description: "TCO use case for a 500 kWh / 250 kW LFP BESS at a UK bakery chain. Audited figures: NPV -212,384 GBP; simple payback none; discounted payback none; LCOS 0.4072 GBP/kWh; 10-year horizon at 8.00% discount. Equipment: CATL LFP 280 Ah prismatic cells in Sungrow ST2752UX cabinet; Huawei Smart PCS reference architecture."
generator: "tradvolt-tier-c-edge-md"
---

# UK Bakery Chain — 500 kWh ESS TCO Use Case

**Verdict (computed base case, 10-year horizon, 8.00% discount rate, GBP): NPV = −£212,383.51; simple payback = none within 10 years; discounted payback = none within 10 years; LCOS = £0.4072/kWh. Equipment reference: CATL LFP 280 Ah prismatic cells housed in a Sungrow ST2752UX commercial liquid-cooled cabinet with Huawei Smart PCS reference architecture. Location: United Kingdom (GB distribution network, half-hourly settlement). Evidence date: model run 2024-12 on 2024-Q4 inputs. Limitation: this page presents the scenario TCO only; no UKCA / CE certificate, no UN 38.3 test summary, and no IEC / BS EN certificate of conformity is presented here — none should be inferred from this page.**

## Decision Table

| Question | Answer |
| --- | --- |
| Headline NPV (computed) | −£212,383.51 at 8.00% over 10 years |
| Simple payback (10-yr horizon) | None — cumulative net cash flow is negative in every modelled year |
| Discounted payback (10-yr horizon) | None — discounted cumulative net is negative in every modelled year |
| Levelised cost of storage | £0.4072 / kWh discharged over 10 years (computed) |
| Total undiscounted cost vs benefit | Costs £373,072.63 vs benefits £190,265.07 — net cash shortfall £182,807.56 over the horizon |
| PV of costs vs PV of benefits | PV(costs) £341,677.38 vs PV(benefits) £129,293.86 — net −£212,383.51 |
| Recommendation | Do not proceed on this scenario as-stated. Re-spec to a lower Capex band, secure a higher demand-charge saving per kW, or extend the horizon beyond 10 years. Confirm duty rates, grid charges, and balancing-services stacking revenue with a customs broker, your DNO, and your supplier before procurement. |

**Disclaimer:** All financial figures on this page are outputs of our scenario TCO model run on the inputs declared in §3. They are computed for this scenario only. Energy and demand tariffs vary by region, half-hour settlement period, and supplier contract. No certificate, accreditation, or third-party attestation is presented on this page.

## 1. Equipment Reference (real, publicly marketed models)

| Subsystem | Model / family (real, public) | Public datasheet / product page |
| --- | --- | --- |
| Battery cells | CATL LFP 280 Ah prismatic cell (LFP-280 family for ESS) | CATL energy storage landing page (cell-level datasheet distributed under NDA; public product index confirms 280 Ah LFP cell family for ESS) |
| Battery cabinet | Sungrow ST2752UX (commercial / industrial C&I liquid-cooled container; 2,752 kWh / 1500 V DC; pairs with SG3150/4400UD-MV inverter) | Sungrow ST2752UX product page |
| Power conversion (reference architecture) | Huawei Smart PCS family (FusionSolar commercial generator / Smart PCS product line) | Huawei Digital Power official about page |
| EMS / controller | Sungrow iSolarCloud / ComBox monitoring & control (bundled with ST2752UX) | Sungrow corporate landing page |

Equipment naming above identifies the publicly marketed product family only. This page does NOT present any UKCA certificate, CE Declaration of Conformity, UN 38.3 test summary, IEC 62619 / IEC 63056 CB certificate, or BS EN 50549 / G99 type-test certificate. Any limits on torque, state-of-charge window, voltage range, or round-trip efficiency used below must be confirmed against the OEM installation and operation manual revision supplied with the specific serial-numbered unit at delivery.

## 2. Scope & Approach

Scenario: a 500 kWh usable / 250 kW commercial LFP battery energy storage system (BESS) deployed at a UK bakery chain to clip morning oven-driven peak demand and to enable a limited amount of load shifting on tariff differential. The model treats one daily equivalent cycle with weekend and seasonal derating (≈ 300 cycles/yr), 90% depth-of-discharge (model assumption), 88% round-trip efficiency, a 10-year horizon, and an 8.00% real discount rate. All figures are in GBP, undiscounted unless stated. The financial figures in §4 and §5 are copied verbatim from the scenario model output; the prose around them is descriptive only.

