# Use Case & TCO — 1 MWp Greenhouse Solar in Indiana (r9)

**Verdict (read first):** For a 1 MWp DC rooftop PV array on a horticultural glasshouse in Indiana (utility rate zone r9), over a 10-year horizon at a 6.00% real discount rate, the scenario model returns **NPV = USD 295,293.34**, **LCOE = USD 0.0730/kWh**, **discounted payback = 5.96 years**, **simple payback = 4.91 years**, **IRR = 15.92%**. Equipment: LONGi Hi-MO 5m LR5-72HTH (540 W mono PERC) + Sungrow SG125HT string inverters + K2 Systems S-Dome 6.10 mounting. Evidence date: 2026-09-22. Limitation: capex, yield, tariff, O&M escalation and residual value are explicit bounded model assumptions; not a substitute for an OEM-quoted RFQ. Confirm duty via [hts.usitc.gov](https://hts.usitc.gov/) before quoting a client.

## Decision table (answer-first)

| Field | Value |
| --- | --- |
| Equipment | LONGi Hi-MO 5m LR5-72HTH (540 W mono PERC) modules + Sungrow SG125HT string inverters + K2 Systems S-Dome 6.10 flat-roof mounting |
| Location | Indiana, U.S. (utility rate zone r9) |
| Horizon | 10 years |
| Discount rate (real) | 6.00% |
| NPV | USD 295,293.34 |
| Discounted payback | 5.96 years (5.962525135240018) |
| Simple payback | 4.91 years (4.90597889894983) |
| LCOE | USD 0.0730/kWh (scenario model output; benefits not netted into numerator) |
| IRR | 15.92% |
| Total undiscounted cost (10-yr) | USD 713,296.09 |
| Total discounted cost / PV of costs | USD 671,761.96 |
| Total undiscounted benefit (10-yr) | USD 1,320,143.53 |
| Total discounted benefit | USD 967,055.29 |
| 10-year energy aggregate (Σ kWh, years 1–10) | 12,463,527 kWh |
| Evidence date | 2026-09-22 (model run date) |
| Limitation | All capex, tariff, yield and O&M inputs are explicit bounded model assumptions. Confirm duty via hts.usitc.gov before quoting a client. |

## 1. Inputs (explicit bounded assumptions)

| Parameter | Value | Unit | Type |
| --- | --- | --- | --- |
| DC capacity | 1,000 | kWp | Model assumption (1 MWp commercial rooftop, Indiana) |
| Specific yield (year 1) | 1,275 | kWh/kWp/yr | Model assumption; cross-check EU PVGIS (SARAH2, Indianapolis TMY, fixed open-rack, GCR 0.40) |
| Annual module degradation | 0.50 | %/yr | Model assumption; cross-check Fraunhofer ISE Photovoltaics Report |
| Module cost (FOB China) | 0.18 | USD/Wp | Model assumption; cross-check BloombergNEF Solar Module Spot Price |
| Inverter cost (string) | 0.06 | USD/Wp | Model assumption; cross-check Fraunhofer ISE Photovoltaics Report |
| BoS (structure, DC/AC cabling, combiner, monitoring) | 0.18 | USD/Wp | Model assumption; cross-check Fraunhofer ISE Photovoltaics Report |
| Soft costs (engineering, permitting, EPC margin) | 0.14 | USD/Wp | Model assumption |
| Fixed O&M (year 1) | 14.00 | USD/kWp/yr | Model assumption (opex.annual_per_kwp) |
| O&M escalation | 2.00 | %/yr | Model assumption (opex.escalation_pct) — bounded |
| Insurance | 0.30 | % of capex/yr | Model assumption (insurance line, applied within O&M) — bounded |
| Export tariff (feed-in, year 1) | 0.099 | USD/kWh | Model assumption (asset.pv.tariff_per_kwh) — bounded |
| Tariff escalation | 1.50 | %/yr | Model assumption (asset.pv.tariff_escalation_pct) — bounded |
| Self-consumption share | 0.00 | % | Model assumption (asset.pv.self_consumption_pct = ZERO-AS-MISSING; all output exported at tariff) — bounded |
| Discount rate (real) | 6.00 | %/yr | Model assumption (post-tax real, 10-yr horizon) — bounded |
| Residual value (year 10) | 0.00 | USD | Model assumption (residual_value.amount, conservative) — bounded |
| Residual year | 10 | yr | Model assumption (residual_value.year) — bounded |
| Project horizon | 10 | yr | Model assumption (base case) — bounded |

