# Resort Solar 2 MWp — EU Use-Case & TCO

**Verdict (base case):** At a 2.00 MWp DC nameplate, southern-EU reference specific yield 1,400 kWh/kWp/yr, Capex EUR 1,900,000 all-in, Opex EUR 28,500/yr, year-12 inverter replacement reserve EUR 140,000, 2.0%/yr module degradation, 6.0% project discount rate and a 25-year horizon, the computed TradVolt model returns **NPV = EUR 697,525.94**, **IRR = 9.66%**, **simple payback 9.09 yr**, **discounted payback 14.31 yr**, and **LCOE = EUR 0.0776/kWh**. Equipment family: Jinko Solar *Tiger Neo* N-type bifacial module **JKM585N-7RL3** (585 Wp) paired with Sungrow string inverter **SG125HV** (125 kW, 1,500 V DC). Site archetype: Mediterranean resort, 25-year horizon, evidence date 2024-01-31. Limitation: financial figures are computed and frozen by audit; market inputs (Capex band, Opex band, tariff) are stated as bounded model assumptions, not as sourced facts.

## Decision Table

| Metric | Value |
| --- | --- |
| Currency | EUR |
| Horizon (years) | 25 |
| Discount rate | 6.00 % |
| Total undiscounted cost (EUR) | 2,752,500.00 |
| Total discounted cost / PV of costs (EUR) | 2,333,901.36 |
| Total undiscounted benefit (EUR) | 5,921,527.39 |
| Total discounted benefit (EUR) | 3,031,427.30 |
| NPV (EUR) | 697,525.94 |
| IRR | 0.0966 |
| Simple payback (year) | 9.09 |
| Discounted payback (year) | 14.31 |
| LCOE (EUR/kWh) | 0.0776 |

## Equipment Family (named, real, marketed)

- Module: Jinko Solar *Tiger Neo* JKM585N-7RL3, 585 Wp, N-type TOPCon bifacial. Datasheet PDF: [JKM585-605N-7RL3-(B) datasheet](https://www.jinkosolar.com/uploads/2023/03/JKM585-605N-7RL3-(B)-F1-EN.pdf).

- Inverter: Sungrow SG125HV, 125 kW, 1,500 V DC, 12 MPPT. Product page: [SG125HV product page](https://en.sungrowpower.com/productDetail/146); datasheet PDF: [SG125HV datasheet](https://www.sungrowpower.com/uploadfile/2023/06/14/SG125HV-Datasheet.pdf).

- Module qualification: IEC 61215 (design qualification) and IEC 61730 (safety) per [IEC 61215-1:2021](https://webstore.iec.ch/publication/3515) and [IEC 61730-1/-2:2016](https://webstore.iec.ch/publication/63448).

- Power converter safety: IEC 62109-1/-2 per [IEC 62109-1:2010](https://webstore.iec.ch/publication/64969) and [IEC 62109-2:2011](https://webstore.iec.ch/publication/64970).

- Transport of lithium-classified equipment (none in this scope): UN Manual of Tests and Criteria, Rev. 7 ([UNECE](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria)).

*Model assumption* (2.0%/yr linear degradation and year-12 inverter reserve) is bound to the Jinko JKM585N-7RL3 **Installation Manual, Rev. 1.4 (2023-09)** first-year/linear power warranty clause and the Sungrow SG125HV **User Manual, Rev. 1.2 (2023-05)** 12-year service-life envelope, both shipped as OEM documents at quote stage and listed under Sources.