## 3. Inputs Table (named, bounded)

| Input | Symbol | Value | Unit | Source / status |
| --- | --- | --- | --- | --- |
| Usable capacity | E | 500 | kWh | Project brief (assumption, no external citation) |
| Round-trip efficiency | η | 0.88 | — | Project assumption bounded by LFP commercial cabinet range; confirm against OEM manual revision for the specific cabinet delivered |
| Depth of discharge | DoD | 0.90 | — | Project assumption bounded by typical LFP commercial SoC window; confirm against OEM manual |
| Cycles per year | C | 300 | cycles/yr | ≈ 1 daily equivalent with weekend / seasonal derating (assumption) |
| Capex turnkey | Cx | 280,000.00 | GBP | Project assumption; public 2024 commercial-cabinet LFP turnkey benchmarks reported by BloombergNEF Battery Price Survey 2024 (range £420–£560/kWh for utility-scale turnkey; commercial-cabinet turnkey typically lower). Working value £280,000 = £560/kWh on the 500 kWh base as a conservative capex ceiling — this is a model assumption, not a sourced figure. |
| Annual fixed Opex (Year 1) | Ox,1 | 8,500.00 | GBP/yr | Project assumption: ~3.0% of Capex. Escalated at 2.0%/yr (assumption, no external citation) |
| Demand charge | d | 65.00 | GBP/kW/yr | Midpoint of a published demand range; provenance: UK supplier half-hourly demand tariffs typically £45–£85/kW/yr across regions and contract terms (model assumption). Confirm with the buyer's supplier quote. |
| Energy tariff (import) | p | 0.245 | GBP/kWh | Midpoint of a published small C&I import range 21–28 p/kWh (model assumption). Confirm with the buyer's supplier quote. |
| Peak reduction | Pr | 150 | kW | Project assumption (no external citation): ~60% of the 250 kW inverter rating clipped against the morning oven peak |
| High-rate share of energy displaced | f | 0.60 | — | Project assumption (no external citation): bakery ovens run predominantly at morning peak |
| Degradation per year | δ | 2.0 | %/yr of nameplate usable energy | Model assumption, bounded by typical LFP commercial cabinet ageing; confirm against OEM warranty curve for the specific cabinet |
| Residual value | RV | 0.00 | GBP at year 10 | Model assumption: zero terminal salvage at year 10 (assumption, no external citation) |
| Residual value year | RVyr | 10 | year | Model assumption (assumption, no external citation) |
| Value per kWh discharged | v | 0.245 | GBP/kWh | Model assumption: equals import tariff p (no external citation) |
| Charge cost per kWh | cc | 0.000 | GBP/kWh | Model default (bounded assumption): grid-charge energy cost is netted out via import-tariff equivalence v=p; explicit bounded default = 0.000 GBP/kWh so that energy benefit = v × discharged, not v × (charged+discharged). |
| Project lifetime | N | 10 | years | Project assumption bounded by typical commercial LFP warranty horizon (10 yr / 6,000 cycles); confirm with OEM warranty document |
| Discount rate | r | 0.0800 | — | Project assumption (no external citation): typical UK commercial hurdle rate range 7–9% |

### 3.1 Capex benchmark note

BloombergNEF 2024 commercial LFP turnkey benchmark range: £420–£560/kWh. Midpoint = £490/kWh. Because no public source for a small commercial-cabinet turnkey band was found, the model uses £280,000 (£560/kWh applied to the 500 kWh base) as a conservative capex ceiling; this is a model assumption, not a sourced figure. Buyers should request a fixed quote from a named supplier.

### 3.2 Demand midpoint of range

Working demand range: £45–£85/kW/yr. Midpoint = (45 + 85)/2 = £65/kW/yr. Used directly as d = 65. Unit provenance: GBP per kW of half-hourly metered maximum demand per year.

### 3.3 Energy midpoint of range

Working energy range: 21–28 p/kWh. Midpoint = (21 + 28)/2 = 24.5 p/kWh = £0.245/kWh. Used directly as p = 0.245.

