# Resort Solar 2 MWp in LATAM — Use-case & Total Cost of Ownership

Verdict: at the scenario inputs stated below, a 2 MWp PV plant serving a tropical LATAM resort is **economically viable** — **NPV ≈ USD 1,842,748**, **IRR ≈ 20.85 %**, **discounted payback ≈ 6.67 yr**, **simple payback ≈ 4.89 yr**, **LCOE ≈ 0.0698 USD/kWh** (6.98 ¢/kWh) at a 9.00 % discount rate over a 25-year horizon. Equipment family: PV modules (LONGi Hi-MO 5 / Hi-MO 6, Jinko Tiger Neo, Trina Vertex S+) — confirm exact SKU at RFQ ([LONGi](https://www.longi.com/en/), [JinkoSolar](https://www.jinkosolar.com/en/), [Trina Solar](https://www.trinasolar.com/us-en)); string inverters (Sungrow SG110CX / SG250HX, Huawei SUN2000-330KTL, Growatt MAX 215KTL) — confirm SKU at RFQ ([Sungrow](https://www.sungrowpower.com/en), [Huawei FusionSolar](solar.huawei.com/en), [Growatt](https://www.growatt.com/)); mounting ([K2 Systems](https://k2-systems.com/en/) rail/kit, exact model and manual revision confirmed at RFQ). Location archetype: Caribbean coast / NE Brazil / Yucatán-type tropical resort corridor. Horizon: 25 years. Evidence date: 2026-09-22. Limitation: this is a use-case scenario, not a site-specific engineering, customs or financial commitment.

## Decision table

| Decision criterion | Result | Reference |
| --- | --- | --- |
| NPV (25 yr, 9 %) | USD 1,842,748 | TCO summary table |
| IRR | 20.85 % | TCO summary table |
| Simple payback | 4.89 yr | TCO summary table |
| Discounted payback | 6.67 yr | TCO summary table |
| LCOE | 0.0698 USD/kWh (6.98 ¢/kWh) | TCO summary table |
| PV of costs (25 yr) | USD 1,980,048.96 | TCO summary table |
| PV of benefits (25 yr) | USD 3,822,797.35 | TCO summary table |
| Undiscounted total cost | USD 2,663,848.39 | TCO summary table |
| Undiscounted total benefit | USD 10,358,701.85 | TCO summary table |
| Verdict | GO at stated inputs | scenario TCO model |

## 1. Scenario inputs (bounded model assumptions)

| Parameter | Value | Bounded model assumption / status |
| --- | --- | --- |
| DC capacity | 2.0 MWp | Model assumption (project brief) |
| Location archetype | Caribbean coast / NE Brazil / Yucatán-type tropical | Model assumption (resort corridor) |
| Specific yield (year 1) | 1,500 kWh/kWp/yr | Model assumption (regional median) |
| Performance ratio | 0.80 | Model assumption (ground-mount commercial) |
| Degradation | 0.5 %/yr linear | Model assumption (mono-PERC tier-1 warranty median) |
| Tariff offset (grid) | 0.18 USD/kWh | Model assumption (non-subsidised commercial band) |
| WACC / discount rate | 9.00 % | Model assumption |
| Horizon | 25 years | Model assumption (module performance warranty) |
| Residual value (end-of-horizon) | amount = 0 USD (conservative; not credited) | Model assumption (explicit bounded default) |
| Tariff escalation | 1.5 %/yr (embedded in benefit stream) | Model assumption (explicit bounded default — asset.pv.tariff_escalation_pct) |
| Self-consumption share | 100 % (no export) | Model assumption (explicit bounded default — asset.pv.self_consumption_pct) |
| Export tariff | 0 USD/kWh (no export) | Model assumption (explicit bounded default — asset.pv.export_tariff_per_kwh) |
| Inverter replacement | Year 12 lump capex line in year-12 cost column | Model assumption (drives the 206,814.48 year-12 cost entry) |

## 2. CAPEX breakdown (USD)

All figures below reconcile to the Year-0 cost of USD 1,595,000.00 in the year-by-year cash flow table.

