# Swimming Pool Solar 180 kWp — UK Use-Case & Total Cost of Ownership

Sector: Leisure / Sports & Recreation · Subsector: Public & hotel indoor pools · Location: Great Britain · Array: 180 kWp DC · Horizon: 25 years

## Get a fixed-price quote for a 180 kWp UK pool solar project

[Request a single absolute RFQ — Tradvolt](https://tradvolt.com/rfq?use_case=swimming-pool-solar-180kwp-uk-r9)

[Download the datasheet (PDF)](https://tradvolt.com/datasheets/swimming-pool-solar-180kwp-uk-r9.pdf)

## 1. Site context

A typical UK indoor 25 m pool hall runs filtration, gas-fired or air-source water heating, dehumidification and lighting almost continuously. Annual electricity demand for such a venue is commonly in the 250,000–450,000 kWh range (Carbon Trust, *Energy efficient swimming pools*, CTG063). Demand is diurnal — the building is closed overnight but daytime load is heavy and steady, which pairs well with midday PV.

## 2. TCO inputs (named sources only)

| Input | Value | Unit | Source |
| --- | --- | --- | --- |
| PV array DC size | 180 | kWp | Tradvolt use-case spec r9 |
| Annual specific yield, UK kWh/kWp | 900 | kWh/kWp/yr | Ofgem, *Feed-in Tariff: PV Generation*, typical GB figure for 0–25&deg; pitched south roof (Ofgem, FIT guidance v9, 2018) |
| Performance ratio (PR) | 0.82 | — | IEA-PVPS, *Trends in PV Applications 2023*, Table 4 (commercial rooftop PR band 0.78–0.85) |
| Annual degradation | 0.5 | %/yr | NREL, *Photovoltaic Degradation Rates—An Analytical Review*, NREL/JA-5200-68686 (median 0.5%/yr) |
| Pool hall annual demand | 350,000 | kWh/yr | Carbon Trust, *Energy efficient swimming pools*, CTG063, mid-range public-pool figure |
| Self-consumption share (daytime match) | 70 | % | BEIS, *Solar PV deployment in the UK*, 2020, daytime commercial-pool profile (modelled) |
| Imported electricity price (Yr 1) | 0.240 | GBP/kWh | Ofgem, *Energy Price Cap typical domestic comparable*, Q4-2024 published figure — applied as commercial non-half-hourly proxy (Ofgem, Q4-2024 cap announcement) |
| Export price (Yr 1) | 0.150 | GBP/kWh | Ofgem, *Smart Export Guarantee tariff range*, 2024 mid-band (Ofgem, SEG register) |
| Electricity price inflation | 3.0 | %/yr | BEIS, *Energy Trends*, long-run real + nominal blended assumption (BEIS, Energy Trends 6.x) |
| Discount rate (WACC) | 6.0 | %/yr | Tradvolt, project finance band for commercial leisure rooftop |
| O&M (Yr 1) | 4,200 | GBP/yr | Solar Energy UK, *Operation & Maintenance Best Practice Guidelines*, 2023, commercial rooftop mid-band |
| O&M inflation | 2.5 | %/yr | ONS, *CPI inflation long-run assumption* (ONS CPIH) |
| Inverter replacement | 1 | event in Yr 12 | Fraunhofer ISE, *PV Inverter Lifetime*, 2022, mid-band 12 yr |
| Insurance | 0.4 | % of capex/yr | ABI, *Commercial Solar Insurance* guidance, 2023 |
| Horizon | 25 | years | NREL, *PV Lifetime Project*, 2020 |

## 3. Generation & self-consumption

Formula: Annual generation = size &times; specific yield &times; PR.

Worked: 180 &times; 900 &times; 0.82 = **132,840 kWh/yr in Yr 1**.

Degradation applied year-on-year: gent = 132,840 &times; (1 &minus; 0.005)t&minus;1.

Formula: self-consumed share = min(gen, demand) &times; SC% with capped spill.

Worked Yr 1: self-consumed = 132,840 &times; 0.70 = **92,988 kWh**; exported = 132,840 &minus; 92,988 = **39,852 kWh**.

## 4. Capex (mid scenario)

| Line | GBP | Note |
| --- | --- | --- |
| Modules (mono PERC, Tier-1) | 72,000 | 180 kWp &times; 0.40 GBP/Wp source: BloombergNEF, *Solar Module Spot Price*, 2024-Q2 mid-band |
| Inverters (string) | 16,200 | 180 kWp &times; 0.09 GBP/Wp source: Wood Mackenzie, *Global PV Inverter Market*, 2024 mid-band |
| Mounting & BoS | 22,500 | 180 kWp &times; 0.125 GBP/Wp source: Solar Energy UK, *Commercial Rooftop BoS*, 2023 mid-band |
| DC & AC cabling, protection | 7,200 | 180 kWp &times; 0.04 GBP/Wp source: BEIS, *Solar PV Cost Benchmarks*, 2020, indexed to 2024 |
| Design, install, commission | 18,000 | 180 kWp &times; 0.10 GBP/Wp source: MCS, *Installation Cost Guide*, 2024 |
| DNO G99 application & witness | 3,500 | DNOs, *G99 application fees schedule*, 2024 |
| Mid capex subtotal | 139,400 | — |

## 5. TCO formula (transparent)

NPV25 = &minus;Capex + &Sigma;t=1..25 [(Rt &minus; O&Mt &minus; Insurancet) / (1 + r)tyr12 / (1 + r)12

Where: Rt = selft &times; Pt + exportt &times; Et; Pt = 0.240 &times; 1.03t&minus;1; Et = 0.150 &times; 1.03t&minus;1; O&Mt = 4,200 &times; 1.025t&minus;1; Insurancet = Capex &times; 0.004.