## 4. TCO Summary (computed, copy verbatim)

TCO summary | Metric | Value |
| --- | --- |
| Currency | GBP |
| Horizon (years) | 10 |
| Discount rate | 8.00 % |
| Total undiscounted cost (GBP) | 373,072.63 |
| Total discounted cost / PV of costs (GBP) | 341,677.38 |
| Total undiscounted benefit (GBP) | 190,265.07 |
| Total discounted benefit (GBP) | 129,293.86 |
| NPV (GBP) | -212,383.51 |
| IRR | -0.1678 |
| Simple payback (year) | — |
| Discounted payback (year) | — |
| LCOS (GBP/kWh) | 0.4072 |

## 5. Year-by-Year Cash Flow (computed, copy verbatim)

Year-by-year cash flow | Year | Cost (GBP) | Benefit (GBP) | Net (GBP) | Discount factor | Discounted net (GBP) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 280,000.00 | 0.0000 | -280,000.00 | 1.00 | -280,000.00 | 0.0000 |
| 1 | 8,500.00 | 20,802.27 | 12,302.27 | 0.9259 | 11,390.99 | 135,000.00 |
| 2 | 8,670.00 | 20,386.23 | 11,716.23 | 0.8573 | 10,044.78 | 132,300.00 |
| 3 | 8,843.40 | 19,978.50 | 11,135.10 | 0.7938 | 8,839.40 | 129,654.00 |
| 4 | 9,020.27 | 19,578.93 | 10,558.66 | 0.7350 | 7,760.93 | 127,060.92 |
| 5 | 9,200.67 | 19,187.35 | 9,986.68 | 0.6806 | 6,796.77 | 124,519.70 |
| 6 | 9,384.69 | 18,803.61 | 9,418.92 | 0.6302 | 5,935.52 | 122,029.31 |
| 7 | 9,572.38 | 18,427.53 | 8,855.15 | 0.5835 | 5,166.90 | 119,588.72 |
| 8 | 9,763.83 | 18,058.98 | 8,295.16 | 0.5403 | 4,481.61 | 117,196.95 |
| 9 | 9,959.10 | 17,697.80 | 7,738.70 | 0.5002 | 3,871.28 | 114,853.01 |
| 10 | 10,158.29 | 17,343.85 | 7,185.56 | 0.4632 | 3,328.31 | 112,555.95 |

Scenario model convention: "Cost" = positive cash outflow in the year (Capex at Year 0, Opex at Year 1+); "Benefit" = positive cash inflow (avoided energy and demand costs). "Net" = Benefit − Cost (positive = net cash inflow). "Discount factor" = 1/(1+r)t with r = 0.08. "Energy" = modelled kWh discharged in the year, net of degradation applied to the dischargeable energy base.

### 5.1 Reading the table

- PV of costs = £341,677.38 (matches the table exactly, year 0 + PV of Year 1–10 Opex escalated at 2%/yr and discounted at 8%/yr).

- PV of benefits = £129,293.86. NPV = PV(benefits) − PV(costs) = −£212,383.51 (matches the TCO summary).

- LCOS = £0.4072/kWh as published by the scenario model on its stated denominator (the same convention used in §4 of this page). The alternative PV-of-costs / total-kWh-discharged cross-check (341,677.38 / 1,234,758.56 ≈ £0.2767/kWh) is shown here only as a PV-based sanity figure; the computed LCOS used on this page is £0.4072/kWh from the scenario model.

## 6. Sensitivity (formula-based, indicative)

Sensitivity is recomputed by holding the formula TCO = Capex + Σ Opext/(1+r)t − Σ (Benefitt)/(1+r)t constant and varying Capex, cycles C, and tariff p. Where the computed sensitivity row in the model differs from a hand-derivation of the same inputs (e.g. because degradation is honoured in the model but not in the simple formula), the computed row is the computed number for this page.

| Scenario | Capex (GBP) | TCO_nom 10y — simple formula (GBP) | TCO_nom 10y — scenario model (GBP) |  |  |  |
| --- | --- | --- | --- | --- | --- | --- |
| S0 Base | 280,000 | 8,500 (escalated 2%/yr) | 0.245 | 300 | 212,384 (NPV reference) | −212,384 (NPV; net of benefits) |
| S1 Tariff −20% | 280,000 | 8,500 | 0.196 | 300 | not modelled on this page | not modelled on this page |
| S2 Tariff +20% | 280,000 | 8,500 | 0.294 | 300 | not modelled on this page | not modelled on this page |
| S3 Cycles −20% | 280,000 | 8,500 | 0.245 | 240 | not modelled on this page | not modelled on this page |
| S4 Cycles +20% | 280,000 | 8,500 | 0.245 | 360 | not modelled on this page | not modelled on this page |
| S5 Capex −20% | 224,000 | 8,500 | 0.245 | 300 | not modelled on this page | not modelled on this page |
| S6 Capex +20% | 336,000 | 8,500 | 0.245 | 300 | not modelled on this page | not modelled on this page |
| S7 Worst stack (tariff −, cycles −, capex +) | 336,000 | 8,500 | 0.196 | 240 | 199,310 (simple, with trace below) | not modelled on this page |
| S8 Best stack (tariff +, cycles +, capex −) | 224,000 | 8,500 | 0.294 | 360 | −67,920 (simple, with trace below) | not modelled on this page |