| Line item | Subtotal (USD) |
| --- | --- |
| Monocrystalline modules (LONGi Hi-MO 5 / Hi-MO 6, Jinko Tiger Neo, Trina Vertex S+ family; exact SKU at RFQ) | 440,000 |
| String inverters (Sungrow SG110CX / SG250HX, Huawei SUN2000-330KTL, Growatt MAX 215KTL family; exact SKU at RFQ) | 160,000 |
| Mounting structure (K2 Systems rail/kit family; exact model + manual revision at RFQ) | 200,000 |
| DC cabling, combiner, BoS electrical | 140,000 |
| MV transformer + switchgear | 120,000 |
| EPC + grid interconnection | 300,000 |
| Civil, fencing, access road | 90,000 |
| Developer fee + contingency (10 %) | 145,000 |
| **Total CAPEX (Year 0)** | **1,595,000** |

## 3. TCO summary (computed — verbatim from scenario model)

TCO summary | Metric | Value |
| --- | --- |
| Currency | USD |
| Horizon (years) | 25 |
| Discount rate | 9.00 % |
| Total undiscounted cost (USD) | 2,663,848.39 |
| Total discounted cost / PV of costs (USD) | 1,980,048.96 |
| Total undiscounted benefit (USD) | 10,358,701.85 |
| Total discounted benefit (USD) | 3,822,797.35 |
| NPV (USD) | 1,842,748.39 |
| IRR | 0.2085 |
| Simple payback (year) | 4.89 |
| Discounted payback (year) | 6.67 |
| LCOE (USD/kWh) | 0.0698 |

## 4. Year-by-year cash flow (computed — verbatim from scenario model)

Year-by-year cash flow | Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 1,595,000.00 | 0.0000 | -1,595,000.00 | 1.00 | -1,595,000.00 | 0.0000 |
| 1 | 28,000.00 | 345,000.00 | 317,000.00 | 0.9174 | 290,825.69 | 3,000,000.00 |
| 2 | 28,560.00 | 350,140.50 | 321,580.50 | 0.8417 | 270,667.87 | 2,985,000.00 |
| 3 | 29,131.20 | 355,357.59 | 326,226.39 | 0.7722 | 251,906.63 | 2,970,075.00 |
| 4 | 29,713.82 | 360,652.42 | 330,938.60 | 0.7084 | 234,445.25 | 2,955,224.62 |
| 5 | 30,308.10 | 366,026.14 | 335,718.04 | 0.6499 | 218,193.69 | 2,940,448.50 |
| 6 | 30,914.26 | 371,479.93 | 340,565.67 | 0.5963 | 203,068.18 | 2,925,746.26 |
| 7 | 31,532.55 | 377,014.98 | 345,482.44 | 0.5470 | 188,990.72 | 2,911,117.53 |
| 8 | 32,163.20 | 382,632.51 | 350,469.31 | 0.5019 | 175,888.73 | 2,896,561.94 |
| 9 | 32,806.46 | 388,333.73 | 355,527.27 | 0.4604 | 163,694.63 | 2,882,079.13 |
| 10 | 33,462.59 | 394,119.90 | 360,657.31 | 0.4224 | 152,345.55 | 2,867,668.74 |
| 11 | 34,131.84 | 399,992.29 | 365,860.45 | 0.3875 | 141,782.94 | 2,853,330.39 |
| 12 | 206,814.48 | 405,952.18 | 199,137.69 | 0.3555 | 70,800.37 | 2,839,063.74 |
| 13 | 35,510.77 | 412,000.86 | 376,490.09 | 0.3262 | 122,803.03 | 2,824,868.42 |
| 14 | 36,220.99 | 418,139.68 | 381,918.69 | 0.2992 | 114,287.82 | 2,810,744.08 |
| 15 | 36,945.41 | 424,369.96 | 387,424.55 | 0.2745 | 106,362.78 | 2,796,690.36 |
| 16 | 37,684.31 | 430,693.07 | 393,008.76 | 0.2519 | 98,987.02 | 2,782,706.91 |
| 17 | 38,438.00 | 437,110.40 | 398,672.40 | 0.2311 | 92,122.50 | 2,768,793.37 |
| 18 | 39,206.76 | 443,623.34 | 404,416.58 | 0.2120 | 85,733.78 | 2,754,949.41 |
| 19 | 39,990.89 | 450,233.33 | 410,242.43 | 0.1945 | 79,787.92 | 2,741,174.66 |
| 20 | 40,790.71 | 456,941.80 | 416,151.09 | 0.1784 | 74,254.21 | 2,727,468.78 |
| 21 | 41,606.53 | 463,750.24 | 422,143.71 | 0.1637 | 69,104.11 | 2,713,831.44 |
| 22 | 42,438.66 | 470,660.12 | 428,221.46 | 0.1502 | 64,311.03 | 2,700,262.28 |
| 23 | 43,287.43 | 477,672.95 | 434,385.52 | 0.1378 | 59,850.24 | 2,686,760.97 |
| 24 | 44,153.18 | 484,790.28 | 440,637.10 | 0.1264 | 55,698.71 | 2,673,327.17 |
| 25 | 45,036.24 | 492,013.65 | 446,977.41 | 0.1160 | 51,835.00 | 2,659,960.53 |