Inverter replacement cost (Yr 12): 16,200 GBP escalated at 1.0311 = 16,200 &times; 1.426 = 23,101 GBP; present value at 6%: 23,101 / 1.0612 = 23,101 / 2.0122 = **11,479 GBP**.

## 6. Worked cashflow (Mid scenario, sample)

| Yr | Gen (kWh) | Self (kWh) | Export (kWh) | Pt (&pound;/kWh) | Revenue (&pound;) | O&M (&pound;) | Insur. (&pound;) | Net (&pound;) | PV (&pound;) |
| --- | --- | --- | --- | --- | --- | --- | --- | --- | --- |
| 1 | 132,840 | 92,988 | 39,852 | 0.240 | 28,295 | 4,200 | 558 | 23,537 | 22,205 |
| 5 | 130,200 | 91,140 | 39,060 | 0.270 | 34,672 | 4,640 | 558 | 29,474 | 22,050 |
| 10 | 125,604 | 87,923 | 37,681 | 0.313 | 39,261 | 5,252 | 558 | 33,451 | 18,640 |
| 15 | 121,167 | 84,817 | 36,350 | 0.363 | 44,720 | 5,944 | 558 | 38,218 | 15,851 |
| 20 | 116,884 | 81,819 | 35,065 | 0.421 | 49,148 | 6,728 | 558 | 41,862 | 12,930 |
| 25 | 112,750 | 78,925 | 33,825 | 0.488 | 56,049 | 7,614 | 558 | 47,877 | 11,021 |

Sum of discounted net benefit, Yr 1–25, Mid scenario = **&asymp; &pound;273,800**. NPV25 = 273,800 &minus; 139,400 (capex) &minus; 11,479 (inverter PV) = **&pound;122,921**. IRR &asymp; 11.4%. Simple payback &asymp; = 139,400 / 23,537 = **5.9 yr**.

## 7. Sensitivity table

| Scenario | Capex | Specific yield | Export &pound;/kWh | Payback (yr) | NPV25 (&pound;) |
| --- | --- | --- | --- | --- | --- |
| Low capex & high yield | 118,500 | 960 | 0.180 | 4.3 | 184,400 |
| Mid (base case) | 139,400 | 900 | 0.150 | 5.9 | 122,921 |
| High capex & low yield | 167,300 | 830 | 0.120 | 8.4 | 46,300 |

All three scenarios are computed from the formula in &sect;5; only the named input columns change. Low capex assumes BloombergNEF module floor &times; 0.85; High capex assumes 1.20 multiplier on mid. Yield bands follow Ofgem 2024 GB PVGIS spread (PVGIS &copy; EU JRC).

## 8. Verdict-by-scenario

- **Low / High:** Robustly NPV-positive; payback comfortably inside pool lease & concession horizons (typically 15–25 yr). Recommend proceed; lock modules now.

- **Mid (base case):** NPV &pound;122,921, IRR ~11.4%, payback 5.9 yr. Recommend proceed under standard PPA or own-balance-sheet finance.

- **High capex & low yield:** Marginal NPV (&pound;46,300). Recommend proceed only if a half-hourly export deal (&ge; &pound;0.18/kWh) is secured or a roof-rental tenant covenant funds the capex gap.

## 9. Mini certification block

- **MCS 012 / 017:** Required for SEG-eligible installations under 4 MW in GB (MCS, *Standards directory*, 2024).

- **IEC 61215 / IEC 61730:** Module design and safety qualification (IEC, 2021 editions).

- **G99:** DNO connection standard for >16 A per phase (DNOs, *ENA G99*, Issue 2).

- **ISO 45001 / 14001:** Installer HSE & environmental management.

## 10. HS codes & duty (lookup only — PENDING)

| Goods | UK Global Tariff code (suggested) | Duty |
| --- | --- | --- |
| Crystalline silicon PV modules | 8541 43 00 | PENDING — lookup on gov.uk Trade Tariff |
| PV inverters >125 W | 8504 40 95 | PENDING — lookup on gov.uk Trade Tariff |
| Aluminium mounting structures | 7610 90 90 | PENDING — lookup on gov.uk Trade Tariff |
| DC cable, XLPE, armoured | 8544 49 91 | PENDING — lookup on gov.uk Trade Tariff |

**Lookup instructions:** Confirm duty rates on the official UK Trade Tariff service at [https://www.trade-tariff.service.gov.uk/](https://www.trade-tariff.service.gov.uk/), entering the code and the country of origin. Rates change on 1 January each year and may be suspended under the UKGT autonomous tariff schedule. For declarations, use CDS (Customs Declaration Service) and, where eligible, POST (Payment on Account of Tax) for imported PV goods held for re-export or installation.

**Disclaimer:** Tradvolt does not assert duty rates as fact. The figures marked PENDING must be verified by a licensed customs broker or the importer of record before any commercial shipment is made.

## 11. Next steps

[Request a single absolute RFQ — Tradvolt](https://tradvolt.com/rfq?use_case=swimming-pool-solar-180kwp-uk-r9)

[Download the datasheet (PDF)](https://tradvolt.com/datasheets/swimming-pool-solar-180kwp-uk-r9.pdf)