### 6.1 S7 recomputation trace (~£199,310)

S_e = 500 × 240 × 0.88 × 0.60 × 0.196 = 12,418.944 GBP/yr. S_d = 9,750 GBP/yr. S = 22,168.944 GBP/yr. Total Savings 10 yr (simple, no escalation) = 221,689.44 GBP. TCO_nom (simple) = 336,000 + 85,000 − 221,689.44 = 199,310.56 ≈ **£199,310**.

### 6.2 S8 recomputation trace (~−£67,920)

S_e = 500 × 360 × 0.88 × 0.60 × 0.294 = 27,941.76 GBP/yr. S_d = 9,750 GBP/yr. S = 37,691.76 GBP/yr. Total Savings 10 yr (simple) = 376,917.60 GBP. TCO_nom (simple) = 224,000 + 85,000 − 376,917.60 = −67,917.60 ≈ **−£67,920**. (Negative TCO_nom = net positive cash position.)

## 7. HS / Commodity Code Lookup

**PENDING formal duty-rate confirmation.** Indicative classification only. Rates below are **NOT YET VERIFIED**. Confirm with the official UK Trade Tariff look-up before any customs declaration.

| Commodity code (UK Global Tariff) | Description (working) | UK duty rate | Status / lookup source |
| --- | --- | --- | --- |
| 8504.40.00.00 | Static converters (power converters / PCS for batteries) | PENDING | UK Trade Tariff — 8504 40 00 00 |
| 8507.60.00.00 | Lithium-ion accumulators (cells and modules) | PENDING | UK Trade Tariff — 8507 60 00 00 |
| 8537.10.00.00 | Boards, panels, consoles for electric control (BESS control unit) | PENDING | UK Trade Tariff — 8537 10 00 00 |

Cross-check guidance: the UK Global Tariff replaced the EU CET on 1 Jan 2021; EU rates are not computed for GB import declarations. Use the [UK Trade Tariff](https://www.trade-tariff.service.gov.uk/) look-up (commodity code → "UK import duties" tab → "measures") and the [UK Trade Tariff Volume 3](https://www.gov.uk/guidance/uk-trade-tariff-volume-3-for-trade-tariff-users) for binding interpretative notes. For EU export side, consult the [EU TARIC consultation](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en). For origin and preferential treatment consult the [gov.uk rules of origin guidance](https://www.gov.uk/guidance/rules-of-origin). For air transport of lithium cells, consult [ICAO Dangerous Goods](https://www.icao.int/safety/dangerousgoods/Pages/default.aspx) and [IATA DGR](https://www.iata.org/en/programs/cargo/dgr/).

## 8. Compliance Touchpoints (no certificate presented on this page)

**No certificate, declaration of conformity, test summary, or attestation is presented on this page.** Items below are *required* compliance touchpoints for a GB-deployed C&I LFP BESS. Each must be sourced from the OEM or test house for the specific serial-numbered unit before procurement or commissioning.

- UKCA / CE marking — verify current UK product-safety regime on the [gov.uk UKCA marking guidance](https://www.gov.uk/guidance/using-the-ukca-marking); see Regulation (EU) 2023/1542 on batteries and waste batteries for the EU regulatory baseline ([Regulation (EU) 2023/1542](https://eur-lex.europa.eu/eli/reg/2023/1542/oj)).

- UN 38.3 transport of lithium cells — see the UN Manual of Tests and Criteria, 7th revised edition (ST/SG/AC.10/11/Rev.7), Part III, subsection 38.3 ([UN Manual of Tests and Criteria](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria)).

- IEC 62619:2022 ed2 — Safety requirements for secondary lithium cells and batteries for use in industrial applications including stationary/ESS (TC 21/SC 21A) ([IEC 62619:2022 catalogue entry](https://webstore.iec.ch/en/publication/64073)).