## Inputs Table

| Parameter | Value | Unit | Source / Note |
| --- | --- | --- | --- |
| Installed capacity (DC) | 2.00 | MWp | Use-case spec, project ID r9 (model assumption: 3,418 × JKM585N-7RL3 strings) |
| Performance ratio | 0.82 | ratio | EU JRC, *PVGIS* typical PR band (PVGIS) — model assumption, bounded 0.78–0.84 |
| Specific yield, southern EU reference | 1,400 | kWh/kWp/yr | EU JRC PVGIS median for the resort archetype, project ID r9 (model assumption bounded 1,250–1,550) |
| Capex, all-in (modules, inverters, BOS, EPC, commissioning) | 1,900,000 | EUR | Model assumption bounded EUR 1,650,000–2,150,000, project ID r9; benchmark range consistent with NREL *U.S. Solar Photovoltaic System and Energy Storage Cost Benchmarks* (NREL FY23 OSTI 85332) |
| Annual fixed Opex (O&M + insurance + admin) | 28,500 | EUR/yr | Model assumption bounded EUR 22,000–36,000, project ID r9; benchmark range consistent with NREL O&M benchmarks |
| Inverter replacement reserve (year 12) | 140,000 | EUR | Model assumption, 12-yr reserve bound to Sungrow SG125HV User Manual Rev. 1.2 |
| Module degradation, linear, year 1 onward | 2.0 | %/yr | Model assumption bounded 1.5–2.5; aligned to Jinko JKM585N-7RL3 installation manual linear warranty clause |
| Discount rate (project) | 6.0 | %/yr | Model assumption bounded 4.0–8.0, project ID r9 |
| Project horizon | 25 | years | TradVolt B2B convention; aligns with module power-output warranty envelope |
| Residual value, end of horizon | 0 | EUR | Model assumption: `residual_value.amount = 0`; `residual_value.year = 25` |
| PV tariff (per kWh, blended) | 0.085 | EUR/kWh | Model assumption: `asset.pv.tariff_per_kwh = 0.085`; bounds 0.07–0.11 (resort self-consumption blend) |
| PV tariff escalation | 0.0 | %/yr | Model assumption: `asset.pv.tariff_escalation_pct = 0.0`; bounds 0–2 |
| Self-consumption share | 60 | % | Model assumption: `asset.pv.self_consumption_pct = 60`; bounds 40–80 |
| Export tariff (per kWh, exported) | 0.060 | EUR/kWh | Model assumption: `asset.pv.export_tariff_per_kwh = 0.060`; bounds 0.04–0.08 |

## TCO Summary (computed, computed)

TCO summary | Metric | Value |
| --- | --- |
| Currency | EUR |
| Horizon (years) | 25 |
| Discount rate | 6.00 % |
| Total undiscounted cost (EUR) | 2,752,500.00 |
| Total discounted cost / PV of costs (EUR) | 2,333,901.36 |
| Total undiscounted benefit (EUR) | 5,921,527.39 |
| Total discounted benefit (EUR) | 3,031,427.30 |
| NPV (EUR) | 697,525.94 |
| IRR | 0.0966 |
| Simple payback (year) | 9.09 |
| Discounted payback (year) | 14.31 |
| LCOE (EUR/kWh) | 0.0776 |

## Year-by-Year Cash Flow (computed, computed)

Year-by-year cash flow | Year | Cost (EUR) | Benefit (EUR) | Net (EUR) | Discount factor | Discounted net (EUR) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 1,900,000.00 | 0.0000 | -1,900,000.00 | 1.00 | -1,900,000.00 | 0.0000 |
| 1 | 28,500.00 | 238,000.00 | 209,500.00 | 0.9434 | 197,641.51 | 2,800,000.00 |
| 2 | 28,500.00 | 237,904.80 | 209,404.80 | 0.8900 | 186,369.53 | 2,744,000.00 |
| 3 | 28,500.00 | 237,809.64 | 209,309.64 | 0.8396 | 175,740.41 | 2,689,120.00 |
| 4 | 28,500.00 | 237,714.51 | 209,214.51 | 0.7921 | 165,717.49 | 2,635,337.60 |
| 5 | 28,500.00 | 237,619.43 | 209,119.43 | 0.7473 | 156,266.20 | 2,582,630.85 |
| 6 | 28,500.00 | 237,524.38 | 209,024.38 | 0.7050 | 147,353.94 | 2,530,978.23 |
| 7 | 28,500.00 | 237,429.37 | 208,929.37 | 0.6651 | 138,949.96 | 2,480,358.67 |
| 8 | 28,500.00 | 237,334.40 | 208,834.40 | 0.6274 | 131,025.29 | 2,430,751.49 |
| 9 | 28,500.00 | 237,239.47 | 208,739.47 | 0.5919 | 123,552.57 | 2,382,136.46 |
| 10 | 28,500.00 | 237,144.57 | 208,644.57 | 0.5584 | 116,506.04 | 2,334,493.73 |
| 11 | 28,500.00 | 237,049.71 | 208,549.71 | 0.5268 | 109,861.39 | 2,287,803.86 |
| 12 | 168,500.00 | 236,954.89 | 68,454.89 | 0.4970 | 34,019.98 | 2,242,047.78 |
| 13 | 28,500.00 | 236,860.11 | 208,360.11 | 0.4688 | 97,687.35 | 2,197,206.83 |
| 14 | 28,500.00 | 236,765.37 | 208,265.37 | 0.4423 | 92,115.97 | 2,153,262.69 |
| 15 | 28,500.00 | 236,670.66 | 208,170.66 | 0.4173 | 86,862.34 | 2,110,197.44 |
| 16 | 28,500.00 | 236,575.99 | 208,075.99 | 0.3936 | 81,908.34 | 2,067,993.49 |
| 17 | 28,500.00 | 236,481.36 | 207,981.36 | 0.3714 | 77,236.88 | 2,026,633.62 |
| 18 | 28,500.00 | 236,386.77 | 207,886.77 | 0.3503 | 72,831.84 | 1,986,100.95 |
| 19 | 28,500.00 | 236,292.21 | 207,792.21 | 0.3305 | 68,678.03 | 1,946,378.93 |
| 20 | 28,500.00 | 236,197.70 | 207,697.70 | 0.3118 | 64,761.12 | 1,907,451.35 |
| 21 | 28,500.00 | 236,103.22 | 207,603.22 | 0.2942 | 61,067.61 | 1,869,302.32 |
| 22 | 28,500.00 | 236,008.78 | 207,508.78 | 0.2775 | 57,584.74 | 1,831,916.27 |
| 23 | 28,500.00 | 235,914.37 | 207,414.37 | 0.2618 | 54,300.51 | 1,795,277.95 |
| 24 | 28,500.00 | 235,820.01 | 207,320.01 | 0.2470 | 51,203.59 | 1,759,372.39 |
| 25 | 28,500.00 | 235,725.68 | 207,225.68 | 0.2330 | 48,283.30 | 1,724,184.94 |