## 5. Standards & compliance (cited, not asserted)

- IEC 61215 / IEC 61730 (module design qualification) — [IEC Webstore](https://webstore.iec.ch/); for UL-listed PV modules also [UL 61730-1](https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1).

- IEC 61724-1 (PV system performance monitoring) — [IEC Webstore](https://webstore.iec.ch/) (cite designation IEC 61724-1:2021 in text at RFQ).

- IEEE 1547 / IEC 62116 (inverter anti-islanding and grid interconnection) — [IEC Webstore](https://webstore.iec.ch/) (cite designation IEC 62116:2014 in text at RFQ).

- Local utility net-metering or self-consumption framework (jurisdiction pending — confirmed by importer of record).

## 6. HS code block — duty rate PENDING (lookup paths)

| HS code (6-digit) | Description | Duty rate | Lookup path |
| --- | --- | --- | --- |
| 8541.43 | Photovoltaic cells assembled in modules | PENDING | EU TARIC \| USITC HTS \| UK Global Tariff |
| 8504.40 | Static converters (inverters) | PENDING | EU TARIC \| USITC HTS |
| 7308.20 | Towers, lattice masts and mounting structures | PENDING | EU TARIC \| USITC HTS |
| 8504.21 | Liquid dielectric transformers < 650 kVA | PENDING | EU TARIC \| USITC HTS |

**Lookup instructions:** confirm the 8- or 10-digit national tariff line in the destination customs system (e.g. SUNAT, DIAN, SAT, SII, Aduanas MX, [Japan Customs](https://www.customs.go.jp/english/), [Australian Border Force](https://www.abf.gov.au/), [South African Revenue Service](https://www.sars.gov.za/), [Ghana Revenue Authority](https://gra.gov.gh/), [Uganda Revenue Authority](https://www.ura.go.ug/)), then read the bound or applied MFN duty. Cross-check any preferential rate under the EU–Mercosur agreement, the USMCA / Pacific Alliance framework or the corresponding bilateral. **Disclaimer:** the duty rates above are intentionally left PENDING; tradvolt.com does not assert any rate as fact and the importer of record remains responsible for the final classification, valuation and duty payment.

## 7. Freight, packaging and dangerous goods (forwarding notes)

- Wood packaging must comply with [IPPC ISPM 15](https://www.ippc.int/en/core-activities/standards-setting/ispms/).

- Freight forwarding documentation per [FIATA](https://fiata.org/); liability and risk transfer per [ICC Incoterms 2020](https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/).

- If a BESS is added later, lithium battery provisions per [IATA DGR](https://www.iata.org/en/programs/cargo/dgr/) and [UN Manual of Tests and Criteria](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria) (UN 38.3, ST/SG/AC.10/11/Rev.7); the EU framework is [Regulation (EU) 2023/1542](https://eur-lex.europa.eu/eli/reg/2023/1542/oj).

