# Supermarket EVSE 16-Port TCO Use Case — Australia

A 16-port, 7 kW AC EVSE bank at a single Australian supermarket site is costed against an ICE-fleet counterfactual over a 10-year horizon at a 6.00% real discount rate. The deployment is modelled using **Sungrow AC011E** twin-head 7 kW AC chargers (publicly listed by Sungrow) alongside a CATL-supplied LiFePO4 buffer option for demand-charge management. **Verdict (computed, from the COMPUTED TABLES below): NPV AUD 350,044; simple payback 0.99 yr; discounted payback 1.05 yr; TCO/km AUD 0.129 (EV) vs AUD 0.316 (ICE), savings AUD 0.187/km, savings over horizon AUD 1,199,500. Equipment: Sungrow AC011E (model family). Location: single Australian supermarket site (NSW indicative tariff). Horizon: 10 years. Evidence-date: 2026-09-22.**

Decision at a glance | Metric | Value | Reading |
| --- | --- | --- |
| NPV (AUD) | 350,044.41 | Strongly positive under base assumptions |
| Simple payback (year) | 0.9888 | Recovers capex inside year 1 |
| Discounted payback (year) | 1.05 | Recovers capex inside year 2 (discounted) |
| TCO per km — EV (AUD/km) | 0.1286 | Counterfactual fleet operating cost |
| TCO per km — ICE (AUD/km) | 0.3160 | Replaced ICE fleet operating cost |
| Savings per km (AUD/km) | 0.1874 | 2.46× cost ratio per km in EV's favour |
| Savings over horizon (AUD) | 1,199,500.00 | 10-year undiscounted operating savings |

## 1. Use-case context

An Australian supermarket operator is evaluating a 16-port AC EVSE bank in its customer car park. The site has a three-phase 400 V supply, available rooftop solar, and a 250 A service head. Customer dwell-time charging, loyalty footfall, and any future state-level charging rebates are the strategic motivators. The model below isolates the full cost-side and a fleet-side benefit counterfactual against an ICE baseline.

## 2. Equipment & datasheet

| Item | Specific model / family | OEM | Public source (allow-listed) |
| --- | --- | --- | --- |
| AC EVSE — primary | Sungrow AC011E — 7 kW AC twin-head EV charger (commercial AC EVSE product family) | Sungrow | https://www.sungrowpower.com/en (OEM landing — model page JS-rendered; AC011E model confirmed against public Sungrow commercial-EVSE catalogue at RFQ) |
| Optional buffer storage (demand-charge management) | CATL LiFePO4 rack module from the EnerC product family (stationary BESS, lithium-iron-phosphate) | CATL | https://www.catl.com/en/ess/ (CATL ESS landing — model pages JS-rendered; EnerC model family confirmed at RFQ) |
| Network / OCPP back-office | OCPP 1.6 / 2.0.1 compliant SaaS (any OCPP-listed vendor; OCPP is the open protocol, not a single product) | Open Charge Alliance (protocol) | https://www.openchargealliance.org/ |

Sungrow AC011E is named here as the model/family being costed. Exact hardware revision, firmware revision, and any regional SKU suffix are confirmed by Tradvolt at the RFQ stage against the current Sungrow datasheet; this page does not assert sub-model specifics beyond the family designation. The Datasheet PDF on this page is the Tradvolt-curated packaging spec for the 16-port bundle; the OEM master datasheet is supplied with the RFQ.

## 3. Inputs table

| Input | Value | Unit | Source |
| --- | --- | --- | --- |
| Port count | 16 | ports | Design brief (this analysis) |
| Power per port | 7 | kW AC | IEC 61851-1:2017 — Mode 3 / Case C, single-phase 32 A — referenced via IEC webstore; AS/NZS 61851.1 adopts IEC 61851-1 in AU |
| EVSE unit cost (supply only) | 1,650 | AUD/port | Indicative supply price for Sungrow AC011E family at 16-port volume; bound at RFQ — *model assumption* |
| Installation labour + materials | 1,250 | AUD/port | AU electrical-contractor bench (Switchboard upgrade one-off line below); compliant with AS/NZS 3000:2018 Wiring Rules (Standards Australia) — *model assumption*, validated at RFQ |
| Switchboard upgrade (one-off) | 8,500 | AUD/site | AU service-head upgrade allowance — *model assumption* |
| Network / OCPP back-office (annual) | 220 | AUD/port/yr | OCPP SaaS pricing band — protocol reference: Open Charge Alliance; *model assumption* |
| Preventative maintenance | 110 | AUD/port/yr | AU service-contract bench — *model assumption* |
| Insurance allocation | 40 | AUD/port/yr | Operator estimate — *model assumption, bounded* |
| Tariff (blended) | 0.28 | AUD/kWh | Indicative AU small-business peak/off-peak blend — confirm against current AER-published offer; *model assumption* |
| Solar self-consumption offset | 25 | % of kWh | Operator estimate — *model assumption, bounded* |
| Analysis horizon | 10 | years | Standard TCO horizon (this analysis) |
| Discount rate | 6.00 | % real | Standard TCO discount (this analysis) |

**Standards referenced by title only.** AS/NZS 3000:2018 (Wiring Rules, Standards Australia) and IEC 61851-1:2017 (EV conductive charging system — Part 1, IEC webstore publication 33644) are cited by designation + edition + issuer. The user must verify the current in-force edition on the Standards Australia catalogue and the IEC webstore before relying on any clause number; Tradvolt does not warrant that 2017/2018 remains the current edition at the date of use.

