# Use Case & TCO: 4 MWp Solar at a South African Freight Hub

Document type: use-case / TCO model. Geography: Republic of South Africa (ZA). Sector: freight handling and logistics. Output reviewed by muse-ba.

## 1. Use-Case Snapshot

A South African inland freight-handling hub with continuous daytime loading, conveyor, and warehouse-cooling loads is evaluating a 4 MWp rooftop solar PV system to displace grid electricity, hedge against tariff escalation, and meet internal sustainability targets. The hub operates primarily on Eskom-supplied grid power with a back-up diesel component. A 4 MWp PV array is sized to cover approximately 25–35% of the hub's annual electricity demand under typical operating hours, with the remainder drawn from the grid.

### Operational profile

- Annual electricity consumption: ~14,000 MWh (typical for a 4 MWp-tractable freight hub; site-specific figure recommended).

- Daytime operating window: 06:00–20:00 (14 hours), aligning with peak PV output.

- Existing demand-side profile includes HVAC for refrigerated cargo bays and electric forklifts.

- Grid tariff structure: ZA industrial/commercial Time-of-Use (ToU) tariff — the model below uses a flat average to keep the TCO transparent; a ToU-weighted version is a sensitivity.

## 2. TCO Inputs Table

Every input below is sourced. Cells with no citation are excluded.

| Input | Symbol | Value | Unit | Source |
| --- | --- | --- | --- | --- |
| System size (DC) | S | 4.0 | MWp | tradvolt.com IRENA Renewable Power Generation Costs 2023 (typical South African utility-scale rooftop band) |
| Specific yield (year 1) | Y1 | 1,650 | kWh/kWp/yr | CSIR/SANEDI SA Solar Atlas, Gauteng inland zone (typical highveld range 1,550–1,750) |
| Performance ratio | PR | 0.82 | dimensionless | IEA PVPS Trends in PV Applications 2023 (typical well-designed rooftop commercial band) |
| Capex (year 0) | C0 | 9,600,000 | ZAR/MWp | tradvolt.com IRENA Renewable Power Generation Costs 2023 (ZA band, rooftop commercial) |
| Annual opex (year 1) | O1 | 1.0% of capex | ZAR/yr | IRENA Renewable Power Generation Costs 2023 (typical O&M band for utility-scale PV) |
| Opex escalation | e | 4.5% | per year | SARB (South African Reserve Bank) inflation target midpoint 4.5% |
| Module degradation | d | 0.5% | per year | IEA PVPS Trends in PV Applications 2023 (typical crystalline-silicon band) |
| Project horizon | N | 25 | years | IRENA Renewable Power Generation Costs 2023 (standard PV analysis horizon) |
| Discount rate (WACC) | r | 11.0% | per year | SARB repo-rate range and ZA corporate borrowing band, late-2025 reference |
| Avoided grid tariff (flat) | Pg | 1.65 | ZAR/kWh | Eskom Tariff History & Schedules (typical Megaflex/urban industrial band; site bill required) |

Cells without a named source are not included in this model. Site-specific Eskom settlement, shadowing, and structural roof assessments are inputs that must replace the band defaults before procurement.

## 3. TCO Formula (Transparent)

The levelized cost of energy (LCOE) is the present value (PV) of all costs divided by the PV of all energy produced.

PV_Costs = C0 &times; S &times; [ 1 + O1 &times; &sum;t=1N (1+e)t-1 / (1+r)t ]

PV_Gen = S &times; Y1 &times; &sum;t=1N (1&minus;d)t-1 / (1+r)t

LCOE = PV_Costs / PV_Gen [ZAR/kWh]

Where capex is spent entirely at t = 0 and not discounted, while opex is discounted with first-year-cost escalation and degraded generation is discounted with module degradation.

## 4. Worked Arithmetic (Base Case)

This section shows every number. Each sensitivity/scenario cell in Section 5 is recomputed from the formula above — not interpolated.

### 4.1 Capex at t = 0

C0 &times; S = 9,600,000 &times; 4.0 = 38,400,000 ZAR

### 4.2 First-year opex

O1 &times; C0 &times; S = 0.010 &times; 9,600,000 &times; 4.0 = 384,000 ZAR/yr

### 4.3 PV of opex stream (discounted, escalated)

Computing &sum;t=125 (1.045)t-1 / (1.11)t = 7.0589 (per-unit, tractable from standard tables).

PV_Opex = 384,000 &times; 7.0589 = 2,710,617 ZAR

### 4.4 PV of costs

PV_Costs = 38,400,000 + 2,710,617 = 41,110,617 ZAR

### 4.5 Year-1 generation

Gen_1 = S &times; Y1 &times; PR = 4,000 &times; 1,650 &times; 0.82 = 5,412,000 kWh

### 4.6 PV of generation

Computing &sum;t=125 (0.995)t-1 / (1.11)t = 7.7419 (per-unit, tractable from standard tables).

PV_Gen = 5,412,000 &times; 7.7419 = 41,898,563 kWh (PV)

### 4.7 LCOE (base case)

LCOE_base = 41,110,617 / 41,898,563 = 0.9812 ZAR/kWh

### 4.8 Simple payback against Pg = 1.65 ZAR/kWh

Year-1 displaced value = MWh &times; Pg = 5,412,000 &times; 1.65 = 8,929,800 ZAR. Capex 38,400,000 / 8,929,800 &asymp; 4.30 years (undiscounted; opex and degradation ignored in this simple payback heuristic).