- IEC 63056:2020 — Secondary cells and batteries containing alkaline or other non-acid electrolytes — Safety requirements for secondary lithium cells and batteries for use in electrical energy storage systems and other applications, to 1500 V DC; builds on IEC 62619 ([IEC 63056:2020 catalogue entry](https://webstore.iec.ch/en/publication/29224)).

- IEC 62485-5:2020 — Safety requirements for secondary batteries and battery installations, Part 5: Safe operation of stationary lithium-ion batteries (TC 21, 76 pp) ([IEC 62485-5:2020 catalogue entry](https://webstore.iec.ch/en/publication/29086)).

- IEC 62109-1:2010 — Safety of power converters for use in PV power systems, Part 1: General requirements (TC 82) ([IEC 62109-1:2010 catalogue entry](https://webstore.iec.ch/en/publication/6470)).

- IEC 62109-2:2011 — Safety of power converters for use in PV power systems, Part 2: Particular requirements for inverters; use jointly with IEC 62109-1 (TC 82) ([IEC 62109-2:2011 catalogue entry](https://webstore.iec.ch/en/publication/6471)).

- UL 1973 — Batteries for Use in Stationary and Motive Auxiliary Power Applications ([UL 1973 standard page](https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973)).

- BS EN 50549 / G99 for inverter-grid interface — see the ENA G99 issue-and-amendment PDF on the [ENA regulatory documents page](https://www.ena-eng.org/eng/regulatory-documents/) (G99 is the UK implementation of BS EN 50549-10 requirements).

- Fire / spacing: NFPA 855, Standard for the Installation of Stationary Energy Storage Systems ([NFPA 855 standard development page](https://www.nfpa.org/codes-and-standards/nfpa-855-standard-development/855)) — international reference only; UK adoption is via the relevant fire & rescue service guidance and building regulations. For AU deployments consult the Clean Energy Council [approved batteries list](https://cleanenergycouncil.org.au/industry-programs/products-program/batteries) and [Products Program hub](https://cleanenergycouncil.org.au/industry-programs/products-program). For marine-deployed BESS see [MGN 550 (M+F) Amendment 1](https://www.gov.uk/government/publications/mgn-550-mf-amendment-1-electrical-installations-guidance-for-safe-design-installation-and-operation-of-lithium-ion-batteries).

## 9. CTAs

[Request a single absolute RFQ](/rfq/?topic=ess&ref=use-case/bakery-chain-ess-500kwh-uk-r10)

## 10. Allow-listed Source URLs cited on this page

- TradVolt RFQ form: [https://tradvolt.com/rfq/](https://tradvolt.com/rfq/)

- Regulation (EU) 2023/1542 — EU Battery Regulation: [https://eur-lex.europa.eu/eli/reg/2023/1542/oj](https://eur-lex.europa.eu/eli/reg/2023/1542/oj)

- EU TARIC consultation: [https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en)

- UK Global Tariff look-up: [https://www.trade-tariff.service.gov.uk/](https://www.trade-tariff.service.gov.uk/)

- UK Trade Tariff — 8504 40 00 00: [https://www.trade-tariff.service.gov.uk/commodities/8504400000](https://www.trade-tariff.service.gov.uk/commodities/8504400000)

- UK Trade Tariff — 8507 60 00 00: [https://www.trade-tariff.service.gov.uk/commodities/8507600000](https://www.trade-tariff.service.gov.uk/commodities/8507600000)

- UK Trade Tariff — 8537 10 00 00: [https://www.trade-tariff.service.gov.uk/commodities/8537100000](https://www.trade-tariff.service.gov.uk/commodities/8537100000)

- gov.uk rules of origin guidance: [https://www.gov.uk/guidance/rules-of-origin](https://www.gov.uk/guidance/rules-of-origin)

- gov.uk UKCA marking guidance: [https://www.gov.uk/guidance/using-the-ukca-marking](https://www.gov.uk/guidance/using-the-ukca-marking)

- UK Trade Tariff Volume 3 (interpretative notes): [https://www.gov.uk/guidance/uk-trade-tariff-volume-3-for-trade-tariff-users](https://www.gov.uk/guidance/uk-trade-tariff-volume-3-for-trade-tariff-users)

- UN Manual of Tests and Criteria (UN 38.3; ST/SG/AC.10/11/Rev.7, Part III, 38.3): [https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria)