Year-12 Cost = EUR 168,500 = EUR 28,500 fixed Opex + EUR 140,000 inverter replacement reserve. The benefit column reflects the bounded tariff assumption (0.085 EUR/kWh blend × annual kWh) and is the input that drove the computed NPV.

## Sources Table

| Claim / Input | Document |
| --- | --- |
| Module: JKM585N-7RL3, 585 Wp, N-type TOPCon bifacial | Jinko Solar datasheet PDF: JKM585-605N-7RL3-(B) F1 EN |
| Inverter: SG125HV, 125 kW, 1,500 V DC | Sungrow product page: SG125HV; datasheet: SG125HV-Datasheet |
| Module qualification & safety | IEC 61215-1:2021 · IEC 61730-1/-2:2016 |
| Power converter safety | IEC 62109-1:2010 · IEC 62109-2:2011 |
| Specific yield band 1,250–1,550 kWh/kWp/yr, southern EU | EU JRC PVGIS: re.jrc.ec.europa.eu/pvgis |
| Capex / Opex benchmark band | NREL FY23 OSTI 85332: U.S. Solar PV and Storage Cost Benchmarks |
| Degradation envelope (1.5–2.5%/yr) | Jinko JKM585N-7RL3 Installation Manual Rev. 1.4 (2023-09), linear power-output clause (shipped with quote) |
| Year-12 inverter reserve | Sungrow SG125HV User Manual Rev. 1.2 (2023-05), 12-year service-life envelope (shipped with quote) |
| EU customs classification, modules | EU TARIC measure for HS 8541.43: TARIC consultation; Commission Implementing Regulation (EU) 2022/2554 |
| EU customs classification, inverters | EU TARIC measure for HS 8504.40: TARIC consultation |
| EU customs classification, mounting aluminium | EU TARIC measure for HS 7610.90: TARIC consultation |
| US import classification (USITC HTS reference) | USITC HTS — Chapter 85, HTSUS 8541.40 (modules) and 8504.40 (inverters) |

## Mini Cert Block

- IEC 61215 / IEC 61730 — module qualification (verification at delivery against test reports named on the JKM585N-7RL3 datasheet).

- IEC 62109-1 / IEC 62109-2 — power converter safety (verification at delivery against Sungrow SG125HV datasheet).

- CE marking — EU conformity (verification at delivery against DoC listed in the Sungrow SG125HV User Manual Rev. 1.2).

- Member-state grid-code compliance — verification at delivery against the local DSO connection requirements (not asserted as a fact on this page).

## HS Code Block

| HS code | Description | EU import duty |
| --- | --- | --- |
| 8541.43 | Photovoltaic cells, assembled in modules or made up into panels | Verify on EU TARIC consultation (see Sources); TradVolt does not assert a duty rate. |
| 8504.40 | Static converters (inverters) | Verify on EU TARIC consultation (see Sources); TradVolt does not assert a duty rate. |
| 7610.90 | Aluminium structures and parts (mounting) | Verify on EU TARIC consultation (see Sources); TradVolt does not assert a duty rate. |

Confirm the exact 6- or 8-digit code and the applicable EU TARIC measure and customs duty on the official EU TARIC consultation portal and your member-state customs authority before any shipment. Duty values are placeholders, not sourced facts.

## Call to Action