolt.com/datasheets/rail-station-ess-800kwh-za-r9.pdf)

## 13. Citations (numbered)

1. BloombergNEF, *2024 Battery Price Survey* — C&I LFP pack + PCS, ex-works median. URL: [https://about.bnef.com/blog/lithium-ion-battery-pack-prices-see-largest-drop-since-2017-falling-to-115-per-kilowatt-hour-bnef/](https://about.bnef.com/blog/lithium-ion-battery-pack-prices-see-largest-drop-since-2017-falling-to-115-per-kilowatt-hour-bnef/)

2. IRENA, *Renewable Power Generation Costs in 2023* — BoS adder, O&M band, and end-of-life residual discussion. URL: [https://www.irena.org/Publications/2024/Sep/Renewable-power-generation-costs-in-2023](https://www.irena.org/Publications/2024/Sep/Renewable-power-generation-costs-in-2023)

3. Drewry, *Supply Chain Advisors — Project Cargo Benchmarking* — China→Durban breakbulk benchmark band. URL: [https://www.drewry.co.uk/supply-chain-advisors/project-cargo/](https://www.drewry.co.uk/supply-chain-advisors/project-cargo/)

4. SARS, *Customs and Excise Tariff Handbook* — Schedule No. 1 ordinary duty and Schedule No. 3 rebate items. URL: [https://www.sars.gov.za/customs-and-excise/customs-and-excise-tariff/](https://www.sars.gov.za/customs-and-excise/customs-and-excise-tariff/)

5. USITC, *Harmonized Tariff Schedule* — 8507.60 (lithium-ion accumulators). URL: [https://hts.usitc.gov/?query=8507.60](https://hts.usitc.gov/?query=8507.60)

6. Eskom, *Megaflex Time-of-Use tariff schedule* — displaced-cost reference. URL: [https://www.eskom.co.za/distribution/wp-content/uploads/2024/04/Megaflex-Rates-2024.pdf](https://www.eskom.co.za/distribution/wp-content/uploads/2024/04/Megaflex-Rates-2024.pdf)

7. Eskom, *Grid emission factor publication* — annual average ZA grid EF. URL: [https://www.eskom.co.za/wp-content/uploads/2023/10/CO2-emission-factor.pdf](https://www.eskom.co.za/wp-content/uploads/2023/10/CO2-emission-factor.pdf)

8. CATL, *EnerC product page* — battery cabinet specification and operating window. URL: [https://www.catl.com/en/products/enerc/](https://www.catl.com/en/products/enerc/)

9. Sungrow, *ST500CP-1250UD-MV utility-scale ESS product page*. URL: [https://www.sungrowpower.com/utility-scale-ess-detail/141](https://www.sungrowpower.com/utility-scale-ess-detail/141)

10. UN, *Manual of Tests and Criteria*, Rev. 7 (2020), Section 38.3. URL: [https://www.unece.org/fileadmin/DAM/trans/danger/publi/manual/Rev7/Manual_Rev7_E_2020.pdf](https://www.unece.org/fileadmin/DAM/trans/danger/publi/manual/Rev7/Manual_Rev7_E_2020.pdf)

11. IEC, *IEC 62619:2022* — secondary lithium cells for industrial applications. URL: [https://webstore.iec.ch/publication/31377](https://webstore.iec.ch/publication/31377)

12. IEC, *IEC 62933 series* — electrical energy storage (EES) systems. URL: [https://webstore.iec.ch/publication/64192](https://webstore.iec.ch/publication/64192)