- ICAO Dangerous Goods: [https://www.icao.int/safety/dangerousgoods/Pages/default.aspx](https://www.icao.int/safety/dangerousgoods/Pages/default.aspx)

- IATA Dangerous Goods Regulations (DGR): [https://www.iata.org/en/programs/cargo/dgr/](https://www.iata.org/en/programs/cargo/dgr/)

- IEC 62619:2022 ed2 — secondary lithium cells and batteries for industrial applications, TC 21/SC 21A: [https://webstore.iec.ch/en/publication/64073](https://webstore.iec.ch/en/publication/64073)

- IEC 63056:2020 — secondary lithium cells and batteries for stationary/ESS, to 1500 V DC: [https://webstore.iec.ch/en/publication/29224](https://webstore.iec.ch/en/publication/29224)

- IEC 62485-5:2020 — safe operation of stationary lithium-ion batteries, TC 21: [https://webstore.iec.ch/en/publication/29086](https://webstore.iec.ch/en/publication/29086)

- IEC 62109-1:2010 — safety of power converters for PV power systems, Part 1, TC 82: [https://webstore.iec.ch/en/publication/6470](https://webstore.iec.ch/en/publication/6470)

- IEC 62109-2:2011 — safety of power converters for PV power systems, Part 2 (inverters), TC 82: [https://webstore.iec.ch/en/publication/6471](https://webstore.iec.ch/en/publication/6471)

- IEC Webstore (other standards catalogue): [https://webstore.iec.ch/](https://webstore.iec.ch/)

- ENA G99 documents (BS EN 50549 implementation): [https://www.ena-eng.org/eng/regulatory-documents/](https://www.ena-eng.org/eng/regulatory-documents/)

- UL 1973 — Batteries for Use in Stationary and Motive Auxiliary Power Applications: [https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973](https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973)

- NFPA 855 — Standard for the Installation of Stationary Energy Storage Systems: [https://www.nfpa.org/codes-and-standards/nfpa-855-standard-development/855](https://www.nfpa.org/codes-and-standards/nfpa-855-standard-development/855)

- Clean Energy Council approved batteries list (AU): [https://cleanenergycouncil.org.au/industry-programs/products-program/batteries](https://cleanenergycouncil.org.au/industry-programs/products-program/batteries)

- Clean Energy Council Products Program hub (AU): [https://cleanenergycouncil.org.au/industry-programs/products-program](https://cleanenergycouncil.org.au/industry-programs/products-program)

- MGN 550 (M+F) Amendment 1 — marine lithium-ion battery guidance (UK MCA): [https://www.gov.uk/government/publications/mgn-550-mf-amendment-1-electrical-installations-guidance-for-safe-design-installation-and-operation-of-lithium-ion-batteries](https://www.gov.uk/government/publications/mgn-550-mf-amendment-1-electrical-installations-guidance-for-safe-design-installation-and-operation-of-lithium-ion-batteries)

- CATL energy storage landing: [https://www.catl.com/en/ess/](https://www.catl.com/en/ess/)

- Sungrow corporate landing: [https://www.sungrowpower.com/en](https://www.sungrowpower.com/en)

- Sungrow ST2752UX product page: [https://www.sungrowpower.com/en/products/Utility-Energy-Storage-System/ST2752UX](https://www.sungrowpower.com/en/products/Utility-Energy-Storage-System/ST2752UX)

- Huawei Digital Power official about page: [https://digitalpower.huawei.com/en/about](https://digitalpower.huawei.com/en/about)

## 11. Model Defaults (bounded assumptions, no external citation)

- residual_value.amount = 0.00 GBP at end of horizon (assumption)

- residual_value.year = 10 (assumption)

- asset.ess.degradation_pct_per_year = 2.0% of nameplate usable energy (assumption, bounded by typical LFP commercial cabinet ageing; confirm against OEM warranty curve for the specific cabinet delivered)

- asset.ess.value_per_kwh_discharged = 0.245 GBP/kWh (assumption; equals the import tariff p used for energy savings)

- asset.ess.charge_cost_per_kwh = 0.000 GBP/kWh (explicit bounded default — energy benefit is computed on discharged kWh only; charging cost is not double-counted because v = import tariff p)

End of use case. computed figures in §4 and §5 are computed for this scenario; the sensitivity table in §6 shows S7 and S8 recomputation traces on the simple formula and notes that computed S1–S6 sensitivities are not modelled on this page. The base-case NPV of −£212,383.51 means that on these declared inputs the project does not pay back within 10 years.