## 2. Equipment specification (real, marketed models)

| Item | Model family | Rated spec | OEM product page |
| --- | --- | --- | --- |
| PV module (mono PERC) | LONGi Hi-MO 5m LR5-72HTH | 540 W STC; Voc ≈ 49.6 V; Isc ≈ 13.9 A | LONGi Hi-MO 9 (Hi-MO family landing; model page JS-rendered, exact datasheet confirmed at RFQ) |
| String inverter | Sungrow SG125HT | 125 kW AC, 1,500 V DC, 6 MPPTs | Sungrow string inverter range (model page JS-rendered; exact datasheet confirmed at RFQ) |
| Flat-roof mounting | K2 Systems S-Dome 6.10 | Aluminium, 10° tilt, ballast / screw options | K2 Systems N-Rack ground-mount system (S-Dome 6.10 manual supplied by K2 at RFQ) |

Alternative Tier-1 module options (real product lines, substitution at RFQ): JinkoSolar Tiger Neo 3.0 ([JinkoSolar Tiger Neo 3.0](https://www.jinkosolar.com/en/site/tigerneo_3); 670 W, 24.8% module efficiency, TOPCon cells); LONGi Hi-MO X6 ([LONGi Hi-MO X6](https://www.longi.com/en/products/modules-series/hi-mo-x6/); HPBC cell efficiency exceeds 25.5%; HPBC+ exceeds 25.8%; variants Explorer, Scientist, Guardian Anti-Dust, Guardian Anti Humidity-Heat, Artist Ultra Black); Trina Solar Vertex S+ ([Trina Solar Vertex S+](https://www.trinasolar.com/en-glb/product/vertex-s-plus)). Alternative string inverters: Huawei SUN2000-150K-MG0 ([Huawei SUN2000-150K-MG0](https://solar.huawei.com/en/products/SUN2000-150K-MG0/)); SMA Sunny Tripower CORE1 50-US / 62-US ([SMA Sunny Tripower CORE1](https://www.sma-america.com/products/solarinverters/sunny-tripower-core1)); Fronius Tauro 50-3-P ([Fronius Tauro 50-3-P](https://www.fronius.com/en-gb/uk/solar-energy/installers-partners/technical-data/all-products/inverters/fronius-tauro/tauro-50-3-p)); Growatt (range landing [Growatt](https://www.growatt.com/), datasheet confirmed at RFQ).

## 3. Capex build-up

Capex per watt = 0.18 + 0.06 + 0.18 + 0.14 = **0.56 USD/Wp**.

Total capex = 0.56 × 1,000,000 Wp = **USD 560,000**.

## 4. TCO summary (computed by scenario model)

TCO summary | Metric | Value |
| --- | --- |
| Currency | USD |
| Horizon (years) | 10 |
| Discount rate | 6.00 % |
| Total undiscounted cost (USD) | 713,296.09 |
| Total discounted cost / PV of costs (USD) | 671,761.96 |
| Total undiscounted benefit (USD) | 1,320,143.53 |
| Total discounted benefit (USD) | 967,055.29 |
| NPV (USD) | 295,293.34 |
| IRR | 0.1592 |
| Simple payback (year) | 4.91 |
| Discounted payback (year) | 5.96 |
| LCOE (USD/kWh) | 0.0730 |

## 5. Year-by-year cash flow (computed by scenario model)

Year-by-year cash flow | Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 560,000.00 | 0.0000 | -560,000.00 | 1.00 | -560,000.00 | 0.0000 |
| 1 | 14,000.00 | 126,225.00 | 112,225.00 | 0.9434 | 105,872.64 | 1,275,000.00 |
| 2 | 14,280.00 | 127,477.78 | 113,197.78 | 0.8900 | 100,745.62 | 1,268,625.00 |
| 3 | 14,565.60 | 128,743.00 | 114,177.40 | 0.8396 | 95,865.55 | 1,262,281.88 |
| 4 | 14,856.91 | 130,020.77 | 115,163.86 | 0.7921 | 91,220.57 | 1,255,970.47 |
| 5 | 15,154.05 | 131,311.23 | 116,157.18 | 0.7473 | 86,799.40 | 1,249,690.61 |
| 6 | 15,457.13 | 132,614.49 | 117,157.36 | 0.7050 | 82,591.32 | 1,243,442.16 |
| 7 | 15,766.27 | 133,930.69 | 118,164.42 | 0.6651 | 78,586.09 | 1,237,224.95 |
| 8 | 16,081.60 | 135,259.96 | 119,178.36 | 0.6274 | 74,773.98 | 1,231,038.82 |
| 9 | 16,403.23 | 136,602.41 | 120,199.18 | 0.5919 | 71,145.71 | 1,224,883.63 |
| 10 | 16,731.30 | 137,958.19 | 121,226.89 | 0.5584 | 67,692.46 | 1,218,759.21 |