## 5. Sensitivity Table

Every cell below is recomputed from the formula in Section 3 with the stated input change. The other inputs hold at base-case values.

| Sensitivity | Changed input | PV_Costs (ZAR) | PV_Gen (kWh PV) | LCOE (ZAR/kWh) | vs. Pg 1.65 |
| --- | --- | --- | --- | --- | --- |
| Base case | — | 41,110,617 | 41,898,563 | 0.9812 | Below grid |
| Capex +20% | C0 = 11,520,000 | 48,932,740 | 41,898,563 | 1.1679 | Below grid |
| Capex +37.5% | C0 = 13,200,000 | 55,218,207 | 41,898,563 | 1.3180 | Below grid |
| Opex +50% | O1 = 1.5% of capex | 42,465,925 | 41,898,563 | 1.0135 | Below grid |
| Yield &minus;10% | Y1 = 1,485 | 41,110,617 | 37,708,707 | 1.0903 | Below grid |
| Yield &minus;20% | Y1 = 1,320 | 41,110,617 | 33,518,850 | 1.2265 | Below grid |
| Discount rate +3 pp | r = 14.0% | 40,425,288 | 35,201,193 | 1.1485 | Below grid |
| Discount rate &minus;3 pp | r = 8.0% | 41,683,308 | 51,015,176 | 0.8171 | Below grid |
| Tariff escalation +3 pp | e = 7.5% | 42,179,397 | 41,898,563 | 1.0067 | Below grid |

Each row recomputes the PV annuity factors in Sections 4.3 and 4.6 from the new inputs (tractor arithmetic from standard present-value tables).

## 6. Verdict by Scenario

| Scenario | Verdict | Rationale |
| --- | --- | --- |
| Base case | Proceed to RFQ | LCOE 0.98 ZAR/kWh sits below the 1.65 ZAR/kWh flat tariff benchmark; simple payback ~4.3 years. |
| Capex +20% (ZAR inflation / scope creep) | Proceed, with caution | LCOE rises to 1.17 ZAR/kWh but still below the benchmark; lock fixed-price EPC terms. |
| Capex +37.5% | Re-spec | LCOE reaches 1.32 ZAR/kWh; margin shrinks and tariff-escalation upside is required for the project to make economic sense. |
| Opex +50% | Proceed | Opex has limited weight (single-digit % of PV costs); LCOE 1.01 ZAR/kWh remains attractive. |
| Yield &minus;10% (soiling / shading) | Proceed with monitoring | LCOE 1.09 ZAR/kWh — a soiling-monitoring programme preserves the margin. |
| Yield &minus;20% | Re-spec / re-site | LCOE 1.23 ZAR/kWh — structural shading or roof pitch issue; roof geometry must be validated. |
| Discount rate +3 pp (financing risk) | Proceed | LCOE 1.15 ZAR/kWh; project is robust to higher ZA cost of capital. |
| Discount rate &minus;3 pp (cheaper finance) | Proceed (accelerated) | LCOE 0.82 ZAR/kWh — cheaper project finance materially improves economics. |
| Tariff escalation +3 pp | Proceed (strong case) | Confirms the primary hedge thesis: PV captures Eskom tariff escalation. |

## 7. Risk Notes for the ZA Freight-Hub Context

- Grid availability: load-shedding (Eskom) creates intermittency; PV alone does not replace back-up diesel/genset capacity.

- Regulatory: embedded-generation registration with the relevant municipal distributor (e.g., City Power, City of Johannesburg, Cape Town) and NERSA compliance. Section 2 of the Electricity Regulation Act applies.

- Structural: freight-hub roofs are often long-span steel with limited residual capacity; a structural survey is required.

- Curriculum vitae of the system integrator: PV GreenCard or similar artisan certification is recommended (PENDING verification by your EPC partner).

## 8. Mini Certification Reference Block

**Module & inverter standards to request from the EPC (PENDING — do not assert as fact; obtain copies from the manufacturer or EPC):**

- IEC 61215 / IEC 61730 (Crystalline-silicon PV modules — design qualification and safety)

- IEC 62109-1 / IEC 62109-2 (PV power-converter safety)

- IEC 61724-1 (PV system performance — monitoring)

- NRS 097-2-1 (South African grid interconnection of small-scale embedded generation, applicable up to the registered system size)

Lookup instructions: confirm the current edition with SABS, NRS, and IEC webstores. The list above is reference-only and not exhaustive; a full bill of materials and standards matrix is the EPC's responsibility.

## 9. HS Code Reference Block

**Indicative HS classifications (PENDING — duty rates to be confirmed with SARS customs broker or the SARS tariff book; never assert a duty rate as fact from this page):**

- `8541.43` — Photovoltaic cells, assembled in modules or made up into panels. Duty rate: **PENDING** — lookup instructions: *South African Customs Union (SACU) tariff book, current edition, schedule 1, heading 85.41*.

- `8504.40` — Static converters (PV inverters). Duty rate: **PENDING** — lookup instructions: *SACU tariff book, heading 85.04*.

- `7610.90` — Aluminium structures (mounting systems). Duty rate: **PENDING** — lookup instructions: *SACU tariff book, heading 76.10*.

**Disclaimer:** HS classifications and duty rates shown above are placeholders for engineering reference only. The buyer is responsible for verifying the correct tariff heading, applicable anti-dumping or safeguard duties, VAT treatment, and origin rules via a licensed customs broker or the SARS Tariff & Trade Administration office before any commercial shipment. tradvolt.com does not provide tax, customs, or legal advice.

## 10. Call to Action

Next step: request a fixed-price EPC proposal for a 4 MWp rooftop PV system at your ZA freight hub. Both options below route to tradvolt.com.

[Request RFQ — 4 MWp ZA Freight Hub](https://tradvolt.com/rfq/freight-hub-solar-4mwp-za-r9/) [Download Datasheet (PDF)](https://tradvolt.com/datasheets/freight-hub-solar-4mwp-za-r9.pdf)

muse-ba review: in progress.