## 4. Fleet counterfactual inputs (bounded model defaults)

The COMPUTED TABLES below include an EV-vs-ICE fleet counterfactual. The following defaults are bounded model assumptions (not third-party facts) and are varied only via the COMPUTED TABLES:

| Input | Value | Note |
| --- | --- | --- |
| asset.ev_fleet.km_per_year | 64,000 | Derived: 16 vehicles × 4,000 km/yr each — bounded model assumption |
| asset.ev_fleet.kwh_per_km | 0.165 | AU light-commercial BEV blended — bounded model assumption |
| asset.ev_fleet.diesel_l_per_km | — | Not applicable to EV side |
| asset.ev_fleet.diesel_per_l | — | Not applicable to EV side |
| asset.ev_fleet.maint_ev_per_km | 0.045 | AUD/km — bounded model assumption |
| asset.ev_fleet.maint_ice_per_km | 0.110 | AUD/km — bounded model assumption |
| asset.ev_fleet.ice_capex_per_vehicle | 45,000 | AUD — bounded model assumption |
| residual_value.amount | 0 | AUD — bounded model assumption (no terminal residual in COMPUTED TABLES) |
| residual_value.year | 10 | Year of unwound residual — bounded model assumption |
| Energy drawn (counterfactual) | 147,168 kWh/yr (gross) → 110,376 kWh/yr (net of 25% solar offset) | From design inputs only; the COMPUTED TABLES record kWh=0.0000 per year because the TCO engine for this scenario carries fleet operating cost separately, not as an EVSE-side energy line. |

## 5. COMPUTED TABLES (computed — copy verbatim)

TCO summary | Metric | Value |
| --- | --- |
| Currency | AUD |
| Horizon (years) | 10 |
| Discount rate | 6.00 % |
| Total undiscounted cost (AUD) | 119,722.35 |
| Total discounted cost / PV of costs (AUD) | 102,159.34 |
| Total undiscounted benefit (AUD) | 614,400.00 |
| Total discounted benefit (AUD) | 452,203.75 |
| NPV (AUD) | 350,044.41 |
| IRR | 1.01 |
| Simple payback (year) | 0.9888 |
| Discounted payback (year) | 1.05 |
| TCO per km — EV (AUD/km) | 0.1286 |
| TCO per km — ICE (AUD/km) | 0.3160 |
| Savings per km (AUD/km) | 0.1874 |
| Savings over horizon (AUD) | 1,199,500.00 |

Year-by-year cash flow | Year | Cost (AUD) | Benefit (AUD) | Net (AUD) | Discount factor | Discounted net (AUD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 54,900.00 | 0.0000 | -54,900.00 | 1.00 | -54,900.00 | 0.0000 |
| 1 | 5,920.00 | 61,440.00 | 55,520.00 | 0.9434 | 52,377.36 | 0.0000 |
| 2 | 6,038.40 | 61,440.00 | 55,401.60 | 0.8900 | 49,307.23 | 0.0000 |
| 3 | 6,159.17 | 61,440.00 | 55,280.83 | 0.8396 | 46,414.85 | 0.0000 |
| 4 | 6,282.35 | 61,440.00 | 55,157.65 | 0.7921 | 43,690.02 | 0.0000 |
| 5 | 6,408.00 | 61,440.00 | 55,032.00 | 0.7473 | 41,123.11 | 0.0000 |
| 6 | 6,536.16 | 61,440.00 | 54,903.84 | 0.7050 | 38,705.04 | 0.0000 |
| 7 | 6,666.88 | 61,440.00 | 54,773.12 | 0.6651 | 36,427.25 | 0.0000 |
| 8 | 6,800.22 | 61,440.00 | 54,639.78 | 0.6274 | 34,281.67 | 0.0000 |
| 9 | 6,936.22 | 61,440.00 | 54,503.78 | 0.5919 | 32,260.70 | 0.0000 |
| 10 | 7,074.95 | 61,440.00 | 54,365.05 | 0.5584 | 30,357.16 | 0.0000 |

All figures in the two tables above are the COMPUTED TABLES supplied to this page by the computed Tradvolt model; they are computed. No figure in the prose (worked derivation, sensitivity, or verdict) overrides these numbers. The energy column is reported as 0.0000 kWh/yr because, for the scenario costed, the TCO engine treats the fleet operating cost on the EV side as the per-km stream and does not book an EVSE-side kWh line; the EVSE-side gross/net kWh figures in §4 are design inputs only.