*LCOE convention:* the COMPUTED TABLES are computed — LCOE = USD 0.0730/kWh. Export revenue is NOT netted into the LCOE numerator.

## 6. Certificate framework (informational only)

The certification framework for a 1 MWp greenhouse-rooftop PV in Indiana (r9) typically references the following standards. *Certificate numbers are project-specific and are not yet issued; tradvolt does not attest to any specific certificate and buyers must obtain certificates from the issuing bodies named below.*

- Modules: [UL 61730-1 (PV Module Safety Qualification — Part 1)](https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1) and IEC 61215-1-1:2021 (crystalline-silicon PV module design qualification, catalogue query via [IEC Webstore — IEC 61215-1-1:2021](https://webstore.iec.ch/en/publication/61346)) — manufacturer certificate, project-specific.

- PV plant design: IEC 62548 (catalogue query via [IEC Webstore](https://webstore.iec.ch/), cite designation IEC 62548:2023 + edition at RFQ).

- Installation: NFPA 70 — US National Electrical Code (NEC 690, r9 jurisdiction) — EPC scope.

- Inverters: UL 1741 and IEEE 1547 (grid support functions) — manufacturer certificate; [IEC 62109-2:2011](https://webstore.iec.ch/en/publication/6471) (inverter safety, particular requirements) used jointly with [IEC 62109-1:2010](https://webstore.iec.ch/en/publication/6470) (PCE safety general requirements, TC 82).

- Greenhouse glazing retention: ASTM E1300 (structural glass review) — project-specific.

## 7. HS code & duty block (lookup required)

**Tariff classification — lookup required.** Do not treat the rates below as facts; they must be confirmed against the official U.S. Harmonized Tariff Schedule (HTSUS) at [hts.usitc.gov](https://hts.usitc.gov/), the WCO HS Nomenclature 2022 edition at [WCO HS Nomenclature 2022 edition](https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition), and the latest CBP rulings at [cbp.gov](https://www.cbp.gov/) before any client quotation. [US Section 301 China tariff actions](https://ustr.gov/trade-topics/enforcement/section-301-investigations/section-301-china-technology-transfer/china-section-301-tariff-actions-and-exclusion-process/four-year-review) may apply independently of base duty.

| Item | Suggested HTS heading | Duty rate | Status |
| --- | --- | --- | --- |
| Crystalline silicon PV modules | 8541.43 | PENDING — verify on hts.usitc.gov | Lookup required |
| String inverters > 50 V | 8504.40 | PENDING — verify on hts.usitc.gov | Lookup required |
| Aluminium mounting structure | 7610.90 | PENDING — verify on hts.usitc.gov | Lookup required |
| DC cables, PV-rated | 8544.49 | PENDING — verify on hts.usitc.gov | Lookup required |

*Disclaimer:* classification depends on cell technology, panel rating, mounting type and country of origin. AD/CVD on certain solar cells from specific origins and Section 201 safeguard measures may apply independently of the base duty. For non-US destinations, see [EU TARIC](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en), [UK Global Tariff](https://www.trade-tariff.service.gov.uk/), [Japan Customs tariff schedule](https://www.customs.go.jp/english/tariff/), [Australian Border Force](https://www.abf.gov.au/), [SARS](https://www.sars.gov.za/), [Ghana Revenue Authority](https://gra.gov.gh/), and [Uganda Revenue Authority](https://www.ura.go.ug/).

## 8. CTAs

[Request a single absolute RFQ for a 1 MWp greenhouse solar system in Indiana (r9).](/rfq/)

Reviewed by tradvolt TCO model (computed), evidence date 2026-09-22. Page is informational; certificate numbers are project-specific and not yet issued. Do not redistribute datasheets outside the buyer's internal team.