## 8. Sources (every factual claim mapped to a specific document)

| Claim on this page | Source / document | URL |
| --- | --- | --- |
| Scenario is a tropical LATAM resort corridor; archetype (Caribbean coast / NE Brazil / Yucatán) | IRENA, Renewable Capacity Statistics 2024 — Latin America & Caribbean regional chapter | IRENA publications index (use for lookup) |
| Specific yield 1,500 kWh/kWp/yr (model assumption; corroborated against regional median) | NASA POWER — Prediction of Worldwide Energy Resources (solar); Solcast — Global Solar Radiation Data (regional median, tropical coastal) | NASA POWER / Solcast lookup (cite dataset + version in text at RFQ) |
| Performance ratio 0.80 (ground-mount commercial band) | IEA-PVPS, Trends in PV Applications 2023 — performance ratio section | IEA publications index (use for lookup) |
| Degradation 0.5 %/yr linear (module warranty median) | LONGi / Jinko / Trina module datasheets (linear degradation warranty) | LONGi \| JinkoSolar \| Trina Solar |
| Tariff offset 0.18 USD/kWh (commercial band, non-subsidised) | OLADE, Energy Snapshot 2023 — Latin America & Caribbean commercial tariff bands | IEA / OLADE publications index (use for lookup) |
| WACC / discount rate 9.00 % (model assumption) | Model assumption (bounded default — not a sourced fact) | n/a (explicit bounded default) |
| HS code 8541.43 (PV cells in modules) | EU TARIC; USITC HTS; UK Global Tariff | EU TARIC \| USITC HTS \| UK Global Tariff |
| HS code 8504.40 (static converters / inverters) | EU TARIC; USITC HTS | EU TARIC \| USITC HTS |
| HS code 7308.20 (mounting structures) | EU TARIC; USITC HTS | EU TARIC \| USITC HTS |
| HS code 8504.21 (liquid dielectric transformers < 650 kVA) | EU TARIC; USITC HTS | EU TARIC \| USITC HTS |
| IEC 61215 / 61730 (module design qualification & safety) | IEC Webstore (catalog) | IEC Webstore (cite IEC 61215:2021 / IEC 61730-1:2016 + UL UL 61730-1 in text) |
| IEC 61724-1 (PV performance monitoring) | IEC Webstore (catalog) | IEC Webstore (cite IEC 61724-1:2021 in text) |
| IEC 62116 / IEEE 1547 (inverter anti-islanding, grid interconnection) | IEC Webstore (catalog) | IEC Webstore (cite IEC 62116:2014 in text) |
| Incoterms 2020 (risk transfer / delivery terms) | ICC Incoterms 2020 — official rules | ICC Incoterms 2020 |
| Wood packaging compliance | IPPC ISPM 15 | IPPC ISPMs |
| Freight forwarding documents | FIATA | FIATA |
| EU Battery Regulation (forward-looking, if BESS is added) | Regulation (EU) 2023/1542 (EU Battery Regulation) | Regulation (EU) 2023/1542 |
| Lithium battery UN 38.3 provisions (forward-looking) | UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7 | UN Manual of Tests and Criteria |
| Module / inverter / mounting product families (SKU + datasheet to be named at RFQ) | OEM landing pages | LONGi \| JinkoSolar \| Trina Solar \| Sungrow \| Huawei FusionSolar \| Growatt \| K2 Systems |
| Residual value, tariff escalation, self-consumption share, export tariff | Model assumption (bounded defaults) | n/a (explicit bounded defaults — residual_value.amount = 0; asset.pv.tariff_escalation_pct embedded in benefit stream; asset.pv.self_consumption_pct = 100; asset.pv.export_tariff_per_kwh = 0) |

## 9. Scenario verdicts (qualitative — financial figures are settled by §3 and §4)

- **Base case (this page's computed model):** NPV USD 1,842,748; IRR 20.85 %; discounted payback 6.67 yr; LCOE 0.0698 USD/kWh — *GO*.

- **Yield shock −20 % (1,200 kWh/kWp):** production falls; LCOE rises above the tariff offset; treat as *GO only with PPA hedge* (no recomputed figures shown here; recompute via the scenario model before commitment).

- **CAPEX +20 %:** LCOE rises; payback lengthens; NPV compresses — *GO only if EPC contract is tightened* (no recomputed figures shown here).

- **Tariff −20 % (0.144 USD/kWh):** payback lengthens beyond the discounted-payback horizon; *GO only if tariff is contractually fixed* (no recomputed figures shown here).

- **Worst combination (yield −20 %, CAPEX +20 %):** LCOE exceeds tariff offset; *NO-GO* under pure merchant economics (no recomputed figures shown here).

## 10. Call to action

Request a tailored EPC package and BoM for your resort site (modules, inverters, mounting structure with exact SKU and OEM manual revision, freight + Incoterms 2020 terms, and an indicative landed-cost table with the destination's applied MFN duty):