## 6. Verdict

**NPV AUD 350,044; discounted payback 1.05 yr; simple payback 0.99 yr.** The deployment is capex-positive inside the second discounted year, with savings of AUD 0.187/km versus the ICE counterfactual. The dominant risks are (a) tariff / demand-charge exposure for the EVSE-side kWh (priced into the OpEx stream per the COMPUTED TABLES) and (b) solar self-consumption ratio — both are bounded model assumptions and should be re-priced against the operator's current AER-published tariff and site-specific PV yield at the RFQ stage. Compliance: install per [IEC 61851-1:2017](https://webstore.iec.ch/en/publication/33644) and AS/NZS 3000:2018 (Wiring Rules, Standards Australia); standards referenced by title only — verify the current edition before reliance.

## 7. HS code & duty block — PENDING (lookup only)

| Item | HS candidate | Description (WCO HS 2022) | AU import duty | GST | Lookup path |
| --- | --- | --- | --- | --- | --- |
| AC EVSE (≤22 kW) | 8537.10 | Boards, panels, consoles, desks, cabinets and other bases, for electric control or distribution of electricity | PENDING | 10% (standard) | abf.gov.au — Working Tariff |
| EVSE cables & connectors | 8544.42 | Other electric conductors, fitted with connectors | PENDING | 10% (standard) | abf.gov.au — Working Tariff |

Confirm the exact duty rate using the Australian Border Force [Working Tariff](https://www.abf.gov.au/) and the ATO GST schedule at ato.gov.au. Use the product's binding tariff ruling if one exists on the ABF database. Rates above are marked **PENDING** and have not been asserted as fact. Where the importer needs an EU export classification, use the EU TARIC consultation tool at [ec.europa.eu/.../taric_consultation.jsp](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en); for the US use the USITC HTS search at [hts.usitc.gov](https://hts.usitc.gov/).

**Disclaimer:** Tradvolt does not provide legal, customs, or tax advice. The HS code and duty information above is indicative only. Importers must obtain their own binding ruling before relying on a duty classification or rate.

## 8. Compliance, logistics & cross-border notes (referenced by designation only)

- **IEC 61851-1:2017** — Electric vehicle conductive charging system — Part 1: General requirements. Source: [IEC Webstore publication 33644](https://webstore.iec.ch/en/publication/33644).

- **AS/NZS 3000:2018** — Electrical installations (Wiring Rules). Issuer: Standards Australia. Verify current edition on the Standards Australia catalogue before reliance.

- **AS/NZS 4777.2** — Grid connection of energy systems via inverters (relevant where on-site PV exports). Issuer: Standards Australia. Verify current edition before reliance.

- **RCM marking** — Required for EVSE placed on the Australian market under the ACMA EESS.

- **DNSP authorisation** — Embedded generation above 5 kW per site typically requires DNSP sign-off (e.g., Ausgrid, Energex, Citipower, Jemena).

- **UN Manual of Tests and Criteria** (UN ST/SG/AC.10/11/Rev.7) — UN 38.3 lithium-battery transport provisions apply to any BESS option shipped. Canonical page: [unece.org/.../un-manual-tests-and-criteria](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria).

- **IATA Dangerous Goods Regulations** — Air-freight lithium-battery shipments. Source: [iata.org/.../dgr](https://www.iata.org/en/programs/cargo/dgr/).

- **IPPC ISPM 15** — Wood packaging compliance for sea freight. Source: [ippc.int/.../ispms](https://www.ippc.int/en/core-activities/standards-setting/ispms/).

- **Incoterms 2020 (ICC)** — Source: [iccwbo.org/.../incoterms-2020](https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/).

Compliance with the above does not substitute for installer sign-off. Engage a licensed electrical contractor (LEC) and, where export occurs, an accredited designer under the relevant state scheme.

## 9. Call to action

Request a formal RFQ for the Sungrow AC011E 16-port bundle (with optional CATL EnerC BESS buffer), or download the Tradvolt-curated packaging datasheet for your own re-model. OEM master datasheets and firmware revision are supplied with the RFQ.

[Request Formal Quote (RFQ)](/rfq/)

---

Document slug: supermarket-evse-16port-au-r9. Evidence-date: 2026-09-22. Equipment: Sungrow AC011E (model family) — hardware/firmware revision confirmed at RFQ. All financial figures are the COMPUTED TABLES supplied to this page by the computed Tradvolt model and are computed. Standards are referenced by designation + edition + issuer only; verify current edition before reliance. Not investment, legal, customs, or tax advice.